Multi-group interconnection blast furnace fan cooling device

By designing multiple interconnected cooling devices, the cooling water for blast furnace blowers was rationally distributed and temperature differences were utilized, solving the problems of wear and icing caused by heat accumulation in blast furnace blowers, improving production stability and reducing energy consumption.

CN224996927UActive Publication Date: 2026-11-20WUAN YUHUA IRON & STEEL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522342208.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-05
Publication Date
2026-11-20
Estimated Expiration
2035-11-05

AI Technical Summary

Technical Problem

During long-term operation, the blast furnace blower experiences heat accumulation, leading to wear and aging of parts, which affects production stability and efficiency. Existing cooling equipment is energy-intensive and prone to freezing in winter, causing equipment damage.

Method used

Multiple interconnected cooling devices are adopted, and the cooling water volume is rationally allocated through the interconnected water circulation structure between the industrial cooling tower and the fan cooling tower, so as to realize the effective circulation of cooling water and the utilization of temperature differences, and avoid local overheating and icing problems.

Benefits of technology

It improves cooling efficiency, reduces energy consumption, ensures stable operation of the fan, prevents equipment failure, reduces maintenance costs, and solves the problem of equipment damage due to icing in winter.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224996927U_ABST
    Figure CN224996927U_ABST
Patent Text Reader

Abstract

The utility model discloses a multi -group intercommunication formula blast furnace fan cooling device, include: equipment base, industrial cooling tower and three fan cooling towers, industrial cooling tower installs on equipment base right -hand side position, three fan cooling towers are set gradually in industrial cooling tower left side position, and the intercommunication water circulation structure is installed on industrial cooling tower with three fan cooling towers, the utility model relates to blast furnace cooling equipment technical field, the beneficial effect of the case is: the blast furnace existing industrial cooling tower, fan cooling tower all independent use each, and the water circulation amount of fan is about 900m3 / h, and the industrial normal pressure water circulation amount is about 3000m3 / h, and the industrial normal pressure water quantity is big in the cooling use process, and the water temperature is high, and the cooling difficulty, need increase the power of industrial cooling tower cooling equipment to guarantee the quick cooling efficiency, thereby cause the high energy consumption, and the water quantity of fan is small, and the temperature is low, and when using, the water tower inside is frozen seriously to the equipment damage problem of low temperature influence in winter.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the technical field of blast furnace cooling equipment, specifically a multi-unit interconnected blast furnace fan cooling device. Background Technology

[0002] In the blast furnace ironmaking process, the blast furnace blower is a key piece of equipment, and its stable operation plays a decisive role in the continuity and efficiency of the entire production process. During prolonged operation, the blast furnace blower generates a large amount of heat. If it cannot be cooled effectively and in a timely manner, the internal components of the blower will experience accelerated wear and aging due to the high temperature, and may even malfunction, leading to a decline in blower performance, affecting the normal air supply to the blast furnace, and consequently causing unstable blast furnace production, reduced production efficiency, and increased production costs. Currently, the existing industrial cooling tower and blower cooling tower are used independently. The blower's water circulation volume is approximately 900 m³ / h, while the industrial atmospheric pressure water circulation volume is approximately 3000 m³ / h. During cooling operations, the large volume and high temperature of the industrial atmospheric pressure water make cooling difficult, requiring increased power in the industrial cooling towers to ensure rapid cooling efficiency, resulting in high energy consumption. Meanwhile, the blower's water volume is small and the temperature is low; in winter, the interior of the water tower is severely affected by low temperatures, leading to severe icing and damage to the equipment. Utility Model Content

[0003] To achieve the above objectives, this utility model is implemented through the following technical solution: a multi-group interconnected blast furnace blower cooling device, comprising: an equipment base, an industrial cooling tower and three blower cooling towers, wherein the industrial cooling tower is installed on the right side of the equipment base, and the three blower cooling towers are arranged sequentially on the left side of the industrial cooling tower, and a connected water circulation structure is installed on the industrial cooling tower and the three blower cooling towers.

