AI Technical Summary

Technical Problem

然而,这种人工操作的方式存在诸多弊端

Benefits of technology

本实用新型实施例的贵金属回收设备包括机架,所述机架设置有取料换盘装置、第一称重装置、输送装置、熔化装置、冷却装置和第二称重装置,取料换盘装置用于将纸箱的箱盖打开后从纸箱中取出装载有贵金属的第二托盘、供给第一托盘且将第一托盘移送至第一称重装置中进行称重、将第二托盘中的贵金属转移至第一托盘内、以及将装载有贵金属的第一托盘移送至第一称重装置中进行称重以及待称重后将装载有贵金属的第一托盘移送至所述输送装置,输送装置用于将装载有贵金属的第一托盘输送至熔化装置,熔化装置用于从输送装置中的第一托盘中取出贵金属,将其熔化后移送至冷却装置中进行冷却,第二称重装置用于从冷却装置中取出已冷却的贵金属,对其贵金属称重后将其移送至被输送装置输送的同一第一托盘内,自动实现回收贵金属,替代人工,避免人工操作方式带来的弊端。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224917859U_ABST
    Figure CN224917859U_ABST
Patent Text Reader

Abstract

The utility model provides a kind of noble metal recovery equipment, it is related to noble metal processing technical field, and noble metal recovery equipment includes rack, rack is equipped with material taking and tray changing device, first weighing device, conveying device, melting device, cooling device and second weighing device, material taking and tray changing device can open carton lid, take out the second tray with noble metal, supply first tray and remove to first weighing device weighing, after noble metal is transferred from second tray to first tray, weigh again, finally first tray is removed to conveying device, conveying device is sent to first tray to melting device, after melting device is taken out noble metal from first tray, remove to cooling device cooling, second weighing device is taken out after cooling noble metal from cooling device, weigh again, remove back to the same first tray, the equipment can automatically recycle noble metal, replace manual work, avoid manual operation drawbacks.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of precious metal processing technology, and in particular to a precious metal recycling device. Background Technology

[0002] In existing precious metal (such as gold and silver) recycling processes, manual operation is typically employed. Specifically, operators must first open the lid of a cardboard box, remove the precious metal, and then melt it in a furnace. After melting, the metal is poured into a cooling device to cool, ultimately completing the recycling process. The entire process relies entirely on manual labor. However, this manual method has many drawbacks. For example, due to the high economic value of precious metals, there is a risk of theft during manual operation. This could not only lead to economic losses for the company but also disrupt the normal operation of precious metal recycling. Furthermore, manual recycling is inefficient and cannot meet the growing demand for precious metal recycling. Therefore, the existing manual operation method is no longer sufficient to meet the development needs of the precious metal recycling industry and urgently requires improvement. Utility Model Content

[0003] The purpose of this invention is to provide a precious metal recycling device to achieve automatic recycling of precious metals.

[0004] To achieve the above objectives, the technical solution of this utility model embodiment is as follows: A precious metal recycling device, comprising: The frame is equipped with a material handling and changing device, a first weighing device, a conveying device, a melting device, a cooling device, and a second weighing device. The material handling and pallet changing device is used to open the lid of the carton, take out the second pallet containing precious metals from the carton, supply the first pallet and transfer the first pallet to the first weighing device for weighing, transfer the precious metals in the second pallet to the first pallet, transfer the first pallet containing precious metals to the first weighing device for weighing, and after weighing, transfer the first pallet containing precious metals to the conveying device. The conveying device is used to transport the first pallet loaded with precious metals to the melting device; The melting device is used to take out precious metal from the first tray in the conveying device, melt it, and then transfer it to the cooling device for cooling. The second weighing device is used to remove the cooled precious metal from the cooling device, weigh the precious metal, and then transfer it to the same first tray being transported by the conveying device.

[0005] Compared with the prior art, the embodiments of this utility model have at least the following technical effects: The precious metal recycling equipment of this utility model includes a frame, which is equipped with a material handling and tray changing device, a first weighing device, a conveying device, a melting device, a cooling device, and a second weighing device. The material handling and tray changing device is used to open the lid of a carton, take out a second tray loaded with precious metals from the carton, supply a first tray and transfer the first tray to the first weighing device for weighing, transfer the precious metals from the second tray to the first tray, and transfer the first tray loaded with precious metals to the first weighing device for weighing, and after weighing, transfer the first tray loaded with precious metals to the conveying device. The conveying device is used to convey the first tray loaded with precious metals to the melting device. The melting device is used to take out the precious metals from the first tray in the conveying device, melt them, and then transfer them to the cooling device for cooling. The second weighing device is used to take out the cooled precious metals from the cooling device, weigh them, and then transfer them to the same first tray conveyed by the conveying device. This automatically realizes the recycling of precious metals, replaces manual labor, and avoids the drawbacks of manual operation. Attached Figure Description

[0006] Figure 1 This is a schematic diagram of the structure of a precious metal recycling device provided in an embodiment of the present invention; Figure 2 A schematic diagram of an embodiment of a material handling and tray changing device; Figure 3 A schematic diagram of the opening mechanism in one embodiment of the material handling and tray changing device; Figure 4 This is a schematic diagram of the material handling mechanism in one embodiment of the material handling and tray changing device; Figure 5 A schematic diagram of the flipping mechanism in one embodiment of the material handling and tray changing device; Figure 6 This is a schematic diagram of the transfer mechanism in one embodiment of the material handling and tray changing device; Figure 7 This is a schematic diagram of the tray mechanism in one embodiment of the material handling and tray changing device; Figure 8 This is a schematic diagram of the positioning mechanism in one embodiment of the material handling and tray changing device; Figure 9 This is a schematic diagram of the clamping mechanism and the robotic arm mechanism in one embodiment of the melting device; Figure 10 A perspective view of one embodiment of the feeding mechanism; Figure 11 A top view of one embodiment of the feeding mechanism; Figure 12 This is a three-dimensional schematic diagram of another embodiment of the feeding mechanism; Figure 13This is a three-dimensional schematic diagram of another embodiment of the feeding mechanism; Figure 14 This is a schematic diagram of one embodiment of the cooling device; Figure 15 This is a schematic diagram of the cavity assembly and support assembly in one embodiment of the cooling device; Figure 16 This is a schematic diagram showing the relative positions of the receiving member and the supporting member in one embodiment of the cooling device; Figure 17 This is a schematic diagram showing the locations of three adhesive tape points on a cardboard box in the prior art; Figure 18 This is a schematic diagram of one embodiment of the unpacking device; Figure 19 This is a three-dimensional schematic diagram of the box-opening tool mechanism in one embodiment of the box-opening device; Figure 20 This is a front view of the box-opening cutter mechanism in one embodiment of the box-opening device; Figure 21 This is a schematic diagram of the structure of one embodiment of the carton separation device; Figure 22 A schematic diagram of an embodiment of a purity detection device; Figure 23 This is a schematic diagram of an embodiment of a palletizing device.

