Formwork system for casting concrete across a ventilator
Patent Information
- Application Number
- CN202522749829.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-25
- Publication Date
- 2026-10-27
- Estimated Expiration
- 2035-12-25
AI Technical Summary
[0004]本实用新型的是提供跨越通风机浇筑混凝土的支模体系,解决了现有技术中存在难以跨越通风机进行混凝土施工的问题
[0013]本实用新型的有益效果是:本实用新型的一种跨越通风机浇筑混凝土的支模体系,通过设立型钢次梁、型钢主梁、钢柱、卧底型钢梁形成的承载力体系,以及纵向钢梁、柱间支撑、与整体构造连接形成的稳定体系,实现跨越通风机进行混凝土施工,安全可靠,施工便利。
Smart Images

Figure CN224903234U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of building engineering equipment technology, specifically relating to a formwork system for pouring concrete across a ventilation fan. Background Technology
[0002] As one of the six major systems in a mine, the ventilation system ensures the ventilation needs of the entire mine and plays a crucial role in the construction and production of the entire mine. Generally, ventilation fans are exhaust fans, and the exhaust air has a certain temperature. In recent years, in order to build more environmentally friendly and energy-saving mines, many mines have started to collect and reuse underground exhaust air, which requires the construction of heat extraction chambers at the top of the ventilation fans to collect heat sources.
[0003] Due to the influence of the exhaust wind environment, the heat exchange room project generally adopts a reinforced concrete frame structure to improve its durability. However, the concrete construction requires the erection of an integral formwork underneath. Due to the influence of the ventilation fan, the formwork needs to be designed to cross the ventilation fan and meet the requirements of load-bearing capacity and stability. Utility Model Content
[0004] This utility model provides a formwork system for pouring concrete across a ventilation fan, which solves the problem in the prior art that it is difficult to carry out concrete construction across a ventilation fan.
[0005] To achieve the above objectives, the technical solution adopted by this utility model is: a formwork system for pouring concrete across a ventilation fan, comprising an overall formwork frame, a pair of main steel beams, multiple secondary steel beams, and multiple steel columns. The multiple secondary steel beams are fixed between the pair of main steel beams, and the multiple steel columns are arranged in two groups. A group of steel columns is fixed to the lower side of each main steel beam, and both ends of the secondary steel beams are fixedly connected to the overall formwork frame.
[0006] As a preferred technical solution of this utility model, it also includes two bottom-type steel beams, each of which is fixed to the lower end of a corresponding set of steel columns.
[0007] As a preferred technical solution of this utility model, a longitudinal steel beam is connected between the middle parts of each group of steel columns.
[0008] As a preferred technical solution of this utility model, inter-column supports are arranged crosswise between the steel columns at both ends.
[0009] As a preferred technical solution of this utility model, steel pipes are fixed at 1 / 3 and 2 / 3 of the column height of the steel column, and the steel pipes are connected to the overall formwork.
[0010] In a preferred embodiment of this invention, the secondary steel beam and the main steel beam are fixed together by U-bolts.
[0011] In a preferred embodiment of this invention, the main steel beam and the steel column are fixed by welding.
[0012] As a preferred technical solution of this utility model, the included angle between the two column supports is controlled between 35° and 55°.
[0013] The beneficial effects of this utility model are: The formwork system for pouring concrete across a ventilation fan of this utility model, through the load-bearing system formed by setting up secondary steel beams, main steel beams, steel columns, and bottom steel beams, as well as the stability system formed by longitudinal steel beams, inter-column supports, and connection with the overall structure, enables concrete construction across the ventilation fan, which is safe, reliable, and convenient to construct. Attached Figure Description
[0014] The accompanying drawings, which are included to provide a further understanding of the present invention and constitute a part of this invention, illustrate exemplary embodiments of the present invention and, together with the description thereof, serve to explain the present invention and do not constitute an undue limitation thereof. In the drawings: Figure 1 This is a plan view of a formwork system for pouring concrete across a ventilation fan, according to the present invention.
[0015] Figure 2 This is an elevation view of a formwork system for pouring concrete across a ventilation fan, according to the present invention.
[0016] Figure 3 This is a cross-sectional view of a formwork system for pouring concrete across a ventilation fan, according to the present invention.
