House building tower crane wall supporting anti-loose fastening buckle

By incorporating sensors and warning lights into the tower crane's support fasteners, combined with circular springs and anti-loosening nuts, the problems of loosening and insufficient monitoring of tower cranes under vibration conditions are solved. This enables real-time monitoring and safety warning of preload, improving the reliability and service life of the connection.

CN224996401UActive Publication Date: 2026-11-20WUHAN MUNICIPAL ENG MECHANIZED CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522652780.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-15
Publication Date
2026-11-20
Estimated Expiration
2035-12-15

AI Technical Summary

Technical Problem

Existing tower crane support fasteners are prone to loosening under vibration conditions and lack real-time monitoring, posing a safety hazard, and current technology cannot provide timely warnings.

Method used

A tower crane buttress anti-loosening fastener was designed, which includes sensors and warning lights. The preload status is monitored by vibration sensors and feedback is provided by warning lights. Combined with circular springs and anti-loosening nuts, dynamic buffering and static locking are achieved to ensure connection reliability.

Benefits of technology

It enables active monitoring and timely early warning of preload under vibration conditions, improving the reliability and safety of the connection, reducing the risk of loosening, and extending the service life of the device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224996401U_ABST
    Figure CN224996401U_ABST
Patent Text Reader

Abstract

The utility model discloses a kind of housing construction tower crane wall fastening fastening parts, belong to tower crane technical field, including hoop, support wall, fixed frame, rotating nut, knob, bolt, sensor, warning light, circular spring, locknut one and locknut two, support wall is fixedly connected in hoop rear side, sensor is fixedly connected in hoop rear side top, warning light is fixedly connected in sensor top, circular spring is fixedly connected around and installed in the outer wall of rotating nut, locknut one is fixedly connected hoop right side with support wall, locknut two is fixedly connected in hoop left side with fixed frame. The utility model is provided with sensor and warning light, solve the problem that pre-tightening force cannot be detected in prior art, there is a security risk, can actively monitor fastening state, early warning to ensure safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of tower crane technology, and in particular to anti-loosening fasteners for tower crane support walls in building construction. Background Technology

[0002] Tower cranes are indispensable vertical transportation equipment in high-rise buildings. As the building height increases, the tower crane body needs to be connected to the main building through a support wall device to ensure the stability of the tower crane itself. The support wall device usually includes clamps and fasteners, which are used to fix the tower body to the building structure.

[0003] Existing support and wall fastening fasteners mostly use bolts and nuts for pre-tightening, relying mainly on the friction between the threaded pairs to prevent loosening. However, during the lifting, slewing, and luffing operations of tower cranes, continuous and intense vibrations and impact loads are generated. This vibration continuously acts on the fastening fasteners. Under continuous vibration and impact, the traditional bolt and nut connection method, which relies solely on friction, will loosen, leading to a decrease in pre-tightening force. This makes the fixation between the clamp and the tower body less secure, greatly reducing the connection reliability of the support and wall fastening device, causing serious safety hazards and threatening construction safety.

[0004] Furthermore, existing technologies lack effective real-time monitoring methods for such a decrease in preload and loosening of fasteners. Maintenance personnel can usually only rely on regular manual inspections and experience-based judgment to re-tighten them. This method is not only inefficient but also has a lag effect, making it impossible to detect and warn of potential problems in the early stages of loosening.

[0005] Therefore, this utility model proposes a fastening fastener for the anti-loosening of tower crane support walls in building construction to address the shortcomings of existing technologies. Utility Model Content

[0006] In view of the existing technology, the anti-loosening fasteners for tower crane support walls in building construction have the problems of loosening under vibration conditions and lack of real-time monitoring of pre-tightening force, which pose safety hazards. This utility model aims to provide an improved anti-loosening fastener for tower crane support walls in building construction that can effectively solve the above problems.

[0007] This utility model provides anti-loosening fasteners for tower crane support walls in building construction, including: clamps, support walls, fixing frames, fixing screws, rotating nuts, knobs, bolts, sensors, warning lights, circular springs, anti-loosening nuts one and two.