[0007] Explanation of icon numbers: 10. Material handling and tray changing device; a10. Material handling base; a11. Carton conveyor line; a12. First defective product conveyor line; a13. Second defective product conveyor line; a20. Carton opening mechanism; a21. First carton opening assembly; a22. Second carton opening assembly; a23. Third carton opening assembly; a24. Fourth carton opening assembly; a210. Suction cup; a211. Rotary drive component; a30. Material handling mechanism; a31. First material handling drive component; a32. Second material handling drive component; a33. Third material handling drive component; a34. Material handling clamp; a40. Tilting mechanism; a41. Placement platform; a42. Pallet flipping assembly; a420. Pallet clamping drive component; a421. Pallet flipping drive component; a422. Pallet clamp; a60. Transfer mechanism; a61. First transfer drive component; a62. Second transfer drive component; a63. Third transfer drive; a64, Fourth movement drive; a65, Pallet chuck; a70, Pallet mechanism; a71, First pallet; a72, Fence; a73, Pallet plate; a74, Lifting drive; a80, Carton; a81, Second pallet; a90, Positioning mechanism; a91, Limiting block; a910, First limiting sub-block; a911, Second limiting sub-block; a92, Tightening block; a920, First tightening sub-block; a921, Second tightening sub-block; a93, Tightening drive; 20, First weighing device; 21, Second weighing device; 22, Conveying device; 30, Purity testing device; g10, Workbench; g14, Detector; g16, Purity testing drive assembly; g18, Purity testing robotic arm; 40, Melting device; b10, Clamping base; b20, Crucible; b21, Body; b30, Chuck; b40, Robotic arm mechanism; b50, Gripping drive assembly; b70, Furnace; 50, Feeding mechanism; c10, Feeding base; c11, Feeding port; c12, Discharge chute; c20, Fixing component; c21, First fixing sub-component; c22, Second fixing sub-component; c23, Third arc-shaped extrusion section; c30, Moving component; c31, First moving sub-component; c310, First arc-shaped extrusion section; c32, Second moving sub-component; c320, Second arc-shaped extrusion section; c33, Forming cavity; c40, Guide funnel; c41, Alignment drive component; c60, feeding drive assembly; c61, first feeding drive component; c62, second feeding drive component; c70, guide component; c80, sealing mechanism; c81, sealing component; c82, sealing drive component; c90, unloading mechanism; c91, unloading rod; c92, unloading drive component; c93, adjusting drive component; 60, cooling device; d10, conveying mechanism; d11, conveyor belt;d12, Conveyor drive assembly; d13, First baffle; d14, Second baffle; d15, Divider plate; d16, First channel; d17, Second channel; d20, Cooling chamber mechanism; d21, Chamber assembly; d210, Receiving component; d2100, Feeding end; d2101, Discharge end; d2102, Receiving space; d2103, Feed inlet; d2104, Opening; d211, Guide component; d2 110. Conical guide channel; d212. Lifting drive component; d213. Translation drive component; d22. Support assembly; d220. Support component; d2200. First support sub-plate; d2201. Second support sub-plate; d221. Support drive component; 70. Carton separation device; f10. Belt drive structure; f12. Discharge structure; f14. Separation drive structure; f16. Inlet; f18. Outlet; 80. Unpacking device; e10. Unpacking base; e20. Unpacking cutter mechanism; e21. First cutter assembly; e210. First blade; e211. First blade drive; e22. Second cutter assembly; e220. Second blade; e221. Second blade drive; e23. Third cutter assembly; e230. Third blade; e231. Third blade drive; e30. Unpacking drive mechanism; e31. First linear module; e32. Second linear module; e33. Cutter drive; e81. First tape; e82. Second tape; e83. Third tape; 90. Palletizing device; h10. Machine base; h12. Feeding assembly; h14. Palletizing assembly; h16. Discharge port; h18. Gripper; h20. First palletizing drive; h22. Second palletizing drive. Detailed Implementation

[0008] The technical solution of this utility model will be further described in detail below with reference to the accompanying drawings and specific embodiments. Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this utility model belongs. The terminology used in this specification of this utility model is for the purpose of describing particular embodiments only and is not intended to limit the utility model. In the following description, the expression "some embodiments" refers to a subset of all possible embodiments; however, it should be understood that "some embodiments" can be the same subset or different subsets of all possible embodiments and can be combined with each other without conflict.

[0009] It should also be noted that when an element is referred to as being "fixed to" another element, it can be directly attached to the other element or there may be an intervening element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or there may be an intervening element. The terms "vertical," "horizontal," "inner," "outer," "left," "right," and similar expressions used herein are for illustrative purposes only and do not represent the only possible implementation.

[0010] Please see Figure 1-23 As shown, one embodiment of this utility model provides a precious metal recycling device, specifically including a frame. The frame is equipped with a material handling and tray changing device 10, a first weighing device 20, a conveying device 22, a melting device 40, a cooling device 60, and a second weighing device 21. The material handling and tray changing device 10 opens the lid of a cardboard box a80 and takes out a second tray a81 containing precious metals from the cardboard box a80. The material handling and tray changing device 10 can supply a first tray a71 and transfer the first tray a71 to the first weighing device 20 for weighing. The material handling and tray changing device 10 transfers the precious metals from the second tray a81 to the first tray a71. The material handling and tray changing device 10 then transfers the first tray containing precious metals to the first tray a71. The first pallet a71 is transferred to the first weighing device 20 for weighing. After weighing, the material handling and pallet changing device 10 transfers the first pallet a71 containing the precious metal to the conveying device 22. In this embodiment, the conveying device 22 can be a belt conveyor line. The conveying device 22 conveys the first pallet a71 containing the precious metal to the melting device 40. The melting device 40 takes out the precious metal from the first pallet a71 in the conveying device 22, melts it, and then transfers it to the cooling device 60 for cooling. The second weighing device 21 takes out the cooled precious metal from the cooling device 60, weighs it, and then transfers it to the same first pallet a71 conveyed by the conveying device 22. In the aforementioned scheme, the various devices cooperate to transfer the precious metal from the second tray a81 to the first tray a71 and place it in the first weighing device 20 for weighing. The weight of the first tray a71 can be known in advance by weighing it through the first weighing device 20. When the first weighing device 20 weighs the first tray a71 already loaded with precious metal, it can know the first weight of the precious metal before melting. The second weighing device 21 takes out the cooled precious metal from the cooling device 60 and weighs the melted precious metal a second time to know the second weight of the precious metal after melting. Subtracting the second weight of the precious metal after melting from the first weight before melting gives the loss of precious metal during the recycling process. This loss value is used to feed back the actual operating status of the precious metal recycling equipment. If there is an abnormality, the machine is stopped in time for correction.

[0011] To facilitate understanding of the aforementioned solution, further explanation is provided below. Please refer to [link / reference needed]. Figure 2-8 As shown, in one embodiment of this utility model, the material picking and pallet changing device 10 includes a material picking base a10, which is provided with an opening mechanism a20, a picking mechanism a30, a flipping mechanism a40, a transfer mechanism a60, and a pallet mechanism a70. The opening mechanism a20 rotates and folds the lid of the carton a80 to make the internal space of the carton a80 visible. The pallet mechanism a70 is used to supply a first pallet a71. The flipping mechanism a40 includes a placement platform a41 and a pallet flipping assembly a42. The picking mechanism a30 is used to remove the second pallet a81 containing precious metals from the carton a80 after the internal space of the carton a80 is visible, and transfer it to the placement platform a41. The transfer mechanism a60 is used to transfer the material from the pallet mechanism a70... The first pallet a71 is removed and placed on top of the second pallet a81, which is placed on the placement platform a41 and contains precious metals. The pallet flipping assembly a42 is used to clamp both pallets and flip them after the first pallet a71 is placed on top of the second pallet a81, so that the precious metals are transferred from the second pallet a81 to the first pallet a71. The material picking mechanism a30 is also used to remove the second pallet a81, which has had its precious metals transferred, from the placement platform a41. The transfer mechanism a60 is also used to transfer the first pallet a71 to the first weighing device 20, transfer the first pallet a71 already loaded with precious metals to the first weighing device 20, and weigh the first pallet a71 to be loaded with precious metals and then transfer it to the conveying device 22.