[0004] The interconnected water circulation structure includes: equipment support, circulation pump set, pumping water pipe, water injection pipe, first branch water pipe, second branch water pipe, filter and purification components, three circulation inlet pipes and three circulation outlet pipes.

[0005] The equipment support is mounted on the equipment base and located in front of the industrial cooling tower. The circulating pump set is mounted on the equipment support. One end of the pumping water pipe is mounted on the circulating pump set, and the other end extends through the top of the industrial cooling tower into its interior. One end of the water injection pipe is mounted on the circulating pump set, and the other end extends through the bottom of the industrial cooling tower into its interior. The first branch water pipe is mounted on the circulating pump set and connected to the pumping water pipe. The second branch water pipe is mounted on the circulating pump set and connected to the water injection pipe. The filter purification component is embedded in the middle of the first and second branch water pipes. Three circulating water inlet pipes are mounted on the first branch water pipe, and the other end extends through the top of the side wall of the three fan cooling towers into its interior. Three circulating water outlet pipes are mounted on the second branch water pipe and extend through the bottom of the outer wall of the three fan cooling towers into their interior.

[0006] Preferably, the circulating pump unit is mounted on the equipment bracket by fixing bolts.

[0007] Preferably, the three circulating water inlet pipes are equipped with flow-stop valves.

[0008] Preferably, the filtration and purification assembly includes: a filter box, a pair of purification chambers, a pair of partition plates, a packing mesh frame, purification packing, and a sealing cover.

[0009] The filter box is installed on the equipment base and embedded in the middle of the first and second water distribution pipes. A pair of purification chambers are opened in the filter box. A pair of partition plates are vertically installed in the middle of the pair of purification chambers. The packing mesh frame is set in the lower part of the purification chamber. The purification packing is placed in the purification chamber and located above the packing mesh frame. The sealing cover is installed at the top of the filter box.

[0010] Preferably, the sealing cover is installed on the filter box by a locking pin.

[0011] Preferably, the sealing cover is placed at the top of the filter box via a support bracket.

[0012] Beneficial effects

[0013] This utility model provides a multi-unit interconnected blast furnace blower cooling device, which has the following beneficial effects: This multi-unit interconnected blast furnace blower cooling device, by setting up an industrial cooling tower and three blower cooling towers, and adopting a connected water circulation structure, achieves effective circulation and distribution of cooling water. The industrial cooling tower and the three blower cooling towers are arranged sequentially and interconnected, which can rationally allocate the cooling water volume according to the actual heat dissipation requirements of the blast furnace blower, ensuring that all parts of the blower are adequately cooled, greatly improving cooling efficiency, effectively avoiding equipment failures caused by local overheating, and ensuring the stable operation of the blast furnace blower. The device connects and circulates the cooling water from different cooling towers, and utilizes the temperature difference between the cooling water in different towers for mutual coordination. In winter, it can balance the temperature of the blower water and the industrial water, solving the problem of blower cooling tower... The problem of internal icing damaging equipment in winter and rising summer temperatures requires balancing the water volume of each cooling tower and the water temperature of the fan and industrial water. This effectively reduces industrial water temperature, decreases fan usage, and thus reduces energy consumption and maintenance costs. While ensuring cooling effect, it also reduces industrial energy consumption and ensures equipment safety. This solution addresses the existing problems of the blast furnace's industrial cooling towers and fan cooling towers, which are currently used independently. The fan water circulation rate is approximately 900 m³ / h, and the industrial atmospheric pressure water circulation rate is approximately 3000 m³ / h. During cooling operation, the large volume and high temperature of the industrial atmospheric pressure water make cooling difficult, requiring increased power in the industrial cooling towers to ensure rapid cooling efficiency, resulting in high energy consumption. Conversely, the small fan water volume and low temperature cause severe icing inside the towers in winter, damaging the equipment. Attached Figure Description

[0014] Figure 1 This is a three-dimensional structural diagram of a multi-group interconnected blast furnace fan cooling device according to the present invention.

[0015] Figure 2 This is a front view structural diagram of a multi-group interconnected blast furnace fan cooling device according to the present invention.