[0008] Furthermore, the support wall is fixedly connected to the rear side of the clamp, the fixing bracket is set on the left side of the clamp, the fixing screws are threadedly connected to the four corners of the support wall, the rotating nut is threadedly connected to the gap on the front side of the clamp, the knob is connected to the left side of the rotating nut, the bolt is connected to the outer wall of the right end of the rotating nut, the sensor is fixedly connected to the top of the rear side of the clamp, the warning light is fixedly connected to the top of the sensor, the circular spring is fixedly installed around the outer wall of the rotating nut, the anti-loosening nut one is fixedly connected to the right side of the clamp and threadedly connected to the support wall, and the anti-loosening nut two is fixedly connected to the left side of the clamp and the fixing bracket.

[0009] Preferably, the anti-loosening fastener for the tower crane support wall of the building also includes a lug, one end of which is welded to the bottom of the clamp, and the other end is connected to the support wall, for transmitting the horizontal force of the tower crane.

[0010] Preferably, a buffer pad is fixedly installed on the rear outer wall of the supporting buttress. The buffer pad is made of elastic material and is used to provide cushioning and distribute pressure between the supporting buttress and the main building support.

[0011] Preferably, the clamp has a two-part structure, with the gap on the front side located between the ends of the two parts. The rotating nut is used to adjust the spacing of the gap to change the tightness of the clamp.

[0012] Preferably, the sensor is a vibration sensor, used to monitor the preload of the clamps when the tower crane is under simulated vibration conditions, and to provide feedback through a warning light.

[0013] Preferably, the warning light includes a green light-emitting unit and a red light-emitting unit, wherein the green light-emitting unit is used to indicate sufficient preload and the red light-emitting unit is used to indicate insufficient preload.

[0014] Preferably, the circular spring is a metal buffer spring, which fits tightly against the outer wall of the rotating nut to absorb the impact force generated during tower crane operation, so as to prevent the rotating nut from loosening due to vibration.

[0015] Preferably, both the first and second anti-loosening nuts are self-locking nuts or combinations of nuts with anti-loosening washers, used to statically lock the clamp after the clamp is adjusted to sufficient preload.

[0016] This utility model has the following beneficial effects: 1. This utility model solves the problem in the prior art that it is impossible to detect the pre-tightening force of the fasteners before the tower crane is in operation, which poses a safety hazard, by setting up a sensor and warning light fixed to the clamp. It achieves the effect of actively monitoring the fastening status, providing early warning, and ensuring fastening safety under simulated vibration conditions.

[0017] 2. This utility model solves the problem that traditional fasteners rely solely on thread friction for anti-loosening and fail under vibration and impact by setting a circular spring on the outer wall of the rotating nut, and cooperating with anti-loosening nut one and anti-loosening nut two. It achieves the effect of combining dynamic buffering and vibration absorption with static double locking, greatly improving the connection reliability and anti-loosening performance.

[0018] 3. This utility model solves the problem of hard metal contact, wear and deformation between the supporting wall and the main building support by fixing buffer pads to the rear outer wall of the supporting wall. It achieves the effects of dispersing pressure, avoiding hard collisions, reducing wear on the contact surface and extending the service life of the device. Attached Figure Description

[0019] The present invention will be further described below with reference to the accompanying drawings and embodiments. In the accompanying drawings: Figure 1 This is a perspective view of the anti-loosening fastening fastener for tower crane support walls in building construction proposed in this utility model; Figure 2 This is a partial structural diagram of the warning light of the anti-loosening fastening fastener for tower crane support wall of a building proposed in this utility model; Figure 3 This is a partial structural diagram of the support wall of the anti-loosening fastener for tower crane support walls in building construction proposed in this utility model; Figure 4 This is a partial structural diagram of the knob of the anti-loosening fastening fastener for the tower crane support wall of the building proposed in this utility model.

[0020] Legend: 1. Clamp; 2. Support for wall; 3. Anti-loosening nut one; 4. Anti-loosening nut two; 5. Fixing bracket; 6. Knob; 7. Circular spring; 8. Rotary nut; 9. Bolt; 10. Sensor; 11. Warning light; 12. Ear rod; 13. Fixing screw; 14. Buffer pad. Detailed Implementation

[0021] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions of the embodiments of this utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this utility model. It should be understood that the specific embodiments described herein are only used to explain this utility model and are not intended to limit this utility model. Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this utility model.

[0022] Example: Please refer to Figures 1 to 4This utility model provides a fastener for preventing loosening of tower crane support walls in building construction. It aims to solve the problem that existing tower crane support wall fasteners loosen under vibration conditions and lack real-time monitoring of pre-tightening force, which leads to safety hazards.