[0012] For more details, please refer to Figure 3As shown, in one embodiment of the present invention, the box opening mechanism a20 includes a first box opening component a21, a second box opening component a22, a third box opening component a23, and a fourth box opening component a24. Each box opening component includes a suction cup a210 and a rotary drive component a211 for driving the suction cup a210 to rotate. The first box opening component a21 and the second box opening component a22 are opposite to each other and spaced apart. The third box opening component a23 and the fourth box opening component a24 are opposite to each other and spaced apart. The first box opening component a21, the second box opening component a22, the third box opening component a23, and the fourth box opening component a24 form a surrounding structure around the carton a80 to be folded. In this embodiment, the first box-opening component a21, the second box-opening component a22, the third box-opening component a23, and the fourth box-opening component a24 are arranged around the cardboard box a80 whose lid is to be folded. Each box-opening component includes a suction cup a210 and a rotary drive component a211 that drives the suction cup a210 to rotate. Under the driving action of the rotary drive component a211, the suction cup a210 of each box-opening component picks up the four lids around the cardboard box a80 and completes the rotation and folding, so that the internal space of the cardboard box a80 is visible (e.g., ...). Figure 2 As shown in the figure, in this embodiment, the rotary drive a211 is a rotary drive cylinder. In other embodiments, the rotary drive a211 can be a rotary motor or a rotary hydraulic cylinder, etc., and can be set according to the specific situation.

[0013] For more details, please refer to Figure 8 As shown, in one embodiment of this utility model, the material handling and tray changing device 10 includes a positioning mechanism a90. When the box opening mechanism a20 rotates and folds the lid of the carton a80, the positioning mechanism a90 positions the carton a80. The positioning mechanism a90 includes a limiting block a91, a pressing block a92, and a pressing drive a93. The pressing drive a93 drives the pressing block a92 to move away from or towards the limiting block a91. The limiting block a91 includes a first limiting sub-block a910 and a second limiting sub-block a911. The first limiting block a910 and the second limiting sub-block a911... Positioning blocks a911 are arranged at a 90-degree angle. The clamping block a92 includes a first clamping sub-block a920 and a second clamping sub-block a921, which are arranged at a 90-degree angle. Under the driving action of the clamping drive member a93, the clamping block a92 and the limiting block a91 move towards each other and clamp the carton a80, thus stably positioning the carton a80. In this embodiment, the clamping drive member a93 is a drive cylinder. In other embodiments, the clamping drive member a93 can be a linear motor or a linear module, etc., and can be set according to the specific situation.

[0014] For more details, please refer to Figure 4As shown, in one embodiment of this utility model, the material handling mechanism a30 includes a first material handling drive a31, a second material handling drive a32, a third material handling drive a33, and two material handling clamps a34. The first material handling drive a31 drives the second material handling drive a32, the third material handling drive a33, and the two material handling clamps a34 to move along the X-axis direction. The second material handling drive a32 drives the third material handling drive a33 and the two material handling clamps a34 to move along the Z-axis direction. The third material handling drive a33 drives the two material handling clamps a34 to move relative to each other to clamp or release the second tray a81. After the internal space of the carton a80 is visible, the picking mechanism a30 can clamp and remove the second tray a81 containing precious metals (such as gold) from the carton a80 and transfer it to the placement platform a41. In this embodiment, the first picking drive a31 and the second picking drive a32 are linear modules, and the third picking drive a33 is a clamping cylinder. In other embodiments, the first picking drive a31 and the second picking drive a32 can also be linear motors, cylinders, or hydraulic cylinders, etc., and the third picking drive a33 can also be linear motors, cylinders, or hydraulic cylinders, etc. The specific settings can be made according to the situation.

[0015] For more details, please refer to Figure 5 As shown, in one embodiment of this utility model, the pallet-flipping assembly a42 includes a pallet-clamping drive a420, a pallet-flipping drive a421, and two pallet clamps a422. The pallet-clamping drive a420 drives the two pallet clamps a422 to move relative to each other to simultaneously clamp or release the two pallets. The pallet-flipping drive a421 drives the pallet-clamping drive a420 and the two pallets clamped by the two pallet clamps a422 to flip. In this embodiment, the pallet-clamping drive a420 is a clamping cylinder, and the pallet-flipping drive a421 is a rotary cylinder. In other embodiments, the pallet-clamping drive a420 can also be a linear motor or a linear module, etc., and the pallet-flipping drive a421 can be a rotary motor, etc. The specific configuration can be adjusted according to the situation.

[0016] For more details, please refer to Figure 1 As shown, in one embodiment of this utility model, both the first weighing device 20 and the second weighing device 21 include a support and a weighing scale disposed on the support. More specifically, please refer to... Figure 6As shown, in one embodiment of this utility model, the transfer mechanism a60 includes a first transfer drive a61, a second transfer drive a62, a third transfer drive a63, a fourth movement drive a64, and two tray chucks a65. The first transfer drive a61 drives the second transfer drive a62, the third transfer drive a63, the fourth movement drive a64, and the two tray chucks a65 to move along the Y-axis direction. The second transfer drive a62 drives the third transfer drive a63, the fourth movement drive a64, and the two tray chucks a65 to move along the X-axis direction. The third transfer drive a63 drives the fourth movement drive a64 and the two tray chucks a65 to move along the Z-axis direction. The fourth movement drive a64 drives the two tray chucks a65 to move relative to each other to clamp or release the first tray a71. The transfer mechanism a60 removes the first tray a71 from the tray mechanism a70 and covers it on the second tray a81, which is already loaded with precious metal, on the placement platform a41. Once the first tray a71 is loaded with precious metal, the transfer mechanism a60 transfers the first tray a71 to the first weighing device 20. In this embodiment, the first transfer drive a61, the second transfer drive a62, and the third transfer drive a63 are linear modules, and the fourth movement drive a64 is a clamping cylinder. In other embodiments, the first transfer drive a61, the second transfer drive a62, and the third transfer drive a63 can also be linear drives such as linear motors.

[0017] For more details, please refer to Figure 7 As shown, in one embodiment of this utility model, the pallet mechanism a70 includes a fence a72, a pallet a73, and a lifting drive a74. The pallet a73 carries multiple stacked first pallets a71. The fence a72 is arranged around the multiple stacked first pallets a71. The lifting drive a74 drives the pallet a73 to move along the Z-axis. In this embodiment, after the uppermost first pallet a71 is removed from the pallet mechanism a70 by the transfer mechanism a60, the lifting drive a74 drives the pallet a73 to move along the Z-axis, and the stacked first pallets a71 move upward by one pallet position. The pallet mechanism a70 then supplies a new first pallet a71. The lifting drive a74 is a linear module.

