A temporary support reinforcing device for a highway reconstruction and expansion traffic guide rail

CN224884608UActive Publication Date: 2026-10-23THE FOURTH ENG CO LTD OF CCCC FIRST HIGHWAY ENG +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522591245.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-05
Publication Date
2026-10-23
Estimated Expiration
2035-12-05

AI Technical Summary

Technical Problem

[0003]当前涉路施工中,临时护栏的背部加固及标志牌安装普遍采用传统的人工操作模式,其核心流程包括三个关键步骤:首先由施工人员借助电钻等工具在护栏背部预设位置进行人工打孔,其次将螺栓、角码等零部件逐一拼接至孔位处,完成基础固定结构的组装;最后通过扳手、套筒等工具将固定杆贯穿相邻护栏的预留孔,实现护栏间的刚性连接,标志牌则需额外通过扎带捆绑或专用夹具固定在加固后的护栏上;这种传统施工方式存在诸多突出问题,已难以适应现代涉路施工高效、安全的作业需求;从施工效率来看,人工打孔过程中受护栏强度不均、操作空间受限等因素影响,返工现象频繁,加之零部件拼接与固定杆安装均依赖人工手动操作;并且,施工完成后,不便于拆卸,显著增加了劳动力成本

Benefits of technology

1、本实用新型所述的一种高速公路改扩建交通导改临时护栏支撑加固装置,工作人员可以提前将固定杆和固定桁架进行安装,当临时护栏完成对地安装后,工作人员通过安装组件依次将安装好的固定杆和固定桁架装到两个临时护栏上,对护栏起到连接稳固作用;摒弃传统人工打孔、校准、清理等繁琐步骤,通过预设插槽与安装组件实现固定杆插件式快速安装,单组临时护栏的固定作业时间从传统15-20分钟缩短至2-3分钟,效率提升。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224884608U_ABST
    Figure CN224884608U_ABST
Patent Text Reader

Abstract

The utility model discloses a highway reconstruction and extension traffic guide changes temporary guardrail support reinforcing device, including temporary guardrail, the lower end middle part of every temporary guardrail all is provided with the drain, and is equipped with the strengthening frame between two temporary guardrails, every temporary guardrail all is provided with four insertion slot, every insertion slot all is equipped with fixed rod, and two fixed rods between same horizontal line are equipped with fixed truss, every fixed rod and temporary guardrail between being equipped with mounting assembly, is used for the convenient installation and dismounting fixed rod, the utility model discloses mounting assembly in proper order with the fixed rod and fixed truss of installation of being installed are installed to two temporary guardrails, play the connecting stable role to guardrail, discard traditional manual punching, calibration, cleaning and other complicated steps, realize fixed rod plug -in type quick installation through the preset insertion slot and mounting assembly, and the fixed operation time of single group temporary guardrail is shortened to 2 3 minutes from traditional 15 20 minutes, and the efficiency is promoted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of highway maintenance technology, and in particular to a temporary guardrail support and reinforcement device for traffic diversion during highway reconstruction and expansion. Background Technology

[0002] In road-related projects such as highway maintenance, reconstruction and expansion, and expressway construction, traffic diversion is a core element in ensuring construction safety and traffic order. Temporary guardrails, as key facilities separating construction areas from traffic areas, have their installation stability and functional integrity directly related to the safety of construction personnel and passing vehicles. To achieve clear traffic guidance, speed limit, detour, and warning signs need to be installed on the guardrails simultaneously. The fixing of these signs often relies on the structural reinforcement of the guardrail itself. Therefore, the reinforcement of the back of the temporary guardrail and the installation of the signs form a closely related construction procedure.

[0003] Currently, in road construction, the reinforcement of temporary guardrails and the installation of signs generally adopt the traditional manual operation mode. The core process includes three key steps: First, construction workers use tools such as electric drills to manually drill holes at pre-set positions on the back of the guardrails. Second, bolts, angle brackets, and other components are assembled one by one to the holes to complete the assembly of the basic fixing structure. Finally, using tools such as wrenches and sockets, fixing rods are inserted through the reserved holes of adjacent guardrails to achieve a rigid connection between the guardrails. The signs need to be additionally fixed to the reinforced guardrails with cable ties or special clamps. This traditional construction method has many prominent problems and is no longer suitable for the efficient and safe operation requirements of modern road construction. From the perspective of construction efficiency, rework is frequent due to factors such as uneven guardrail strength and limited operating space during manual drilling. In addition, the splicing of components and the installation of fixing rods all rely on manual operation. Furthermore, after construction, it is not convenient to disassemble, which significantly increases labor costs.