[0023] Please refer to Figure 1 , Figure 3 and Figure 4 The anti-loosening fastening fastener for tower crane support walls in building construction includes a clamp 1 and a support wall 2 fixedly connected to the rear side of the clamp 1. The clamp 1 is used to wrap and stabilize the tower body, and the support wall 2 is used to connect to the main building structure. The clamp 1 has a two-part structure. Fixing screws 13 are threaded at the four corners of the support wall 2. The fixing screws 13 are used to anchor the support wall 2 to the main building support. A buffer pad 14 is fixedly installed on the rear outer wall of the support wall 2. The buffer pad 14 is made of elastic material and is used to provide cushioning and distribute pressure between the support wall 2 and the main building support. One end of the lug 12 is welded to the bottom of the clamp 1, and the other end of the lug 12 is connected to the support wall 2. The lug 12 is used to transmit the horizontal force of the tower crane. It is located between the two halves in the gap on the front side of the clamp 1. The rotating nut 8 is threaded through and connected to the gap on the front side of the clamp 1. The knob 6 is rotatably connected to the left side of the rotating nut 8, and the bolt 9 is rotatably connected to the outer wall of the right end of the rotating nut 8. Rotating the knob 6 can drive the rotating nut 8 to adjust the gap and change the tightness of the clamp 1. The bolt 9 is used to strengthen the connection between the rotating nut 8 and the clamp 1.

[0024] Please refer to Figure 1 and Figure 4 To achieve dynamic anti-loosening, a circular spring 7 is fixedly installed around the outer wall of the rotating nut 8. The circular spring 7 is a metal buffer spring. The circular spring 7 fits tightly against the outer wall of the rotating nut 8 to absorb the impact force generated when the tower crane is working, so as to prevent the rotating nut 8 from loosening due to vibration.

[0025] Please refer to Figure 1 and Figure 3 To achieve static locking, the fastener also includes a fixing bracket 5. Anti-loosening nut 1 3 is fixedly connected to the right side of the clamp 1 and threadedly connected to the support wall 2. Anti-loosening nut 2 4 is fixedly connected to the left side of the clamp 1 and the fixing bracket 5. The fixing bracket 5 is located on the left side of the clamp 1. Anti-loosening nut 1 3 and anti-loosening nut 2 4 are both self-locking nuts or combinations of nuts with anti-loosening washers, used to statically lock the clamp 1 after the clamp 1 is adjusted to sufficient preload.

[0026] Please refer to Figure 1 and Figure 2To achieve active monitoring, the fastener also includes a sensor 10, which is fixedly connected to the top rear side of the clamp 1. A warning light 11 is fixedly connected to the top of the sensor 10. The sensor 10 is a vibration sensor, used to monitor the preload status of the clamp 1 when the tower crane is under simulated vibration conditions, and to provide feedback through the warning light 11. The warning light 11 includes a green light-emitting unit and a red light-emitting unit. The green light-emitting unit is used to indicate that the preload is sufficient, and the red light-emitting unit is used to indicate that the preload is insufficient.

[0027] Please refer to Figure 1 , Figure 2 and Figure 4 Sensor 10 is fixedly connected to the top rear side of clamp 1. Sensor 10 has a detection module for monitoring vibration or pressure. The function of sensor 10 is to detect the tightness of clamp 1 and whether the preload is sufficient when the tower crane is started to perform small slewing or luffing movements to simulate vibration conditions before operation. Warning light 11 is fixedly connected to the top of sensor 10. Warning light 11 is equipped with a green light-emitting unit and a red light-emitting unit. When sensor 10 detects sufficient preload and stable clamp 1, the green light-emitting unit remains constantly lit. When sensor 10 detects insufficient preload or abnormal vibration, the red light-emitting unit flashes, thus providing a clear visual indication. The operator is reminded to tighten the screws again. A circular spring 7 is correspondingly installed on the outer wall of the rotating nut 8. The circular spring 7 is fixedly installed around the outer wall of the rotating nut 8. The circular spring 7 is a metal buffer spring. In the assembled state, the circular spring 7 fits tightly against the outer wall of the rotating nut 8. This cooperative structure between the circular spring 7 and the rotating nut 8 ensures that when the tower crane generates continuous vibration and impact force during operation, the circular spring 7 can absorb and buffer the impact energy by its own elastic deformation, avoiding the impact force from acting directly on the threaded connection between the rotating nut 8 and the clamp 1, thereby reducing the risk of the rotating nut 8 loosening and maintaining the locked state of the clamp 1.

