Indoor glass partition construction hoisting and clamping structure
Patent Information
- Application Number
- CN202522549549.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-01
- Publication Date
- 2026-10-23
- Estimated Expiration
- 2035-12-01
AI Technical Summary
[0003]在建筑装饰工程中,玻璃隔断吊装夹固节点能够增强璃隔断的稳定性、安全性以及与周边结构的协调性,然而在长期使用过程中,受到建筑物自身震动、风力等外力作用,玻璃隔断容易出现松动、晃动现象,对于不同厚度的玻璃隔断,定制夹具难以提供足够且均匀的夹持力,导致玻璃隔断在夹持部位受力不均,容易出现破裂风险,特别是在玻璃隔断的边角处,破裂隐患更为突出,为此,需要提供一种室内玻璃隔断施工吊装夹固构造,通过主体钢架和吊装组件的配合,为玻璃隔断提供了稳定的吊装固定,同时吊装组件中的定位螺帽可调节夹板间距,适应不同厚度玻璃隔断的安装需求,同时确保夹板垂直,使橡胶夹片能稳定夹持玻璃隔断,提高了夹持稳定性
1、本实用新型通过主体钢架和吊装组件的配合使用,对玻璃隔断进行吊装固定,同时在吊装丝杆和镀锌扣件的配合使用,对轻钢龙骨吊顶和双层石膏板进行安装,使得玻璃隔断和双层石膏板形成垂直隔断,即可达到夹持稳定牢靠和适用不同厚度安装需求的目的;
Smart Images

Figure CN224884963U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of interior decoration construction technology, and in particular relates to an installation and clamping structure for interior glass partitions. Background Technology
[0002] Glass partition construction is the process of dividing space within a building using glass as the main material. During construction, the location and dimensions are first determined according to the design plan, and the frame or fasteners, such as metal keel or steel frame, are installed. Then, the cut glass is precisely installed and fixed, which can be done by methods such as lamination, bolt connection, or sealing with glue.
[0003] In architectural decoration projects, the hoisting and clamping joints of glass partitions can enhance the stability, safety, and coordination with the surrounding structure of the glass partitions. However, during long-term use, glass partitions are prone to loosening and swaying due to external forces such as building vibration and wind. For glass partitions of different thicknesses, customized clamps cannot provide sufficient and uniform clamping force, resulting in uneven stress on the glass partition at the clamping points, which easily leads to the risk of breakage, especially at the corners of the glass partition, where the risk of breakage is more prominent. Therefore, it is necessary to provide a hoisting and clamping structure for indoor glass partition construction. Through the cooperation of the main steel frame and hoisting components, a stable hoisting and fixing structure for the glass partition is provided. At the same time, the positioning nuts in the hoisting components can adjust the spacing of the clamping plates to adapt to the installation requirements of glass partitions of different thicknesses, while ensuring that the clamping plates are vertical, so that the rubber clamps can stably clamp the glass partition, thereby improving the clamping stability. Utility Model Content
[0004] The purpose of this utility model is to provide a hoisting and clamping structure for indoor glass partition construction. Through the cooperation of the main steel frame and the hoisting components, a stable hoisting and fixing structure is provided for the glass partition. At the same time, the positioning nuts in the hoisting components can adjust the spacing of the clamping plates to adapt to the installation requirements of glass partitions of different thicknesses. Meanwhile, it ensures that the clamping plates are vertical, so that the rubber clamps can stably hold the glass partition, thereby improving the clamping stability and solving the above-mentioned technical problems.
[0005] The technical solution of this utility model to solve the above-mentioned technical problems is as follows: An indoor glass partition construction hoisting and clamping structure includes light steel keel ceilings on both sides below the main steel frame: double-layer gypsum board is installed at the bottom of the light steel keel ceiling, galvanized main keel is welded to the top of the light steel keel ceiling, galvanized fasteners are fitted on the surface of the galvanized main keel, hoisting screws are fixedly connected to the top of the galvanized fasteners, the top of the hoisting screws is fixedly connected to the wall, a glass partition is installed between the two light steel keel ceilings, a hoisting assembly is provided on the top of the glass partition, the hoisting assembly includes galvanized channel steel welded to the bottom of the main steel frame, multiple pins are provided through the top of the galvanized channel steel, threaded pins are welded to both sides of the pins, clamps are fitted on the surface of the threaded pins, rubber clamps are rotatably connected to the bottom of the opposite side of the two clamps, the rubber clamps are pressed against the surface of the glass partition, and tie bolts are provided through the two clamps.
