A device for injecting hydrogen-rich gas into a blast furnace

By setting through holes and reinforcing structures on the blast furnace tuyeres, the composite injection of pulverized coal and hydrogen-rich gas was achieved, solving the problem of reduced coke ratio in the blast furnace and improving the economy and stability of the blast furnace.

CN224996929UActive Publication Date: 2026-11-20ZHONGTIAN IRON & STEEL GRP (NANTONG) CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522549607.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-01
Publication Date
2026-11-20
Estimated Expiration
2035-12-01

AI Technical Summary

Technical Problem

In existing technologies, when using hydrogen-rich gas injection, pulverized coal injection must be stopped in the blast furnace, which leads to a decrease in the blast furnace coke ratio and is not conducive to cost reduction and efficiency improvement.

Method used

Through holes are installed on the blast furnace tuyeres to achieve composite injection of pulverized coal and hydrogen-rich gas. The diameter and angle of the through holes are adjusted to increase the gas flow rate and mixing effect. Safety and stability are ensured by structural reinforcement such as flanges and steel reinforcement welding.

Benefits of technology

It achieves the coordinated injection of pulverized coal and hydrogen-rich gas, maintaining a certain amount of coal injection while reducing carbon emissions, improving the economic indicators of the blast furnace, and ensuring stable furnace conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224996929U_ABST
    Figure CN224996929U_ABST
Patent Text Reader

Abstract

The application relates to a device for injecting hydrogen-rich gas into a blast furnace and relates to the technical field of blast furnace equipment. The device comprises a small sleeve body, the diameter of the small sleeve body gradually decreases from one end to the other end, the small sleeve body is hollow, a water-cooling cavity structure is arranged on the inner wall of the small sleeve body, a water inlet and a water outlet are arranged on the end wall of the small sleeve body with a larger diameter, the water inlet and the water outlet are in communication with the water-cooling cavity structure, a through hole is further arranged on the end wall of the small sleeve body with the larger diameter, the through hole is located between the water inlet and the water outlet, the through hole is not in communication with the water-cooling cavity structure, the end of the through hole is located on the inner surface of the front end of the small sleeve body, and the through hole is in communication with a gas pipe stub. The device can realize composite injection of the blast furnace tuyere, and solves the problem that hydrogen-rich gas can only be injected after the injection of pulverized coal is stopped.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of blast furnace equipment technology, and in particular to a device for injecting hydrogen-rich gas into a blast furnace. Background Technology

[0002] The tuyere sleeve is a device that supplies high-temperature hot air into the blast furnace and provides efficient cooling through internal water circulation, protecting the blast furnace structure. Its internal structure is a complex water-cooled cavity, made of high thermal conductivity materials such as copper alloys, and manufactured using special processes such as spinning and ceramic lining. The pulverized coal injection lance is inserted through the direct-fired pipe, with its nozzle ultimately positioned inside the tuyere sleeve, injecting pulverized coal into the blast furnace tuyere.

[0003] The related technology designs a blast furnace tuyeres sleeve, including a sleeve body, the diameter of which gradually decreases from one end to the other. The sleeve body is hollow inside, and a water-cooled cavity structure is provided on the inner wall of the sleeve body. A water inlet and a water outlet are opened on the end wall of the sleeve body with a larger diameter, and both the water inlet and the water outlet are connected to the water-cooled cavity structure.

[0004] Regarding the aforementioned technologies, the inventors discovered that when hydrogen-rich gas injection technology is used in blast furnaces, the equipment for injecting pulverized coal is often occupied. Hydrogen-rich gas is injected into the blast furnace through a coal injection gun. This method requires stopping the injection of pulverized coal at the tuyeres, which has an adverse effect on reducing the coke ratio of the blast furnace and is not conducive to cost reduction and efficiency improvement. Therefore, it needs to be improved. Utility Model Content

[0005] In order to realize the composite injection of existing blast furnace tuyeres and solve the problem that pulverized coal injection must be stopped before hydrogen-rich gas can be injected, this application provides a device for injecting hydrogen-rich gas into a blast furnace.