[0016] Figure 3 This is a schematic diagram of the main sectional view of the filter box of a multi-unit interconnected blast furnace blower cooling device according to the present invention.

[0017] Figure 4 This is a side sectional view of the filter box of a multi-unit interconnected blast furnace blower cooling device according to the present invention.

[0018] In the diagram: 1-Equipment base; 2-Industrial cooling tower; 3-Fan cooling tower; 4-Equipment support; 5-Circulating pump set; 6-Water delivery pipe; 7-Water injection pipe; 8-First branch pipe; 9-Second branch pipe; 10-Circulating water inlet pipe; 11-Circulating water outlet pipe; 12-Fixing bolt; 13-Stop valve; 14-Filter box; 15-Purification chamber; 16-Partition partition; 17-Packaging mesh frame; 18-Purification packing; 19-Sealing cover; 20-Locking pin; 21-Supporting bracket. Detailed Implementation

[0019] Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this utility model.

[0020] Example: Please refer to Figure 1-4A multi-unit interconnected blast furnace fan cooling device is described. The industrial cooling tower 2 is placed at a designated position on the right side of the equipment base 1 and securely installed on the equipment base 1 using bolts and other fasteners. Three fan cooling towers 3 are then hoisted to a predetermined position on the left side of the industrial cooling tower 2 and installed on the equipment base 1 using appropriate fixing methods, ensuring accurate relative positioning between the cooling towers. An equipment bracket 4 is installed on the equipment base 1 in front of the industrial cooling tower 2, ensuring that the equipment bracket 4 is securely installed and level. A circulating pump unit 5 is installed on the equipment bracket 4 using fixing bolts 12. Before installation, all components of the circulating pump unit 5 are checked for damage. The circulating pump unit 5 is placed at the designated position on the equipment bracket 4, aligning the mounting holes, and then the fixing bolts 12 are tightened sequentially. Ensure that the circulating pump set 5 is tightly connected to the equipment support 4 without shaking. Connect one end of the pumping water pipe 6 to the water inlet of the circulating pump set 5, and slowly insert the other end into the industrial cooling tower 2 from above to a suitable depth. Seal the connection with sealant to prevent leakage. Install one end of the water injection pipe 7 on the water outlet of the circulating pump set 5, and insert the other end into the industrial cooling tower 2 from below. Seal the connection as well. Install the first water distribution pipe 8 and the second water distribution pipe 9, and install them on the corresponding interfaces of the circulating pump set 5, so that the first water distribution pipe 8 is connected to the pumping water pipe 6 and the second water distribution pipe 9 is connected to the water injection pipe 7. Install the filter box 14 on the equipment base 1 and embed it between the first water distribution pipe 8 and the second water distribution pipe 9. A pair of purification chambers 15 are formed in the filter box 14. A pair of partition plates 16 are vertically installed in the middle of the pair of purification chambers 15, ensuring that the partition plates 16 are firmly installed, dividing the purification chambers 15 into an n-shaped space. A packing mesh frame 17 is set in the lower part of the purification chamber 15. The purification packing 18 is evenly placed in the purification chamber 15 and located above the packing mesh frame 17, ensuring that the purification packing 18 is fully filled and evenly distributed. The sealing cover 19 is installed at the top of the filter box 14 by locking pins 20, ensuring that the sealing cover is secure during installation. 19 is tightly fitted to the top of the filter box 14, and then the locking pins 20 are tightened in sequence to prevent cooling water leakage. The three circulating water inlet pipes 10 are installed on the first branch pipe 8, so that their other ends pass through the upper side wall of the three fan cooling towers 3 and extend into the appropriate position inside the fan cooling tower 3. The three circulating water outlet pipes 11 are installed on the second branch pipe 9 and pass through the lower side wall of the three fan cooling towers 3 and extend into their interior. The flow cut-off switch valves 13 are installed on the three circulating water inlet pipes 10 respectively. When installing, ensure that the installation direction of the flow cut-off switch valves 13 is correct.

