A device for positioning and driving a steel pipe pile in water

CN224902171UActive Publication Date: 2026-10-27ZHEJIANG XINWAN MUNICIPAL ENG CONSTR CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522535277.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-28
Publication Date
2026-10-27
Estimated Expiration
2035-11-28

AI Technical Summary

Technical Problem

[0003]本实用新型的目的在于克服现有技术存在的不足,而提供一种水中钢管桩定位插打装置,解决现有技术中钢管桩插打时候的安装精度,保证整体钢栈桥及水中钻孔平台的稳定性

Benefits of technology

[0005]本实用新型的有益效果为:与现有技术相比,通过设置横向调节组件和纵向调节组件,使钢管桩定位准确,垂直度得到保证;并且,保证整体钢栈桥及水中钻孔平台的稳定性,同时此装置施工人员可以按需自行制造该装置,结构简单,安全性能够得到保证,省时省力,钢管桩也可连续施工作业,保证了质量,提高了栈桥的施工效率。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224902171U_ABST
    Figure CN224902171U_ABST
Patent Text Reader

Abstract

The utility model relates to a kind of water steel pipe pile positioning and driving device, including the support frame of square frame structure;Support frame is divided into the frame of two layers, two layers of frame are symmetrically distributed, and the rear end both sides between two layers of frame are connected and fixed by connecting frame, and the front end of two layers of frame is respectively equipped with horizontal adjusting assembly and longitudinal adjusting assembly, and the vertical positioning of steel pipe pile insertion and driving is adjusted by the adjustment of horizontal adjusting assembly and longitudinal adjusting assembly, and the rear end of the upper layer frame of support frame is fixed with counterweight beam, and the support frame is fixed on bridge by counterweight beam;The utility model is by being provided with horizontal adjusting assembly and longitudinal adjusting assembly, so that steel pipe pile positioning is accurate, perpendicularity is guaranteed, simultaneously this device construction personnel can manufacture the device as needed by oneself, structure is simple, safety can be guaranteed, save time and effort, steel pipe pile can also continuous construction operation, quality is guaranteed, improve the construction efficiency of trestle.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of bridge construction technology, and in particular relates to a positioning and driving device for steel pipe piles in water. Background Technology

[0002] In the construction of bridges in waterways, due to navigation requirements, temporary steel trestle bridges and underwater drilling platforms are typically erected to ensure the construction of the bridge's pile foundations and substructure. These steel trestle bridges and drilling platforms generally use steel pipe piles as their foundations. The overall structure is considered a high-risk, large-scale project; therefore, the installation accuracy of the steel pipe piles plays a crucial role in the stability of the entire steel trestle bridge and drilling platform. However, in actual implementation, due to various factors such as the bridge span, the size and number of steel pipe piles, and complex hydrological conditions, the positioning of the steel pipe piles is difficult, and the verticality of the piles is hard to control, making it difficult to guarantee the overall structural stability. Summary of the Invention

[0003] The purpose of this utility model is to overcome the shortcomings of the existing technology and provide a positioning and driving device for steel pipe piles in water, which solves the problem of installation accuracy when driving steel pipe piles in the existing technology and ensures the stability of the overall steel trestle bridge and the underwater drilling platform.

[0004] The purpose of this utility model is achieved through the following technical solution: This underwater steel pipe pile positioning and driving device includes a support frame with a square frame structure; the support frame is divided into upper and lower frames, which are symmetrically distributed and connected and fixed at their rear ends by connecting frames; the front ends of the two frames are respectively provided with a horizontal adjustment component and a vertical adjustment component, and the vertical positioning of the steel pipe pile is achieved by adjusting the horizontal adjustment component and the vertical adjustment component; and a counterweight beam is fixed at the rear end of the upper frame of the support frame, and the support frame is fixed to the bridge by the counterweight beam.

[0005] The beneficial effects of this utility model are as follows: Compared with the prior art, by setting up horizontal adjustment components and vertical adjustment components, the steel pipe piles are accurately positioned and the verticality is guaranteed; in addition, the stability of the overall steel trestle bridge and the underwater drilling platform is guaranteed. At the same time, the construction personnel can manufacture the device themselves as needed. The structure is simple, the safety is guaranteed, time and labor are saved, the steel pipe piles can also be continuously constructed, the quality is guaranteed, and the construction efficiency of the trestle bridge is improved.