[0017] In the diagram, 1. secondary steel beam, 2. main steel beam, 3. steel column, 4. integral formwork, 5. bottom steel beam, 6. longitudinal steel beam, 7. inter-column bracing, 8. steel pipe. Detailed Implementation
[0018] The technical solution of this utility model will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0019] Example 1 like Figure 1 As shown, the present invention provides a formwork system for pouring concrete across a ventilation fan, comprising an integral formwork 4, a pair of main steel beams 2, multiple secondary steel beams 1, and multiple steel columns 3. The multiple secondary steel beams 1 are fixed between the pair of main steel beams 2, and the multiple steel columns 3 are arranged in two groups. A group of steel columns 3 is fixed to the lower side of each main steel beam 2, and the two ends of the secondary steel beams 1 are fixedly connected to the integral formwork 4.
[0020] The secondary steel beam 1 spans the ventilation fan laterally, using 22-type I-beams. The spacing is consistent with the spacing of the scaffolding to be erected above (generally 900mm). The length is the span of the steel column 3 plus twice the spacing between adjacent uprights of the overall formwork 4, facilitating the connection of one end of the secondary steel beam 1 to the overall formwork 4.
[0021] The main steel beam 2, located longitudinally beneath the secondary steel beam 1, is made of type 22 I-beams and extends 300mm beyond the steel columns 3 at both ends. The secondary steel beam 1 and the main steel beam 2 are fixed together using U-bolts. The steel columns 3 are made of 100mm × 6mm square steel, spaced twice the spacing of the secondary steel beams 1 (generally 1800mm). The main steel beam 2 and the steel columns 3 are fixed together by welding.
[0022] Example 2 like Figure 1 As shown in Example 1, Example 2, a formwork system for pouring concrete across a ventilation fan, also includes an integral formwork 4, a pair of main steel beams 2, multiple secondary steel beams 1, and multiple steel columns 3. The multiple secondary steel beams 1 are fixed between the pair of main steel beams 2, and the multiple steel columns 3 are arranged in two groups. A group of steel columns 3 is fixed to the lower side of each main steel beam 2, and the two ends of the secondary steel beams 1 are fixedly connected to the integral formwork 4.
[0023] The secondary steel beam 1 spans the ventilation fan laterally, using 22-type I-beams. The spacing is consistent with the spacing of the scaffolding to be erected above (generally 900mm). The length is the span of the steel column 3 plus twice the spacing between adjacent uprights of the overall formwork 4, facilitating the connection of one end of the secondary steel beam 1 to the overall formwork 4.
[0024] The main steel beam 2, located longitudinally beneath the secondary steel beam 1, is made of type 22 I-beams and extends 300mm beyond the steel columns 3 at both ends. The secondary steel beam 1 and the main steel beam 2 are fixed together using U-bolts. The steel columns 3 are made of 100mm × 6mm square steel, spaced twice the spacing of the secondary steel beams 1 (generally 1800mm). The main steel beam 2 and the steel columns 3 are fixed together by welding.
[0025] like Figure 2 As shown, unlike Embodiment 1, Embodiment 2 of this utility model, a formwork system for pouring concrete across a ventilation fan, also includes two bottom-type steel beams 5, each of which is fixed to the lower end of a corresponding set of steel columns 3.
[0026] like Figure 2 As shown, the bottom-mounted steel beam 5 arranged at the bottom of the steel column 3 is used to transfer the load of the steel column 3 and improve the overall integrity. It is made of 22-type I-beams, with a length that is 500mm wider than the steel columns 3 at both ends. The steel column 3 and the bottom-mounted steel beam 5 are fixed by welding.
[0027] Example 3 like Figure 1 As shown in Example 1, Example 3, a formwork system for pouring concrete across a ventilation fan, also includes an integral formwork 4, a pair of main steel beams 2, multiple secondary steel beams 1, and multiple steel columns 3. The multiple secondary steel beams 1 are fixed between the pair of main steel beams 2, and the multiple steel columns 3 are arranged in two groups. A group of steel columns 3 is fixed to the lower side of each main steel beam 2, and the two ends of the secondary steel beams 1 are fixedly connected to the integral formwork 4.
