By using ultra-high performance concrete with no-removal formwork and a splicing connection method for the reinforcement layer, the problem of strength reduction in bridge pier structures caused by freeze-thaw cycles and corrosion was solved. This achieved efficient reinforcement and simple construction, extended the service life of the bridge structure, and reduced the impact on river flow.

CN224997394UActive Publication Date: 2026-11-20CHINA WEST CONSTR ACAD OF BUILDING MATERIALS CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202522729759.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-23
Publication Date
2026-11-20
Estimated Expiration
2035-12-23

AI Technical Summary

Technical Problem

Existing bridge pier structures suffer from concrete cracking and steel reinforcement corrosion due to factors such as freeze-thaw cycles and salt corrosion, resulting in reduced strength. Furthermore, existing reinforcement methods increase the cross-sectional area of ​​the piers and the complexity of construction, affecting river flow.

Method used

Using ultra-high performance concrete formwork and reinforcement layer without removal, a ring cavity is formed by assembling prefabricated semi-circular formwork and filling it with a steel cage and ultra-high performance concrete reinforcement layer. Combined with bolt or clip connection, high-strength reinforcement is achieved.

Benefits of technology

It is simple to construct, saves construction time, enhances structural strength, extends service life, reduces the impact on river flow, and improves connection efficiency and strength.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224997394U_ABST
    Figure CN224997394U_ABST
Patent Text Reader

Abstract

This utility model belongs to the field of concrete construction technology, specifically relating to a bridge pier reinforcement structure, including an ultra-high performance concrete formwork that can be removed and an ultra-high performance concrete reinforcement layer. Both the formwork and reinforcement layer possess high strength and durability. The formwork is formed by assembling and fixing two semi-circular templates together, creating an annular cavity between the formwork and the pier. The reinforcement layer is poured and filled into the annular cavity, containing a steel cage surrounding the pier. The pier surface has chisel marks and steel bars are inserted, with the exposed steel bars extending at least 5cm beyond the pier surface. The gaps between the steel cage, the pier, and the formwork are all no less than 2cm. This structure features simple and convenient construction, significantly reduces construction time, provides high reinforcement strength, greatly enhances structural strength, extends the service life of the engineering structure, and has minimal impact on river flow.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of concrete building technology, specifically relating to a bridge pier reinforcement structure. Background Technology

[0002] Reinforced concrete structures, with their wide applicability, low cost, and ease of construction, have become the most widely used structural form, extensively applied to bridge piers. Design institutes design the strength and durability of bridge structures based on their actual usage conditions. However, with prolonged use, bridge pier structures suffer from concrete cracking due to freeze-thaw cycles and salt corrosion, further weakened by steel reinforcement corrosion, or structural damage from external forces such as water flow and sand. Therefore, to ensure the normal use of bridge structures, it is necessary to reinforce their structural strength.

[0003] Existing reinforcement methods include: a bridge pier reinforcement device disclosed in application number 202120668851.9 that facilitates reducing water flow impact; a bridge pier reinforcement device and its construction method disclosed in application number 201910823339.4; and an anti-scour cofferdam for bridge pier reinforcement disclosed in application number 201921190570.8. However, all of these methods significantly increase the cross-sectional area of ​​the bridge pier, occupy more land resources, reduce the cross-sectional area of ​​the river channel, and are relatively complex and cumbersome in construction. Utility Model Content

[0004] In view of the shortcomings of the existing technology, this utility model aims to provide a bridge pier reinforcement structure that is simple and convenient to construct, can greatly save construction time, has high reinforcement strength, can greatly enhance the structural strength, extend the service life of the engineering structure, and has little impact on river flow.

[0005] To achieve the above objectives, the present invention adopts the following technical solution: A bridge pier reinforcement structure includes an ultra-high performance concrete formwork (1) and an ultra-high performance concrete reinforcement layer (2). The ultra-high performance concrete formwork (1) and the ultra-high performance concrete reinforcement layer (2) have high strength and high durability. The ultra-high performance concrete formwork (1) is formed by assembling and fixing two semi-circular formworks (10). The ultra-high performance concrete formwork (1) can be prefabricated in advance and assembled on site, eliminating the need for formwork removal, saving resources, and greatly reducing the construction period. An annular cavity (4) is formed between the ultra-high performance concrete formwork (1) and the pier (3). The ultra-high performance concrete reinforcement layer (2) is poured and filled into the annular cavity (4) and contains a steel cage (5). The steel cage (5) surrounds the pier (3).

