PEM / AEM electrolyzer and pem stack integrated test device

By integrating the electrolytic cell and fuel cell stack testing channels into a comprehensive testing device, the problem of synchronous testing that traditional testing benches cannot solve is solved. This enables parallel testing of PEM/AEM electrolytic cells and PEM fuel cells, improving testing efficiency and reducing costs.

CN224997057UActive Publication Date: 2026-11-20GREER ENERGY TECHNOLOGY (CHANGZHOU) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522598481.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-08
Publication Date
2026-11-20
Estimated Expiration
2035-12-08

AI Technical Summary

Technical Problem

Traditional test benches cannot achieve simultaneous testing of PEM/AEM electrolyzers and PEM stacks, resulting in cumbersome equipment switching, lengthy testing cycles, and a lack of comparability of performance-related data, making it difficult to support the integrated R&D and testing needs of hydrogen energy production and application.

Method used

Design a comprehensive testing device for PEM/AEM electrolyzers and PEM stacks, integrating power supply, independent water supply unit, independent alkali supply unit, load, hydrogen control unit, and air control unit to form testing channels for electrolyzers and stacks. PLC intelligent control is adopted to realize parallel testing of the two types of equipment and independent supply of media.

Benefits of technology

It enables parallel testing of PEM/AEM electrolyzers and PEM stacks, improving testing efficiency, reducing equipment procurement and site investment costs, enhancing space utilization, and meeting the integrated testing needs of hydrogen energy production and application.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224997057U_ABST
    Figure CN224997057U_ABST
Patent Text Reader

Abstract

The utility model relates to a kind of PEM / AEM electrolytic cell and PEM pile comprehensive testing device, at least including power supply, independent water supply unit, independent alkali supply unit, load, hydrogen control unit and air control unit, including power supply, independent water supply unit, independent alkali supply unit, load, hydrogen control unit and air control unit cooperation use, form electrolytic cell test channel and pile test channel;Electrolytic cell test channel: power supply is PEM / AEM electrolytic cell, pump, heater component provides electric energy;Independent water supply unit, independent alkali supply unit are used for the electrolyte supply of PEM electrolytic cell and AEM electrolytic cell, connect with electrolytic cell anode electrolyte inlet;And hydrogen, oxygen side tank outlet place is all equipped with valve, for the switching of two electrolytic cell test;Pile test channel: load drives fuel cell stack output certain power, connect with pile;Hydrogen control unit, air control unit are used for the control of fuel cell stack into stack gas flow, temperature, humidity and pressure, connect with fuel cell stack cathode and anode.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to testing technology and its equipment, specifically, a comprehensive testing device for PEM / AEM electrolytic cells and PEM stacks. Background Technology

[0002] Based on the preparation method, hydrogen energy can be divided into: Gray hydrogen, produced from fossil fuels; Blue hydrogen is obtained by combining hydrogen production from fossil fuels with carbon capture. Green hydrogen is produced by electrolyzing water using renewable energy.

[0003] Hydrogen production via electrolyzers is a key pathway for green hydrogen supply, while hydrogen fuel cells are the core equipment for the efficient utilization of hydrogen energy. Anion exchange membrane electrolyzers and proton exchange membrane electrolyzers, as core devices for green hydrogen production, together with hydrogen fuel cells, form a closed loop of the hydrogen energy industry chain from production to application.

[0004] Among them, the anion exchange membrane electrolyzer is abbreviated as AEM electrolyzer, and the proton exchange membrane electrolyzer is abbreviated as PEM electrolyzer.

[0005] Traditional test benches, limited by their single-function design and fixed test channels, are often only compatible with one type of electrolyzer, including PEM / AEM electrolyzers or PEM stacks. Furthermore, their test procedures, media supply, and parameter control logic are independent, making simultaneous testing of both core equipment types impossible. To achieve parallel verification of the hydrogen production performance of the electrolyzer and the power generation performance of the stack, two dedicated test systems must be configured. This not only results in cumbersome equipment switching and lengthy testing cycles, but also leads to a lack of comparability in performance correlation data between the two types of equipment due to differences in testing environments, including temperature control accuracy and data acquisition frequency. This makes it difficult to support the integrated R&D and testing needs of hydrogen energy production and application.

[0006] Therefore, it is necessary to provide a comprehensive testing device for PEM / AEM electrolyzers and PEM stacks to solve the above problems. Utility Model Content

[0007] The purpose of this invention is to provide a comprehensive testing device for PEM / AEM electrolytic cells and PEM stacks.