[0018] For more details, please refer to Figure 2As shown, in one embodiment of this utility model, the material handling and tray changing device 10 further includes a carton conveyor line a11 and a first abnormal product conveyor line a12. After the carton a80 is taken out of the second tray a81, the carton conveyor line a11 transports it to the collection box for centralized collection of the carton a80. When the carton a80 is rotated and folded by the carton opening mechanism a20, the inside of the carton a80 is visible. If the vision mechanism detects that the second tray a81 inside the carton a80 does not contain precious metal, or detects that the precious metal contained in the second tray a81 has an abnormal shape (the shape of the precious metal is inconsistent with the precious metal shape information obtained by scanning the QR code on the outside of the carton a80), the first abnormal product conveyor line a12 can transport the carton a80 to the manual re-inspection station for further inspection by workers.

[0019] For more details, please refer to Figure 2 As shown, in one embodiment of this utility model, the material handling and pallet changing device 10 further includes a second abnormal product conveying line a13. After the first weighing device 20 weighs the first pallet a71 containing precious metals, it is found that the first weight of the precious metals is abnormal (the first weight of the precious metals is inconsistent with the weight information of the precious metals obtained by scanning the QR code on the outside of the carton a80). The second abnormal product conveying line a13 transports the first pallet a71 containing precious metals to the manual re-inspection station, where workers further inspect the abnormality of the first weight of the precious metals.

[0020] Please see Figure 9As shown, in one embodiment of this utility model, the melting device 40 includes a furnace b70, a crucible b20, a clamping mechanism, a feeding mechanism 50, and a robotic arm mechanism b40. The crucible b20 is used to hold precious metals and is placed inside the furnace b70 for melting. The crucible b20 includes a body b21 and a receiving groove disposed within the body b21. The body b21 has an arc-shaped outer wall. The clamping mechanism includes a clamping base b10, a clamping drive assembly b50 disposed on the clamping base b10, and two clamps b30. Each clamp b30 is provided with a clamping portion, and the clamping portion is provided with a clamping groove. The clamping groove includes a first clamping groove wall and a second clamping groove wall arranged at a preset angle. The two clamps b30 have the... The clamping parts are arranged adjacent to each other at one end. The clamping drive assembly b50 is used to drive the clamping parts in the two clamps b30 to move closer or further apart from each other, and to clamp or release the body b21 with the arc-shaped outer wall through the two clamping grooves, so as to realize the clamping mechanism to hold the crucible b20. The feeding mechanism 50 is used to take out the precious metal from the first tray a71 in the conveying device 22 and feed it into the empty crucible b20 held by the clamping mechanism. The robotic arm mechanism b40 is used to drive the clamping mechanism to transfer the crucible b20, which is held by the clamping mechanism and loaded with precious metal, to the furnace b70, and to feed the melted precious metal into the cooling device 60 after the precious metal is melted in the crucible b20.

[0021] For more details, please refer to Figure 10-13As shown, in one embodiment of this utility model, the feeding mechanism 50 includes a feeding base c10, a fixing member c20, a moving member c30, a feeding drive assembly c60, and a feeding assembly. The feeding base c10 is provided with a feeding port c11. The fixing member c20 is fixed on the feeding base c10. The moving member c30 is disposed on the feeding base c10. The moving member c30 has a first working position and a second working position. When the moving member c30 is in the first working position, the moving member c30, the fixing member c20, and the feeding base c10 form a feeding trough c12. When the moving member c30 is in the second working position, the moving member c30 and the fixing member c20 form a feeding trough c12. A molding cavity c33 is formed, the molding cross-section of which is smaller than that of the feeding port c11, and the molding cavity c33 is aligned with the feeding port c11 along the discharge direction of the feeding port c11. The feeding drive component c60 is used to drive the moving part c30 to switch between a first working position and a second working position. The feeding component is used to take out precious metal from the first tray a71 in the conveying device 22 and feed it into the discharge trough c12. In this embodiment, the feeding component is a combination mechanism of a linear module and a clamping cylinder. Under the drive of the linear module, the clamping cylinder drives the clamping element to take out precious metal from the first tray a71 and feed it into the discharge trough c12. When the moving part c30 is in the first working position, it forms a feeding trough c12 with the fixed part c20 and the feeding base c10, which facilitates the feeding of precious metals. When it is in the second working position, it forms a forming cavity c33 with the fixed part c20. The forming cross-section of the forming cavity c33 is smaller than that of the feeding port c11 and is aligned with it, so that the precious metal can fall smoothly into the feeding port c11 by its own weight after forming, and then fall smoothly into the crucible b20. This realizes the automatic forming and feeding of precious metals into the crucible b20, which improves production efficiency.

[0022] For more details, please refer to Figure 10-13As shown, in one embodiment of this utility model, the fixing member c20 includes a first fixing sub-member c21 and a second fixing sub-member c22 arranged perpendicularly to each other; the moving member c30 includes a first moving sub-member c31 and a second moving sub-member c32 arranged perpendicularly to each other; and the feeding drive assembly c60 includes a first feeding drive member c61 and a second feeding drive member c62. The first feeding drive member c61 drives the first moving sub-member c31 to move relative to the first fixing sub-member c21 between a first working position and a second working position. The second feeding drive member c62 drives the second moving sub-member c32 to move relative to the second fixing sub-member c22 between a first working position and a second working position. The first fixing sub-member c21 and the second fixing sub-member c22 are arranged perpendicularly to each other, and the first moving sub-member c31 and the second moving sub-member c32 are also arranged perpendicularly to each other, making the shapes of the precious metal feeding groove c12 and the forming cavity c33 more regular, which is beneficial to the stable forming of the precious metal in the forming cavity c33.

[0023] For more details, please refer to Figure 10-13 As shown, in one embodiment of the present invention, the first movable sub-component c31 is provided with a first arc-shaped extrusion part c310 at one end near the first fixed sub-component c21, the second movable sub-component c32 is provided with a second arc-shaped extrusion part c320 at one end near the second fixed sub-component c22, and a third arc-shaped extrusion part c23 is provided between the first fixed sub-component c21 and the second fixed sub-component c22. The first arc-shaped extrusion part c310, the second arc-shaped extrusion part c320 and the third arc-shaped extrusion part c23 form a circular cylindrical forming cavity c33 when the movable sub-component c30 is in the second working position, and the feeding port c11 is circular cylindrical. When the moving part c30 is in the second working position, the first arc-shaped extrusion part c310, the second arc-shaped extrusion part c320 and the third arc-shaped extrusion part c23 form a forming cavity c33 in the shape of a circular cylindrical hole, and the feeding port c11 is also in the shape of a circular cylindrical hole, which can extrude the precious metal into a cylindrical shape, so that the precious metal can be discharged from the feeding port c11 after being extruded into a cylindrical shape.