[0006] Preferably, the frame includes two longitudinal I-beams and two transverse channel steels. The two transverse channel steels are fixed between the two longitudinal I-beams by welding and are located at the rear end of the frame. With the above structure, forming is more convenient, and the structure is simple and low in cost.

[0007] Preferably, the connecting frame includes two vertical channel steels and one diagonal channel steel. The two vertical channel steels are fixed between the upper and lower frames by welding, and the two vertical channel steels are distributed one-to-one with the two horizontal channel steels. The diagonal channel steel is fixed between the two vertical channel steels by welding. With the above structure, the structure between the upper and lower frames is more stable, and the spacing between the upper and lower frames can be adjusted according to the actual positioning height of the steel pipe pile to control the verticality of the steel pipe pile.

[0008] Preferably, the lateral adjustment assembly on each layer of the frame includes two lateral adjustment shafts and several lateral slide rails. The two lateral adjustment shafts are fixed at the front end between the two longitudinal I-beams and have insertion holes for inserting steel pipe piles. The several lateral slide rails are movably connected between the two lateral adjustment shafts, and several adjusting nuts are connected to the lateral adjustment shafts. Each lateral slide rail has adjusting nuts on both sides at both ends. Through the above structure, the cooperation between the adjusting nuts and the lateral adjustment shafts allows the lateral slide rails to limit the diameter and lateral spacing of the steel pipe piles.

[0009] Preferably, each of the two longitudinal I-beams on each layer of the frame has a mounting plate for installing the longitudinal adjustment component fixed to both sides of its front end by welding. There are four mounting plates, with two mounting plates installed along the length of each longitudinal I-beam. One mounting plate is flush with one of the transverse channel steels, and the other mounting plate is located at the end of the longitudinal I-beam. The above structure facilitates the installation of the longitudinal adjustment component between the longitudinal adjustment component and the frame.

[0010] Preferably, the longitudinal adjustment assembly on each layer of the frame includes four longitudinal adjustment shafts and two longitudinal slide rails. Two longitudinal adjustment shafts are installed on each of the two mounting plates on each longitudinal I-beam. The two longitudinal slide rails are movably connected between the four longitudinal adjustment shafts, and several adjusting nuts are connected to the longitudinal adjustment shafts. Adjusting nuts are also provided on both sides of each end of the longitudinal slide rail. Through the above structure, the longitudinal slide rails can limit the diameter and longitudinal spacing of the steel pipe piles by cooperating with the adjusting nuts and the longitudinal adjustment shafts.

[0011] Preferably, the longitudinal adjustment component is located above the transverse adjustment component, and the longitudinal adjustment component and the transverse adjustment component are arranged in a cross-shaped staggered pattern; this facilitates the adjustment of the adjustment components by construction personnel, and the two components working together can limit the diameter and verticality of the steel pipe pile. Attached Figure Description

[0012] Figure 1This is a three-dimensional structural diagram of the underwater steel pipe pile positioning and driving device of this utility model.

[0013] Figure 2 This is a top view schematic diagram of the underwater steel pipe pile positioning and driving device of this utility model.

[0014] Figure 3 This is a top-view enlarged structural schematic diagram of the underwater steel pipe pile positioning and driving device of this utility model.

[0015] The labels in the attached diagram are as follows: 1. Support frame; 2. Lateral adjustment assembly; 3. Longitudinal adjustment assembly; 4. Steel pipe pile; 5. Counterweight beam; 6. Adjusting nut; 11. Frame; 12. Connecting frame; 13. Mounting plate; 21. Lateral adjustment shaft; 22. Lateral slide rail; 31. Longitudinal adjustment shaft; 32. Longitudinal slide rail; 11-1. Longitudinal I-beam; 11-2. Lateral channel steel; 12-1. Vertical channel steel; 12-2. Diagonal channel steel. Detailed Implementation