[0028] As a preferred embodiment, in order to maintain the stability of the overall structure and the effective transmission of horizontal force, the fastener also includes a lug 12. One end of the lug 12 is fixed to the bottom of the clamp 1 by welding, and the other end of the lug 12 is connected to the support wall 2. The lug 12 is used to transmit the horizontal force of the tower crane.

[0029] As another preferred embodiment, in order to distribute pressure, avoid hard metal-to-hard contact, and reduce wear and deformation of the contact surface, a buffer pad 14 is fixedly installed on the rear outer wall of the support wall 2. The buffer pad 14 is made of elastic material and is used to provide buffering and distribute pressure between the support wall 2 and the main building support.

[0030] As another preferred embodiment, in order to adjust the tightness of the tower body, the clamp 1 has a two-part structure, with the gap on the front side located between the ends of the two parts. The rotating nut 8 is threaded through and connected to the gap on the front side. The rotating nut 8 is used to adjust the spacing of the gap to change the tightness of the clamp 1 on the tower body.

[0031] As another preferred embodiment, in order to confirm the fastening status safely before work, the sensor 10 is a vibration sensor 10, which is used to monitor the preload of the clamp 1 when the tower crane performs small-amplitude rotation and luffing movements to simulate vibration conditions, and provides real-time feedback to the operator through the warning light 11.

[0032] As another preferred embodiment, in order to clearly indicate to the operator whether the preload is sufficient, the warning light 11 includes a green light-emitting unit and a red light-emitting unit. The green light-emitting unit is used to indicate that the preload is sufficient, and the red light-emitting unit is used to indicate that the preload is insufficient. When the red light-emitting unit flashes, it prompts the operator to retighten.

[0033] As another preferred embodiment, in order to ensure the effectiveness and durability of dynamic buffering, the circular spring 7 is a metal buffer spring. The circular spring 7 is closely attached to the outer wall of the rotating nut 8 to absorb the impact force generated when the tower crane is working, so as to prevent the rotating nut 8 from loosening due to vibration.

[0034] In another preferred embodiment, in order to statically lock the position of the clamp 1 and ensure that the clamp 1 does not loosen after being adjusted to the correct position, both the first anti-loosening nut 3 and the second anti-loosening nut 4 are self-locking nuts or nut combinations with anti-loosening washers. The first anti-loosening nut 3 is fixedly connected to the right side of the clamp 1 and threadedly connected to the support wall 2, and the second anti-loosening nut 4 is fixedly connected to the left side of the clamp 1 and the fixing frame 5. The first anti-loosening nut 3 and the second anti-loosening nut 4 are used to provide static locking for the clamp 1 after it has been adjusted to the preload.

[0035] Working principle: During tightening, the clamp 1 wraps around the outside of the tower body for stability, and the support wall 2 is fixedly connected to the back of the clamp 1. Through the synergistic action of the support wall 2 and the fixing screw 13, the clamp 1 is firmly fixed to the main support of the building. Then, the operator turns the knob 6 connected to the left side of the rotating nut 8. The knob 6 drives the rotating nut 8 to turn in or out of the gap on the front side of the clamp 1, thereby adjusting the tightness of the clamp 1. After adjustment, the connection between the rotating nut 8 and the clamp 1 can be strengthened by turning the bolt 9 connected to the outer wall of the right end of the rotating nut 8. After adjustment, the anti-loosening nut 13 is fixedly connected to the right side of the clamp 1 and threaded to the support wall 2. The anti-loosening nut 24 is fixedly connected to the left side of the clamp 1 and the fixing bracket 5 set on the left side of the clamp 1. Both anti-loosening nuts 13 and anti-loosening nuts 24 are self-locking nuts or combinations of nuts with anti-loosening washers, which together statically lock the clamp 1 to prevent the clamp 1 from loosening. When the tower crane vibrates during operation, the circular spring 7 fixedly installed around the outer wall of the rotating nut 8 undergoes elastic deformation. The circular spring 7 is a metal buffer spring that can absorb and buffer the impact force generated by the vibration, avoiding the impact force from acting directly on the threaded connection of the rotating nut 8 and reducing the risk of the rotating nut 8 loosening. Before starting work, the tower crane can be started to perform small slewing and luffing movements to simulate vibration conditions. At this time, the sensor 10 fixedly connected to the top of the rear side of the clamp 1, which is a vibration sensor, starts to monitor the preload of the clamp 1. The warning light 11 fixedly connected to the top of the sensor 10 provides feedback based on the signal from the sensor 10. If the red light-emitting unit of the warning light 11 flashes, it indicates that the preload is insufficient and the knob 6 needs to be tightened again. If the green light-emitting unit of the warning light 11 remains green, it indicates that the preload is sufficient and it is safe to work. During the entire working process, the lug 12 welded to the bottom of the clamp 1 and connected to the support wall 2 continuously transmits the horizontal force of the tower crane to maintain structural stability. At the same time, the buffer pad 14 fixedly installed on the outer wall of the rear side of the support wall 2 can distribute the pressure between the support wall 2 and the main building support, avoid metal-to-metal contact, and reduce wear and deformation of the contact surface.