[0006] Among them, the surface of the pier (3) has chisel marks and is inlaid with steel bars (30). The steel bars (30) extend at least 5cm beyond the surface of the pier (3). The gap between the steel cage (5) and the pier (3) and the ultra-high performance concrete formwork (1) is not less than 2cm. The length of the steel bars extending beyond the surface of the pier is equal to the thickness of the steel cage plus the gap between the steel cage and the pier. This allows the ultra-high performance concrete reinforcement layer poured in the annular cavity to be tightly connected to the pier. The overall structural strength of the reinforcement structure is high, which greatly enhances the structural strength and extends the service life of the engineering structure. Moreover, this reinforcement structure can reduce the impact on the river flow in terms of thickness compared with the existing method.

[0007] As an alternative, one side of the semicircular template (10) has a protrusion (101) that is not less than 3cm, and the other side of the semicircular template (10) has a groove (102). The two semicircular templates (10) are connected by the protrusion (101) and the groove (102) and are fixed by fasteners. The two semicircular templates are easy to assemble and connect, which is efficient and the connection structure is strong.

[0008] As an improvement, one side of the protrusion (101) has a square snap-fit ​​protrusion (103), and one side of the groove (102) has a square snap-fit ​​groove (104) that snaps into the square snap-fit ​​protrusion (103); the connection between the two semicircular templates is more secure.

[0009] As another alternative, one side of the semicircular template has a protrusion (101) that is not less than 3cm, and the two sides of the protrusion (101) have square buckle protrusions (103); the other side of the semicircular template (10) has a groove (102), and the two sides of the groove (102) have square buckle slots (104) that are buckled and connected to the square buckle protrusions (103). The two semicircular templates (10) are fixedly connected by the protrusion (101) and the groove (102) and by the square buckle protrusions (103) to the square buckle slots (104). Similarly, the two semicircular templates are easy to assemble and connect, and the connection structure is strong.

[0010] Preferably, the fasteners are bolt assemblies.

[0011] In one alternative, the protrusion (101) and the groove (102) are respectively provided with threaded holes (105). The bolt assembly includes a bolt (106) and a washer (107). The bolt (106) is connected to the threaded hole (105) to fix the two semi-circular templates (10). The washer (107) is installed on the bolt (106) and covers the threaded hole (105).

[0012] Alternatively, the protrusion (101) and the groove (102) are respectively provided with a smooth connecting hole (108). The bolt assembly includes a bolt (106), a nut (109) and a washer (107). The bolt (106) passes through the smooth connecting hole (108) and is fastened to the nut (109) to fix the two semi-circular templates (10). The washer (107) is installed on the bolt (106) and covers the smooth connecting hole (108).

[0013] This utility model has the following beneficial effects: (1) The bridge pier reinforcement structure of this utility model is simple and convenient to construct and can greatly save the construction period; (2) The bridge pier reinforcement structure of this utility model has high reinforcement strength, which can greatly enhance the structural strength and extend the service life of the engineering structure; (3) The bridge pier reinforcement structure of this utility model can reduce the impact on river flow compared with the existing methods. (4) The bridge pier reinforcement structure of this utility model further improves the assembly connection efficiency and connection structure strength by optimizing the assembly connection method. Attached Figure Description

[0014] Figure 1 This is a top view of the bridge pier reinforcement structure of this utility model; Figure 2 This is the first embodiment of the semi-circular template assembly connection for the bridge pier reinforcement structure of this utility model; Figure 3 This is a second embodiment of the semi-circular template assembly connection for the bridge pier reinforcement structure of this utility model; Figure 4 This is the third embodiment of the semi-circular template assembly connection for the bridge pier reinforcement structure of this utility model; Figure 5 This is the first fastening embodiment of the bolt assembly for the bridge pier reinforcement structure of this utility model; Figure 6 This is the second fastening embodiment of the bolt assembly for the bridge pier reinforcement structure of this utility model.

