Technical Problem

目前,预制楼板的后浇带处的模板支设还是采用传统的形式,即先搭设脚手架,再在脚手架上搭设木质模板,而传统的模板搭设不仅会影响现场的施工空间,而且施工流程繁琐、稳定性差、严密性差、材料浪费严重,同时易出现跑浆、漏浆现象

Benefits of technology

[0011]本实用新型的有益效果是:为了提升预制楼板后浇带的支模效率、简化施工流程,同时为了解决模板支设的稳定性差和严密性差,材料浪费严重,易跑浆、漏浆等问题,使用该新型预制楼板后浇带吊模装置可以有效解决存在的上述问题。该新型预制楼板后浇带吊模装置在吊模模板前端设置了定位凸榫,且其进深长度不应小于50mm,在吊模模板后端设置了定位凹槽,且其开槽深度不应小于50mm,这不仅大大提升了模板安装效率,而且增强了模板拼接的牢固性和严密性,为了方便模板的安装和拆卸,在吊模模板的底面上设置了把手,为了提升模板的整体性和稳定性,将吊模模板、定位凸榫、定位凹槽和把手设置为一体结构,为了保护预制楼板,同时防止混凝土浇筑出现漏浆、跑浆现象,在吊模模板的顶面长边两侧设置有橡胶垫圈。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224918854U_ABST
    Figure CN224918854U_ABST
Patent Text Reader

Abstract

The utility model relates to a novel prefabricated floor post-cast strip hanging mould device, which is composed of a prefabricated floor, a hanging mould template, a backing plate, a positioning tenon, a positioning groove, a fastening connecting rod, a fastening nut, a reserved steel bar, a reserved bolt hole, a reinforcing plate, a rubber gasket and a handle. The end of the prefabricated floor is provided with a reserved steel bar, and the prefabricated floor is provided with a reserved bolt hole. The hanging mould template is provided with a reserved bolt hole corresponding to the prefabricated floor. The front end of the hanging mould template is provided with a positioning tenon, and the rear end of the hanging mould template is provided with a positioning groove. Rubber gaskets are arranged on the top surface of the hanging mould template on both sides of the long side. A handle is arranged on the bottom surface of the hanging mould template. The hanging mould template and the handle are arranged in an integrated structure. The prefabricated floor is provided with a backing plate on the top surface. The backing plate is provided with a reserved bolt hole. Four fastening connecting rods are arranged on the reinforcing plate at equal intervals, and the fastening connecting rods are welded and fixed to the reinforcing plate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of precast floor slab construction applications, and in particular to a novel precast floor slab post-pouring strip hoisting formwork device. Background Technology

[0002] Because prefabricated buildings are inherently green and environmentally friendly, a certain proportion of prefabricated components are used in construction projects. Among these, precast floor slabs are the most widely used. The pouring of the post-cast strip between precast floor slabs is crucial during installation, as it directly affects the overall construction quality. Currently, the formwork erection at the post-cast strip of precast floor slabs still uses traditional methods: first, scaffolding is erected, and then wooden formwork is placed on top of it. This traditional method not only affects the on-site construction space but also involves a cumbersome process, poor stability, poor sealing, and significant material waste. Furthermore, it is prone to grout leakage and other problems.

[0003] Therefore, in order to address these shortcomings, there is an urgent need for a new type of precast floor slab post-pouring strip hoisting device to solve the above problems, so as to comprehensively improve functionality, stability and convenience. Summary of the Invention

[0004] The purpose of this utility model is to overcome the aforementioned problems in the existing technology and provide a novel precast slab post-pouring strip formwork hoisting device. To achieve the above technical objective and effect, this utility model is implemented through the following technical solution:

[0005] A novel precast floor slab post-cast strip hoisting device comprises a precast floor slab, a hoisting template, a pad, positioning tenons, positioning grooves, fastening connecting rods, fastening nuts, reserved reinforcing bars, reserved bolt holes, a reinforcing plate, rubber washers, and a handle. Reserved reinforcing bars are provided at the ends of the precast floor slab, with the reserved reinforcing bars of adjacent precast floor slabs staggered. Reserved bolt holes are provided on the precast floor slab, and the hoisting template has reserved bolt holes corresponding to those on the precast floor slab. A pad is placed on top of the precast floor slab, with reserved bolt holes corresponding to those on the pad. Four fastening connecting rods are evenly spaced on the reinforcing plate and welded to the reinforcing plate. The top of the fastening connecting rods is threaded. The hoisting template is fixedly connected to the precast floor slab via the fastening connecting rods and fastening nuts.