[0004] To address this issue, a temporary guardrail support and reinforcement device for highway reconstruction and expansion is proposed to solve the problems existing in the current technology. Utility Model Content

[0005] The purpose of this utility model is to address the aforementioned problems by providing a temporary guardrail support and reinforcement device for highway reconstruction and expansion. This utility model uses installation components to sequentially attach pre-installed fixing rods and fixing trusses to two temporary guardrails, providing a stable connection. It eliminates the tedious steps of traditional manual drilling, calibration, and cleaning, achieving rapid plug-in installation of the fixing rods through pre-set slots and installation components. The fixing time for a single set of temporary guardrails is reduced from the traditional 15-20 minutes to 2-3 minutes, significantly improving efficiency. To achieve the above-mentioned utility model objectives, the technical solution adopted is as follows: According to one aspect of this utility model, a temporary guardrail support and reinforcement device for traffic diversion in highway reconstruction and expansion is provided, including temporary guardrails, two of which are arranged horizontally side by side, each of which has a drainage outlet in the middle of its lower end, and a reinforcing frame between the two temporary guardrails. Each of the temporary guardrails has four slots, which are arranged in pairs on the left and right sides of the temporary guardrail, with two slots on the same side arranged vertically in sequence. Each slot has a fixing rod, and a fixing truss is provided between two fixing rods on the same horizontal line. An installation component is provided between each fixing rod and the temporary guardrail for convenient installation and disassembly of the fixing rod.

[0006] Preferably, the installation assembly includes a fixing component and a connector. The fixing component includes two fixing plates disposed on each temporary guardrail, and each fixing plate is disposed above a corresponding slot. The fixing plate has a cavity and an insertion port that communicates with the cavity. A sleeve is disposed in the cavity and extends outward through the insertion port. The sleeve is coaxially arranged with the slot. A connector is disposed in the sleeve for installing and removing the fixing rod.

[0007] Preferably, the connector includes a collet disposed inside the sleeve. The collet is hollow and has a contact inclined ring on its top outer circumference. The upper end of the sleeve has an internal thread. The upper end of the sleeve has a gasket with a through groove arranged coaxially with the insertion port. The lower end of the gasket has a pressing inclined surface that cooperates with the contact inclined ring. The outer circumference of the gasket has an external thread that meshes with the internal thread.

[0008] Preferably, the chuck has four slots, and each slot extends downward to a distance of 1-2 mm from the bottom of the chuck, so that the chuck can clamp and open.

[0009] Preferably, the bottom circumference of the sleeve is evenly distributed with multiple limiting blocks, and the bottom of the chuck is provided with multiple limiting grooves, and the multiple limiting grooves cooperate with the multiple limiting blocks.

[0010] In summary, due to the adoption of the above technical solution, the beneficial effects of this utility model are: 1. The present invention relates to a temporary guardrail support and reinforcement device for highway reconstruction and expansion. Workers can pre-install fixed rods and fixed trusses. After the temporary guardrails are installed on the ground, workers can use the installation components to sequentially install the pre-installed fixed rods and fixed trusses onto the two temporary guardrails, thus connecting and stabilizing the guardrails. It eliminates the tedious steps of traditional manual drilling, calibration, and cleaning. Through the pre-set slots and installation components, the fixed rods can be quickly installed by plugging them in. The fixing time for a single set of temporary guardrails is reduced from the traditional 15-20 minutes to 2-3 minutes, improving efficiency.

[0011] 2. The temporary guardrail support and reinforcement device for highway reconstruction and expansion described in this utility model has a hollow structure for the clamp with four downward-extending slots. The 1-2mm bottom connection section not only ensures the structural strength of the clamp but also provides it with sufficient elastic opening and clamping stroke, which can be adapted to fixing rods of different diameters. Attached Figure Description

[0012] Figure 1 This is a three-dimensional schematic diagram of the present invention; Figure 2 This is a utility model Figure 1 A partial cross-sectional diagram; Figure 3 This is a utility model Figure 2 Enlarged view of point A; Figure 4 This is an exploded view of the internal structure of the fixed disk of this utility model; Figure 5 This is a utility model Figure 4 A partial sectional view; In the attached diagram, 1 is a temporary guardrail; 2 is a drain outlet; 3 is a reinforcing frame; 4 is a slot; 5 is a fixing rod; 6 is a fixing truss; 7 is a fixing plate; 8 is a cavity; 9 is a socket; 10 is a sleeve; 11 is a clamp; 12 is a contact ring; 13 is an internal thread; 14 is a gasket; 15 is a through groove; 16 is an external thread; 17 is an extrusion bevel; 18 is a slot; 19 is a limiting block; and 20 is a limiting groove. Detailed Implementation

[0013] To make the objectives, technical solutions, and advantages of this utility model clearer, the following detailed description is provided with reference to the accompanying drawings and preferred embodiments. However, it should be noted that many details listed in the specification are merely to provide the reader with a thorough understanding of one or more aspects of the utility model, and these aspects can be achieved even without these specific details.