[0008] The technical solution is as follows: A comprehensive testing device for PEM / AEM electrolyzer and PEM stack includes at least a power supply, an independent water supply unit, an independent alkali supply unit, a load, a hydrogen control unit, and an air control unit. The power supply, independent water supply unit, independent alkali supply unit, load, hydrogen control unit, and air control unit are used in conjunction to form an electrolyzer testing channel and a stack testing channel. Electrolyzer test channel: The power supply provides electrical energy to the PEM / AEM electrolyzer, pump, and heater components; the independent water supply unit and independent alkali supply unit are used to supply electrolyte to the PEM electrolyzer and AEM electrolyzer, and are connected to the electrolyte inlet of the electrolyzer anode; and valves are installed at the hydrogen and oxygen side outlets for switching between the two types of electrolyzer tests; The fuel cell stack test channel is connected to the fuel cell stack via a load that drives the fuel cell stack to output a certain power. The hydrogen control unit and air control unit are used to control the flow rate, temperature, humidity and pressure of the gas entering the fuel cell stack, and are connected to the anode and cathode of the fuel cell stack.

[0009] Furthermore, in the fuel cell stack channels: It is equipped with a hydrogen control unit and an air control unit for controlling the gas inlet flow rate, temperature, humidity and pressure of the fuel cell stack; Equipped with a circulating cooling water control unit, this system uses a closed-loop precision temperature control structure and PLC control logic to address performance degradation, membrane module aging, and data distortion caused by abnormal temperatures during equipment operation.

[0010] Furthermore, the hydrogen control unit is used to control the flow rate, temperature, humidity and pressure of hydrogen entering the fuel cell stack. It is connected sequentially through a hydrogen cylinder, a flow controller, a heating and humidification device, a temperature sensor entering the stack, a pressure transmitter entering the stack, the fuel cell stack, a temperature sensor exiting the stack, a pressure transmitter exiting the stack and a back pressure valve.

[0011] Furthermore, the air control unit is used to control the air flow, temperature, humidity and pressure of the fuel cell stack. It is connected in sequence through an air compressor, flow controller, heating and humidification device, stack temperature sensor, stack pressure transmitter, fuel cell stack, stack temperature sensor, stack pressure transmitter and back pressure valve.

[0012] Furthermore, the circulating cooling water control unit, through a closed-loop precision temperature control structure and PLC control logic, solves the problems of performance degradation, membrane module aging, and data distortion caused by abnormal temperature during equipment operation. It is connected in sequence to the cooling water tank, water pump, water flow meter, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, and outfeed pressure transmitter.

[0013] Furthermore, independent water supply units and independent alkali supply units are set up in the electrolyzer test channel for electrolyte supply to the PEM and AEM electrolyzer stacks; Specifically: In the PEM electrolysis cell channel, deionized water enters the PEM electrolysis cell channel separator sequentially from the water tank and water pump, and then enters the electrolysis cell sequentially through the circulation pump, water flow meter and switch valve to undergo electrolysis reaction. In the AEM channel, the alkali solution enters the AEM electrolytic cell channel separator sequentially from the alkali solution tank and the alkali replenishment pump, and then passes through the alkali solution pump, alkali solution flow meter, and switch valve in sequence before entering the AEM electrolytic cell to undergo the electrolytic reaction.

[0014] Furthermore, the electrolytic cell test channel is equipped with independent water supply units and independent alkali supply units for the electrolyte supply of PEM and AEM electrolytic cell stacks. At the same time, valves are installed at the inlet and outlet of the cell for switching control of the two electrolytic cell test channels. Open the pump and inlet / outlet valves of the independent alkali / water supply unit. The electrolyte enters the corresponding primary gas-water separator from the water tank / alkali tank. After being heated, it enters the electrolytic cell through the circulating electrolyte path to undergo an electrolytic reaction. Electrolysis produces hydrogen and oxygen containing electrolyte. After exiting the cell, the hydrogen passes through the switch valve, temperature sensor, pressure transmitter, and shut-off valve in sequence, and then connects to the shared primary gas-water separator and secondary gas-liquid separator. After exiting the PEM electrolytic cell, the oxygen passes through the switch valve, temperature sensor, pressure transmitter, primary gas-water separator, and shut-off valve, and then connects to the shared secondary gas-liquid separator.

