AI Technical Summary

Technical Problem

[0004]本实用新型的目的在于提供一种固定基座式幕墙施工三维吊装系统,解决现有的问题

Benefits of technology

实现三维吊装:通过前支臂实现前后移动、钢梁实现左右移动、卷扬机实现上下移动,无需挪动吊装架体即可完成三维吊装作业,灵活性强。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224917383U_ABST
    Figure CN224917383U_ABST
Patent Text Reader

Abstract

The utility model discloses a fixed base formula curtain wall construction three -dimensional hoist system relates to building construction equipment technical field. The utility model discloses a kind of hoisting frame body, three sets of hoist pulley subassembly, a piece of steel beam, two pieces of steel beam sleeve, bolt subassembly and a set of finished product hanging type winch;The front supporting arm of hoisting frame body is as running track, hoist pulley subassembly is installed to realize the front and back movement of the hoisted article;Steel beam is installed between the front supporting arm of two hoisting frame bodies by steel beam sleeve and bolt subassembly, hoist pulley subassembly is installed on steel beam to realize the left and right movement of the hoisted article;Finished product hanging type winch is installed on hoist pulley, provides power for hoisting to realize the up and down hoisting of the hoisted article.The utility model realizes front and back movement by front supporting arm, realizes left and right movement by steel beam, realizes up and down movement by winch, without moving hoisting frame body, three -dimensional hoisting operation can be completed, and it is strong in flexibility.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of building construction equipment technology, and in particular relates to a three-dimensional hoisting system for fixed-base curtain wall construction. Background Technology

[0002] In the construction of building curtain walls, the hoisting of exterior facade materials is a critical step. Currently, the industry often uses unauthorized methods such as transporting materials using suspended platforms or hoisting materials using winches. Such operations are prone to safety accidents and have low hoisting efficiency, failing to meet the requirements for hoisting precision and flexibility in curtain wall construction.

[0003] To address the aforementioned issues, this utility model provides a three-dimensional hoisting system for building curtain wall construction. This system enables hoisting operations in three dimensions—front-to-back, left-to-right, and up-down—without moving the hoisting frame. It is also simple to install, highly safe, and highly efficient. Utility Model Content

[0004] The purpose of this invention is to provide a three-dimensional hoisting system for fixed-base curtain wall construction, thereby solving existing problems.

[0005] To solve the above-mentioned technical problems, this utility model is achieved through the following technical solution: This utility model relates to a three-dimensional hoisting system for fixed-base curtain wall construction, comprising two hoisting frames, three sets of hoisting pulley assemblies, one steel beam, two steel beam sleeves, bolt assemblies, and one set of prefabricated hanging winches. The front support arm of the hoisting frame serves as a running track for the installation of the hoisting pulley assemblies to achieve the forward and backward movement of the hoisted object. The steel beam is installed between the front support arms of the two hoisting frames via steel beam sleeves and bolt assemblies, and the hoisting pulley assemblies are installed on the steel beam to achieve the left and right movement of the hoisted object. The prefabricated hanging winch is installed on the hoisting pulleys to provide power for hoisting and to achieve the vertical lifting of the hoisted object.

[0006] In one embodiment, the hoisting frame includes a front support, a rear support, a front support arm, a rear support arm, a wire rope, turnbuckles, and a counterweight. The front support includes a lower front support, an upper front support bolted to the lower front support, and a top front support bolted to the upper front support. The rear support includes a lower rear support and an upper rear support bolted to the lower rear support. The front and rear supports are connected by a bolt assembly to secure the rear support arm. The front support is bolted to the front end of the front support at the same horizontal level. Pulleys are provided at the front end of the front support arm, the rear end of the rear support arm, and the top of the top front support. One end of the wire rope is fixed to the front end of the front support arm, and the other end passes through the top pulley of the top front support and the rear pulley of the rear support, and is finally connected to the turnbuckle fixed to the rear support arm. The tension of the wire rope is adjusted and tightened by the turnbuckles.

[0007] In one embodiment, the materials of the front support arm and steel beam of the hoisting frame include steel pipes, I-beams, or H-beams.

[0008] In one embodiment, the hanging pulley assembly includes two pulley seats, a rotating roller, and two sets of bolt assemblies, with each set of bolt assemblies sequentially positioned on one of the two pulley seats. The rotating roller is fitted onto the circumferential side of the bolt between the two upper pulley seats. The steel beam sleeve includes a square steel tube and steel lugs fixed to the side wall of the square steel tube. The steel lugs are fitted onto the circumferential side of the bolt between the two lower pulley seats.

[0009] In one embodiment, the hoisting pulley assembly is secured to the front support arm or steel beam by its own grooved pulley, enabling movement along the front support arm or steel beam; the distance between the two sets of hoisting frames matches the length of the steel beam and can be flexibly adjusted according to the weight of the hoisted object.