[0024] For more details, please refer to Figure 10-13As shown, in one embodiment of this utility model, the feeding mechanism 50 further includes a guide member c70. The guide member c70 is disposed on the feeding base c10. A first guide groove is formed between the guide member c70 and the second fixed sub-member c22 to guide the movement of the first moving sub-member c31, and a second guide groove is formed between the guide member c70 and the first fixed sub-member c21 to guide the movement of the second moving sub-member c32. The first guide groove and the second guide groove formed between the guide member c70 and the fixed sub-member guide the movement of the first moving sub-member c31 and the second moving sub-member c32, respectively, so that the moving sub-member c30 can always maintain an accurate position and direction during the movement, avoiding the offset and shaking of the moving sub-member c30 during the movement, thereby improving the stability of extrusion molding, ensuring the accuracy of the shape and size of the molding cavity c33, further improving the quality and consistency of precious metal molding, and thus ensuring that precious metals of different sizes and shapes can fall smoothly into the crucible b20 for melting.

[0025] For further details, please refer to Figure 10-13 As shown, in one embodiment of this utility model, the first feeding drive component c61 and the second feeding drive component c62 are both linear modules. The use of linear modules for both the first feeding drive component c61 and the second feeding drive component c62 allows for precise control of the movement stroke of the first moving sub-component c31 and the second moving sub-component c32, thereby achieving precise control of the extrusion stroke. This results in a more uniform and stable extrusion force on the precious metal during the forming process, avoiding poor forming or damage to the precious metal due to inaccurate extrusion stroke, and further improving the stability of extrusion molding.

[0026] For further details, please refer to Figure 10-13 As shown, in one embodiment of this utility model, the feeding mechanism 50 further includes a sealing mechanism c80. The sealing mechanism c80 includes a sealing component c81 and a sealing drive component c82. The sealing component c81 is disposed above the feeding base c10, and the sealing drive component c82 is used to drive the sealing component c81 to switch back and forth between the position of sealing the discharge groove c12 and the position of unsealing the discharge groove c12. When the precious metal is compressed, the sealing component c81 can seal the discharge groove c12 to prevent the precious metal from jumping out under the extrusion force.

[0027] For further details, please refer to Figure 10-13As shown, in one embodiment of this utility model, the feeding mechanism 50 further includes a discharge mechanism c90. The discharge mechanism c90 includes a discharge rod c91 and a discharge drive component c92. The discharge drive component c92 is used to drive the discharge rod c91 to move within the feeding port c11 along the discharge direction of the feeding port c11. When precious metals become stuck or blocked within the feeding port c11, the discharge rod c91 can clear the blockage in time, ensuring that the precious metals can be smoothly discharged from the feeding port c11, avoiding production interruptions and equipment damage caused by precious metal jamming, and improving the continuity and stability of production. The discharge mechanism c90 also includes an adjustment drive component c93. The discharge drive component c92 is used to drive the discharge rod c91 and the discharge drive component c92 to move along the discharge direction perpendicular to the feeding port c11. Before the feeding rod c91 is inserted into the feeding port c11, adjusting the drive component c93 can easily align the feeding rod c91 with the feeding port c11, improving the accuracy and convenience of the feeding operation. The feeding mechanism 50 also includes a guide funnel c40 and an alignment drive component c41. The guide funnel c40 is used to guide the precious metal into the discharge trough c12, and the alignment drive component c41 is used to drive the guide funnel c40 to switch back and forth between the position aligned with the discharge trough c12 and the position receiving the precious metal. The guide funnel c40 can smoothly guide the precious metal from a distance into the discharge trough c12, and the alignment drive component c41 can make the guide funnel c40 automatically align with the discharge trough c12, enhancing the applicability and versatility of the device.

[0028] Please see Figure 14-16As shown, in one embodiment of this utility model, the cooling device 60 includes a conveying mechanism d10, a cooling chamber mechanism d20, and a cooling mechanism. The conveying mechanism d10 includes a conveyor belt d11 and a conveying drive assembly d12 for driving the conveyor belt d11. The cooling chamber mechanism d20 includes a chamber assembly d21 and a support assembly d22. The chamber assembly d21 includes a receiving member d210, which includes a receiving space d2102 and an opening d2104 communicating with the receiving space d2102. The support assembly d22 includes a support member d220, which is disposed above the conveyor belt d11. The receiving member d210 is disposed on the support member d220. Above 220, the support member d220 has a first working position and a second working position. When the support member d220 is in the first working position, the support member d220 blocks the opening d2104. The receiving space d2102 of the receiving member d210 and the support member d220 form a cooling cavity for temporarily storing precious metals. When the support member d220 is in the second working position, the support member d220 does not block the opening d2104. The precious metals in the receiving space d2102 fall into the conveyor belt d11 through the opening d2104. The cooling mechanism is used to blow air to cool the precious metals temporarily stored in the cooling cavity when the support member d220 is in the first working position. When the precious metal cooling device 60 is in its initial state, the support member d220 is in the second working position, and the support member d220 does not block the opening d2104. When cooling of the precious metal is required, the support member d220 switches to the first working position, and the support member d220 blocks the opening d2104. The receiving space d2102 of the receiving member d210 and the support member d220 form a cooling chamber. The cooling mechanism blows air to cool the precious metal entering the cooling chamber (in this embodiment, the precious metal to be cooled can...). The precious metal enters the receiving space d2102 of the receiving member d210 through the opening d2104, allowing it to cool down rapidly. After the precious metal cools down, the supporting member d220 switches back to the second working position. The supporting member d220 does not block the opening d2104, and the cooled precious metal falls through the opening d2104 onto the conveyor belt d11. The conveyor belt d11 automatically transports the cooled precious metal to the next station. Thus, the cooling and conveying are completed, achieving a seamless connection from cooling to transfer, reducing manual intervention, and improving the processing efficiency of precious metals.

[0029] For more details, please see Figure 14-16As shown, in one embodiment of this utility model, the receiving member d210 includes a feeding end d2100 and a discharging end d2101 opposite to the feeding end d2100. The receiving space d2102 is disposed between the feeding end d2100 and the feeding end d2101. The feeding end d2100 is provided with an inlet d2103 communicating with the receiving space d2102, and the opening d2104 is disposed at the discharging end d2101. The feeding end d2100 of the receiving member d210 has an inlet d2103, allowing precious metals to enter the cooling chamber through the inlet d2103 before cooling, facilitating the precious metal feeding operation. Further details can be found in the following description. Figure 2-3 As shown, in one embodiment of this utility model, the receiving member d210 is provided with a guide member d211 at the feeding end d2100. The guide member d211 is provided with a conical flow channel d2110 that guides the precious metal to the inlet d2103. In this embodiment, the guide member d211 with the conical flow channel d2110 is provided to ensure that the precious metal is smoothly fed into the inlet d2103 before cooling, and then enters the cooling chamber for cooling.

[0030] Please see Figure 14-16 As shown, in one embodiment of this utility model, the cooling mechanism includes a sealing cover, an air inlet pipe, and a fan. The sealing cover is provided with an air inlet, which is connected to the air inlet pipe. The air inlet pipe is connected to the fan. The cooling mechanism also includes a cooling drive component, which drives the sealing cover to switch back and forth between a position sealing the inlet d2103 and a position unsealing the inlet d2103. In this embodiment, when the precious metal to be cooled enters the cooling chamber through the inlet d2103, the cooling drive component drives the sealing cover to move to the position of the inlet d2103. The fan blows air into the cooling chamber through the air inlet pipe. In this embodiment, the cooling drive component is a cylinder. In other embodiments, it can also be a hydraulic cylinder, a linear motor, or a linear module, etc., which can be selected and set according to specific circumstances. In other embodiments, the cooling mechanism can also use cooling water for cooling, or simultaneously use air cooling and water cooling to complete the cooling.