[0021] Working process: The circulating pump set 5 installed on the equipment support 4 starts to draw high-temperature cooling water from the industrial cooling tower 2 through the pumping water pipe 6 and delivers it outward through the pumping force of the circulating pump set 5. It is distributed to the circulating water inlet pipe 10 through the first water distribution pipe 8 and injected into the fan cooling tower 3. At the same time, another part of the circulating pump set 5 starts to draw low-temperature cooling water from the three fan cooling towers 3 through the second water distribution pipe 9 and the circulating water outlet pipe 11 and inject it into the industrial cooling tower 2 through the water injection pipe 7. In this way, the water volume and water temperature of a single cooling tower are balanced by the water temperature difference of the cooling water in different cooling towers, which effectively reduces the water temperature to provide protection for the blast furnace. At the same time, it can also ensure equipment safety and prevent equipment damage caused by freezing in winter.

[0022] During the use of the equipment, it can be connected and combined at any time. If a single unit fails, the water supply to that unit can be cut off for maintenance through the shut-off switch valve 13.

[0023] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A multi-unit interconnected blast furnace blower cooling device, comprising: The equipment base (1), industrial cooling tower (2) and three fan cooling towers (3) are characterized in that the industrial cooling tower (2) is installed on the right side of the equipment base (1), and the three fan cooling towers (3) are arranged sequentially on the left side of the industrial cooling tower (2). A water circulation structure is installed on the industrial cooling tower (2) and the three fan cooling towers (3). The interconnected water circulation structure includes: equipment support (4), circulation pump group (5), pumping water pipe (6), water injection pipe (7), first water distribution pipe (8), second water distribution pipe (9), filter purification component, three circulating water inlet pipes (10) and three circulating water outlet pipes (11). The equipment bracket (4) is installed on the equipment base (1) and located in front of the industrial cooling tower (2). The circulating pump set (5) is installed on the equipment bracket (4). One end of the pumping water pipe (6) is installed on the circulating pump set (5) and the other end extends through the top of the industrial cooling tower (2) into its interior. One end of the water injection pipe (7) is installed on the circulating pump set (5) and the other end extends through the bottom of the industrial cooling tower (2) into its interior. The first water distribution pipe (8) is installed on the circulating pump set (5) and connected to the pumping water... Pipe (6) is connected, the second water distribution pipe (9) is installed on the circulating pump group (5) and connected to the water injection pipe (7), the filter purification component is embedded in the middle position of the first water distribution pipe (8) and the second water distribution pipe (9), the three circulating water inlet pipes (10) are installed on the first water distribution pipe (8) and the other end extends through the upper side wall of the three fan cooling towers (3) into the middle, the three circulating water outlet pipes (11) are installed on the second water distribution pipe (9) and extend through the lower side wall of the three fan cooling towers (3) into their interior.

2. The multi-group interconnected blast furnace blower cooling device according to claim 1, characterized in that, The circulating pump unit (5) is mounted on the equipment bracket (4) by fixing bolts (12).

3. The multi-group interconnected blast furnace blower cooling device according to claim 1, characterized in that, Three circulating water inlet pipes (10) are equipped with flow-stop valves (13).

4. A multi-unit interconnected blast furnace blower cooling device according to claim 1, characterized in that, The filtration and purification assembly includes: a filter box (14), a pair of purification chambers (15), a pair of partition plates (16), a packing mesh frame (17), purification packing (18), and a sealing cover (19). The filter box (14) is installed on the equipment base (1) and embedded in the middle of the first water distribution pipe (8) and the second water distribution pipe (9). A pair of purification chambers (15) are opened in the filter box (14). A pair of partition plates (16) are vertically installed in the middle of the pair of purification chambers (15). The packing mesh frame (17) is set in the lower part of the purification chamber (15). The purification packing (18) is placed in the purification chamber (15) and located above the packing mesh frame (17). The sealing cover plate (19) is installed at the top of the filter box (14).

5. A multi-unit interconnected blast furnace blower cooling device according to claim 4, characterized in that, The sealing cover (19) is installed on the filter box (14) by locking pin (20).

6. A multi-unit interconnected blast furnace blower cooling device according to claim 4, characterized in that, The sealing cover (19) is placed on top of the filter box (14) via the support bracket (21).