[0006] The device for injecting hydrogen-rich gas into a blast furnace provided in this application adopts the following technical solution: A device for injecting hydrogen-rich gas into a blast furnace includes a small sleeve body with a diameter that gradually decreases from one end to the other. The small sleeve body is hollow inside, and a water-cooled cavity structure is formed in the inner wall of the small sleeve body. A water inlet and a water outlet are formed in the end wall of the larger diameter end of the small sleeve body, and both the water inlet and the water outlet are connected to the water-cooled cavity structure. A through hole is also formed in the end wall of the larger diameter end of the small sleeve body, and the through hole is located between the water inlet and the water outlet. The through hole is not connected to the water-cooled cavity structure, and the end of the through hole is located on the inner surface of the front end of the small sleeve body. A gas pipe is connected to the through hole.

[0007] By adopting the above technical solution, composite injection can be effectively realized, solving the problem that pulverized coal injection must be stopped before hydrogen-rich gas injection can be achieved. This realizes the synergistic coexistence of pulverized coal injection and hydrogen-rich gas injection technologies, and achieves the superposition of hydrogen-rich gas injection on the basis of maintaining a certain amount of pulverized coal injection. This can minimize carbon emissions while ensuring economic efficiency, and at the same time ensure the stable and smooth operation of the blast furnace. It is also conducive to reducing the coke ratio of the blast furnace and improving the economic indicators of the blast furnace.

[0008] Preferably, the through hole includes a rear section, a middle section, and a front section. The rear section of the through hole has a size of φ42mm, the middle section has a size of φ30mm, and the rear section has a size of φ25mm. The angle between the through hole and the horizontal plane gradually changes from 10° in the front section to 30° in the rear section.

[0009] By adopting the above technical solution, the diameter of the through hole gradually decreases, which can increase the gas flow rate, and the angle with the horizontal plane gradually increases, which can adjust the position of the hydrogen-rich gas ejected, so that it can be fully mixed with the hot air and increase the utilization rate.

[0010] Preferably, the inner wall of the rear section of the through hole is provided with an inner thread.

[0011] By adopting the above technical solution, the internal thread is set to facilitate the connection between the through hole and the air pipe, which is convenient for subsequent tightening and welding sealing work.

[0012] Preferably, a flange is provided at the connection between the tracheal tube connector and the small sleeve body.

[0013] By adopting the above technical solution, the flange can be installed to reinforce the gas pipe short connection, thereby improving stability and safety.

[0014] Preferably, the inlet is connected to an inlet pipe, the outlet is connected to an outlet pipe, and the air pipe short circuit is welded to the inlet pipe and the outlet pipe using steel bars.

[0015] By adopting the above technical solution and welding the three components with steel bars, a stable triangular support can be formed, further preventing the pipe from loosening and leaking, and improving safety and stability.

[0016] Preferably, a shut-off valve is provided on the tracheal tube short connector.

[0017] By adopting the above technical solution, the shut-off valve is used to close when the hydrogen-rich gas injection is stopped, cutting off the furnace interior from the outside and preventing backfire.

[0018] Preferably, a pressure relief valve is provided on the tracheal tube short connector.

[0019] By adopting the above technical solution, the pressure relief valve is used to release pressure when hydrogen-rich gas is stopped, ensuring safety.

[0020] Preferably, the trachea is connected to a metal flexible tube.

[0021] By adopting the above technical solution, the metal hose is connected to an external gas source, which typically includes hydrogen-rich gas and safety gas. The hydrogen-rich gas is used for normal purging, while the safety gas is used to apply pressure to the furnace when the hydrogen-rich gas purging is stopped. At the same time, it can purge the hydrogen-rich gas in the pipeline to ensure safety.