[0015] Among them, 1-Ultra-high performance concrete formwork that does not need to be removed; 2-Ultra-high performance concrete reinforcement layer; 3-Pier column; 4-Annular cavity; 5-Reinforcing cage; 10-Semi-circular formwork; 30-Reinforcing bar; 101-Protrusion; 102-Groove; 103-Square buckle protrusion; 104-Square buckle groove; 105-Screw hole; 106-Bolt; 107-Washer; 108-Smooth connection hole; 109-Nut. Detailed Implementation

[0016] The present invention will be further described below with reference to the accompanying drawings and specific embodiments, so as to better understand the technical concept claimed by the present invention.

[0017] like Figure 1 and Figure 2 The bridge pier reinforcement structure shown includes an ultra-high performance concrete formwork 1 (non-removable) and an ultra-high performance concrete reinforcement layer 2. Both the ultra-high performance concrete formwork 1 and the ultra-high performance concrete reinforcement layer 2 possess high strength and high durability. The ultra-high performance concrete formwork 1 is formed by assembling and fixing two semi-circular formworks 10 together. One side of each semi-circular formwork 10 has a protrusion 101, which is at least 3cm long, and the other side has a groove 102. The two semi-circular formworks 10 are connected by the protrusion 101 and the groove 102, and are fixed together by fasteners. The assembly and connection of the two semi-circular formworks 10 is convenient and efficient, while also providing high structural strength. Furthermore, the ultra-high performance concrete formwork 1 can be prefabricated and assembled on-site, eliminating the need for formwork removal, saving resources, and significantly reducing construction time. After the ultra-high performance concrete formwork 1 is assembled, an annular cavity 4 is formed between it and the pier column 3. The ultra-high performance concrete reinforcement layer 2 is poured and filled into the annular cavity 4 and contains a steel cage 5, which surrounds the pier column 3.

[0018] The pier 3 has chisel marks on its surface and is inlaid with reinforcing bars 30. The reinforcing bars 30 extend at least 5 cm beyond the surface of the pier 3. The gaps between the reinforcing cage 5 and the pier 3, and between the ultra-high performance concrete formwork 1, are all no less than 2 cm. The length of the reinforcing bars 30 extending beyond the surface of the pier 3 is equal to the thickness of the reinforcing cage 5 plus the gap between the reinforcing cage 5 and the pier 3. This allows the ultra-high performance concrete reinforcement layer 2, poured in the annular cavity 4, to be tightly connected to the pier 3. The overall structural strength of the reinforcement structure is high, greatly enhancing the structural strength to extend the service life of the engineering structure. Furthermore, this reinforcement structure, in terms of thickness, can reduce the impact on river flow compared to existing methods.

[0019] like Figure 3 As shown, in Figure 1-2 Based on the embodiment shown, a square buckle protrusion 103 can be provided on one side of the protrusion 101, and a square buckle groove 104 corresponding to the square buckle protrusion 103 can be provided on one side of the groove 102 to make the connection between the two semicircular templates 10 more secure.

[0020] Or, different from Figure 2 , Figure 3 Examples of fastener-based fixed connections, such as Figure 4As shown, a protrusion 101 is provided on one side of the semicircular template 10, the protrusion 101 being no less than 3cm, and square snap-fit ​​protrusions 103 are provided on both sides of the protrusion 101. A groove 102 is provided on the other side of the semicircular template 10, and square snap-fit ​​slots 104 are provided on both sides of the groove 102, corresponding to the square snap-fit ​​protrusions 103. The two semicircular templates 10 are fixedly connected by the protrusion 101 and the groove 102 engaging and being snapped into the square snap-fit ​​slots 104 by the square snap-fit ​​protrusions 103. Similarly, the two semicircular templates 10 are easy to assemble and connect, efficient, and have high structural strength.