[0036] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances. Furthermore, in the description of this utility model, unless otherwise stated, "a plurality of" means two or more.

[0037] It should be understood that those skilled in the art can make improvements or modifications based on the above description, and all such improvements and modifications should fall within the protection scope of the appended claims.

Claims

1. A fastener for preventing loosening of tower crane support walls in building construction, characterized in that, include: The clamp (1); the support wall (2), which is fixedly connected to the rear side of the clamp (1); the fixing bracket (5); the fixing screw (13), which is threadedly connected to the four corners of the support wall (2); the rotating nut (8), which is threadedly connected to the gap on the front side of the clamp (1); the knob (6), which is rotatably connected to the left side of the rotating nut (8); the bolt (9), which is rotatably connected to the outer wall of the right end of the rotating nut (8); characterized in that it further includes: a sensor (10), which is a sensor The device (10) is fixedly connected to the top rear side of the clamp (1); the warning light (11) is fixedly connected to the top of the sensor (10); the circular spring (7) is fixedly installed around the outer wall of the rotating nut (8); the first anti-loosening nut (3) is fixedly connected to the right side of the clamp (1) and threadedly connected to the support wall (2); and the second anti-loosening nut (4) is fixedly connected to the left side of the clamp (1) and the fixing frame (5), and the fixing frame (5) is located on the left side of the clamp (1).

2. The anti-loosening fastener for tower crane support walls in building construction according to claim 1, characterized in that, The fastener also includes a lug (12), one end of which is welded to the bottom of the clamp (1) and the other end is connected to the support wall (2) to transmit the horizontal force of the tower crane.

3. The anti-loosening fastener for tower crane support walls in building construction according to claim 1, characterized in that, A buffer pad (14) is fixedly installed on the rear outer wall of the supporting wall (2). The buffer pad (14) is made of elastic material and is used to provide buffering and distribute pressure between the supporting wall (2) and the main building support.

4. The anti-loosening fastener for tower crane support walls in building construction according to claim 1, characterized in that, The clamp (1) has a two-part structure, and the gap on the front side is located between the ends of the two parts. The rotating nut (8) is used to adjust the spacing of the gap to change the tightness of the clamp (1).

5. The anti-loosening fastener for tower crane support walls in building construction according to claim 1, characterized in that, The sensor (10) is a vibration sensor (10) used to monitor the preload state of the clamp (1) when the tower crane is under simulated vibration conditions, and to provide feedback through the warning light (11).

6. The anti-loosening fastener for tower crane support walls in building construction according to claim 1, characterized in that, The warning light (11) includes a green light-emitting unit and a red light-emitting unit.

7. The anti-loosening fastener for tower crane support walls in building construction according to claim 6, characterized in that, The green light-emitting unit is used to indicate that the preload is sufficient, and the red light-emitting unit is used to indicate that the preload is insufficient.

8. The anti-loosening fastener for tower crane support walls in building construction according to claim 1, characterized in that, The circular spring (7) is a metal buffer spring.

9. The anti-loosening fastener for tower crane support walls in building construction according to claim 8, characterized in that, The circular spring (7) fits tightly against the outer wall of the rotating nut (8) to absorb the impact force generated when the tower crane is working, so as to prevent the rotating nut (8) from loosening due to vibration.

10. The anti-loosening fastener for tower crane support walls in building construction according to claim 1, characterized in that, The first anti-loosening nut (3) and the second anti-loosening nut (4) are both self-locking nuts or nut combinations with anti-loosening washers, used to statically lock the clamp (1) after the clamp (1) is adjusted to sufficient preload.