[0014] Please see Figures 1 to 5 This utility model provides a temporary guardrail support and reinforcement device for traffic diversion in highway reconstruction and expansion, and the technical solution is as follows: The system includes temporary guardrails 1, with two temporary guardrails 1 arranged horizontally side by side. Each temporary guardrail 1 has a drainage outlet 2 at the lower center, and a reinforcing frame 3 is provided between the two temporary guardrails 1. Each temporary guardrail 1 has four slots 4, which are arranged in pairs on the left and right sides of the temporary guardrail 1. Two slots 4 on the same side are arranged vertically in sequence. Each slot 4 has a fixing rod 5, and a fixing truss 6 is provided between two fixing rods 5 on the same horizontal line. An installation component is provided between each fixing rod 5 and the temporary guardrail 1 for convenient installation and disassembly of the fixing rod 5.

[0015] Workers can pre-install the fixing rods 5 and fixing trusses 6. After the temporary guardrail 1 is installed on the ground, workers can use the installation components to install the fixed rods 5 and fixing trusses 6 onto the two temporary guardrails 1 in sequence, which will connect and stabilize the guardrails. This eliminates the tedious steps of traditional manual drilling, calibration, and cleaning. The fixed rods 5 can be quickly installed by plugging them in through the pre-set slots 4 and the installation components. The fixing time for a single set of temporary guardrails 1 is reduced from the traditional 15-20 minutes to 2-3 minutes, which improves efficiency. At the same time, the fixing trusses 6 simultaneously complete the lateral reinforcement of adjacent guardrails, realizing the integration of installation and reinforcement, which improves the overall efficiency.

[0016] The installation assembly includes a fixing component and a connector. The fixing component includes two fixing plates 7 disposed on each temporary guardrail 1, and each fixing plate 7 is disposed above a corresponding slot 4. A cavity 8 is formed inside the fixing plate 7, and an insertion port 9 is formed on the fixing plate 7, and the insertion port 9 communicates with the cavity 8. A sleeve 10 is provided inside the cavity 8, and the sleeve 10 extends outward through the insertion port 9. The sleeve 10 is coaxially arranged with the slot 4. A connector is provided inside the sleeve 10 for installing and removing the fixing rod 5.

[0017] The sleeve 10, coaxially arranged with the fixing plate 7 and the slot 4, forms a directional guiding structure. When the fixing rod 5 is inserted, it can be precisely aligned with the slot 4 along the sleeve 10 without additional hole calibration, completely avoiding the deviation problem of traditional manual drilling, ensuring the consistency of the installation position of the fixing rod 5, simplifying the installation operation, further shortening the installation time of a single set of guardrails, and improving construction efficiency. The sleeve 10 provides a stable installation carrier for the connector. The connector can adopt convenient structures such as quick locking and threaded engagement. After the fixing rod 5 is inserted into the slot 4, it can be quickly fixed through the connector in the sleeve 10 without additional auxiliary tools. When disassembling, only the connector needs to be operated to unlock, realizing the non-destructive separation of the fixing rod 5 from the guardrail, improving the efficiency of installation and disassembly.

[0018] The connector includes a collet 11 disposed inside the sleeve 10. The collet 11 is hollow and has a contact inclined ring 12 on its top outer circumference. The upper end of the sleeve 10 has an internal thread 13 and a cover 14. The cover 14 has a through groove 15 arranged coaxially with the insertion port 9. The lower end of the cover 14 has a pressing inclined surface 17 that cooperates with the contact inclined ring 12. The outer circumference of the cover 14 has an external thread 16 that meshes with the internal thread 13. The collet 11 has four slots 18, and each slot 18 extends downward to a distance of 1-2 mm from the bottom of the collet 11. The collet 11 can clamp and open.