[0006] Preferably, the pin has two hexagonal nuts threaded onto its surface, and the hexagonal nuts are tightly pressed against the surface of the galvanized channel steel.
[0007] Preferably, both sides of the threaded pin surface are threaded with locking nuts, and the locking nuts are tightly pressed against the surface of the clamping plate.
[0008] Preferably, galvanized square tubes are welded to opposite sides of both of the light steel keel ceilings, and weather-resistant silicone sealant is filled between the galvanized square tubes and the glass partition.
[0009] Preferably, the surface of the threaded pin is threaded with a positioning nut, and one side of the positioning nut is in close contact with the surface of the clamping plate.
[0010] The beneficial effects of this utility model are: 1. This utility model uses the main steel frame and hoisting components to hoist and fix the glass partition. At the same time, the hoisting screw rod and galvanized fastener are used to install the light steel keel ceiling and double-layer gypsum board, so that the glass partition and double-layer gypsum board form a vertical partition, which can achieve the purpose of clamping stably and reliably and adapting to different thickness installation requirements. 2. This utility model, through the combined use of galvanized square tubes and weather-resistant silicone sealant, seals the connection between the light steel keel ceiling and the glass partition, and also isolates the galvanized square tubes and the glass partition, effectively preventing damage to the glass partition caused by thermal expansion and contraction. 3. The present invention adjusts the distance between the clamping plate and the pin by setting the positioning nut, so that the clamping plate can be in a vertical state, thereby allowing the rubber clamping piece to be stably clamped on the surface of the glass partition. Attached Figure Description
[0011] in: Figure 1 This is a front view schematic diagram of one embodiment of the present utility model; Figure 2 This is one embodiment of the present utility model. Figure 1 A magnified view of point A in the middle; Figure 3 This is a perspective view of a hoisting assembly according to an embodiment of the present invention; Figure 4 This is a three-dimensional exploded view of a hoisting assembly according to an embodiment of the present invention.
[0012] The attached diagram lists the components represented by each number as follows: 1. Main steel frame; 2. Light steel keel ceiling; 3. Double-layer gypsum board; 4. Galvanized main keel; 5. Hanging screw rod; 6. Galvanized fastener; 7. Glass partition; 8. Hanging assembly; 81. Galvanized channel steel; 82. Pin rod; 83. Hexagonal nut; 84. Threaded pin; 85. Clamping plate; 86. Rubber clamp; 87. Tie bolt; 88. Locking nut; 9. Galvanized square tube; 10. Weather-resistant silicone sealant; 11. Positioning nut. Detailed Implementation
[0013] In the following description, embodiments of the installation, hoisting, and clamping structure for indoor glass partitions according to the present invention will be described with reference to the accompanying drawings.
[0014] Figure 1-4This invention illustrates an embodiment of an indoor glass partition installation and clamping structure, comprising a light steel keel ceiling 2 located on both sides below the main steel frame 1. The bottom of the light steel keel ceiling 2 is fitted with double-layer gypsum board 3, and the top of the light steel keel ceiling 2 is welded with a galvanized main keel 4. Galvanized fasteners 6 are fitted onto the surface of the galvanized main keel 4, and a lifting screw 5 is fixedly connected to the top of the galvanized fastener 6. The top of the lifting screw 5 is fixedly connected to the wall. A glass partition 7 is installed between the two light steel keel ceilings 2. A lifting assembly 8 is installed at the top. The lifting assembly 8 includes a galvanized channel steel 81 welded to the bottom of the main steel frame 1. Multiple pins 82 are installed through the top of the galvanized channel steel 81. Two hexagonal nuts 83 are threaded to the surface of the pins 82. The hexagonal nuts 83 are tightly pressed against the surface of the galvanized channel steel 81. Locking nuts 88 are threaded to both sides of the surface of the threaded pins 84. The locking nuts 88 are tightly pressed against the surface of the clamping plate 85. Threaded pins 84 are welded to both sides of the pins 82. The surface of the threaded pins 84 is threaded... A positioning nut 11 is attached, with one side of the positioning nut 11 tightly fitting against the surface of the clamping plate 85. The positioning nut 11 adjusts the distance between the clamping plate 85 and the pin 82, ensuring the clamping plate 85 is vertical. This allows the rubber clamping piece 86 to be stably clamped onto the surface of the glass partition 7. A clamping plate 85 is fitted onto the surface of the threaded pin 84. Rubber clamping pieces 86 are rotatably connected to the bottom of opposite sides of both clamping plates 85, pressing the rubber clamping pieces 86 against the surface of the glass partition 7. A tie bolt 87 is installed between the two clamping plates 85. Galvanized square tubes 9 are welded to the opposite sides of the two light steel keel ceilings 2. Weather-resistant silicone sealant 10 is filled between the galvanized square tubes 9 and the glass partition 7. The combination of galvanized square tubes 9 and weather-resistant silicone sealant 10 seals the connection between the light steel keel ceiling 2 and the glass partition 7 and isolates the galvanized square tubes 9 and the glass partition 7, effectively preventing damage to the glass partition 7 due to thermal expansion and contraction.