[0031] Please see Figure 14-16 As shown, in one embodiment of the present invention, the supporting component d22 further includes a supporting drive component d221, which drives the supporting component d220 to switch between a first working position and a second working position. In this embodiment, the supporting drive component d221 is a drive cylinder. In other embodiments, a linear motor or linear module may be selected according to the actual situation.

[0032] Please see Figure 14-16As shown, in one embodiment of this utility model, the conveying mechanism d10 further includes a first baffle d13 and a second baffle d14. The first baffle d13 and the second baffle d14 are respectively located on opposite sides of the conveyor belt d11 along its width direction, and the first baffle d13 and the second baffle d14 extend along the length direction of the conveyor belt d11. A partition plate d15 is also provided between the first baffle d13 and the second baffle d14, and the partition plate d15 extends along the length direction of the conveyor belt d11. A first channel d16 is formed between the first baffle d13 and the partition plate d15, and a second channel d17 is formed between the second baffle d14 and the partition plate d15. In this embodiment, by setting the first baffle d13, the second baffle d14, and the partition plate d15, the first channel d16 and the second channel d17 are formed on the conveyor belt d11. The cooled precious metal can be conveyed to the next station along the first channel d16 or the second channel d17, thereby improving the transfer efficiency of the precious metal. For further details, please refer to Figure 14-16 As shown, in one embodiment of this utility model, the support member d220 includes a first support sub-plate d2200 and a second support sub-plate d2201. The first support sub-plate d2200 is disposed above the conveyor belt d11 and within the first channel d16, and the second support sub-plate d2201 is disposed above the conveyor belt d11 and within the second channel d17. In this embodiment, the support member d220 is configured to include a first support sub-plate d2200 and a second support sub-plate d2201. The first support sub-plate d2200 corresponds to the first channel d16, and the second support sub-plate d2201 corresponds to the second channel d17. The receiving member d210 can optionally form a cooling chamber with either the first support sub-plate d2200 or the second support sub-plate d2201. Further details can be found in the following description. Figure 14-16 As shown, in one embodiment of this utility model, the cavity assembly d21 further includes a lifting drive d212 and a translation drive d213. The lifting drive d212 drives the translation drive d213 to move in a direction close to or away from the support member d220. The translation drive d213 drives the receiving member d210 to switch back and forth between a position corresponding to the first channel d16 and a position corresponding to the second channel d17. In this embodiment, by setting the lifting drive d212 and the translation drive d213, conditions are provided for the receiving member d210 to selectively form a cooling cavity with the first support sub-plate d2200 or the second support sub-plate d2201. In this embodiment, the lifting drive d212 and the translation drive d213 are set as driving cylinders. In other embodiments, they can be linear motors or linear modules, etc., depending on the specific situation.

[0033] In one embodiment of this utility model, the precious metal cooling device 60 further includes a vision mechanism, which includes a bracket and a lens mounted on the bracket. The lens takes pictures of the cooling cavity to determine whether there is precious metal to be cooled in the cooling cavity. If the vision mechanism detects that there is no precious metal in the cooling cavity, the blowing cooling operation of the cooling mechanism is suspended.

[0034] Please see Figure 18-20 As shown, in one embodiment of this utility model, the precious metal recycling equipment includes an opening device 80. The opening device 80 includes an opening base e10, an opening tool mechanism e20 disposed on the opening base e10, and an opening drive mechanism e30. The opening tool mechanism e20 includes a first tool assembly e21, a second tool assembly e22, and a third tool assembly e23. The first tool assembly e21 includes a first blade e210, which extends along the Z-axis. The second tool assembly e22 includes a second blade e220, and the third tool assembly e23 includes a third blade e230. Both the second blade e220 and the third blade e230 are arranged at a preset angle to the Z-axis. The opening drive mechanism e30 is connected to the opening base e10 and is used to drive the opening tool mechanism e20 to move within a preset coordinate system, which includes the X-axis, Y-axis, and Z-axis. The first blade e210 extends along the Z-axis. Under the drive of the driving mechanism, the first blade e210 moves along the Y-axis and Z-axis, thereby cutting the first tape e81 of the carton a80. The second blade e220 and the third blade e230 are both arranged at a preset angle to the Z-axis. Under the drive of the driving mechanism, the second blade e220 and the third blade e230 move along the X-axis and Z-axis, thereby cutting the second tape e82 and the third tape e83 of the carton a80 (e.g., ...). Figure 20 As shown, the angle between the second blade e220 and the third blade e230 and the Z-axis is α, and the angle α ranges from 40 degrees to 50 degrees. In this embodiment, α is 45 degrees. This replaces manual labor to remove the tape seals on the three parts of the carton a80, thus providing conditions for the subsequent automated opening of the carton a80 lid.

[0035] For more details, please refer to Figure 18-20 As shown, in one embodiment of this utility model, the first tool assembly e21 further includes a first blade driver e211, which drives the first blade e210 to move along the Z-axis direction. The second tool assembly e22 further includes a second blade driver e221, which drives the second blade e220 to move along a direction forming a preset angle with the Z-axis (e.g., ...). Figure 20As shown, the angle between the second blade e220 and the Z-axis is α, and the direction of movement of the second blade e220 is as follows. Figure 20 (As indicated by the arrow), the third tool assembly e23 also includes a third blade drive e231, which drives the third blade e230 to move along a direction that forms a preset angle with the Z-axis (e.g., ...). Figure 20 As shown, the angle between the third blade e230 and the Z-axis is α, and the moving direction of the second blade e220 is as follows. Figure 20 (As indicated by the arrows) In this embodiment, the first blade drive e211, the second blade drive e221, and the third blade drive e231 are all drive cylinders. In other embodiments, they can be linear motors or linear modules, etc., and can be selected and set according to specific circumstances. The first blade e210 can move along the Z-axis direction under the drive of the first blade drive e211, thereby first puncturing the first tape e81 of the carton a80. Then, under the drive of the carton opening drive mechanism e30, the first blade e210 moves along the Y-axis and Z-axis directions, cutting the first tape e81 of the carton a80 and releasing the first tape e81 from the carton a80. The second blade e220 moves along a direction with a preset angle to the Z-axis under the drive of the second blade drive e221 (e.g., ...). Figure 20 As shown), the second tape e82 of the carton a80 is first punctured. Then, under the driving action of the carton opening drive mechanism e30, the second blade e220 moves along the X and Z axes, cutting the second tape e82 of the carton a80 and releasing the second tape e82 from the carton a80. The third blade e230 moves along a direction with a preset angle to the Z axis under the drive of the third blade drive member e231 (as shown). Figure 20 As shown), the third tape e83 of the carton a80 is punctured first, and then the third blade e230 is driven by the opening drive mechanism e30, and the first blade e210 moves along the X and Z axes to cut the third tape e83 of the carton a80, thus releasing the seal of the carton a80 by the third tape e83.