[0015] Furthermore, if an AEM electrolyzer test is to be performed, the PEM channel pump and the inlet / outlet switch valves are closed, and the AEM electrolyzer inlet / outlet switch valves are opened. After the oxygen exits the cell, it passes through the switch valve, the primary gas-liquid separator, the scrubber, and the shut-off valve in sequence before being connected to the shared secondary gas-liquid separator.

[0016] Furthermore, a parallel testing channel for the electrolyzer and fuel cell is established: The fuel cell stack test channel consists of: a hydrogen control unit, which sequentially connects to a hydrogen cylinder, flow controller, heating and humidification device, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, outfeed pressure transmitter, and back pressure valve, for controlling the flow rate, temperature, humidity, and pressure of hydrogen entering the fuel cell stack; an air control unit, which sequentially connects to an air compressor, flow controller, heating and humidification device, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, outfeed pressure transmitter, and back pressure valve, for controlling the flow rate, temperature, humidity, and pressure of air entering the fuel cell stack; and a circulating cooling water control unit, which connects from the cooling water tank to a water pump, water flow meter, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, and outfeed pressure transmitter, for controlling the temperature of the fuel cell stack. Electrolyzer Test Channel: Turn on the pump of the independent alkali / water supply unit. The electrolyte enters the corresponding primary gas-liquid separator from the alkali tank / water tank. After being heated, it passes through the circulation pump, flow meter, and switch valve in sequence before entering the electrolyzer to undergo an electrolytic reaction. Electrolysis produces hydrogen and oxygen containing electrolyte. After exiting the cell, the hydrogen passes through the switch valve, temperature sensor, pressure transmitter, and shut-off valve in sequence and is connected to the shared primary gas-liquid separator, back pressure valve, and secondary gas-liquid separator. For PEM (or AEM) electrolyzers, the oxygen exits the cell through the switch valve, temperature sensor, pressure transmitter, primary gas-liquid separator (+washer), and shut-off valve before being connected to the shared secondary gas-liquid separator.

[0017] Compared with the prior art, the beneficial effects of this utility model are as follows: 1) Integrating PEM electrolyzer, AEM electrolyzer, and PEM stack test channels, one set of equipment meets the integrated testing needs of core equipment at both hydrogen production and consumption ends, solves the problem of dedicated testing stations in traditional testing benches, meets the parallel testing needs of electrolyzers and fuel cells, and improves testing efficiency; 2) It can be used for switching tests between PEM and AEM electrolyzers without disassembling and reassembling the pipeline or replacing the core components. It adopts a combination of independent supply of two media and PLC intelligent control to realize the switching test between PEM and AEM electrolyzers. 3) The integrated structural design eliminates the need for multiple sets of testing equipment, significantly reducing the site area occupied, greatly improving space utilization, and effectively reducing equipment procurement and site investment costs. Attached Figure Description

[0018] Figure 1 This is one of the structural schematic diagrams of this utility model.

[0019] Figure 2 This is the second structural schematic diagram of this utility model. Figure 2 The upper half is a schematic diagram of the PEM electrolytic cell test channel, and the lower half is a schematic diagram of the AEM electrolytic cell test channel. Detailed Implementation Example:

[0020] Please see Figure 1-2 This embodiment demonstrates a comprehensive testing device for a PEM / AEM electrolyzer and a PEM stack, which includes at least a power supply, an independent water supply unit, an independent alkali supply unit, a load, a hydrogen control unit, and an air control unit. The power supply, independent water supply unit, independent alkali supply unit, load, hydrogen control unit and air control unit are used together to form the electrolytic cell test channel and the fuel cell stack test channel; Electrolyzer test channel: The power supply provides electrical energy to the PEM / AEM electrolyzer, pump, and heater components; the independent water supply unit and independent alkali supply unit are used to supply electrolyte to the PEM electrolyzer and AEM electrolyzer, and are connected to the electrolyte inlet of the electrolyzer anode; and valves are installed at the hydrogen and oxygen side outlets for switching between the two types of electrolyzer tests; The fuel cell stack test channel is connected to the fuel cell stack via a load that drives the fuel cell stack to output a certain power. The hydrogen control unit and air control unit are used to control the flow rate, temperature, humidity and pressure of the gas entering the fuel cell stack, and are connected to the anode and cathode of the fuel cell stack.