[0010] In one embodiment, the steel beam and the steel beam sleeve are fitted together by insertion, and the length and width of the inner cavity of the steel beam sleeve are 2mm to 3mm larger than the length and width of the outer surface of the steel beam.

[0011] The front and rear supports of the hoisting frame are not limited to counterweights. They can be fixed by means of double beam clamps or single beam diagonal steel wire ropes, depending on the structural characteristics of the building. The system can be used in conjunction with a suspended platform or can operate independently.

[0012] This utility model has the following beneficial effects: Achieving three-dimensional hoisting: The front boom moves forward and backward, the steel beam moves left and right, and the winch moves up and down, allowing three-dimensional hoisting operations to be completed without moving the hoisting frame, offering high flexibility.

[0013] High safety: The hoisting frame is fixed in a flexible and stable manner, and the connection of each component is reliable, avoiding safety hazards caused by improper operation.

[0014] Efficiency Improvement: Simple installation and quick commissioning significantly improve the hoisting efficiency of curtain wall construction.

[0015] Wide adaptability: It can be used with suspended platforms or operated independently, and is suitable for curtain wall construction scenarios of different building structures.

[0016] Of course, any product implementing this utility model does not necessarily need to achieve all of the advantages described above at the same time. Attached Figure Description

[0017] To more clearly illustrate the technical solutions of the embodiments of this utility model, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0018] Figure 1 This is a schematic diagram of the overall structure of a three-dimensional hoisting system for fixed-base curtain wall construction. Figure 2 for Figure 1 Schematic diagram of the rear support structure in the A-direction; Figure 3 for Figure 1 Schematic diagram of the front support structure in the B direction; Figure 4 for Figure 1 Sectional view of AA in the middle; Figure 5 This is a front view of the hanging pulley assembly in this utility model; Figure 6 This is a side view of the hanging pulley assembly in this utility model; Figure 7 This is a front view of the steel beam sleeve in this utility model; Figure 8 This is a side view of the steel beam sleeve in this utility model.

[0019] The attached diagram lists the components represented by each number as follows: 1. Counterweight; 2. Lower rear support; 4. Upper rear support; 5. Turnbuckle; 6. Wire rope; 7. Rear outrigger; 8. Lower front support; 10. Upper front support; 11. Top front support; 12. Front outrigger; 13. Pulley assembly; 1301. Pulley seat; 1302. Rotating drum; 1303. Bolt assembly; 14. Steel beam; 15. Steel beam sleeve; 1501. Steel lug; 1502. Square steel pipe; 17. Finished hanging winch. Detailed Implementation

[0020] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0021] In the description of this utility model, it should be understood that the terms "upper", "middle", "outer", "inner", etc., which indicate orientation or positional relationship, are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the components or elements referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model.

[0022] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installed," "equipped with," "connected," etc., should be interpreted broadly. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be a connection within two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0023] Please see Figures 1-8 As shown, this utility model is a three-dimensional hoisting system for fixed-base curtain wall construction, including two hoisting frames, three sets of hoisting pulley assemblies 13, one steel beam 14, two steel beam sleeves 15, bolt assemblies, and one set of prefabricated hanging winches 17; the front support arm 12 of the hoisting frame serves as the running track for the hoisting pulley assembly 13 to be installed to realize the forward and backward movement of the hoisted object; the steel beam 14 is installed between the front support arms 12 of the two hoisting frames through the steel beam sleeves 15 and bolt assemblies, and the hoisting pulley assembly 13 is installed on the steel beam 14 to realize the left and right movement of the hoisted object; the prefabricated hanging winch 17 is installed on the hoisting pulleys to provide power for hoisting to realize the up and down lifting of the hoisted object.

[0024] Furthermore, the hoisting frame includes a front support, a rear support, a front boom 12, a rear boom 7, a wire rope 6, turnbuckles 5, and a counterweight 1; the front support includes a lower front support 8, an upper front support 10 bolted to the lower front support 8, and a top front support 11 bolted to the upper front support 10; the rear support includes a lower rear support 2, and an upper rear support 4 bolted to the lower rear support 2. The front support and the rear support... The rear support arm 7 is fixed together with the frame by bolt assembly. The front support arm 12 is fixed to the front end of the front support arm 12 at the same horizontal direction by bolt assembly. The front end of the front support arm 12, the rear end of the rear support arm 7 and the top of the front support arm 11 are all equipped with pulleys. One end of the wire rope 6 is fixed to the front end of the front support arm 12, and the other end passes through the top pulley of the front support arm 11 and the rear pulley of the rear support arm 7 in sequence, and is finally fixedly connected to the turnbuckle 5 fixed on the rear support arm 7. The tension of the wire rope 6 is adjusted and tightened by the turnbuckle 5.