[0028] The secondary steel beam 1 spans the ventilation fan laterally, using 22-type I-beams. The spacing is consistent with the spacing of the scaffolding to be erected above (generally 900mm). The length is the span of the steel column 3 plus twice the spacing between adjacent uprights of the overall formwork 4, facilitating the connection of one end of the secondary steel beam 1 to the overall formwork 4.
[0029] The main steel beam 2, located longitudinally beneath the secondary steel beam 1, is made of type 22 I-beams and extends 300mm beyond the steel columns 3 at both ends. The secondary steel beam 1 and the main steel beam 2 are fixed together using U-bolts. The steel columns 3 are made of 100mm × 6mm square steel, spaced twice the spacing of the secondary steel beams 1 (generally 1800mm). The main steel beam 2 and the steel columns 3 are fixed together by welding.
[0030] like Figure 2 As shown, unlike Embodiment 1, Embodiment 3 of this utility model, a formwork system for pouring concrete across a ventilation fan, further includes two bottom-type steel beams 5, each bottom-type steel beam 5 being fixed to the lower end of a corresponding set of steel columns 3; a longitudinal steel beam 6 is connected between the middle parts of each set of steel columns 3.
[0031] like Figure 2 As shown, the lower-lying steel beam 5 at the bottom of steel column 3 is used to transfer the load of steel column 3 and improve the overall integrity. It is made of 22mm I-beam, with a length extending 500mm beyond each end of steel column 3. Steel column 3 is welded to the lower-lying steel beam 5. A longitudinal steel beam 6, made of 10mm channel steel, is located at half the height of steel column 3. The longitudinal steel beam 6 is fixed to steel column 3 with U-bolts. The main function of the longitudinal steel beam 6 is to ensure the longitudinal stability of the system.
[0032] Example 4 like Figure 1 As shown in Example 1, Example 4, a formwork system for pouring concrete across a ventilation fan, also includes an integral formwork 4, a pair of main steel beams 2, multiple secondary steel beams 1, and multiple steel columns 3. The multiple secondary steel beams 1 are fixed between the pair of main steel beams 2, and the multiple steel columns 3 are arranged in two groups. A group of steel columns 3 is fixed to the lower side of each main steel beam 2, and the two ends of the secondary steel beams 1 are fixedly connected to the integral formwork 4.
[0033] The secondary steel beam 1 spans the ventilation fan laterally, using 22-type I-beams. The spacing is consistent with the spacing of the scaffolding to be erected above (generally 900mm). The length is the span of the steel column 3 plus twice the spacing between adjacent uprights of the overall formwork 4, facilitating the connection of one end of the secondary steel beam 1 to the overall formwork 4.
[0034] The main steel beam 2, located longitudinally beneath the secondary steel beam 1, is made of type 22 I-beams and extends 300mm beyond the steel columns 3 at both ends. The secondary steel beam 1 and the main steel beam 2 are fixed together using U-bolts. The steel columns 3 are made of 100mm × 6mm square steel, spaced twice the spacing of the secondary steel beams 1 (generally 1800mm). The main steel beam 2 and the steel columns 3 are fixed together by welding.
[0035] like Figure 2 As shown, unlike Embodiment 1, Embodiment 4 of this utility model, a formwork system for pouring concrete across a ventilation fan, further includes two bottom-type steel beams 5, each bottom-type steel beam 5 being fixed to the lower end of a corresponding set of steel columns 3; longitudinal steel beams 6 are connected between the middle parts of each set of steel columns 3; and inter-column supports 7 are arranged crosswise between the steel columns 3 at both ends.
[0036] like Figure 2 As shown, the lower-lying steel beam 5 at the bottom of steel column 3 is used to transfer the load of steel column 3 and improve the overall integrity. It is made of 22mm I-beams, with a length extending 500mm beyond each end of steel column 3. Steel column 3 is welded to the lower-lying steel beam 5. A longitudinal steel beam 6, made of 10mm channel steel, is installed at half the column height of steel column 3. The longitudinal steel beam 6 is fixed to steel column 3 with U-bolts. Inter-column bracing 7 is installed at both ends of steel column 3, using two X-shaped 48mm steel pipes. The main function of the longitudinal steel beam 6 and the inter-column bracing 7 is to ensure the longitudinal stability of the system.
