Intermittent-continuous dual mode multiple refrigerant line refrigeration system

By designing parallel refrigeration units and distribution tanks, the problem of the refrigeration system's inability to integrate intermittent and continuous modes was solved, achieving efficient utilization and stable supply of the refrigeration system, and adapting to the collaborative production of multiple glue-making lines.

CN224997112UActive Publication Date: 2026-11-20JILIN TANGU CARBON FIBER CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522520664.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-27
Publication Date
2026-11-20
Estimated Expiration
2035-11-27

AI Technical Summary

Technical Problem

Existing refrigeration systems cannot effectively integrate intermittent and continuous refrigeration modes, resulting in wasted equipment resources and high energy consumption, making it difficult to meet the collaborative operation needs of multiple glue production lines.

Method used

By setting up multiple sets of refrigeration and distribution devices in parallel, combined with storage tanks, control devices and return pipelines, a dual-mode refrigeration system of intermittent and continuous operation is realized, which dynamically controls the material flow direction, avoids frequent start-stop, and isolates the interference of different operating modes.

Benefits of technology

It achieves efficient utilization of the refrigeration system, reduces equipment investment and energy consumption, improves equipment utilization and production stability, and adapts to the collaborative production needs of multiple glue-making lines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224997112U_ABST
    Figure CN224997112U_ABST
Patent Text Reader

Abstract

The utility model relates to refrigerating system technical field, specifically disclose a kind of intermittent-continuous double mode multi-gel line refrigeration system. The system includes preprocessing device, shunt setting multiple sets of refrigerating device and distribution device, wherein, the import of each refrigerating device is communicated with the outlet of the preprocessing device, distribution device, including storage tank, the import of storage tank is communicated with the outlet of multiple sets of refrigerating device, the outlet of storage tank is connected with multiple intermittent or continuous gel line respectively by pipeline, control device is respectively equipped on each pipeline, and material distribution in storage tank is controlled. System realizes that material is distributed as needed, both retains the flexible operation mode of original intermittent gel line, also meets the continuous cooling supply demand of newly added continuous gel line, effectively avoids equipment frequent start-stop, significantly improves refrigeration equipment utilization, reduces energy consumption and operating cost, provides reliable low-temperature guarantee for multi-gel line collaborative production.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of refrigeration system technology, specifically, it relates to an intermittent-continuous dual-mode multi-line refrigeration system. Background Technology

[0002] In chemical production, a stable low-temperature supply of DMAC (dimethylacetamide) is crucial for ensuring the normal operation of the batching process. To meet the production demands of various carbon fiber products, multiple spinning lines are typically set up to operate in parallel. These spinning lines are production lines used to prepare carbon fiber spinning solutions. They involve dissolving and mixing polymer raw materials with the solvent DMAC under low-temperature conditions to form a spinning solution that meets the requirements for carbon fiber precursor production. In the current production layout, there are three spinning lines, designated as Spinning Line A, Spinning Line B, and Spinning Line C. These three lines operate in an intermittent refrigeration mode. Each spinning line is equipped with an independent refrigeration system, which mainly consists of key components such as a refrigeration circulation tank, a chiller, a circulation pump, inlet and outlet pipelines, regulating valves, and venting pipelines. The refrigeration system cools the DMAC (dimethylacetamide) at room temperature. The cooled DMAC is then supplied as a raw material to the corresponding spinning line for batching. The dedicated refrigeration system is activated during production and shut down synchronously when the spinning line stops.

[0003] With the expansion of production scale and changes in market demand, enterprises need to add glue-making lines D and E, both of which adopt a continuous cooling mode and require stable cooling 24 hours a day. Building separate cooling systems for these new lines would not only significantly increase capital investment in equipment but also lead to additional energy consumption and space occupation, such as increasing the complexity of spare parts reserves and troubleshooting, and raising maintenance costs. On the other hand, the existing A / B / C lines have high energy consumption due to intermittent start-stop cycles; building new systems would further increase total energy consumption, contradicting the requirements for energy conservation and carbon reduction. More importantly, the start-stop characteristics of intermittent systems are inherently contradictory to the continuous cooling requirements of continuous systems. Therefore, in existing technologies, glue-making lines using different operating modes (intermittent and continuous) have independently set up cooling systems. Traditional solutions cannot achieve resource coordination between intermittent and continuous modes and are difficult to adapt to the coordinated operation of the two types of glue-making lines.

[0004] Therefore, there is an urgent need for an innovative solution that integrates existing refrigeration system resources, eliminating the need to equip new glue-making lines with entirely new refrigeration systems. This solution can retain the intermittent refrigeration function of lines A / B / C while meeting the continuous refrigeration requirements of lines D / E, thereby achieving continuous operation and efficient utilization of the refrigeration system. This will increase production capacity while reducing production costs and resource consumption, and comprehensively optimize the overall system performance.

[0005] In view of this, this utility model is hereby proposed. Utility Model Content

[0006] The technical problem to be solved by this utility model is to overcome the shortcomings of the prior art. By integrating existing refrigeration resources, while retaining the existing intermittent refrigeration, it can meet the new continuous refrigeration demand without the need to equip new refrigeration units. Ultimately, it can improve the utilization rate of refrigeration equipment, reduce production costs, and comprehensively optimize the system's operating efficiency, providing a stable and reliable low-temperature supply solution for the coordinated and efficient production of multiple glue-making lines.