[0021] In the fuel cell stack channel: A hydrogen control unit 2 and an air control unit 10 are provided for controlling the gas inlet flow rate, temperature, humidity and pressure of the fuel cell stack; Equipped with a circulating cooling water control unit 18, it solves the problems of performance degradation, membrane module aging, and data distortion caused by abnormal temperature during equipment operation through a closed-loop precision temperature control structure and PLC control logic.

[0022] The hydrogen control unit 2 is used to control the flow rate, temperature, humidity and pressure of hydrogen entering the fuel cell stack. It is connected in sequence through the hydrogen cylinder 3, flow controller 4, heating and humidification device 5, entry temperature sensor 6, entry pressure transmitter, fuel cell stack 1, exit temperature sensor 7, exit pressure transmitter 8 and back pressure valve 9.

[0023] The air control unit 10 is used to control the air flow, temperature, humidity and pressure of the fuel cell stack. It is connected in sequence through the air compressor 11, flow controller 12, heating and humidification device 13, stack temperature sensor 14, stack pressure transmitter, fuel cell stack 1, stack temperature sensor 15, stack pressure transmitter 16 and back pressure valve 17.

[0024] The circulating cooling water control unit 18 solves the problems of performance degradation, membrane module aging, and data distortion caused by abnormal temperature during equipment operation through a closed-loop precision temperature control structure and PLC control logic. It is connected in sequence to the cooling water tank 19, water pump 20, water flow meter 21, infeed temperature sensor 22, infeed pressure transmitter, fuel cell stack 1, outfeed temperature sensor 23, and outfeed pressure transmitter 24.

[0025] In the electrolyzer test channel, independent water supply units and independent alkali supply units are set up for the electrolyte supply of PEM and AEM electrolyzer stacks; Specifically: In the PEM electrolysis cell channel, deionized water enters the PEM electrolysis cell channel separator sequentially from the water tank and water pump, and then enters the electrolysis cell sequentially through the circulation pump, water flow meter and switch valve to undergo electrolysis reaction. In the AEM channel, the alkali solution enters the AEM electrolytic cell channel separator sequentially from the alkali solution tank and the alkali replenishment pump, and then passes through the alkali solution pump, alkali solution flow meter, and switch valve in sequence before entering the AEM electrolytic cell to undergo the electrolytic reaction.

[0026] The electrolytic cell test channel is equipped with independent water supply units and independent alkali supply units for the electrolyte supply of PEM and AEM electrolytic cell stacks. At the same time, valves are installed at the inlet and outlet of the cell for switching control of the two electrolytic cell test channels. Open the pump and inlet / outlet valves of the independent alkali / water supply unit. The electrolyte enters the corresponding primary gas-water separator from the water tank / alkali tank. After being heated, it enters the electrolytic cell through the circulating electrolyte path to undergo an electrolytic reaction. Electrolysis produces hydrogen and oxygen containing electrolyte. After exiting the cell, the hydrogen passes through the switch valve, temperature sensor, pressure transmitter, and shut-off valve in sequence, and then connects to the shared primary gas-water separator and secondary gas-liquid separator. After exiting the PEM electrolytic cell, the oxygen passes through the switch valve, temperature sensor, pressure transmitter, primary gas-water separator, and shut-off valve, and then connects to the shared secondary gas-liquid separator.

[0027] If an AEM electrolyzer test is to be performed, the PEM channel pump and the inlet / outlet switch valves are closed, and the AEM electrolyzer inlet / outlet switch valves are opened. After the oxygen exits the cell, it passes through the switch valve, the primary gas-liquid separator, the scrubber, and the shut-off valve in sequence before being connected to the shared secondary gas-liquid separator.

[0028] Forming a parallel testing channel for electrolyzers and fuel cells: The fuel cell stack test channel consists of: a hydrogen control unit, which sequentially connects to a hydrogen cylinder, flow controller, heating and humidification device, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, outfeed pressure transmitter, and back pressure valve, for controlling the flow rate, temperature, humidity, and pressure of hydrogen entering the fuel cell stack; an air control unit, which sequentially connects to an air compressor, flow controller, heating and humidification device, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, outfeed pressure transmitter, and back pressure valve, for controlling the flow rate, temperature, humidity, and pressure of air entering the fuel cell stack; and a circulating cooling water control unit, which connects from the cooling water tank to a water pump, water flow meter, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, and outfeed pressure transmitter, for controlling the temperature of the fuel cell stack. Electrolyzer Test Channel: Turn on the pump of the independent alkali / water supply unit. The electrolyte enters the corresponding primary gas-liquid separator from the alkali tank / water tank. After being heated, it passes through the circulation pump, flow meter, and switch valve in sequence before entering the electrolyzer to undergo an electrolytic reaction. Electrolysis produces hydrogen and oxygen containing electrolyte. After exiting the cell, the hydrogen passes through the switch valve, temperature sensor, pressure transmitter, and shut-off valve in sequence and is connected to the shared primary gas-liquid separator, back pressure valve, and secondary gas-liquid separator. For PEM (or AEM) electrolyzers, the oxygen exits the cell through the switch valve, temperature sensor, pressure transmitter, primary gas-liquid separator (+washer), and shut-off valve before being connected to the shared secondary gas-liquid separator.