[0025] The height of the hoisting frame can be adjusted by using the round holes on the lower rear support 2, upper rear support 4, lower front support 8, and upper front support 10, combined with bolt assemblies.

[0026] In this embodiment, the materials of the front support arm 12 and steel beam 14 of the fixed base curtain wall construction three-dimensional hoisting system include steel pipes, I-beams or H-beams.

[0027] Furthermore, the shearing pulley assembly 13 includes two pulley seats 1301, a rotating roller 1302, and two sets of bolt assemblies 1303. The two sets of bolt assemblies are respectively positioned on the two pulley seats 1301. The rotating roller 1302 is sleeved on the bolt periphery between the two upper pulley seats 1301. The steel beam sleeve 15 includes a square steel tube 1502 and steel lugs 1501 fixed to the side wall of the square steel tube 1502. The steel lugs 1501 are sleeved on the bolt periphery between the two lower pulley seats 1301.

[0028] Furthermore, the hoisting pulley assembly 13 is secured to the front support arm 12 or the steel beam 14 by its own grooved pulley, enabling it to move along the front support arm 12 or the steel beam 14; the distance between the two hoisting frames is matched with the length of the steel beam 14, and can be flexibly adjusted according to the weight of the hoisted object.

[0029] Furthermore, the steel beam 14 and the steel beam sleeve 15 are fitted together by insertion, and the length and width of the inner cavity of the steel beam sleeve 15 are 2mm to 3mm larger than the length and width of the outer surface of the steel beam.

[0030] Example 2 Please see Figures 1-8 As shown in the figure, this embodiment is an installation process for a three-dimensional hoisting system for fixed-base curtain wall construction. The steps are as follows: Step 1: Assemble the hoisting frame: Use bolt assemblies to connect the lower rear support 2 to the upper rear support 4 and the rear support arm 7. Similarly, assemble the front support (lower front support 8, upper front support 10, top front support 11, and front support arm 12), and adjust the frame height according to the hoisting height through the bolt holes.

[0031] Step 2: Connect and tension the wire rope: Connect the rear support arm 7, the top support of the front support 11, and the front support arm 12 with the wire rope 6, and tension the wire rope with turnbuckles 5.

[0032] Step 3: Install the counterweights: Stack the counterweights 1 one by one and thread them onto the round tube of the lower bracket 2 of the rear bracket.

[0033] Step 4: Install the forward and backward movement assembly: Install the lifting pulley assembly 13 on the front support arm 12 to enable the suspended item to move forward and backward.

[0034] Step 5: Install the left and right movement assembly: Connect the steel lugs 1501 of the steel beam sleeve 15 to the bolt assembly 1303 of the lifting pulley assembly 13, insert the steel beam 14 into the steel beam sleeve 15 and fix it with the bolt assembly, and install the lifting pulley assembly 13 on the steel beam 14 to realize the left and right movement of the suspended object.

[0035] Step Six: Install the winch: Install the prefabricated hanging winch 17 onto the lifting pulley assembly 13 to achieve vertical lifting. The prefabricated hanging winch provides power for lifting, enabling the vertical lifting of objects.

[0036] Example 3 This embodiment describes the component parameters and connections of a three-dimensional hoisting system for fixed-base curtain wall construction: Counterweight 1: Made of concrete blocks with a central hole, it is stacked one by one and threaded through the four round pipes of the lower support 2 of the rear support, arranged in four vertical columns. The number can be increased or decreased according to the lifting weight to enhance the stability of the frame.

[0037] The lower rear support bracket 2 is made of 80×80×4 steel square tubing; the upper rear support bracket 4 is made of 70×70×4 steel square tubing; the two are connected by bolt assemblies (8.8 grade high-strength bolts, with nuts, flat washers, and spring washers).

[0038] Rear support arm 7: The material is 70×70×4 steel square tube, which is bolted to the upper support 4 of the rear bracket.

[0039] The front support lower bracket 8, the front support upper bracket 10, and the front support top bracket 11 are structurally identical to the rear support lower bracket 2 and the rear support upper bracket 4, respectively. The front support top bracket 11 is made of 80×80×4 steel square tube. The front support arm 12 is made of 80×80×4 steel square tube and is connected to the front support top bracket 11.

[0040] Wire rope 6: 8.3mm in diameter (structure 4×31WS+FC), connects the rear support arm 7, the top support arm 11 of the front support, and the front support arm 12, and is tensioned by turnbuckle 5.

[0041] The hanging pulley assembly 13 consists of a pulley seat (steel) 1301, a rotating drum (steel) 1302, and a bolt assembly 1303. It moves by being secured to the front support arm 12 or the steel beam 14 by a grooved pulley.