[0007] To solve the above-mentioned technical problems, the technical solution of this utility model is as follows: This utility model provides an intermittent-continuous dual-mode multi-line cooling system, comprising: Pretreatment device; Multiple sets of refrigeration units are connected in parallel, and the inlet of each refrigeration unit is connected to the outlet of the pretreatment unit. The distribution device includes a storage tank. The inlet of the storage tank is connected to the outlet of multiple sets of refrigeration units. The outlet of the storage tank is connected to multiple intermittent or continuous glue-making lines through pipelines. Each pipeline is equipped with a control device to control the distribution of materials in the storage tank.

[0008] Based on the existing intermittent refrigeration system of the intermittent glue-making line, this utility model eliminates the need to equip the newly added continuous glue-making line with a completely new refrigeration system. It reconstructs the original multiple independent intermittent refrigeration systems into multiple sets of refrigeration devices connected in parallel, adds storage tanks and control devices to construct a distribution device, and transforms it into an intermittent-continuous dual-mode multi-glue-making line refrigeration system that includes a pretreatment device, multiple sets of parallel refrigeration devices and a distribution device. This achieves the goal of meeting the continuous refrigeration requirements of the newly added glue-making line while retaining the original intermittent refrigeration function.

[0009] It should be noted that the glue-making line mentioned in this utility model is a spinning solution production line, especially a spinning solution production line for carbon fiber precursor.

[0010] The pretreatment device, refrigeration device, and distribution device of this utility model can always maintain continuous operation. The material flow direction is controlled by the control device to achieve on-demand distribution. For example, when the continuous glue-making line is running stably, the control device distributes the material to the continuous glue-making line, and the cold supply is guaranteed by multiple sets of refrigeration devices set in parallel. When the intermittent glue-making line needs to stop feeding, the control device stops distributing the material to the intermittent glue-making line. The pretreatment device and refrigeration device do not need to stop and can continue to serve the continuous glue-making line.

[0011] The control device controls the material distribution, which is especially suitable for situations with multiple intermittent glue production lines. It can avoid energy consumption and lifespan reduction caused by frequent start-ups and shutdowns of the refrigeration unit. It can achieve the coordinated operation of intermittent and continuous modes, which not only maintains the flexibility of the original intermittent production, but also meets the stability of continuous production, and greatly improves the utilization rate of the refrigeration unit and the overall operating efficiency of the system.

[0012] As the core buffer and temporary storage component of the distribution device, the storage tank can centrally store the low-temperature materials after refrigeration and filtration, so that the incoming low-temperature materials are fully mixed, reduce local temperature deviations, and ensure that the temperature of the materials flowing to the glue production line is uniform.

[0013] In the above technical solution, the pipeline includes a first main conveying pipeline and a second main conveying pipeline. The first main conveying pipeline is connected to at least one intermittent glue-making line, and the second main conveying pipeline is connected to at least one continuous glue-making line.

[0014] In the above technical solution, the first main conveying pipeline is provided with multiple branches, each branch being connected to an intermittent glue-making line; the second main conveying pipeline is provided with multiple branches, each branch being connected to a continuous glue-making line.

[0015] In the above technical solution, the first main conveying pipeline and the second main conveying pipeline are respectively equipped with a batching pump.

[0016] This invention features a dedicated batching pump on the conveying pipeline for supplying materials to both intermittent and continuous glue-making lines, achieving physical isolation and independent control of the material supply for both intermittent and continuous glue-making modes. By using dedicated pumps and pipelines, this system effectively avoids interference from frequent start-ups and shutdowns of the intermittent glue-making line and sudden flow changes on the stable operation of the continuous glue-making line.

[0017] In the above technical solution, a return pipeline is provided on the first main conveying pipeline and / or the second main conveying pipeline, and the return pipeline is connected to the storage tank.

[0018] This invention enhances the flexibility and stability of the system by designing a return pipeline to provide a material circulation path. The return pipeline allows excess or redundant material to be returned to the storage tank when the glue-making line does not need material temporarily, instead of forcibly shutting down upstream equipment, thereby avoiding frequent start-ups and shutdowns of core components such as pumps.

[0019] The introduction of a reflux line, working in conjunction with system control devices (such as valve assemblies), can dynamically adjust the material flow direction. For example, when an intermittent glue-making line suspends production, opening the reflux line allows materials to return to the storage tank for buffering and reuse. This not only maintains a stable liquid level in the tank but also ensures sufficient suction capacity for the batching pump, preventing the risk of dry running or cavitation. Simultaneously, the reflux function helps absorb system pressure fluctuations; for instance, when pump outlet pressure is abnormal, reflux can quickly balance the pressure, reducing the impact on pipelines and equipment.

[0020] This invention improves the system's adaptability in both intermittent and continuous modes by designing a reflux pipeline, enabling the refrigeration unit to operate continuously without needing to shut down synchronously with the start and stop of the glue-making line. This reduces energy consumption and equipment wear, extending service life. Furthermore, the reflux pipeline design supports material recycling, improving resource efficiency and providing a reliable foundation for collaborative production across multiple glue-making lines, thus optimizing overall performance.

[0021] In the above technical solution, the control device is respectively installed on the first main conveying pipeline or its branch, the second main conveying pipeline or its branch and the return pipeline, to distribute the material to the intermittent glue-making line, the continuous glue-making line or return it to the storage tank.