[0036] Please see Figure 18-20 As shown, in one embodiment of this utility model, the box-opening drive mechanism e30 includes a first linear module e31 and a second linear module e32. The box-opening base e10 is connected to the moving part of the second linear module e32. The first linear module e31 drives the second linear module e32, the box-opening base e10, and the box-opening cutter mechanism e20 to move along the Y-axis direction, and the second linear module e32 drives the box-opening base e10 and the box-opening cutter mechanism e20 to move along the Z-axis direction. Further details can be found in the following documentation. Figure 18-20As shown, in one embodiment of this utility model, the box-opening drive mechanism e30 includes a tool drive component e33, which is disposed on the base. The tool drive component e33 drives the second tool assembly e22 and the third tool assembly e23 to move along the X-axis. In this embodiment, the tool drive component e33 is a drive cylinder. In other embodiments, it can be a linear motor or a linear module, etc., which can be selected and set according to specific circumstances.

[0037] Please see Figure 21As shown, in one embodiment of this utility model, the precious metal recycling equipment includes a carton separation device 70. The carton separation device 70 includes a belt drive structure f10, a discharge structure f12, and a separation drive structure f14. The discharge structure f12 is located at one end of the belt drive structure f10, and the belt drive structure f10 is used to transport the carton a80 to the discharge structure f12. The discharge structure f12 includes an inlet f16 and an outlet f18. The inlet f16 faces the belt drive structure f10, and the orientation of the outlet f18 forms an angle with the orientation of the inlet f16. The separation drive structure f14 can move relative to the discharge structure f12 and is used to drive the carton a80 in the discharge structure f12 to move towards the outlet f18. The discharge structure f12 includes an inlet f16 and an outlet f18. The inlet f16 faces the belt drive structure f10, meaning it is located on the side of the discharge structure f12 closest to the belt drive structure. When the belt drive structure f10 moves the material towards the discharge structure f12, the carton a80 can enter the discharge structure f12 through the inlet f16. The orientation of the outlet f18 forms an angle with the orientation of the inlet f16, which is the direction of material movement when it exits the discharge structure f12. The separation drive structure f14 drives the carton a80 inside the discharge structure f12 towards the outlet f18. The orientation of the inlet f16 is the direction of material movement when it enters the discharge structure f12. The belt drive structure f10 drives the carton a80 towards the inlet f16, causing the carton a80 on the discharge structure f12 to exit through the outlet f18. The orientation of the discharge port f18 forms an angle with the orientation of the inlet port f16, meaning the feeding direction and discharge direction of the discharge structure f12 are different. By setting up a belt drive structure f10, a discharge structure f12, and a separation drive structure f14, the discharge structure f12 can achieve automatic feeding via the belt drive structure f10 and automatic discharging via the separation drive structure f14. Since the feeding direction and discharge direction of the cartons a80 are different, multiple cartons a80 can be separated by changing their movement direction without human intervention. In this embodiment, the belt drive structure f10 can be a belt conveyor line, and the driving force of the separation drive structure f14 comes from a drive cylinder. In one embodiment of the present invention, the precious metal recycling equipment further includes a flattening device, which includes a flattening platform, a pressing block disposed at a distance from the flattening platform, and a flattening drive connected to the pressing block. The top of the flattening platform is recessed with a receiving portion, and the pressing block is located directly above the receiving portion. In this embodiment, the flattening drive is a drive cylinder. After the precious metal is melted, the flattening device can flatten the precious metal.

[0038] Please see Figure 22As shown, in one embodiment of this utility model, the precious metal recycling equipment further includes a purity detection device 30. The purity detection device 30 includes a workbench g10, a detector g14 disposed on the workbench g10 for detecting the purity of the precious metal, a purity detection drive assembly g16 disposed on the workbench g10, and a purity detection robotic arm g18 connected to the purity detection drive assembly g16. The purity detection drive assembly g16 is used to drive the purity detection robotic arm g18 to transfer the precious metal between the first tray a71 of the conveying device 22 and the detector g14. The detector g14 includes a detection body and an upper cover that movably cooperates with the detection body. The detection body has a receiving space for accommodating the precious metal. The purity detection device further includes an upper cover drive member connected to the upper cover. The upper cover drive member is used to drive the upper cover to move relative to the detection body to expose or cover the receiving space. The detector g14 is installed on the workbench g10. After the precious metal is flattened, the detector g14 is used to detect the purity of the precious metal. In this embodiment, the purity detection drive component g16 and the purity detection robotic arm g18 can be linear modules. In other embodiments, they can be cylinders or linear motors, etc.

[0039] Please see Figure 23As shown, in one embodiment of this utility model, the precious metal recycling equipment includes a palletizing device 90. The palletizing device 90 is used to palletize the first pallet a71 containing precious metal in the conveying device 22. The palletizing device 90 includes a machine base h10 and a feeding assembly h12 and a palletizing assembly h14 disposed on the machine base h10. The machine base h10 is provided with a discharge port h16. The palletizing device 90 forms multiple palletizing spaces below the discharge port h16. The palletizing assembly h14 includes a gripping component h18 and a first palletizing drive. The device includes a moving component h20 and a second palletizing drive component h22. A gripping component h18 is used to grip materials. The first palletizing drive component h20 is connected to the gripping component h18 and drives the gripping component h18 to move along the Z-axis. The second palletizing drive component h22 is connected to the gripping component h18 and drives the gripping component h18 to move along the X-axis. Multiple palletizing spaces are arranged along the X-axis. The feeding assembly h12 can move relative to the gripping component h18 to transport the first pallet a71 to the gripping component h18. In this embodiment, the gripping component h18 can be a cylinder, while the first palletizing drive component h20 and the second palletizing drive component h22 can be linear modules. The feeding assembly h12 is driven by a cylinder for conveying. To describe it further, the gripper h18 grips the first pallet a71 and moves the first pallet a71 together. The first palletizing drive h20 is connected to the gripper h18 and is used to drive the gripper h18 to move up and down along the longitudinal direction Y, thereby moving the gripped first pallet a71 along the longitudinal direction Y. When the gripper h18 moves down under the action of the first palletizing drive h20, it can move the first pallet a71 down together and pass through the material drop port h16, so that the first pallet a71 enters the palletizing space. The gripper h18 releases the first pallet a71 and stores the first pallet a71 in the palletizing space. Then it rises and grips the first pallet a71 that has been transported. After repeating this action, multiple first pallets a71 can be stacked in the palletizing space to complete the palletizing operation.

[0040] In one embodiment of this utility model, the precious metal recycling equipment includes a video recording device, which automatically records the entire automatic recycling process of the precious metal recycling equipment and monitors the recycling process in real time.

[0041] The above are merely specific embodiments of this utility model, but the protection scope of this utility model is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in this utility model should be included within the protection scope of this utility model. The protection scope of this utility model shall be determined by the protection scope of the claims.

Claims

1. A precious metal recycling device, characterized in that, include: The frame is equipped with a material handling and changing device, a first weighing device, a conveying device, a melting device, a cooling device, and a second weighing device. The material handling and pallet changing device is used to open the lid of the carton, take out the second pallet containing precious metals from the carton, supply the first pallet and transfer the first pallet to the first weighing device for weighing, transfer the precious metals in the second pallet to the first pallet, transfer the first pallet containing precious metals to the first weighing device for weighing, and after weighing, transfer the first pallet containing precious metals to the conveying device. The conveying device is used to convey the first pallet loaded with precious metals to the melting device; The melting device is used to take out precious metal from the first tray in the conveying device, melt it, and then transfer it to the cooling device for cooling. The second weighing device is used to remove the cooled precious metal from the cooling device, weigh the precious metal, and then transfer it to the same first tray being transported by the conveying device.