[0029] Compared with the prior art, the beneficial effects of this utility model are as follows: 1) Integrating PEM electrolyzer, AEM electrolyzer, and PEM stack test channels, one set of equipment meets the integrated testing needs of core equipment at both hydrogen production and consumption ends, solves the problem of dedicated testing stations in traditional testing benches, meets the parallel testing needs of electrolyzers and fuel cells, and improves testing efficiency; 2) It can be used for switching tests between PEM and AEM electrolyzers without disassembling and reassembling the pipeline or replacing the core components. It adopts a combination of independent supply of two media and PLC intelligent control to realize the switching test between PEM and AEM electrolyzers. 3) The integrated structural design eliminates the need for multiple sets of testing equipment, significantly reducing the site area occupied, greatly improving space utilization, and effectively reducing equipment procurement and site investment costs.

[0030] For those skilled in the art, various modifications and improvements can be made without departing from the inventive concept of this utility model, and these all fall within the protection scope of this utility model.

Claims

1. A comprehensive testing device for PEM / AEM electrolyzers and PEM stacks, characterized in that: It includes at least a power supply, an independent water supply unit, an independent alkali supply unit, a load, a hydrogen control unit, and an air control unit. The power supply, independent water supply unit, independent alkali supply unit, load, hydrogen control unit, and air control unit are used together to form an electrolytic cell test channel and a fuel cell stack test channel. Electrolyzer test channel: The power supply provides electrical energy to the PEM / AEM electrolyzer, pump, and heater components; the independent water supply unit and independent alkali supply unit are used to supply electrolyte to the PEM electrolyzer and AEM electrolyzer, and are connected to the electrolyte inlet of the electrolyzer anode; and valves are installed at the hydrogen and oxygen side outlets for switching between the two types of electrolyzer tests; The fuel cell stack test channel is connected to the fuel cell stack via a load that drives the fuel cell stack to output a certain power. The hydrogen control unit and air control unit are used to control the flow rate, temperature, humidity and pressure of the gas entering the fuel cell stack, and are connected to the anode and cathode of the fuel cell stack.

2. The integrated testing device for PEM / AEM electrolyzer and PEM stack according to claim 1, characterized in that: In the fuel cell stack channel: It is equipped with a hydrogen control unit and an air control unit for controlling the gas inlet flow rate, temperature, humidity and pressure of the fuel cell stack; Equipped with a circulating cooling water control unit, this system uses a closed-loop precision temperature control structure and PLC control logic to address performance degradation, membrane module aging, and data distortion caused by abnormal temperatures during equipment operation.

3. The integrated testing device for PEM / AEM electrolyzer and PEM stack according to claim 2, characterized in that: The hydrogen control unit is used to control the flow rate, temperature, humidity and pressure of hydrogen entering the fuel cell stack. It is connected in sequence through a hydrogen cylinder, a flow controller, a heating and humidification device, a temperature sensor entering the stack, a pressure transmitter entering the stack, the fuel cell stack, a temperature sensor exiting the stack, a pressure transmitter exiting the stack and a back pressure valve.

4. The integrated testing device for PEM / AEM electrolyzer and PEM stack according to claim 3, characterized in that: The air control unit is used to control the air flow, temperature, humidity and pressure of the fuel cell stack. It is connected in sequence through an air compressor, flow controller, heating and humidification device, stack inlet temperature sensor, stack inlet pressure transmitter, fuel cell stack, stack outlet temperature sensor, stack outlet pressure transmitter and back pressure valve.