[0022] This invention can dynamically guide materials from the storage tank to three destinations based on real-time production needs: intermittent glue-making line, continuous glue-making line, or return to the storage tank. For example, when the intermittent glue-making line needs to be fed, the control device on the branch leading to that glue-making line is activated; when a glue-making line suspends production, the control device on its branch is deactivated, and the control device on the return pipeline is activated, allowing the material to return to the storage tank for circulation, thereby ensuring that the upstream pump and refrigeration unit can operate continuously and stably without shutdown.

[0023] The control device typically consists of various valves (such as on / off valves and regulating valves) and their actuators, and can integrate pressure and flow sensors to form an interlocked control system. For example, the control device installed on the return pipeline of the first main conveying pipeline can be interlocked with the outlet pressure of the batching pump. When the pressure fluctuates, it automatically adjusts the return flow rate to achieve automatic pressure stabilization. This design allows the flow and pressure fluctuations caused by the frequent start-stop operations of the intermittent glue-making line to be quickly absorbed and buffered by the control device on its dedicated pipeline, without being transmitted to the continuous glue-making line side. This effectively isolates the mutual interference between different operating modes, ensuring the stability of continuous production and product quality.

[0024] Furthermore, this modular control device design provides the system with excellent scalability. When a new glue-making line needs to be added, only parallel control devices and branch lines need to be added to the corresponding main delivery pipeline. This expansion method does not require modification of core components such as pretreatment devices, refrigeration devices, and storage tanks, greatly reducing the complexity and cost of system expansion. This allows the present invention to flexibly adapt to future adjustments in production scale. In the above technical solution, the refrigeration device includes a refrigeration cycle storage tank and a refrigeration machine. The inlet of the refrigeration cycle storage tank is connected to the outlet of the pretreatment device, the outlet is connected to the inlet of the refrigeration machine, and the outlet of the refrigeration machine is connected to the inlet of the storage tank.

[0025] In the above technical solution, the outlet of the refrigeration unit is connected to the refrigeration circulation storage tank through a refrigeration return pipeline, and the material returns to the refrigeration circulation storage tank for cyclic refrigeration.

[0026] The refrigeration device of this utility model mainly includes two key pieces of equipment: a refrigeration circulation tank and a refrigeration machine. The inlet of the refrigeration circulation tank receives materials that have been pre-processed by the pretreatment device, and its outlet is connected to the inlet of the refrigeration machine. After the refrigeration machine performs deep cooling on the materials, its outlet is finally connected to the inlet of the storage tank of the distribution device.

[0027] To optimize refrigeration efficiency and temperature control, a refrigeration return pipeline is installed at the outlet of the refrigeration unit, allowing the material to return to the refrigeration circulation tank for cyclic refrigeration. The cooling capacity can continuously accumulate and exchange within the loop, resulting in a more stable and lower material temperature. When the storage tank needs replenishment, deeply cooled material can be drawn from the refrigeration unit.

[0028] In the above technical solution, the outlet of the refrigeration unit is provided with an outlet regulating valve, the inlet of the refrigeration cycle storage tank is provided with an inlet regulating valve, the outlet regulating valve is interlocked with the liquid level of the storage tank of the distribution device and / or the outlet temperature of the corresponding refrigeration unit, and the inlet regulating valve is interlocked with the liquid level of the corresponding refrigeration cycle storage tank.

[0029] This invention incorporates interlocking control valves at key nodes, enabling efficient, precise, and automated operation of the refrigeration system, and significantly improving the system's adaptability and stability in both intermittent and continuous modes.

[0030] A temperature-interlocked outlet regulating valve is installed at the refrigeration unit outlet, enabling precise dual control of the liquid level and temperature of the material output from the refrigeration system. When the liquid level in the refrigerated storage tank is lower than a preset value, the outlet regulating valve opens wider, increasing the material supply to the tank and preventing insufficient suction from the batching pump due to low liquid level. When the liquid level is higher than the preset value, the valve opens narrower to prevent overload overflow of the storage tank, thus maintaining a stable liquid level and ensuring continuous material supply to subsequent batching devices. Simultaneously, if the refrigeration unit outlet temperature exceeds a set threshold, the regulating valve can dynamically adjust its opening (e.g., increasing flow rate to improve heat exchange efficiency or coordinating with refrigeration unit load adjustment) to promote cooling output and lower the material temperature. If the temperature is lower than the threshold, the valve opens narrower to avoid over-refrigeration and energy waste, ensuring that the temperature of the material entering the storage tank always meets the requirements of the adhesive manufacturing process. This independent interlocking control for each refrigeration circuit can adapt to fluctuations in material demand under both intermittent and continuous modes, ensuring stable supply and temperature consistency. Furthermore, precise adjustment of each circuit reduces energy loss, improving overall system efficiency and the stability of adhesive product quality.

[0031] An inlet regulating valve is installed at the inlet of the refrigeration cycle storage tank to achieve independent and precise control of the material quantity of each refrigeration circuit: when the liquid level of the refrigeration cycle storage tank is lower than the preset value, the opening of the inlet regulating valve increases, increasing the amount of material entering the refrigeration cycle storage tank; when the liquid level is higher than the preset value, the opening of the regulating valve decreases, reducing the feed, thereby ensuring that the liquid level of the refrigeration cycle storage tank is maintained within a stable range.