[0015] Working principle: In use, the user welds the galvanized channel steel 81 to the bottom of the main steel frame 1, then inserts the pin 82 from bottom to top through the galvanized channel steel 81, so that the two clamping plates 85 are located on both sides of the glass partition 7. Next, the user adjusts the rubber clamping piece 86 to a suitable height, tightens the hexagonal nut 83, and connects and fixes the pin 82 and the galvanized channel steel 81. Then, the user tightens the locking nut 88 to clamp and fix the clamping plate 85. Finally, the user inserts the tie bolt 87 through the two clamping plates 85 and tightens it, so that the clamping plate 85 drives the rubber clamping piece 86 to press tightly against the surface of the glass partition 7, thus clamping and fixing the glass partition 7. Next, the user adjusts the position of the positioning nut 11 according to the thickness of the glass partition 7, so that the positioning nut 11 is tightly pressed against the surface of the clamp 85, supporting and fixing the clamp 85 so that the clamp 85 remains vertical. Then, the user erects the light steel keel ceiling 2, and uses the hanging screw rod 5, galvanized fastener 6 and galvanized main keel 4 to hoist and fix the light steel keel ceiling 2. Finally, the user fixes the double-layer gypsum board 3 at the bottom of the light steel keel ceiling 2, and fills the space between the galvanized square tube 9 and the glass partition 7 with weather-resistant silicone sealant 10 to seal the space between the glass partition 7 and the galvanized square tube 9.
[0016] In summary, this indoor glass partition installation and clamping structure, through the combined use of the main steel frame 1 and the hoisting components 8, hoists and fixes the glass partition 7. At the same time, through the combined use of the hoisting screw rods 5 and galvanized fasteners 6, the light steel keel ceiling 2 and double-layer gypsum board 3 are installed, so that the glass partition 7 and the double-layer gypsum board 3 form a vertical partition, thus achieving the purpose of stable and reliable clamping and adapting to different thickness installation requirements.
Claims
1. A hoisting and clamping structure for the construction of an indoor glass partition, characterized in that, This includes, assuming, light steel keel ceilings (2) on both sides below the main steel frame (1): The bottom of the light steel keel ceilings (2) is fitted with double-layer gypsum board (3), the top of the light steel keel ceilings (2) is welded with galvanized main keel (4), the surface of the galvanized main keel (4) is fitted with galvanized fasteners (6), the top of the galvanized fasteners (6) is fixedly connected with a lifting screw rod (5), the top of the lifting screw rod (5) is fixedly connected to the wall, a glass partition (7) is installed between the two light steel keel ceilings (2), and a lifting assembly is provided on the top of the glass partition (7). The hoisting assembly (8) includes a galvanized channel steel (81) welded to the bottom of the main steel frame (1). Multiple pins (82) are provided through the top of the galvanized channel steel (81). Threaded pins (84) are welded to both sides of the pins (82). Clamping plates (85) are fitted on the surface of the threaded pins (84). Rubber clips (86) are rotatably connected to the bottom of the opposite side of the two clamping plates (85). The rubber clips (86) are pressed against the surface of the glass partition (7). Tie bolts (87) are provided through the two clamping plates (85).
2. The indoor glass partition construction hoisting and clamping structure according to claim 1, characterized in that, The pin (82) has two hexagonal nuts (83) threadedly connected to its surface, and the hexagonal nuts (83) are tightly pressed against the surface of the galvanized channel steel (81).
3. The indoor glass partition construction hoisting and clamping structure according to claim 2, characterized in that, Both sides of the threaded pin (84) are threaded with locking nuts (88), which are tightly pressed against the surface of the clamping plate (85).
4. The indoor glass partition construction hoisting and clamping structure according to claim 3, characterized in that, Galvanized square tubes (9) are welded to the opposite side of the two light steel keel ceilings (2), and weather-resistant silicone sealant (10) is filled between the galvanized square tubes (9) and the glass partition (7).
5. The indoor glass partition construction hoisting and clamping structure according to claim 4, characterized in that, The threaded pin (84) is threadedly connected to a positioning nut (11), and one side of the positioning nut (11) is in close contact with the surface of the clamping plate (85).