[0042] Steel beam 14: The material is 80×80×4 square steel tube; Steel beam sleeve 15: It is welded from steel lug 1501 and square steel tube 1502 (90×90×4). The steel beam 14 is inserted into the steel beam sleeve 15 and fixed by bolt assembly.

[0043] Finished hanging winch 17: The upper hook is connected to the bolt assembly 1303 of the hanging pulley assembly 13, and the lower hook suspends the hoisted object, providing the hoisting force.

[0044] In the description of this specification, references to terms such as "an embodiment," "example," and "specific example" indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of the present invention. In this specification, illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.

[0045] The preferred embodiments of this utility model disclosed above are merely illustrative of the present utility model. These preferred embodiments do not exhaustively describe all details, nor do they limit the utility model to the specific implementations described. Clearly, many modifications and variations can be made based on the content of this specification. This specification selects and specifically describes these embodiments to better explain the principles and practical applications of this utility model, thereby enabling those skilled in the art to better understand and utilize it. This utility model is limited only by the claims and their full scope and equivalents.

Claims

1. A three-dimensional hoisting system for fixed-base curtain wall construction, characterized in that, The system includes two sets of hoisting frames, three sets of hoisting pulley assemblies (13), one steel beam (14), two steel beam sleeves (15), bolt assemblies, and one set of prefabricated hanging winches (17). The front support arm (12) of the hoisting frame serves as the running track for the hoisting pulley assembly (13) to be installed to realize the forward and backward movement of the hoisted item. The steel beam (14) is installed between the front support arms (12) of the two hoisting frames through the steel beam sleeve (15) and bolt assemblies. The hoisting pulley assembly (13) is installed on the steel beam (14) to realize the left and right movement of the hoisted item. The prefabricated hanging winch (17) is installed on the hoisting pulleys to provide power for hoisting to realize the up and down lifting of the hoisted item.

2. The three-dimensional hoisting system for fixed-base curtain wall construction according to claim 1, characterized in that, The hoisting frame includes a front support, a rear support, a front boom (12), a rear boom (7), a wire rope (6), turnbuckles (5), and a counterweight (1); the front support includes a lower front support (8), an upper front support (10) bolted to the lower front support (8), and a top front support (11) bolted to the upper front support (10); the rear support includes a lower rear support (2) bolted to the lower rear support (2), and an upper rear support (4) bolted to the lower rear support (2). The front and rear supports are connected by a... The rear support arm (7) is fixed together by bolt assembly. The front end of the front support arm (12) is fixed to the front support arm (12) by bolt assembly at the same horizontal direction. The front end of the front support arm (12), the rear end of the rear support arm (7) and the top of the top support of the front support arm (11) are all provided with pulleys. One end of the wire rope (6) is fixed to the front end of the front support arm (12), and the other end passes through the top pulley of the top support of the front support arm (11) and the rear pulley of the rear support arm (7) in sequence, and is finally fixedly connected to the turnbuckle (5) fixed on the rear support arm (7). The tension of the wire rope (6) is adjusted and tightened by the turnbuckle (5).

3. The three-dimensional hoisting system for fixed-base curtain wall construction according to claim 1, characterized in that, The materials of the front support arm (12) and steel beam (14) of the hoisting frame include steel pipes, I-beams or H-beams.

4. The three-dimensional hoisting system for fixed-base curtain wall construction according to claim 1, characterized in that, The hanging pulley assembly (13) includes two pulley seats (1301), a rotating drum (1302), and two sets of bolt assemblies (1303). The two sets of bolt assemblies are respectively connected to the two pulley seats (1301). The rotating drum (1302) is sleeved on the bolt periphery between the two upper pulley seats (1301). The steel beam sleeve (15) includes a square steel tube (1502) and a steel lug (1501) fixed on the side wall of the square steel tube (1502). The steel lug (1501) is sleeved on the bolt periphery between the two lower pulley seats (1301).

5. A three-dimensional hoisting system for fixed-base curtain wall construction according to claim 1, characterized in that, The hoisting pulley assembly (13) is secured to the front support arm (12) or steel beam (14) by its own grooved pulley, thereby enabling movement along the front support arm (12) or steel beam (14); the distance between the two sets of hoisting frames is matched with the length of the steel beam (14), and can be flexibly adjusted according to the weight of the hoisted object.

6. The three-dimensional hoisting system for fixed-base curtain wall construction according to claim 1, characterized in that, The steel beam (14) and the steel beam sleeve (15) are fitted together by inserting into each other. The length and width of the inner cavity of the steel beam sleeve (15) are 2mm to 3mm larger than the length and width of the outer surface of the steel beam.