[0037] Example 5 like Figure 1 As shown in Example 1, Example 5, a formwork system for pouring concrete across a ventilation fan, also includes an integral formwork 4, a pair of main steel beams 2, multiple secondary steel beams 1, and multiple steel columns 3. The multiple secondary steel beams 1 are fixed between the pair of main steel beams 2. The multiple steel columns 3 are arranged in two groups, with a group of steel columns 3 fixed to the lower side of each main steel beam 2. The two ends of the secondary steel beams 1 are fixedly connected to the integral formwork 4.
[0038] The secondary steel beam 1 spans the ventilation fan laterally, using 22-type I-beams. The spacing is consistent with the spacing of the scaffolding to be erected above (generally 900mm). The length is the span of the steel column 3 plus twice the spacing between adjacent uprights of the overall formwork 4, facilitating the connection of one end of the secondary steel beam 1 to the overall formwork 4.
[0039] The main steel beam 2, located longitudinally beneath the secondary steel beam 1, is made of type 22 I-beams and extends 300mm beyond the steel columns 3 at both ends. The secondary steel beam 1 and the main steel beam 2 are fixed together using U-bolts. The steel columns 3 are made of 100mm × 6mm square steel, spaced twice the spacing of the secondary steel beams 1 (generally 1800mm). The main steel beam 2 and the steel columns 3 are fixed together by welding.
[0040] like Figure 2 and Figure 3 As shown, unlike Embodiment 1, Embodiment 5 of this utility model, a formwork system for pouring concrete across a ventilation fan, further includes two bottom-type steel beams 5, each bottom-type steel beam 5 being fixed to the lower end of a corresponding set of steel columns 3; longitudinal steel beams 6 are connected between the middle parts of each set of steel columns 3; inter-column supports 7 are arranged crosswise between two adjacent steel columns 3; the included angle between the two inter-column supports 7 is controlled between 35° and 55°.
[0041] like Figure 2 As shown, the bottom-mounted steel beam 5 at the base of steel column 3 is used to transfer the load of steel column 3 and improve the overall integrity. It is made of 22mm I-beams, with a length extending 500mm beyond each end of steel column 3. Steel column 3 and bottom-mounted steel beam 5 are welded together. A longitudinal steel beam 6, made of 10mm channel steel, is installed at half the column height of steel column 3. The longitudinal steel beam 6 is fixed to steel column 3 with U-bolts. Inter-column bracing 7 is installed at both ends of steel column 3, using 48mm steel pipes arranged in two X-shapes, with the angle between the beam and the horizontal controlled between 35° and 55°. The main function of the longitudinal steel beam 6 and inter-column bracing 7 is to ensure the longitudinal stability of the system.
[0042] Example 6 like Figure 1 As shown in Example 1, Example 6, a formwork system for pouring concrete across a ventilation fan, also includes an integral formwork 4, a pair of main steel beams 2, multiple secondary steel beams 1, and multiple steel columns 3. The multiple secondary steel beams 1 are fixed between the pair of main steel beams 2, and the multiple steel columns 3 are arranged in two groups. A group of steel columns 3 is fixed to the lower side of each main steel beam 2, and the two ends of the secondary steel beams 1 are fixedly connected to the integral formwork 4.
[0043] The secondary steel beam 1 spans the ventilation fan laterally, using 22-type I-beams. The spacing is consistent with the spacing of the scaffolding to be erected above (generally 900mm). The length is the span of the steel column 3 plus twice the spacing between adjacent uprights of the overall formwork 4, facilitating the connection of one end of the secondary steel beam 1 to the overall formwork 4.
[0044] The main steel beam 2, located longitudinally beneath the secondary steel beam 1, is made of type 22 I-beams and extends 300mm beyond the steel columns 3 at both ends. The secondary steel beam 1 and the main steel beam 2 are fixed together using U-bolts. The steel columns 3 are made of 100mm × 6mm square steel, spaced twice the spacing of the secondary steel beams 1 (generally 1800mm). The main steel beam 2 and the steel columns 3 are fixed together by welding.