[0006] Preferably, the front end of the hanging mold template is provided with a positioning tenon, and the rear end of the hanging mold template is provided with a positioning groove.

[0007] Preferably, the depth of the positioning tenon should not be less than 50mm, and the groove depth of the positioning groove should not be less than 50mm.

[0008] Preferably, a handle is provided on the bottom surface of the hanging formwork template.

[0009] Preferably, the lifting mold template, the positioning tenon, and the positioning groove are an integral structure, and the lifting mold template and the handle are an integral structure.

[0010] Preferably, rubber gaskets are provided on both sides of the long side of the top surface of the hanging mold template.

[0011] The beneficial effects of this utility model are as follows: To improve the formwork efficiency of post-cast strips in precast floor slabs and simplify the construction process, and to solve problems such as poor stability and tightness of formwork support, serious material waste, and easy grout leakage, this new type of precast floor slab post-cast strip formwork hanging device can effectively solve the above-mentioned problems. This new type of precast floor slab post-cast strip formwork hanging device has a positioning tenon at the front end of the hanging formwork with a depth of not less than 50mm, and a positioning groove at the rear end with a groove depth of not less than 50mm. This not only greatly improves the formwork installation efficiency but also enhances the firmness and tightness of the formwork splicing. To facilitate the installation and disassembly of the formwork, a handle is provided on the bottom surface of the hanging formwork. To improve the integrity and stability of the formwork, the hanging formwork, positioning tenon, positioning groove, and handle are integrated into a single structure. To protect the precast floor slab and prevent grout leakage during concrete pouring, rubber gaskets are provided on both sides of the long side of the top surface of the hanging formwork.

[0012] The method of using this utility model is as follows: First, place the first hanging formwork template at the post-pouring strip position of the two precast floor slabs, aligning the hanging formwork template with the reserved bolt holes of the precast floor slabs. Then, insert the fastening connecting rod into the reserved bolt holes, and place the pad through the fastening connecting rod on the top surface of the precast floor slab. Tighten each fastening connecting rod with the fastening nut. When installing the second hanging formwork template, first insert the positioning protrusion at the front end of the second hanging formwork template into the positioning groove at the rear end of the first hanging formwork template to complete the splicing of the two hanging formwork templates. Then, repeat the above steps to fix the second hanging formwork template. Repeat the above steps until the formwork of the post-pouring strip of the precast floor slab is completed. Finally, pour the concrete. After the concrete reaches the required strength, loosen the fastening nut and remove the pad, fastening connecting rod and hanging formwork template in sequence to complete the pouring of the post-pouring strip of the precast floor slab. Attached Figure Description

[0013] Figure 1 A schematic diagram of the overall structure of this utility model.

[0014] Figure 2 A schematic diagram of the bottom surface of the overall structure of this utility model.

[0015] Figure 3 A schematic diagram of the prefabricated floor slab structure of this utility model.

[0016] Figure 4A schematic diagram of the hanging formwork template structure of this utility model.

[0017] Figure 5 A schematic diagram of the bottom surface of the hanging formwork template of this utility model.

[0018] Figure 6 A schematic diagram of the fastening connecting rod structure of this utility model.

[0019] Attached reference numerals: 1 Precast floor slab, 2 Hanging formwork template, 3 Pad plate, 4 Positioning tenon, 5 Positioning groove, 6 Fastening connecting rod, 7 Fastening nut, 8 Reserved reinforcing bar, 9 Reserved bolt hole, 10 Reinforcing plate, 11 Rubber washer, 12 Handle. Detailed Implementation

