A steel column hoisting and installing device for integral jacking of a steel structure roof
Patent Information
- Application Number
- CN202522355746.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-06
- Publication Date
- 2026-10-23
- Estimated Expiration
- 2035-11-06
AI Technical Summary
由于吊装延长钢柱300的空间较小,传统的起重设备远远超吊装空间
[0009](1)本实用新型通过设置第一支撑梁、第二支撑梁、第一工字钢和第二工字钢,将第一支撑梁、第二支撑梁的中部分别焊接在上钢柱的前后,并将第一工字钢和第二工字钢的一端焊接在第一支撑梁、第二支撑梁上,以提供吊装滑动支撑。
Smart Images

Figure CN224883543U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of overall lifting and renovation technology for steel structure roofs, and in particular to a steel column hoisting and installation device for overall lifting of steel structure roofs. Background Technology
[0002] A domestic integrated transportation hub project uses a steel structure roof with overall plan dimensions of 43 meters × 55.6 meters. The main steel structure building is approximately 9.2 meters high, with a total weight of about 650 tons. The frame columns and frame beams are rigidly connected. To meet the requirements of a smart hub, the roof needs to be raised by 1.2 meters. Several popular space frame installation methods in the domestic and international markets include high-altitude assembly, overall jacking, overall lifting, overall hoisting, and sliding construction. Through analysis and comparison, and considering factors such as the steel space frame structure, site environment, and construction requirements of the integrated transportation hub project, the overall jacking method was chosen for construction. This overall jacking involves expanding and assembling the structure using a cumulative jacking method on a ground-based formwork. After the jacking support columns have raised the steel structure roof, a 1.2-meter-high extension steel column 300 needs to be installed between the upper steel column 200 and the lower steel column 100. Due to the limited space for hoisting the extension steel column 300, traditional lifting equipment would far exceed the available space.
[0003] Therefore, a simple and reliable steel column hoisting and installation device for the overall lifting of steel structure roofs is proposed. Utility Model Content
[0004] To address the aforementioned problems, the purpose of this utility model is to provide a steel column hoisting and installation device for the overall lifting of a steel structure roof. The technical solution adopted by this utility model is as follows:
[0005] A steel column hoisting and installation device for integrally lifting a steel structure roof includes an extended steel column hoisted between a lower steel column and an upper steel column. Several lifting lugs are welded to both sides of the extended steel column. The device comprises a first support beam and a second support beam welded to the front and rear sides of the upper steel column, a first I-beam connected at one end to one end of the first and second support beams, a second I-beam connected at the other end of the first and second support beams, a pulley assembly slidably fitted onto the first and second I-beams and corresponding to each lifting lug, and a hoist located at the lower part of the pulley assembly. The lower part of the hoist is hung on the lifting lugs. The first and second I-beams are arranged parallel to each other.
[0006] Furthermore, the pulley assembly includes a first pulley support and a second pulley support, a connecting rod disposed between the first pulley support and the second pulley support, a lifting lug hook hung on the connecting rod, several traveling pulleys disposed on the inner sides of the first pulley support and the second pulley support, and side pulleys disposed on the first pulley support and the second pulley support; the hoist is hung on the lifting lug hook; the traveling pulleys are sleeved on the first I-beam or the second I-beam; the side pulleys are pressed against the side of the first I-beam or the second I-beam.
[0007] Furthermore, at least two of each of the lifting lugs, pulley assemblies, and hoists are provided.
[0008] Compared with the prior art, the present invention has the following beneficial effects:
[0009] (1) This utility model provides hoisting sliding support by setting up a first support beam, a second support beam, a first I-beam and a second I-beam, welding the middle parts of the first support beam and the second support beam to the front and rear of the upper steel column respectively, and welding one end of the first I-beam and the second I-beam to the first support beam and the second support beam.
[0010] (2) By setting up a pulley assembly and a hoist, the present invention moves along the first I-beam and the second I-beam to facilitate the hoisting and moving of the extended steel column between the lower steel column and the upper steel column, thus ensuring the reliability of its hoisting.
[0011] In summary, this utility model has the advantages of simple structure and reliable hoisting, and has high practical and promotional value in the field of overall lifting and renovation technology of steel structure roofs. Attached Figure Description
[0012] To more clearly illustrate the technical solutions of the embodiments of this utility model, the drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of this utility model and should not be regarded as a limitation on the scope of protection. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.
[0013] Figure 1 This is a structural schematic diagram of the present invention from a first angle.
[0014] Figure 2 This is a structural schematic diagram of the present invention from a second angle.
[0015] Figure 3 This is a schematic diagram of the pulley assembly of this utility model.
[0016] In the above figures, the component names corresponding to the reference numerals are as follows:
[0017] 100. Lower steel column; 200. Upper steel column; 300. Extension steel column; 301. Lifting lug; 1. First support beam; 2. Second support beam; 3. First I-beam; 4. Second I-beam; 5. Pulley assembly; 6. Hoist; 51. First pulley support seat; 52. Second pulley support seat; 53. Connecting rod; 54. Lifting lug buckle; 55. Traveling pulley; 56. Side pulley. Detailed Implementation
[0018] To make the objectives, technical solutions, and advantages of this application clearer, the present invention will be further described below with reference to the accompanying drawings and embodiments. The embodiments of this utility model include, but are not limited to, the following embodiments. All other embodiments obtained by those skilled in the art based on the embodiments in this application without inventive effort are within the scope of protection of this application.
