A centralized photovoltaic racking assembly job work station
Patent Information
- Application Number
- CN202620206711.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2026-02-11
- Publication Date
- 2026-10-30
- Estimated Expiration
- 2036-02-11
AI Technical Summary
[0002]目前,桩基之间及顶部架设支架及安装光伏组件时无安装人员站立的平台,一般是通过搭设脚手架进行施工,其存在的不足是:一方面是需要大量脚手架且搭设的时间长、转运繁琐,另一方面脚手架高度及稳定性不佳,存在隐患
利用本实用新型,能解决高桩(如水库、池塘、沙漠、山地均可能涉及高桩)支架组件安装的难题,集成定位、人员活动空间、储物收纳、安全于一体的功能,提高施工效率、工程质量及人员安全,适应范围广;
Smart Images

Figure CN224918825U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of photovoltaic installation technology, specifically to a centralized photovoltaic support module workstation. Background Technology
[0002] Currently, there is no platform for installers to stand on when erecting supports between pile foundations and on top, and when installing photovoltaic modules. Construction is generally carried out by erecting scaffolding. The shortcomings of this method are: on the one hand, it requires a large amount of scaffolding, and the erection time is long and the transportation is cumbersome; on the other hand, the height and stability of the scaffolding are not good, which poses potential hazards.
[0003] CN221856319U discloses a piling-type photovoltaic support module installation platform, including a column; an upper suspension member disposed at the upper end of the column; a lower fixing member disposed at the lower end of the column; a bracket device disposed on one side of the column; and a long step supported by multiple bracket devices simultaneously. To a certain extent, this installation platform can solve the problem of high-piling installation in dry land and ponds, improving the installation efficiency and quality of photovoltaic panels and increasing the safety of installers. However, the upper suspension member structure is not suitable for the installation of some supports. Furthermore, it is still lacking in installation efficiency, construction convenience, and safety, requiring further improvement. Utility Model Content
[0004] The technical problem to be solved by this utility model is to provide a centralized photovoltaic support module workstation that is more adaptable, more convenient to construct, safer to operate, and can improve construction efficiency and ensure project quality, in order to address the shortcomings of the above-mentioned technologies.
[0005] The technical solution adopted by this utility model to solve its technical problem is: a centralized photovoltaic support module operation station, including foundation piles arranged at intervals, on which a standing platform support is fixedly installed, and on both sides of the top of the standing platform support are square steel combined plates, which are located on the same horizontal plane and scaffolding steps are installed between them, a steel wire rope safety cable is installed on the top of the foundation pile, and a material bracket is installed on the square steel combined plate.
[0006] Furthermore, the support frame for the standing platform includes square steel uprights, square steel cross braces are welded to the top left and right sides of the square steel uprights on the same horizontal plane, square steel diagonal braces are welded between the square steel cross braces and the square steel uprights, two sets of first clamps are welded to the front side of the square steel uprights, and L-shaped angle irons are welded to the outer ends of the square steel cross braces. A laser instrument platform is also provided at the outer end of one side of the square steel cross brace.
[0007] Furthermore, located on the rear side of the square steel uprights, between the left-side square steel horizontal brace and the right-side square steel diagonal brace, a square steel connecting rod is welded to further stabilize the overall support of the standing platform frame.
[0008] Furthermore, the square steel composite plate includes three parallel square steel bars, which are welded together by rectangular iron sheets arranged at intervals. It can provide support for construction workers and is also used to install scaffolding boards and material supports.
[0009] Furthermore, the scaffolding planks are connected to the square steel composite flat plates via hooks at both ends, providing sufficient space for construction workers to move around and also serving as a platform for placing large materials, such as photovoltaic panels and support materials, thereby improving construction convenience and efficiency. Specifically, the number of scaffolding planks can be arranged according to the actual situation to facilitate construction.
[0010] Furthermore, a second clamp is fixedly installed on the top of the foundation pile. A hole for installing a steel wire rope safety cable is opened on the outer side of the second clamp. One end of the steel wire rope safety cable passes through the hole and is fixed by a rope clamp. Correspondingly, the other end of the steel wire rope safety cable is also installed and fixed using the same structure.