[0032] In the above technical solution, the pretreatment device includes a precooling device and a filtration device. The material is cooled by the precooling device and filtered by the filtration device before entering the refrigeration device.

[0033] Pre-cooling devices (such as heat exchangers and air-cooled units) are responsible for initially cooling materials at room temperature, reducing the heat load on the main refrigeration unit and improving the overall energy efficiency of the system. Filtration devices are used to remove solid impurities from the materials, preventing them from entering precision refrigeration equipment and causing wear or blockage, thus ensuring long-term stable operation of the system.

[0034] In the above technical solution, a filter is also provided between the refrigeration device and the storage tank. The material output by the refrigeration device enters the storage tank after being filtered by the filter. The filtration accuracy of the filter is higher than that of the pretreatment device.

[0035] This invention creates a final fine filtration barrier for materials before they enter the storage tank by adding a filter between the outlet of the refrigeration unit and the inlet of the distribution unit. This design effectively intercepts minute impurities that may remain from previous processes by filtering the refrigerated material with high precision, ensuring extremely high purity of the materials supplied to both intermittent and continuous glue-making lines. This fundamentally avoids abnormal glue-making reactions, product quality fluctuations, and wear or blockage of precision valves and pumps caused by impurities. It provides reliable material purity assurance for dual-mode collaborative production, significantly improving system stability and the consistency of final product quality.

[0036] By adopting the above technical solution, this utility model has the following beneficial effects compared with the prior art.

[0037] This invention eliminates the need to equip new continuous gluing lines with a completely new refrigeration system. By integrating existing pretreatment and refrigeration equipment, it transforms the originally independently operating intermittent refrigeration resources into a shareable intermittent-continuous dual-mode refrigeration system. This avoids resource idleness, significantly reduces equipment investment costs, and substantially reduces energy consumption, providing an efficient and stable refrigeration solution for collaborative production of multiple types and multiple gluing lines.

[0038] This invention enables continuous operation at all times, eliminating the need for frequent shutdowns of core equipment such as pumps and chillers due to the start and stop of the glue production line. This avoids energy consumption and equipment lifespan reduction during start-up and shutdown, significantly improving equipment utilization and reducing long-term operating costs.

[0039] This invention effectively isolates the volatility of intermittent production from the stability required for continuous production at both the physical structure and control system levels by distributing control devices across each delivery pipeline, branch line, and return pipeline, and introducing an interlocking control mechanism based on key parameters such as pump outlet pressure. This design ensures both the constantness of continuous glue-making process parameters, thereby improving product quality, and the flexibility of intermittent glue-making line scheduling, preventing interference between the two processes.

[0040] Meanwhile, the system achieves dynamic and precise control of parameters such as material flow rate, pressure, and temperature, flexibly adapting to the different operating requirements of both intermittent and continuous glue-making lines without shutdown. On the one hand, it meets the periodic feeding needs of the original intermittent glue-making line; on the other hand, it provides a stable cooling source for the continuous glue-making line. The entire process is highly automated, significantly reducing operational errors that may be caused by manual intervention, lowering labor intensity, and ultimately achieving efficient collaborative production between intermittent and continuous glue-making lines.

[0041] This invention significantly enhances scalability and ease of maintenance. The parallel refrigeration and distribution devices allow for flexible addition or removal of pipeline branches and control devices. When a new glue-making line needs to be added in the future, only parallel control devices and branches need to be added to the corresponding main delivery pipeline, without modifying the core structure of the pretreatment device, refrigeration device, etc. Expansion is simple and cost-effective, and it can flexibly adapt to the needs of production scale expansion and multi-specification product production.

[0042] The specific embodiments of this utility model will be described in further detail below with reference to the accompanying drawings. Attached Figure Description

[0043] The accompanying drawings, as part of this utility model, are used to provide a further understanding of the present utility model. The illustrative embodiments and descriptions of the present utility model are used to explain the present utility model, but do not constitute an undue limitation of the present utility model. Obviously, the drawings described below are merely some embodiments; those skilled in the art can obtain other drawings based on these drawings without creative effort. In the drawings: Figure 1 This is a schematic diagram of the intermittent cooling system process for the three glue-making lines on site. Figure 2 This is a schematic diagram of the intermittent-continuous dual-mode multi-line cooling system of this utility model.

[0044] Attached reference numerals: 1-First stage filter, 2-DMAC storage tank, 3-Cooling plate heat exchanger, 4-Air-cooled unit, 5-Second stage filter, 6-First refrigeration cycle storage tank, 7-First refrigeration unit, 8-Second refrigeration cycle storage tank, 9-Second refrigeration unit, 10-Third refrigeration cycle storage tank, 11-Third refrigeration unit, 12-Third stage filter, 13-Storage tank, 100-Feed pump, 101-First circulation pump, 102-Second circulation pump, 103-Third circulation pump. 104-Fourth Circulation Pump, 105-Fifth Circulation Pump, 106-Sixth Circulation Pump, 107-First Feeding Pump, 108-Second Feeding Pump, 109-Third Feeding Pump, 110-Fourth Feeding Pump, 201-First Return Valve Group, 202-Second Return Valve Group, 301-First Intermittent Feeding Valve Group, 302-Second Intermittent Feeding Valve Group, 303-Third Intermittent Feeding Valve Group, 401-First Continuous Feeding Valve Group, 402-Second Continuous Feeding Valve Group.