[0022] In summary, this application includes at least one of the following beneficial technical effects: 1. The composite tuyeres of the blast furnace in this application can effectively realize composite injection, solving the problem that pulverized coal injection must be stopped before hydrogen-rich gas can be injected. It realizes the synergistic coexistence of pulverized coal injection and hydrogen-rich gas injection technologies, and achieves the superposition of hydrogen-rich gas injection on the basis of maintaining a certain amount of pulverized coal injection. This can minimize carbon emissions while ensuring economic efficiency, and at the same time ensure the stable and smooth operation of the blast furnace. It is also conducive to reducing the coke ratio of the blast furnace and improving the economic indicators of the blast furnace. 2. The diameter of the through hole of the small sleeve of the blast furnace composite tuyeres gradually decreases, which can increase the gas flow rate, and the angle with the horizontal plane gradually increases, which can adjust the position of the hydrogen-rich gas injection, so as to fully mix it with the hot air and increase the utilization rate. Attached Figure Description

[0023] Figure 1 This is a cross-sectional view of a device for injecting hydrogen-rich gas into a blast furnace, according to an embodiment of this application.

[0024] Figure 2 This is a schematic diagram of the structure of the small kit body according to an embodiment of this application.

[0025] Figure 3 This is a schematic diagram of the connection structure between the small sleeve body and the short-circuit trachea in an embodiment of this application.

[0026] Explanation of reference numerals in the attached drawings: 1. Small sleeve body; 11. Water-cooled cavity structure; 12. Water inlet; 13. Water outlet; 14. Through hole; 2. Air pipe short connector; 21. Flange; 22. Shut-off valve; 23. Pressure relief valve; 24. Metal hose; 3. Water inlet pipe; 4. Water outlet pipe; 5. Reinforcing bar. Detailed Implementation

[0027] The following is in conjunction with the appendix Figure 1-3 This application will be described in further detail.

[0028] This application discloses an apparatus for injecting hydrogen-rich gas into a blast furnace. (See also...) Figure 1 , Figure 2 and Figure 3It includes a small sleeve body 1, the diameter of which gradually decreases from one end to the other. The small sleeve body 1 is hollow inside, and a water-cooled cavity structure 11 is provided on the inner wall of the small sleeve body 1. A water inlet 12 and a water outlet 13 are provided on the end wall of the end with a larger diameter of the small sleeve body 1. Both the water inlet 12 and the water outlet 13 are connected to the water-cooled cavity structure 11. The water inlet 12 is connected to a water inlet pipe 3, and the water outlet 13 is connected to a water outlet pipe 4.

[0029] Reference Figure 1 , Figure 2 and Figure 3 The end wall of the smaller sleeve body 1 with a larger diameter is also provided with a through hole 14. The through hole 14 is located between the water inlet 12 and the water outlet 13. The through hole 14 is not connected to the water-cooled cavity structure 11. The end of the through hole 14 is located on the inner surface of the front end of the smaller sleeve body 1. The through hole 14 includes a rear section, a middle section and a front section. The rear section of the through hole 14 has a size of φ42mm, the middle section has a size of φ30mm and the rear section has a size of φ25mm. The angle between the through hole 14 and the horizontal plane gradually changes from 10° in the front section to 30° in the rear section. The gradually decreasing diameter of the through hole 14 can increase the gas flow rate, and the gradually increasing angle with the horizontal plane can adjust the position of the hydrogen-rich gas ejection, so that it can be fully mixed with the hot air and increase the utilization rate.

[0030] Reference Figure 1 , Figure 2 and Figure 3 The inner wall of the rear section of the through hole 14 is provided with an internal thread, and the through hole 14 is connected to the air pipe short connector 2 through the internal thread, so that the air pipe short connector 2 can be tightened, welded and sealed in the future. In this embodiment, flanges 21 are provided at the connection between the air pipe short connector 2 and the through hole 14, the connection between the water inlet pipe 3 and the water inlet 12, and the connection between the water outlet pipe 4 and the water outlet 13, so as to reinforce the corresponding pipes. The air pipe short connector 2 is welded to the water inlet pipe 3 and the water outlet pipe 4 with steel bars 5, which can form a stable triangular support, further preventing the pipe from loosening and leaking, and improving safety and stability.