[0021] exist Figure 2 , Figure 3 In the embodiments: the fastener adopts a bolt assembly, and the fastening connection of the bolt assembly has the following two forms: 1. such as Figure 5 As shown, the protrusion 101 and the groove 102 are respectively provided with threaded holes 105. The bolt assembly includes a bolt 106 and a washer 107. The bolt 106 is connected to the threaded hole 105 to fix the two semi-circular templates 10. The washer 107 is installed on the bolt 106 and covers the threaded hole 105. The bolt assembly is convenient and quick to tighten and can prevent grout leakage when pouring concrete in the annular cavity 4 through the washer 107.

[0022] 2. For example Figure 6 As shown, the protrusion 101 and the groove 102 are respectively provided with smooth connecting holes 108. The bolt assembly includes a bolt 106, a nut 109 and a washer 107. The bolt 106 passes through the smooth connecting hole 108 and is fastened to the nut 109 to fix the two semi-circular templates 10. The washer 107 is installed on the bolt 106 and covers the smooth connecting hole 108, which can also achieve the same effect. Figure 5 The tightening effect of the bolt assembly shown.

[0023] For those skilled in the art, various other corresponding changes and modifications can be made based on the technical solutions and concepts described above, and all such changes and modifications should fall within the protection scope of the claims of this utility model.

Claims

1. A bridge pier reinforcement structure, characterized in that, include: The ultra-high performance concrete formwork (1) is formed by assembling and fixing two semi-circular formworks (10) together, and forming an annular cavity (4) between it and the pier (3). Ultra-high performance concrete reinforcement layer (2), poured and filled in the annular cavity (4) and containing a steel cage (5) surrounding the pier column (3); The surface of the pier (3) has chisel marks and is inlaid with steel bars (30). The steel bars (30) extend at least 5cm out of the surface of the pier (3). The gap between the steel cage (5) and the pier (3) and the ultra-high performance concrete formwork (1) is not less than 2cm.

2. The bridge pier reinforcement structure as described in claim 1, characterized in that, One side of the semicircular template (10) has a protrusion (101) that is not shorter than 3cm, and the other side of the semicircular template (10) has a groove (102). The two semicircular templates (10) are connected by the protrusion (101) and the groove (102) and are fixedly connected by fasteners.

3. The bridge pier reinforcement structure as described in claim 2, characterized in that, One side of the protrusion (101) has a square snap-fit ​​protrusion (103), and one side of the groove (102) has a square snap-fit ​​groove (104) that snaps into the square snap-fit ​​protrusion (103).

4. The bridge pier reinforcement structure as described in claim 1, characterized in that, One side of the semicircular template (10) has a protrusion (101) not shorter than 3cm, and the two sides of the protrusion (101) have square buckle protrusions (103); the other side of the semicircular template (10) has a groove (102), and the two sides of the groove (102) have square buckle slots (104) that are buckled and connected to the square buckle protrusions (103). The two semicircular templates (10) are fixedly connected by the protrusions (101) and the grooves (102) and by the square buckle protrusions (103) to the square buckle slots (104).

5. The bridge pier reinforcement structure as described in claim 2 or 3, characterized in that, The fasteners are bolt assemblies.

6. The bridge pier reinforcement structure as described in claim 5, characterized in that, The protrusion (101) and the groove (102) are respectively provided with threaded holes (105). The bolt assembly includes a bolt (106) and a washer (107). The bolt (106) is connected to the threaded hole (105) to fix the two semi-circular templates (10). The washer (107) is installed on the bolt (106) and covers the threaded hole (105).

7. The bridge pier reinforcement structure as described in claim 5, characterized in that, The protrusion (101) and the groove (102) are respectively provided with smooth connecting holes (108). The bolt assembly includes a bolt (106), a nut (109) and a washer (107). The bolt (106) passes through the smooth connecting hole (108) and is fastened to the nut (109) to fix the two semi-circular templates (10). The washer (107) is installed on the bolt (106) and covers the smooth connecting hole (108).

Citation Information

Patent Citations

  • A bridge pier reinforcement device and construction method thereof

    CN110468745B

  • Anti-scouring cofferdam for reinforcing pier

    CN210459251U

  • Pier reinforcing device capable of conveniently reducing water flow impact

    CN215441508U