[0045] It should be noted that these accompanying drawings and textual descriptions are not intended to limit the scope of the present invention in any way, but rather to illustrate the concept of the present invention to those skilled in the art by referring to specific embodiments. Detailed Implementation

[0046] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions in the embodiments will be clearly and completely described below with reference to the accompanying drawings. The following embodiments are used to illustrate this utility model, but are not intended to limit the scope of this utility model. It is understood that the specific embodiments described herein are merely for explaining this utility model, and not for limiting this utility model. It should also be noted that, for ease of description, only the parts related to this utility model are shown in the accompanying drawings, not all of them.

[0047] The technical solution of this utility model will be further described below with reference to the accompanying drawings and specific embodiments.

[0048] Before detailing the innovative solution of this utility model, it is necessary to first explain the configuration of the original field system in order to better understand the improvements and technical advantages of this utility model.

[0049] like Figure 1 As shown, the original on-site system had three completely independent intermittent refrigeration systems set up for the three glue-making lines (Line A, Line B, and Line C). The incoming DMAC material first undergoes preliminary filtration through filter 1, and then enters the DMAC storage tank 2 for temporary storage. The feed pump 100 draws material from the storage tank, subjecting it to two stages of pre-cooling: passing it through a cooling plate heat exchanger 3 and an air-cooled unit 4. The pre-cooled material then undergoes further filtration through a second filter 5.

[0050] Subsequently, the material is diverted to three independent refrigeration branches: the first branch includes a first refrigeration circulation tank 6, a first circulation pump 101, a first chiller 7, and a second circulation pump 102; the second branch includes a second refrigeration circulation tank 8, a second circulation pump 103, a second chiller 9, and a third circulation pump 104; and the third branch includes a third refrigeration circulation tank 10, a third circulation pump 105, a third chiller 11, and a fourth circulation pump 106. The material from the chiller outlet of each branch flows back to the refrigeration circulation tank of that branch, and then the material in the refrigeration circulation tank is distributed to the corresponding intermittent glue-making lines A / B / C via dedicated circulation pumps 102 / 104 / 106.

[0051] This independently configured refrigeration system has obvious limitations: each system operates completely independently, making it impossible to share and optimize the allocation of cooling resources; the intermittent operation mode leads to frequent start-ups and shutdowns of equipment, resulting in high energy consumption; and it is difficult to adapt to the stable cooling demand of newly added continuous glue-making lines.

[0052] Example 1 like Figure 2 As shown, this utility model reconstructs the original system to form an intermittent-continuous dual-mode multi-line refrigeration system consisting of a pretreatment device, multiple sets of parallel refrigeration devices, and a distribution device. The pretreatment device retains the original system's primary filter 1, DMAC storage tank 2, feed pump 100, cooling plate heat exchanger 3, air-cooled unit 4, and secondary filter 5. The key improvement lies in reconstructing the original three independent refrigeration branches into three sets of parallel refrigeration devices and adding a distribution device. The specific structure and process are as follows: (1) Pretreatment device It consists of a primary filter 1, a DMAC storage tank 2, a feed pump 100, a cooling plate heat exchanger 3, an air-cooled unit 4, and a secondary filter 5, which realizes the initial impurity removal of DMAC incoming material (the primary filter 1 filters out impurities with larger particle sizes), temporary storage, two-stage cooling (plate heat exchanger + air cooling), and medium particle size impurity removal (the secondary filter 5 filters out medium particle sizes). (2) Parallel refrigeration units The inlet of each refrigeration unit is connected to the outlet of the pretreatment unit. That is, the inlet of the refrigeration cycle storage tank 6 / 8 / 10 is connected to the outlet of the second filter 5. The outlet of the refrigeration cycle storage tank 6 / 8 / 10 is connected to the inlet of the refrigeration machine 7 / 9 / 11 through the circulation pump 101 / 103 / 105. The cold material refrigerated by the refrigeration machine 7 / 9 / 11 is partially returned to the refrigeration cycle storage tank 6 / 8 / 10 through the return pipeline, and partially transported to the distribution device. (3) Dispensing device The distribution device includes a storage tank 13, whose inlet is connected to the outlet of three sets of refrigeration units. The outlet is connected to multiple intermittent glue-making lines A / B / C and continuous glue-making lines D / E via pipelines. Each pipeline is equipped with a control device to achieve on-demand distribution of materials.

[0053] As the core buffer and temporary storage component of the distribution device, the storage tank 13 can centrally store the low-temperature materials after refrigeration and filtration, so that the incoming low-temperature materials are fully mixed, reduce local temperature deviations, and ensure that the temperature of the materials flowing to the glue production line is uniform.

[0054] Example 2 Based on Embodiment 1, this embodiment includes a first main conveying pipeline and a second main conveying pipeline. The first main conveying pipeline is connected to at least one intermittent glue-making line, and the second main conveying pipeline is connected to at least one continuous glue-making line. The first main conveying pipeline has multiple branches, each of which is connected to an intermittent glue-making line; the second main conveying pipeline also has multiple branches, each of which is connected to a continuous glue-making line.

[0055] Furthermore, a first batching pump 107 is installed on the first main conveying pipeline, which is responsible for conveying the material in the storage tank 13 to the intermittent glue-making line; a second batching pump 108 is installed on the second main conveying pipeline, which is responsible for conveying the material in the storage tank 13 to the continuous glue-making line. This dedicated line design physically isolates the intermittent and continuous glue-making modes, effectively avoiding mutual interference between different operating modes.