2. The precious metal recycling equipment according to claim 1, characterized in that, The material handling and pallet changing device includes a material handling base, which is equipped with an opening mechanism, a material handling mechanism, a flipping mechanism, a transfer mechanism, and a pallet mechanism. The opening mechanism is used to rotate and fold the lid of the carton to make the internal space of the carton visible. The pallet mechanism is used to supply a first pallet. The flipping mechanism includes a placement platform and a pallet flipping assembly. The picking mechanism is used to pick up the second pallet containing precious metals from the carton after the internal space of the carton is visible, and transfer it to the placement platform. The transfer mechanism is used to take out the first pallet from the pallet mechanism and cover it on the second pallet containing precious metals placed on the placement platform. The pallet flipping assembly is used to clamp both pallets and flip them after the first pallet covers the second pallet, so that the precious metals are transferred from the second pallet to the first pallet. The picking mechanism is also used to pick up the second pallet containing the transferred precious metals from the placement platform. The transfer mechanism is also used to transfer the first pallet to the first weighing device, transfer the first pallet containing precious metals to the first weighing device, and transfer the first pallet containing precious metals to the conveying device after weighing.

3. The precious metal recycling equipment according to claim 1, characterized in that, The melting device includes a furnace, a crucible, a clamping mechanism, a feeding mechanism, and a robotic arm mechanism; The crucible is used to hold precious metals and is placed in a furnace for melting the precious metals. The crucible includes a body and a receiving groove disposed in the body. The body has an arc-shaped outer wall. The clamping mechanism includes a clamping base, a clamping drive assembly disposed on the clamping base, and two clamps. Each clamp is provided with a clamping part and a clamping groove. The clamping groove includes a first clamping groove wall and a second clamping groove wall arranged at a preset angle. The two clamps are arranged adjacent to each other at one end with the clamping part. The clamping drive assembly is used to drive the clamping parts of the two clamps to move closer or further away from each other. The clamping mechanism clamps or releases the body with the arc-shaped outer wall through the two clamping grooves to achieve the clamping of the crucible by the clamping mechanism. The feeding mechanism is used to take out precious metal from the first tray in the conveying device and feed it into an empty crucible held by the clamping mechanism. The robotic arm mechanism is used to drive the clamping mechanism to transfer the crucible held by the clamping mechanism and loaded with precious metal to the furnace, and to feed the molten precious metal into the cooling device after the precious metal has melted in the crucible.

4. The precious metal recycling equipment according to claim 3, characterized in that, The feeding mechanism includes a feeding base, a fixing member, a moving member, a feeding drive assembly, and a feeding component. The feeding base is provided with a feeding port. The fixing member is fixed on the feeding base. The moving member is disposed on the feeding base and has a first working position and a second working position. When the moving member is in the first working position, the moving member, the fixing member, and the feeding base form a feeding trough. When the moving member is in the second working position, the moving member and the fixing member form a forming cavity. The forming cross-section of the forming cavity is smaller than the feeding port, and the forming cavity is aligned with the feeding port along the discharge direction of the feeding port. The feeding drive assembly is used to drive the moving member to switch between the first working position and the second working position. The feeding component is used to take out precious metal from the first tray in the conveying device and feed it into the feeding trough.

5. The precious metal recycling equipment according to claim 1, characterized in that, The cooling device includes a conveying mechanism, a cooling chamber mechanism, and a cooling mechanism. The conveying mechanism includes a conveyor belt and a conveying drive assembly for driving the conveyor belt. The cooling chamber mechanism includes a chamber assembly and a support assembly. The chamber assembly includes a receiving member, which includes a receiving space and an opening communicating with the receiving space. The support assembly includes a support member, which is disposed above the conveyor belt. The receiving member is disposed above the support member. The support member has a first working position and a second working position. When the support member is in the first working position, the support member blocks the opening. The receiving space of the receiving member and the support member form a cooling chamber for temporarily storing precious metals. When the support member is in the second working position, the support member does not block the opening, and the precious metals in the receiving space fall through the opening onto the conveyor belt. The cooling mechanism is used to cool the precious metals temporarily stored in the cooling chamber by blowing air when the support member is in the first working position.

6. The precious metal recycling equipment according to claim 1, characterized in that, The precious metal recycling equipment includes an opening device, which comprises an opening base, an opening cutter mechanism disposed on the opening base, and an opening drive mechanism. The opening cutter mechanism comprises a first cutter assembly, a second cutter assembly, and a third cutter assembly. The first cutter assembly comprises a first blade extending along the Z-axis. The second cutter assembly comprises a second blade, and the third cutter assembly comprises a third blade. Both the second and third blades are arranged at a preset angle to the Z-axis. The opening drive mechanism is connected to the opening base and is used to drive the opening cutter mechanism to move within a preset coordinate system, which includes the X-axis, Y-axis, and Z-axis.

7. The precious metal recycling equipment according to claim 1, characterized in that, The precious metal recycling equipment includes a carton separation device, which includes a belt drive structure, a discharge structure, and a separation drive structure. The discharge structure is located at one end of the belt drive structure and is used to transport the carton to the discharge structure. The discharge structure includes an inlet and an outlet. The inlet faces the belt drive structure, and the outlet faces an angle with the inlet. The separation drive structure can move relative to the discharge structure and is used to drive the carton in the discharge structure to move towards the outlet.

8. The precious metal recycling equipment according to claim 1, characterized in that, The precious metal recycling equipment also includes a flattening device, which includes a flattening platform, a pressing block disposed at a distance from the flattening platform, and a flattening drive connected to the pressing block. The top of the flattening platform is recessed with a receiving portion, and the pressing block is located directly above the receiving portion.

9. The precious metal recycling equipment according to claim 1, characterized in that, The precious metal recycling equipment also includes a purity testing device, which includes a workbench, a detector disposed on the workbench for detecting the purity of the precious metal, a purity testing drive assembly disposed on the workbench, and a purity testing robotic arm connected to the purity testing drive assembly. The purity testing drive assembly is used to drive the purity testing robotic arm to transfer the precious metal between the first tray of the conveying device and the detector. The detector includes a detection body and an upper cover that movably cooperates with the detection body. The detection body has a receiving space for accommodating the precious metal. The purity testing device also includes an upper cover drive member connected to the upper cover. The upper cover drive member is used to drive the upper cover to move relative to the detection body to expose or cover the receiving space.

10. The precious metal recycling equipment according to claim 1, characterized in that, The precious metal recycling equipment includes a palletizing device for palletizing the first pallet containing precious metal in the conveying device. The palletizing device includes a machine base and a feeding assembly and a palletizing assembly disposed on the machine base. The machine base has a through-hole for material discharge. The palletizing device forms multiple palletizing spaces below the material discharge hole. The palletizing assembly includes a gripper, a first palletizing drive, and a second palletizing drive. The gripper is used to grip material. The first palletizing drive is connected to the gripper and is used to drive the gripper to move along the Z-axis. The second palletizing drive is connected to the gripper and is used to drive the gripper to move along the X-axis. The multiple palletizing spaces are arranged along the X-axis. The feeding assembly can move relative to the gripper to transport the first pallet to the gripper.