[0016] The present invention will now be described in detail with reference to the accompanying drawings: as shown in the drawings Figures 1 to 3 As shown, this utility model includes a support frame 1 with a square frame structure; the support frame 1 is divided into upper and lower frames 11, which are symmetrically distributed and connected and fixed at their rear ends by a connecting frame 12. The front ends of the two frames 11 are respectively provided with a horizontal adjustment component 2 and a vertical adjustment component 3, and the vertical positioning of the steel pipe pile 4 is achieved by adjusting the horizontal adjustment component 2 and the vertical adjustment component 3. A counterweight beam 5 is fixed at the rear end of the upper frame 11 of the support frame 1, and the support frame 1 is fixed to the bridge by the counterweight beam 5. The counterweight beam 5 is made of two large I-beams and is fixed on both sides of the rear end of the upper frame 11, which increases the load on the bridge, prevents the structure from overturning, and plays an overall anti-overturning role.

[0017] The frame 11 includes two longitudinal H-beams 11-1 and two transverse channel steels 11-2. The two transverse channel steels 11-2 are fixed between the two longitudinal H-beams 11-1 by welding and are located at the rear end of the frame 11.

[0018] The connecting frame 12 includes two vertical channel steels 12-1 and one diagonal channel steel 12-2. The two vertical channel steels 12-1 are fixed between the upper and lower frames 11 by welding, and the two vertical channel steels 12-1 are distributed one-to-one with the two horizontal channel steels 11-2 respectively. The diagonal channel steel 12-2 is fixed between the two vertical channel steels 12-1 by welding.

[0019] The lateral adjustment assembly 2 on each layer of frame 11 includes two lateral adjustment shafts 21 and several lateral slide rails 22. The two lateral adjustment shafts 21 are fixed at the front end between two longitudinal I-beams 11-1 and have insertion holes for inserting steel pipe piles 4. The several lateral slide rails 22 are movably connected between the two lateral adjustment shafts 21, and several adjusting nuts 6 are connected to the lateral adjustment shafts 21. Adjusting nuts 6 are also provided on both sides of each end of each lateral slide rail 22. The lateral slide rails 22 mainly serve as lateral limiters. The lateral slide rails 22 can slide left and right through the lateral adjustment shafts 21 to limit the lateral displacement of the steel pipe piles 4 and adjust the lateral spacing of the steel pipe piles.

[0020] On each layer of frame 11, the front ends of the two longitudinal I-beams 11-1 are fixed with mounting plates 13 for installing longitudinal adjustment components 3 by welding. There are four mounting plates 13. Two mounting plates 13 are installed along the length of each longitudinal I-beam 11-1. One mounting plate 13 is flush with one of the transverse channel steels 11-2, and the other mounting plate 13 is located at the end of the longitudinal I-beam 11-1.

[0021] The longitudinal adjustment assembly 3 on each layer of frame 11 includes four longitudinal adjustment shafts 31 and two longitudinal slide rails 32. Two longitudinal adjustment shafts 31 are installed on each of the two mounting plates 13 on each longitudinal I-beam 11-1. The two longitudinal slide rails 32 are movably connected between the four longitudinal adjustment shafts 31, and several adjusting nuts 6 are connected to the longitudinal adjustment shafts 31. Adjusting nuts 6 are also provided on both sides of each end of each longitudinal slide rail 32. The longitudinal slide rails 32 mainly serve a longitudinal limiting function. The longitudinal slide rails 32 can slide back and forth through the longitudinal adjustment shafts 31 to limit the longitudinal displacement of the steel pipe pile 4, and together with the transverse slide rails 22, they position the diameter of the steel pipe pile 4.

[0022] The longitudinal adjustment component 3 is located above the lateral adjustment component 2, and the longitudinal adjustment component 3 and the lateral adjustment component 2 are arranged in a cross-shaped staggered pattern.

[0023] The adjusting nut 6 is located on the horizontal adjusting shaft 21 and the vertical adjusting shaft 31, and serves to fix the horizontal slide rail 22 and the vertical slide rail 32.