[0056] Furthermore, the control devices on the first and second main delivery pipelines are specifically embodied in dedicated valve groups installed on each branch.

[0057] like Figure 2 As shown, on the first main conveying pipeline or its branches, the material distribution to intermittent glue-making lines A, B, and C can be controlled respectively by adjusting the first intermittent dispensing valve group 301, the second intermittent dispensing valve group 302, and the third intermittent dispensing valve group 303. On the second main conveying pipeline or its branches, the material supply to continuous glue-making lines D and E is achieved through the first continuous dispensing valve group 401 and the second continuous dispensing valve group 402. These control devices can be automatic control valve groups and interlocked with pressure and flow sensors.

[0058] Example 3 Based on Example 2, a first return pipeline and a second return pipeline are respectively provided on the first main conveying pipeline and the second main conveying pipeline. The first / second return pipeline is connected to the storage tank 13, so that excess material can be returned to the storage tank 13 through the return pipeline for recycling, avoiding ineffective discharge or equipment overload. Meanwhile, the return pipeline can maintain a stable liquid level in storage tank 13, ensuring that the batching pump always has sufficient suction volume to avoid dry running and cavitation, and ensuring the safety of continuous equipment operation.

[0059] Furthermore, a control device is installed on the return pipeline, specifically a return valve assembly installed on the return pipeline, such as... Figure 2 As shown, the first reflux valve group 201 is installed on the first reflux pipeline, and the second reflux valve group 202 is installed on the second reflux pipeline.

[0060] Furthermore, the reflux valve assembly is interlocked with the corresponding batching pump outlet pressure. When pressure fluctuations are detected, the opening degree is automatically adjusted to maintain stable system pressure. For example, interlocking the first reflux valve assembly 201 with the outlet pressure of the first batching pump 107 enables dynamic and precise control of the feed pressure of the intermittent glue-making line: when the intermittent glue-making line starts or stops or the load changes suddenly, causing the pump outlet pressure to exceed the preset threshold, the opening degree of the first reflux valve assembly 201 increases, allowing more material to return to the storage tank 13 through the reflux pipeline, reducing the amount of material flowing to the glue-making line, thereby quickly reducing the outlet pressure and avoiding excessive pressure from impacting or damaging the pipelines, valves, and glue-making line equipment; when the outlet pressure is lower than the preset threshold, the valve assembly opening degree decreases, reducing the amount of refluxed material, increasing the feed to the glue-making line, and increasing the outlet pressure to meet the material requirements of the intermittent glue-making line. This real-time responsive interlocking control can adapt to load fluctuations caused by frequent start-stop of the intermittent glue-making line, maintain the pump outlet pressure within a stable range, ensure the continuity and stability of material supply, avoid equipment wear or failure caused by sudden pressure changes, extend the service life of the first batching pump and subsequent pipelines and valves, reduce production interruptions caused by abnormal pressure, and improve production efficiency and system reliability in intermittent mode.

[0061] Interlocking the second reflux valve assembly 202 with the outlet pressure of the second batching pump 108 provides a stable supply pressure guarantee for the continuous glue-making line. When the continuous glue-making line operates continuously for a long time, and the production load is slightly adjusted or the pipeline resistance changes, causing the outlet pressure of the second batching pump 108 to exceed the preset threshold, the opening of the second reflux valve assembly 202 increases, causing some material to flow back to the storage tank 13, reducing the amount of material flowing to the continuous glue-making line, quickly reducing the outlet pressure, and avoiding overload damage to the pipeline interface, valve seals, and glue-making line reaction equipment caused by high pressure. When the outlet pressure is lower than the preset threshold, the valve assembly opening decreases, reducing the amount of refluxed material, increasing the supply to the glue-making line, and increasing the pressure to match the material demand of continuous production. This real-time dynamic interlocking regulation can accurately respond to load fluctuations in the continuous glue-making line, stabilize the outlet pressure within the process requirement range, and ensure the uniformity and continuity of material supply. This avoids abnormal glue-making reactions or product quality fluctuations caused by unstable pressure, and reduces mechanical wear on the second batching pump 108 and subsequent pipeline equipment caused by sudden pressure changes, thereby reducing the risk of downtime due to malfunctions and ensuring production efficiency and long-term system reliability in the continuous glue-making mode.

[0062] Example 4 Furthermore, three filters 12 are installed between the refrigeration unit and the storage tank. Their filtration accuracy is higher than that of the pretreatment unit, forming a final fine filtration barrier.

[0063] The filters at each stage employ a stepped filtration design. For example, the first filter 1 filters out larger particles (e.g., particles ≥ 0.5 μm) from the raw materials, preventing them from entering pretreatment equipment such as the feed pump and cooling plate heat exchanger, thus avoiding wear or blockage and ensuring stable operation of the pretreatment unit. The second filter 5 further filters medium-sized particles (e.g., particles ≥ 0.3 μm), preventing them from entering precision components such as the circulating pump and refrigeration unit, reducing malfunctions caused by impurities and extending the service life of the refrigeration equipment. The third filter 12 filters out tiny impurities (e.g., particles ≥ 0.1 μm) with the highest precision, ensuring the purity of materials entering the storage tank 13 and the glue-making line, and preventing impurities from affecting the glue-making reaction or product quality. This tiered filtration design avoids the frequent clogging caused by a single high-precision filter intercepting a large number of large particles, reducing maintenance frequency and costs. It also ensures the cleanliness of materials at each stage through step-by-step purification, forming a complete impurity control chain from pretreatment to refrigeration to batching, ultimately ensuring stable operation of the system equipment and the quality of the glue-making product.