[0020] According to the attached drawings, a novel precast floor slab post-cast strip hoisting device comprises a precast floor slab 1, a hoisting template 2, a pad 3, a positioning tenon 4, a positioning groove 5, a fastening connecting rod 6, a fastening nut 7, reserved reinforcing bars 8, reserved bolt holes 9, a reinforcing plate 10, rubber washers 11, and a handle 12. Reserved reinforcing bars 8 are provided at the ends of the precast floor slab 1, and the reserved reinforcing bars 8 of adjacent precast floor slabs 1 are staggered. Reserved bolt holes 9 are provided on the precast floor slab 1. The formwork template 2 is provided with reserved bolt holes 9 corresponding to the precast floor slab 1. A pad 3 is provided on the top of the precast floor slab 1. The pad 3 is provided with reserved bolt holes 9 corresponding to the precast floor slab 1. Four fastening connecting rods 6 are provided at equal intervals on the reinforcing plate 10. The fastening connecting rods 6 are welded and fixed to the reinforcing plate 10. The top of the fastening connecting rods 6 is provided with threads. The formwork template 2 is fixedly connected to the precast floor slab 1 through the fastening connecting rods 6 and fastening nuts 7.

[0021] As an improvement, in order to facilitate the splicing and installation of the template and improve the template installation efficiency, the front end of the hanging template 2 is provided with a positioning tenon 4, and the rear end of the hanging template 2 is provided with a positioning groove 5.

[0022] As an improvement, in order to enhance the firmness and tightness of the template splicing, the depth of the positioning tenon 4 should not be less than 50mm, and the groove depth of the positioning groove 5 should not be less than 50mm.

[0023] As an improvement, a handle 12 is provided on the bottom surface of the hanging formwork template 2 to facilitate the installation and disassembly of the template.

[0024] As an improvement, in order to enhance the integrity and stability of the template, the hanging template 2, the positioning tenon 4 and the positioning groove 5 are integrated into one structure, and the hanging template 2 and the handle 12 are integrated into one structure.

[0025] As an improvement, in order to prevent grout leakage and runoff during concrete pouring, and to protect the precast floor slab, rubber gaskets 11 are provided on both sides of the long side of the top surface of the suspended formwork 2.

[0026] For those skilled in the art, the present invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of the present invention. Without departing from the spirit and scope of the present invention, various changes, modifications, substitutions and improvements can be made to these embodiments, all of which fall within the scope of the present invention as claimed.

Claims

1. A novel precast floor slab post-cast strip hoisting formwork device, comprising a precast floor slab (1), hoisting formwork template (2), pad plate (3), positioning tenon (4), positioning groove (5), fastening connecting rod (6), fastening nut (7), reserved reinforcing bar (8), reserved bolt hole (9), reinforcing plate (10), rubber washer (11), and handle (12), characterized in that: The precast floor slab (1) is provided with reserved steel bars (8) at its end. The reserved steel bars (8) of two adjacent precast floor slabs (1) are staggered. The precast floor slab (1) is provided with reserved bolt holes (9). The formwork template (2) is provided with reserved bolt holes (9) corresponding to the precast floor slab (1). The precast floor slab (1) is provided with a pad (3). The pad (3) is provided with reserved bolt holes (9) corresponding to the precast floor slab (1). The reinforcing plate (10) is provided with four fastening connecting rods (6) at equal intervals. The fastening connecting rods (6) are welded and fixed to the reinforcing plate (10). The top of the fastening connecting rods (6) is provided with threads. The formwork template (2) is fixedly connected to the precast floor slab (1) through the fastening connecting rods (6) and fastening nuts (7).

2. The novel precast slab post-pouring strip hoisting formwork device as described in claim 1, characterized in that: The front end of the hanging mold template (2) is provided with a positioning tenon (4), and the rear end of the hanging mold template (2) is provided with a positioning groove (5).

3. The novel precast slab post-pouring strip hoisting formwork device as described in claim 2, characterized in that: The depth of the positioning tenon (4) should not be less than 50 mm, and the groove depth of the positioning groove (5) should not be less than 50 mm.

4. The novel precast slab post-pouring strip hoisting formwork device as described in claim 2, characterized in that: A handle (12) is provided on the bottom surface of the hanging formwork template (2).

5. A novel precast slab post-pouring strip hoisting formwork device as described in claim 4, characterized in that: The hanging mold template (2), the positioning tenon (4) and the positioning groove (5) are an integral structure, and the hanging mold template (2) and the handle (12) are set as an integral structure.

6. The novel precast slab post-pouring strip hoisting formwork device as described in claim 1, characterized in that: Rubber gaskets (11) are provided on both sides of the long side of the top surface of the hanging formwork template (2).