[0031] Reference Figure 1 , Figure 2 and Figure 3 The gas pipe short connector 2 is equipped with a shut-off valve 22, which is used to close when the injection of hydrogen-rich gas is stopped, cutting off the furnace from the outside and preventing backfire. The gas pipe short connector 2 is also equipped with a pressure relief valve 23, which is used to release pressure when the injection of hydrogen-rich gas is stopped, ensuring safety. The end of the gas pipe short connector 2 away from the small sleeve body 1 is also connected to a metal hose 24. The metal hose 24 is connected to an external gas source, which usually includes hydrogen-rich gas and safety gas. The hydrogen-rich gas is used for normal injection, and the safety gas is used to apply pressure to the furnace when the injection of hydrogen-rich gas is stopped, preventing backfire, and at the same time, it can purge the hydrogen-rich gas in the pipeline to ensure safety.

[0032] The implementation principle of the device for injecting hydrogen-rich gas into a blast furnace according to the embodiments of this application is as follows: By setting a through hole 14 on the basis of the original tuyeres sleeve, hydrogen-rich gas can be injected at the same time as pulverized coal injection, thereby effectively realizing composite injection. This solves the problem that pulverized coal injection must be stopped before hydrogen-rich gas can be injected, realizing the synergistic coexistence of pulverized coal injection and hydrogen-rich gas injection technologies. It achieves the superposition of hydrogen-rich gas injection on the basis of maintaining a certain amount of pulverized coal injection, which can minimize carbon emissions while ensuring economic efficiency, and at the same time ensure the stable and smooth operation of the blast furnace. This is conducive to reducing the blast furnace coke ratio and improving the economic indicators of the blast furnace.

[0033] The above are all preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.

Claims

1. A device for injecting hydrogen-rich gas into a blast furnace, comprising a small sleeve body, the diameter of which gradually decreases from one end to the other, the small sleeve body being hollow inside, a water-cooled cavity structure formed in the inner wall of the small sleeve body, and a water inlet and a water outlet formed in the end wall of the larger diameter end of the small sleeve body, both of which are connected to the water-cooled cavity structure, characterized in that: The end wall of the larger diameter end of the small sleeve body is also provided with a through hole. The through hole is located between the water inlet and the water outlet. The through hole is not connected to the water-cooled cavity structure. The end of the through hole is located on the inner surface of the front end of the small sleeve body. The through hole is connected to a short-circuit air pipe.

2. The apparatus for injecting hydrogen-rich gas into a blast furnace according to claim 1, characterized in that: The through hole includes a rear section, a middle section, and a front section. The rear section of the through hole has a size of φ42mm, the middle section has a size of φ30mm, and the rear section has a size of φ25mm. The angle between the through hole and the horizontal plane gradually changes from 10° in the front section to 30° in the rear section.

3. The apparatus for injecting hydrogen-rich gas into a blast furnace according to claim 2, characterized in that: The inner wall of the rear section of the through hole is provided with an inner thread.

4. The apparatus for injecting hydrogen-rich gas into a blast furnace according to claim 1, characterized in that: A flange is provided at the connection between the tracheal tube and the small sleeve body.

5. The apparatus for injecting hydrogen-rich gas into a blast furnace according to claim 1, characterized in that: The inlet is connected to an inlet pipe, and the outlet is connected to an outlet pipe. The air pipe is short-connected to both the inlet and outlet pipes and is welded with steel bars.

6. The apparatus for injecting hydrogen-rich gas into a blast furnace according to claim 1, characterized in that: A shut-off valve is installed on the tracheal tube short connector.

7. The apparatus for injecting hydrogen-rich gas into a blast furnace according to claim 1, characterized in that: A pressure relief valve is installed on the tracheal tube short connector.

8. The apparatus for injecting hydrogen-rich gas into a blast furnace according to claim 1, characterized in that: The trachea is short-connected to a flexible metal tube.