[0064] Example 5 Based on Example 1, this embodiment includes an inlet regulating valve and an outlet regulating valve for each refrigeration unit. The inlet regulating valves of refrigeration cycle storage tanks 6 / 8 / 10 are interlocked with the liquid level of the corresponding tanks: when the liquid level of the refrigeration cycle storage tank is lower than a preset value, the opening of the corresponding inlet regulating valve increases, increasing the amount of material entering the refrigeration cycle storage tank; when the liquid level is higher than the preset value, the opening of the corresponding inlet regulating valve decreases, reducing the feed, thus ensuring stable liquid level and uniform material temperature in the refrigeration cycle storage tank.

[0065] The outlet regulating valves at the outlets of chillers 7 / 9 / 11 are dually interlocked with the liquid level in storage tank 13 and the outlet temperature of the chiller, enabling precise control of the material supply and refrigeration temperature. For example, if the chiller outlet temperature is higher than the set threshold, the outlet regulating valve can dynamically adjust its opening (e.g., increasing the flow rate to improve heat exchange efficiency or coordinating with chiller load adjustment) to promote cooling output and reduce the material temperature; if the temperature is lower than the threshold, the opening is reduced to avoid over-cooling and energy waste, ensuring that the temperature of the material entering the storage tank always meets the requirements of the adhesive manufacturing process.

[0066] This hierarchical interlocking control strategy ensures the stable operation of the system in both intermittent and continuous modes, meeting the stable cooling requirements of the continuous glue-making line while adapting to the fluctuating requirements of the intermittent glue-making line.

[0067] Example 6 In this embodiment, the second circulation pump 102, the fourth circulation pump 104, and the sixth circulation pump 106 of the original intermittent cooling system of the glue production line are retained as backup pumps for the first circulation pump 101, the third circulation pump 103, and the fifth circulation pump 105, respectively. The backup pumps are connected in parallel with the corresponding main pumps to make full use of existing resources, achieve rapid switching when the main pump fails, ensure continuous operation of the system, and reduce the risk of production stoppage.

[0068] Furthermore, the feed pump 100, the first batching pump 107, and the second batching pump 108 are all equipped with standby pumps, connected in parallel with the main pumps. This further ensures the normal operation of the production line while improving maintenance convenience, especially when the core equipment is running continuously (without frequent start-stop cycles). Figure 2 As shown, the third batching pump 109 and the fourth batching pump 110 are the standby pumps for the first batching pump 107 and the second batching pump 108, respectively.

[0069] Example 7 This embodiment demonstrates in detail how the system responds to dynamic adjustments in production plans and achieves collaborative work under different modes through specific changes in operating scenarios.

[0070] Assume that intermittent glue-making lines A and B are currently operating, while line C is suspended; continuous glue-making lines D and E are operating continuously. The system workflow is as follows: the pretreatment unit operates continuously, providing the system with stably processed materials; three sets of refrigeration units operate in parallel, providing stable cooling to storage tank 13 through coordinated control of the outlet regulating valve; the first batching pump 107 transports materials to lines A and B, while maintaining stable pipeline pressure through precise adjustment of the first reflux valve group 201; the second batching pump 108 continuously supplies materials to lines D and E, and the second reflux valve group 202 automatically fine-tunes according to pressure changes.

[0071] Scenario Change 1: When the intermittent glue-making line C needs to be added to the system, simply open the corresponding third intermittent batching valve group 303, and the system can smoothly transition to the new operating state without any downtime for adjustment. Specifically: The opening of the third intermittent batching valve group 303 reduces the total flow resistance of the first main conveying pipeline. The outlet pressure and total flow rate of the first batching pump 107 decrease. At this time, the first reflux valve group 201, interlocked with the outlet pressure of the first batching pump 107, detects the pressure drop and automatically and precisely reduces its opening. Reducing reflux is equivalent to increasing the effective flow rate to the glue-making line. This action quickly compensates for the increased flow demand caused by the opening of line C, thereby stabilizing the pump's outlet pressure within the set range.

[0072] As the opening of the first reflux valve assembly 201 decreases, more material is distributed to the three operating intermittent glue-making lines. The system smoothly transitions from feeding material to lines A and B to a new steady state feeding material to lines A, B, and C. The entire flow redistribution process is dynamic, continuous, and smooth, effectively avoiding hydraulic shocks caused by sudden changes in flow in the pipeline system.

[0073] Furthermore, during the entire start-up process of line C, the second main conveying pipeline serving the continuous glue-making line remains completely unaffected. The operation of the second batching pump 108, the status of the second return valve group 202, and the material supply to lines D and E remain consistently stable. This fully demonstrates that this invention achieves physical isolation between intermittent and continuous modes through an independent pipeline system and control device.