[0019] In this embodiment, the term "and / or" is merely a description of the relationship between related objects, indicating that there can be three relationships. For example, A and / or B can represent three situations: A exists alone, A and B exist simultaneously, and B exists alone.
[0020] The terms "first" and "second," etc., used in the specification and claims of this embodiment are used to distinguish different objects, not to describe a specific order of objects. For example, "first target object" and "second target object," etc., are used to distinguish different target objects, not to describe a specific order of target objects.
[0021] In the embodiments of this application, the terms "exemplary" or "for example" are used to indicate that something is an example, illustration, or description. Any embodiment or design that is described as "exemplary" or "for example" in the embodiments of this application should not be construed as being more preferred or advantageous than other embodiments or design. Specifically, the use of the terms "exemplary" or "for example" is intended to present the relevant concepts in a specific manner.
[0022] In the description of the embodiments in this application, unless otherwise stated, "multiple" means two or more. For example, multiple processing units means two or more processing units; multiple systems means two or more systems.
[0023] like Figures 1 to 3As shown, this embodiment provides a steel column hoisting and installation device for the overall lifting of a steel structure roof, which hoists an extended steel column 300 between the lower steel column 100 and the upper steel column 200. To achieve the hoisting of the extended steel column 300, several lifting lugs 301 are welded to both sides of the extended steel column 300. Taking four lifting lugs 301 as an example, two are welded to each side. Similarly, two pulley assemblies 5 are respectively provided on the first I-beam 3 and the second I-beam 4, corresponding one-to-one with the positions of the lifting lugs 301.
[0024] Here, the steel column hoisting and installation device includes a first support beam 1 and a second support beam 2 welded to the front and rear sides of the upper steel column 200, a first I-beam 3 connected at one end to one end of the first support beam 1 and the second support beam 2, a second I-beam 4 connected at one end to the other end of the first support beam 1 and the second support beam 2, a pulley assembly 5 slidably sleeved on the first I-beam 3 and the second I-beam 4 and corresponding one-to-one with the lifting lugs 301, and a hoist 6 located at the lower part of the pulley assembly 5. The lower part of the hoist 6 is hung on the lifting lugs 301, and the first I-beam 3 and the second I-beam 4 are arranged parallel to each other. It should be noted that the distance between the first I-beam 3 and the second I-beam 4 is slightly larger than the side width of the upper steel column 200 (e.g., ...). Figure 2 (as shown), so that the pulley assembly 5 can be reliably moved to the position corresponding to the upper steel column 200.
[0025] In this embodiment, the pulley assembly 5 includes a first pulley support 51 and a second pulley support 52, a connecting rod 53 disposed between the first pulley support 51 and the second pulley support 52, a lifting lug 54 hung on the connecting rod 53, several traveling pulleys 55 disposed on the inner sides of the first pulley support 51 and the second pulley support 52, and side pulleys 56 disposed on the first pulley support 51 and the second pulley support 52. The hoist 6 is hung on the lifting lug 54. Taking the first I-beam 3 as an example, the first pulley support 51 and the second pulley support 52 are respectively placed on the two sides of the first I-beam 3, the traveling pulleys 55 are sleeved on the first I-beam 3, and the side pulleys 56 press against the sides of the first I-beam 3. In this way, the pulley assembly 5 can be slidably sleeved on the first I-beam 3 or the second I-beam 4.
[0026] In this embodiment, after the extended steel column 300 is hoisted to the lower steel column 100 and the upper steel column 200, it can be welded together, and then the first support beam 1, the second support beam 2, the first I-beam 3, the second I-beam 4 and the lifting lug 301 can be disassembled.
[0027] The above embodiments are merely preferred embodiments of this utility model and are not intended to limit the scope of protection of this utility model. Any changes made based on the design principles of this utility model, or any non-creative changes made on this basis, shall fall within the scope of protection of this utility model.
Claims
1. A steel column hoisting and installation device for integral lifting of a steel structure roof, wherein an extended steel column (300) is hoisted between a lower steel column (100) and an upper steel column (200), characterized in that, The extended steel column (300) has several lifting lugs (301) welded to both sides. The steel column hoisting and installation device includes a first support beam (1) and a second support beam (2) welded to the front and rear sides of the upper steel column (200), a first I-beam (3) with one end connected to one end of the first support beam (1) and the second support beam (2), a second I-beam (4) with one end connected to the other end of the first support beam (1) and the second support beam (2), a pulley assembly (5) slidably sleeved on the first I-beam (3) and the second I-beam (4) and corresponding one-to-one with the lifting lugs (301), and a hoist (6) set at the lower part of the pulley assembly (5). The lower part of the hoist (6) is hung on the lifting lugs (301). The first I-beam (3) and the second I-beam (4) are arranged in parallel.
2. The steel column hoisting and installation device for integral lifting of a steel structure roof according to claim 1, characterized in that, The pulley assembly (5) includes a first pulley support (51) and a second pulley support (52), a connecting rod (53) between the first pulley support (51) and the second pulley support (52), a lifting lug (54) hanging on the connecting rod (53), several traveling pulleys (55) on the inner side of the first pulley support (51) and the second pulley support (52), and side pulleys (56) on the first pulley support (51) and the second pulley support (52); the hoist (6) is hung on the lifting lug (54); the traveling pulleys (55) are sleeved on the first I-beam (3) or the second I-beam (4); the side pulleys (56) are pressed against the side of the first I-beam (3) or the second I-beam (4).
3. A steel column hoisting and installation device for integral lifting of a steel structure roof according to claim 1 or 2, characterized in that, At least two of each of the lifting lugs (301), pulley assembly (5), and hoist (6) are provided.