[0011] Furthermore, the material rack includes a material box, and hooks are welded to both sides of the material box. The material rack can be installed on the square steel outside the square steel combined plate by means of the hooks, and is used to store some small tools or materials, such as electric wrenches, screws, etc.
[0012] Compared with the prior art, the present invention has the following beneficial effects: This utility model can solve the problem of installing support components for high piles (such as reservoirs, ponds, deserts, and mountains). It integrates positioning, personnel activity space, storage, and safety functions, improving construction efficiency, project quality, and personnel safety, and has a wide range of applications. In addition, this utility model has a simple structure, is easy to manufacture and has low cost. It is detachable, easy to install and use, and provides convenience for subsequent process construction. Attached Figure Description
[0013] Figure 1 This is a schematic diagram of the structure of an embodiment of the present utility model; Figure 2 for Figure 1 The schematic diagram of the structure of the standing platform support shown in the embodiment is as follows; Figure 3 for Figure 1 A schematic diagram of the structure of the square steel composite plate in the embodiment shown; Figure 4 for Figure 1A schematic diagram of the structure of the scaffolding platform in the embodiment shown; Figure 5 for Figure 1 A schematic diagram of the connection of the steel wire rope safety main cable in the embodiment shown; Figure 6 for Figure 1 A schematic diagram of the material tray structure of the embodiment shown; Figure 7 for Figure 1 The diagram shows the working conditions of the embodiment shown. Explanation of the reference numerals in the figure: 1. Foundation piles; 2. Standing platform support; 2-1. Square steel uprights, 2-2. Square steel cross braces, 2-3. Square steel diagonal braces, 2-4. First clamp, 2-5. L-shaped angle iron, 2-6. Laser instrument platform, 2-7. Square steel connecting rods; 3. Square steel composite plate; 4. Scaffolding planks; 5. Steel wire rope safety main cable; 5-1. Second clamp; 5-2. Rope clamp; 6. Material tray. Detailed Implementation
[0014] The present invention will be further described below with reference to the accompanying drawings and embodiments. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0015] Reference Figures 1 to 7 This embodiment provides a centralized photovoltaic support module workstation, including foundation piles 1 arranged at intervals. Each foundation pile 1 is fixedly installed with a standing platform support 2. Square steel combined flat plates 3 are installed on both sides of the top of the standing platform support 2. The square steel combined flat plates 3 are located on the same horizontal plane, and scaffolding boards 4 are installed between them. A steel wire rope safety cable 5 is installed on the top of the foundation pile 1, and a material support 6 is installed on the square steel combined flat plate 3.
[0016] In this embodiment, the foundation pile 1 includes a foundation pile body, and a bracket for installing photovoltaic panels is fixedly installed on the top of the foundation pile body. This is existing technology and will not be described in detail here.
[0017] In this embodiment, the standing platform support 2 includes a square steel upright 2-1. Square steel cross braces 2-2 are welded to the top left and right sides of the square steel upright 2-1 on the same horizontal plane. Square steel diagonal braces 2-3 are welded between the square steel cross braces 2-2 and the square steel upright 2-1. Two sets of first clamps 2-4 are welded to the front side of the square steel upright 2-1 for clamping with the foundation pile 1 to achieve installation and fixation. L-shaped angle irons 2-5 are welded to the outer end of the square steel cross braces 2-2 to limit the installation of the square steel combined plate 3. At the same time, they are used in conjunction with the scaffolding board 4 to achieve positioning of the square steel combined plate 3. A laser instrument platform 2-6 is also provided at the outer end of one side of the square steel cross brace 2-2. Based on this, the standing platform support 2 can be installed on the same horizontal plane with the help of a laser instrument.
[0018] Among them, located on the rear side of the square steel upright 2-1, between the left square steel horizontal brace 2-2 and the right square steel diagonal brace 2-3, a square steel connecting rod 2-7 is also welded, which plays a role in further stabilizing the overall support of the standing platform bracket 2.
[0019] In this embodiment, the square steel combination plate 3 includes three parallel square steel bars, which are welded together by rectangular iron sheets arranged at intervals. This provides support for construction workers and is also used to install scaffolding boards 4 and material supports 6.