[0074] Scenario Change 2: If the intermittent glue production line B needs to be paused, simply close the corresponding second intermittent batching valve group 302 to cut off the material supply to line B. Almost simultaneously, the system control logic or interlocking device will adjust the opening of the first return valve group 201 accordingly, specifically: Because the second intermittent batching valve group 302 is closed, the total resistance of the outlet pipeline of the first batching pump 107 increases, causing the pressure to rise. At this time, the first return valve group 201, which is interlocked with the pump outlet pressure, will sensitively and automatically increase its opening, allowing the material originally planned to be delivered to line B to smoothly return to the storage tank 13 through the return pipeline. This process quickly absorbs pressure fluctuations, ensuring the stability of material supply to line A. More importantly, it completely avoids the impact of frequent start-stop cycles on the first batching pump 107 caused by the start and stop of line B.

[0075] Throughout the entire process, the pretreatment unit, refrigeration unit, and the second main conveying pipeline serving the continuous glue-making line (including the second batching pump 108, the second reflux valve group 202, and the continuous batching valve group 401 / 402) all maintained their original operation without any interference. The continuous production stability of lines D and E was ensured. The system smoothly transitioned from a state where lines A and B were running and line C was suspended to a state where only line A was running and lines B and C were suspended, without requiring any equipment shutdowns.

[0076] Through the above two scene transitions (C line joining the running and B line pausing the running), it can be clearly seen that: This utility model's intermittent-continuous dual-mode multi-gluing line refrigeration system can quickly respond to the start and stop commands of any intermittent gluing line. By operating the corresponding intermittent batching valve group and reflux valve group in a coordinated manner, it can achieve precise flow distribution and stable pressure control, and has flexible scheduling capabilities.

[0077] This invention achieves physical isolation of operating modes. Any flow and pressure fluctuations generated by any operation of the intermittent glue-making line are effectively confined within its primary main delivery pipeline system, and are quickly absorbed and balanced through a reflux design. This ensures that the production environment of the continuous glue-making line is completely unaffected by intermittent operation, guaranteeing the stability of its process parameters and successfully resolving the core contradiction of two drastically different operating modes—intermittent and continuous—coexisting within the same system.

[0078] Furthermore, this invention also embodies a high degree of automation and reliability. Based on the interlocking control of the valve group and the pump outlet pressure, the system can automatically and quickly maintain the balance of the entire pipeline, greatly reducing the intensity of manual operation and the risk of error, and ensuring the reliability of long-term operation.

[0079] In summary, this utility model, through its unique system architecture and intelligent control strategy, successfully achieves efficient, stable, and flexible coordination between intermittent and continuous production within a unified refrigeration system, providing strong technical support for enterprises to improve production efficiency and reduce operating costs.

[0080] The above description is merely a preferred embodiment of the present utility model and is not intended to limit the present utility model in any way. Although the present utility model has been disclosed above with reference to a preferred embodiment, it is not intended to limit the present utility model. Any person skilled in the art can make some modifications or alterations to the above-described technical content to create equivalent embodiments without departing from the scope of the present utility model. Any simple modifications, equivalent changes, and alterations made to the above embodiments based on the technical essence of the present utility model without departing from the scope of the present utility model shall still fall within the scope of the present utility model.

Claims

1. A cooling system for intermittent-continuous dual-mode multi-line glue application, characterized in that, include: Pretreatment device; Multiple sets of refrigeration units are connected in parallel, and the inlet of each refrigeration unit is connected to the outlet of the pretreatment unit. The distribution device includes a storage tank. The inlet of the storage tank is connected to the outlet of multiple sets of refrigeration units. The outlet of the storage tank is connected to multiple intermittent or continuous glue-making lines through pipelines. Each pipeline is equipped with a control device to control the distribution of materials in the storage tank.

2. The system according to claim 1, characterized in that, The pipeline includes a first main conveying pipeline and a second main conveying pipeline. The first main conveying pipeline is connected to at least one intermittent glue-making line, and the second main conveying pipeline is connected to at least one continuous glue-making line.

3. The system according to claim 2, characterized in that, The first main conveying pipeline has multiple branches, each branch being connected to an intermittent glue-making line; the second main conveying pipeline has multiple branches, each branch being connected to a continuous glue-making line.

4. The system according to claim 2, characterized in that, A batching pump is installed on the first main conveying pipeline and the second main conveying pipeline respectively.

5. The system according to claim 2, characterized in that, A return pipeline is provided on the first main delivery pipeline and / or the second main delivery pipeline, and the return pipeline is connected to the storage tank.

6. The system according to claim 5, characterized in that, The control devices are respectively installed on the first main conveying pipeline or its branch, the second main conveying pipeline or its branch, and the return pipeline, to distribute materials to the intermittent glue-making line, the continuous glue-making line, or return them to the storage tank.

7. The system according to any one of claims 1-6, characterized in that, The refrigeration device includes a refrigeration cycle storage tank and a refrigeration machine. The inlet of the refrigeration cycle storage tank is connected to the outlet of the pretreatment device, and the outlet is connected to the inlet of the refrigeration machine. The outlet of the refrigeration machine is connected to the inlet of the storage tank.

8. The system according to claim 7, characterized in that, The outlet of the refrigeration unit is connected to the refrigeration circulation tank through a refrigeration return pipeline, and the material returns to the refrigeration circulation tank for cyclic refrigeration.

9. The system according to any one of claims 1-6, characterized in that, The pretreatment device includes a precooling device and a filtration device. The material is cooled by the precooling device and filtered by the filtration device before entering the refrigeration device.

10. The system according to any one of claims 1-6, characterized in that, A filter is also provided between the refrigeration unit and the storage tank. The material output from the refrigeration unit is filtered by the filter before entering the storage tank.