[0019] The collet 11 features a hollow structure with four downward-extending slots 18. The 1-2mm bottom connection section ensures the structural strength of the collet 11 while providing ample elastic opening and clamping stroke, making it compatible with fixing rods 5 of different diameters (with a compatibility error range of ±0.5mm). Through the wedge-shaped engagement of the contact ring 12 and the extrusion slope 17, the axial pressure is converted into radial clamping force when the cover 14 is rotated, achieving multi-point uniform clamping of the fixing rod 5. Utilizing the meshing structure of the external thread 16 of the cover 14 and the internal thread 13 of the sleeve 10, the collet 11 can be clamped and released simply by manually rotating the cover 14, without the need for additional tools such as wrenches or sleeves 10. This allows for independent operation by a single person, reducing the locking / unlocking time of a single fixing rod 5 to less than 30 seconds. Compared to the rust and adhesion and forced prying required for disassembling traditional fixing rods 5, this structure allows for easy unloading by simply turning, avoiding the cumbersome, time-consuming, and laborious disassembly process of traditional methods.

[0020] The sleeve 10 has multiple limiting blocks 19 evenly distributed around its bottom circumference, and the chuck 11 has multiple limiting grooves 20 at its bottom, with the multiple limiting grooves 20 cooperating with the multiple limiting blocks 19.

[0021] The limiting block 19 at the bottom of the sleeve 10 and the limiting groove 20 at the bottom of the chuck 11 form a circumferential positioning structure, which can completely limit the rotation of the chuck 11 within the sleeve 10, preventing the chuck 11 from rotating synchronously with the pad 14 when the rotating pad 14 applies clamping force, ensuring that the contact inclined ring 12 and the extrusion inclined surface 17 always maintain precise contact, and efficiently converting axial pressure into radial clamping force; and through the limitation of the limiting groove 20 and the limiting block 19, the chuck 11 and the sleeve 10 are detachably connected, and the chuck 11 can be replaced when it is worn, ensuring the stability of clamping the fixed rod 5.

[0022] The above description is only a preferred embodiment of the present utility model. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the principle of the present utility model, and these improvements and modifications should also be considered within the protection scope of the present utility model.

Claims

1. A temporary guardrail support and reinforcement device for traffic diversion during highway reconstruction and expansion, characterized in that, include: Temporary guardrail (1), two temporary guardrails (1) are arranged horizontally side by side, each temporary guardrail (1) has a drainage outlet (2) in the middle of its lower end, and a reinforcing frame (3) is provided between the two temporary guardrails (1). Each temporary guardrail (1) has four slots (4), and the four slots (4) are arranged in pairs on the left and right sides of the temporary guardrail (1). The two slots (4) on the same side are arranged vertically in sequence. Each slot (4) has a fixing rod (5), and a fixing truss (6) is provided between the two fixing rods (5) on the same horizontal line. Each fixing rod (5) and the temporary guardrail (1) are provided with an installation component for convenient installation and disassembly of the fixing rod (5).

2. The temporary guardrail support and reinforcement device for traffic diversion in highway reconstruction and expansion according to claim 1, characterized in that: The installation assembly includes a fixing component and a connector. The fixing component includes two fixing plates (7) set on each temporary guardrail (1), and each fixing plate (7) is set above the corresponding slot (4). A cavity (8) is opened in the fixing plate (7), and an insertion port (9) is opened on the fixing plate (7), and the insertion port (9) communicates with the cavity (8). A sleeve (10) is provided in the cavity (8), and the sleeve (10) extends outward through the insertion port (9). The sleeve (10) is coaxially arranged with the slot (4). A connector is provided in the sleeve (10) for installing and removing the fixing rod (5).

3. The temporary guardrail support and reinforcement device for highway reconstruction and expansion as described in claim 2, characterized in that: The connector includes a collet (11) disposed inside the sleeve (10). The collet (11) is hollow and has a contact inclined ring (12) on its top outer circumference. The upper end of the sleeve (10) is provided with an internal thread (13). The upper end of the sleeve (10) is provided with a pad (14), and the pad (14) is provided with a through groove (15) arranged coaxially with the socket (9). The lower end of the pad (14) is provided with a pressing inclined surface (17) that cooperates with the contact inclined ring (12). The outer circumference of the pad (14) is provided with an external thread (16) that meshes with the internal thread (13).

4. The temporary guardrail support and reinforcement device for traffic diversion in highway reconstruction and expansion according to claim 3, characterized in that: The chuck (11) has four slots (18), and each slot (18) extends downward to a distance of 1-2 mm from the bottom of the chuck (11), so that the chuck (11) can clamp and open.

5. The temporary guardrail support and reinforcement device for traffic diversion in highway reconstruction and expansion according to claim 3, characterized in that: The sleeve (10) has multiple limiting blocks (19) evenly distributed around its bottom circumference, and the chuck (11) has multiple limiting grooves (20) at its bottom, with the multiple limiting grooves (20) cooperating with the multiple limiting blocks (19).