[0045] like Figure 2 and Figure 3 As shown, unlike Embodiment 1, Embodiment 6 of this utility model, a formwork system for pouring concrete across a ventilation fan, further includes two bottom-type steel beams 5, each bottom-type steel beam 5 being fixed to the lower end of a corresponding set of steel columns 3; longitudinal steel beams 6 are connected between the middle parts of each set of steel columns 3; column supports 7 are arranged crosswise between the steel columns 3 at both ends; the included angle between the two column supports 7 is controlled between 35° and 55°; and multiple steel pipes 8 are provided on the side of the steel columns 3.
[0046] like Figure 2 As shown, the bottom-mounted steel beam 5 at the base of steel column 3 is used to transfer the load of steel column 3 and improve the overall integrity. It is made of 22mm I-beams, with a length extending 500mm beyond each end of steel column 3. Steel column 3 and bottom-mounted steel beam 5 are welded together. A longitudinal steel beam 6, made of 10mm channel steel, is installed at half the column height of steel column 3. The longitudinal steel beam 6 is fixed to steel column 3 with U-bolts. Inter-column bracing 7 is installed at both ends of steel column 3, using 48mm steel pipes arranged in two X-shapes, with the angle between the beam and the horizontal controlled between 35° and 55°. The main function of the longitudinal steel beam 6 and inter-column bracing 7 is to ensure the longitudinal stability of the system.
[0047] like Figure 3 As shown, steel columns 3 are connected to the overall formwork 4 by 48mm steel pipes 8 at 1 / 3 and 2 / 3 of their height, with the distance between the main nodes of the steel pipes 8 and the overall formwork 4 not exceeding 200mm. The maximum outer edge distance between the steel column 3 and the ventilation fan should be greater than 200mm. The two ends of the secondary steel beam 1 are connected to the overall formwork, and the distance between the secondary steel beam 1 and the highest point of the ventilation fan should be greater than 200mm. The connection between the steel pipes 8, the secondary steel beam 1, and the overall formwork 4 primarily ensures the lateral stability of the system.
[0048] The foregoing description illustrates and describes several preferred embodiments of the utility model. However, as previously stated, it should be understood that the utility model is not limited to the forms disclosed herein and should not be construed as excluding other embodiments. It can be used in various other combinations, modifications, and environments, and can be altered within the scope of the utility model concept described herein through the foregoing teachings or the technology or knowledge in related fields. Any modifications and variations made by those skilled in the art that do not depart from the spirit and scope of the utility model should be within the protection scope of the appended claims.
Claims
1. A formwork system for pouring concrete across a ventilation fan, characterized in that, It includes an overall formwork (4), a pair of steel main beams (2), multiple steel secondary beams (1) and multiple steel columns (3). The multiple steel secondary beams (1) are fixed between the pair of steel main beams (2). The multiple steel columns (3) are arranged in two groups. A group of steel columns (3) is fixed to the lower side of each steel main beam (2). The two ends of the steel secondary beams (1) are fixedly connected to the overall formwork (4).
2. The formwork system for pouring concrete across a ventilation fan according to claim 1, characterized in that, It also includes two bottom-mounted steel beams (5), each of which is fixed to the lower end of a corresponding set of steel columns (3).
3. The formwork system for pouring concrete across a ventilation fan according to claim 2, characterized in that, A longitudinal steel beam (6) is connected between the middle parts of each group of steel columns (3).
4. The formwork system for pouring concrete across a ventilation fan according to claim 3, characterized in that, Intercolumn bracing (7) is arranged between the steel columns (3) at both ends.
5. The formwork system for pouring concrete across a ventilation fan according to claim 4, characterized in that, Steel pipes (8) are fixed at 1 / 3 and 2 / 3 of the height of the steel column (3), and the steel pipes (8) are connected to the overall formwork.
6. The formwork system for pouring concrete across a ventilation fan according to claim 5, characterized in that, The secondary steel beam (1) and the main steel beam (2) are fixed together by U-bolts.
7. The formwork system for pouring concrete across a ventilation fan according to claim 6, characterized in that, The main steel beam (2) and the steel column (3) are fixed by welding.
8. The formwork system for pouring concrete across a ventilation fan according to claim 7, characterized in that, The included angle between the two column supports (7) is controlled between 35° and 55°.