[0024] The working principle of this utility model is as follows: First, the number of transverse slide rails 22 is determined according to the number of steel pipe piles 4. Generally, one steel pipe pile 4 is equipped with two transverse slide rails 22, but the steel pipe pile 4 located on the side of the support frame 1 can be equipped with one transverse slide rail 22, because one side can abut against the longitudinal I-beam 11-1. Then, the diameter of the steel pipe pile 4 is determined by the sliding of the transverse slide rails 22 and the longitudinal slide rails 32, and it is ensured that the transverse slide rails 22 and the longitudinal slide rails 32 on the upper and lower frames 11 are aligned in the vertical direction. Finally, the steel pipe pile 4 is vertically placed between the preset transverse slide rails 22 and the longitudinal slide rails 32 and submerged in water. At this time, the adjustment nuts 6 on both sides of the transverse slide rails 22 and the longitudinal slide rails 32 are used to limit the movement, that is, the transverse slide rails 22 and the longitudinal slide rails 32 abut against the circumferential wall of the steel pipe pile 4.

[0025] The above are merely specific embodiments of this application, but the scope of protection of this application is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in this application should be included within the scope of protection of this application. Therefore, the scope of protection of this application should be determined by the scope of the claims.

Claims

1. A positioning and driving device for steel pipe piles in water, comprising a support frame (1) with a square frame structure; characterized in that: The support frame (1) is divided into two layers of frames (11), which are symmetrically distributed. The two rear ends of the two layers of frames (11) are connected and fixed by a connecting frame (12). The front ends of the two layers of frames (11) are respectively provided with a horizontal adjustment component (2) and a vertical adjustment component (3). The vertical positioning of the steel pipe pile (4) is achieved by adjusting the horizontal adjustment component (2) and the vertical adjustment component (3). A counterweight beam (5) is fixed on the rear end of the upper frame (11) of the support frame (1), and the support frame (1) is fixed on the bridge by the counterweight beam (5).

2. The underwater steel pipe pile positioning and driving device according to claim 1, characterized in that: The frame (11) includes two longitudinal I-beams (11-1) and two transverse channel steels (11-2). The two transverse channel steels (11-2) are fixed between the two longitudinal I-beams (11-1) by welding and are located at the rear end of the frame (11).

3. The underwater steel pipe pile positioning and driving device according to claim 2, characterized in that: The connecting frame (12) includes two vertical channel steels (12-1) and one oblique channel steel (12-2). The two vertical channel steels (12-1) are fixed between the upper and lower frames (11) by welding. The two vertical channel steels (12-1) are distributed one-to-one with the two horizontal channel steels (11-2). The oblique channel steel (12-2) is fixed between the two vertical channel steels (12-1) by welding.

4. The underwater steel pipe pile positioning and driving device according to claim 2, characterized in that: The lateral adjustment assembly (2) on each layer of the frame (11) includes two lateral adjustment shafts (21) and several lateral slide rails (22). The two lateral adjustment shafts (21) are fixed at the front end between the two longitudinal I-beams (11-1) and have insertion holes for inserting steel pipe piles (4). Several lateral slide rails (22) are movably connected between the two lateral adjustment shafts (21), and several adjusting nuts (6) are connected on the lateral adjustment shafts (21). The adjusting nuts (6) are provided on both sides of each end of the lateral slide rail (22).

5. The underwater steel pipe pile positioning and driving device according to claim 2, characterized in that: On each layer of the frame (11), the front ends of the two longitudinal I-beams (11-1) are fixed with mounting plates (13) for installing the longitudinal adjustment assembly (3) by welding. There are four mounting plates (13). Two mounting plates (13) are installed along the length of each longitudinal I-beam (11-1). One mounting plate (13) is flush with one of the transverse channel steels (11-2), and the other mounting plate (13) is located at the end of the longitudinal I-beam (11-1).

6. The underwater steel pipe pile positioning and driving device according to claim 5, characterized in that: The longitudinal adjustment assembly (3) on each layer of the frame (11) includes four longitudinal adjustment shafts (31) and two longitudinal slide rails (32). Two longitudinal adjustment shafts (31) are installed on the two mounting plates (13) on each longitudinal I-beam (11-1). The two longitudinal slide rails (32) are movably connected between the four longitudinal adjustment shafts (31). Several adjusting nuts (6) are connected on the longitudinal adjustment shafts (31). The adjusting nuts (6) are provided on both sides of each longitudinal slide rail (32).

7. The underwater steel pipe pile positioning and driving device according to claim 1, characterized in that: The longitudinal adjustment component (3) is located above the lateral adjustment component (2), and the longitudinal adjustment component (3) and the lateral adjustment component (2) are arranged in a cross-shaped staggered pattern.