[0020] In this embodiment, the scaffolding platform 4 is a finished product, connected to the square steel composite plate 3 via hooks at both ends. This provides sufficient space for construction workers and can also serve as a platform for placing large materials, such as photovoltaic panels and support materials, thereby improving construction convenience and efficiency. Specifically, the number of scaffolding platform 4 can be arranged according to actual conditions to facilitate construction.
[0021] In this embodiment, a second clamp 5-1 is fixedly installed on the top of the foundation pile 1. A hole for installing a steel wire rope safety siding 5 is provided on the outer side of the second clamp 5-1. One end of the steel wire rope safety siding 5 passes through this hole and is fixed by a rope clamp 5-2. Correspondingly, the other end of the steel wire rope safety siding 5 is also installed and fixed using the same structure. During construction, workers can attach their safety ropes to the steel wire rope safety siding 5 to ensure their safety.
[0022] In this embodiment, the material rack 6 includes a material box, and hooks are welded to both sides of the material box. The material rack 6 can be installed on the square steel outside the square steel composite plate 3 using these hooks to store small tools or materials, such as electric wrenches and screws. During construction, workers can place tools and commonly used accessories in the material rack 6 for easy access and placement.
[0023] Specific implementation process: During construction, the standing platform support 2 is first fixedly installed on the foundation pile 1. During installation, a laser device can be used to ensure the standing platform support 2 is installed on the same horizontal plane. Then, the square steel combined plate 3 is installed on the standing platform support 2. Next, scaffolding boards 4 are installed between the square steel combined plates 3, and material supports 6 are installed on the square steel combined plates 3. Finally, steel wire rope safety cables 5 are installed on the foundation pile 1. During the installation of the photovoltaic support and photovoltaic panels, construction workers attach safety ropes to the steel wire rope safety cables 5 and perform construction work on the square steel combined plates 3 and scaffolding boards 4. Specific working conditions are as follows: Figure 7 As shown.
[0024] Although embodiments of the present invention have been shown and described above, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A centralized photovoltaic support module operation station, comprising foundation piles arranged at intervals, characterized in that: Each foundation pile is fixedly equipped with a standing platform support. Square steel combined flat plates are installed on both sides of the top of the standing platform support. The square steel combined flat plates are located on the same horizontal plane, and scaffolding boards are installed between them. A steel wire rope safety cable is installed on the top of the foundation pile, and a material support is installed on the square steel combined flat plate.
2. The centralized photovoltaic support module workstation according to claim 1, characterized in that: The support frame for the standing platform includes square steel uprights. Square steel cross braces are welded to the top left and right sides of the square steel uprights on the same horizontal plane. Square steel diagonal braces are welded between the square steel cross braces and the square steel uprights. Two sets of first clamps are welded to the front side of the square steel uprights. L-shaped angle irons are welded to the outer ends of the square steel cross braces. A laser instrument platform is also provided at the outer end of one side of the square steel cross brace.
3. A centralized photovoltaic support module workstation according to claim 2, characterized in that: Located behind the square steel upright, a square steel connecting rod is welded between the square steel horizontal brace on the left and the square steel diagonal brace on the right.
4. A centralized photovoltaic support module workstation according to claim 1 or 2, characterized in that: The square steel composite plate comprises three parallel square steel bars, which are welded together by rectangular iron sheets arranged at intervals.
5. A centralized photovoltaic support module workstation according to claim 1 or 2, characterized in that: The scaffolding platform is connected to the square steel composite plate via hooks at both ends.
6. A centralized photovoltaic support module workstation according to claim 1 or 2, characterized in that: A second clamp is fixedly installed on the top of the foundation pile. A hole for installing a steel wire rope safety cable is opened on the outer side of the second clamp. One end of the steel wire rope safety cable passes through the hole and is fixed by a rope clamp. Correspondingly, the other end of the steel wire rope safety cable is also installed and fixed using the same structure.
7. A centralized photovoltaic support module workstation according to claim 1 or 2, characterized in that: The material tray includes a material box, and hooks are welded to both sides of the material box. The material tray can be installed on the square steel on the outside of the square steel composite plate by means of the hooks.