5. The integrated testing device for PEM / AEM electrolyzer and PEM stack according to claim 4, characterized in that: The circulating cooling water control unit solves the problems of performance degradation, membrane module aging, and data distortion caused by abnormal temperature during equipment operation through a closed-loop precision temperature control structure and PLC control logic. It is connected in sequence to the cooling water tank, water pump, water flow meter, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, and outfeed pressure transmitter.

6. The integrated testing device for PEM / AEM electrolyzer and PEM stack according to claim 1, characterized in that: In the electrolyzer test channel, independent water supply units and independent alkali supply units are set up for the electrolyte supply of PEM and AEM electrolyzer stacks; Specifically: In the PEM electrolysis cell channel, deionized water enters the PEM electrolysis cell channel separator sequentially from the water tank and water pump, and then enters the electrolysis cell sequentially through the circulation pump, water flow meter and switch valve to undergo electrolysis reaction. In the AEM channel, the alkali solution enters the AEM electrolytic cell channel separator sequentially from the alkali solution tank and the alkali replenishment pump, and then passes through the alkali solution pump, alkali solution flow meter, and switch valve in sequence before entering the AEM electrolytic cell to undergo the electrolytic reaction.

7. The integrated testing device for PEM / AEM electrolyzer and PEM stack according to claim 1, characterized in that: The electrolytic cell test channel is equipped with independent water supply units and independent alkali supply units for the electrolyte supply of PEM and AEM electrolytic cell stacks. At the same time, valves are installed at the inlet and outlet of the cell for switching control of the two electrolytic cell test channels. Open the pump and inlet / outlet valves of the independent alkali / water supply unit. The electrolyte enters the corresponding primary gas-water separator from the water tank / alkali tank. After being heated, it enters the electrolytic cell through the circulating electrolyte path to undergo an electrolytic reaction. Electrolysis produces hydrogen and oxygen containing electrolyte. After exiting the cell, the hydrogen passes through the switch valve, temperature sensor, pressure transmitter, and shut-off valve in sequence, and then connects to the shared primary gas-water separator and secondary gas-liquid separator. After exiting the PEM electrolytic cell, the oxygen passes through the switch valve, temperature sensor, pressure transmitter, primary gas-water separator, and shut-off valve, and then connects to the shared secondary gas-liquid separator.

8. The integrated testing device for PEM / AEM electrolyzer and PEM stack according to claim 7, characterized in that: If an AEM electrolyzer test is to be performed, the PEM channel pump and the inlet / outlet switch valves are closed, and the AEM electrolyzer inlet / outlet switch valves are opened. After the oxygen exits the cell, it passes through the switch valve, the primary gas-liquid separator, the scrubber, and the shut-off valve in sequence before being connected to the shared secondary gas-liquid separator.

9. The integrated testing device for PEM / AEM electrolyzer and PEM stack according to claim 1, characterized in that: Forming a parallel testing channel for electrolyzers and fuel cells: The fuel cell stack test channel consists of: a hydrogen control unit, which sequentially connects to a hydrogen cylinder, flow controller, heating and humidification device, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, outfeed pressure transmitter, and back pressure valve, for controlling the flow rate, temperature, humidity, and pressure of hydrogen entering the fuel cell stack; an air control unit, which sequentially connects to an air compressor, flow controller, heating and humidification device, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, outfeed pressure transmitter, and back pressure valve, for controlling the flow rate, temperature, humidity, and pressure of air entering the fuel cell stack; and a circulating cooling water control unit, which connects from the cooling water tank to a water pump, water flow meter, infeed temperature sensor, infeed pressure transmitter, fuel cell stack, outfeed temperature sensor, and outfeed pressure transmitter, for controlling the temperature of the fuel cell stack. Electrolyzer Test Channel: Turn on the pump of the independent alkali / water supply unit. The electrolyte enters the corresponding primary gas-liquid separator from the alkali tank / water tank. After being heated, it passes through the circulation pump, flow meter, and switch valve in sequence before entering the electrolyzer to undergo an electrolytic reaction. Electrolysis produces hydrogen and oxygen containing electrolyte. After exiting the cell, the hydrogen passes through the switch valve, temperature sensor, pressure transmitter, and shut-off valve in sequence, and is connected to the shared primary gas-liquid separator, back pressure valve, and secondary gas-liquid separator. After exiting the PEM or AEM electrolyzer, the oxygen exits through the switch valve, temperature sensor, pressure transmitter, primary gas-liquid separator + scrubber, and shut-off valve, and is connected to the shared secondary gas-liquid separator.