Temporary steel platform for facilitating the operation of a soil removal machine in top-down construction

By designing a temporary steel platform in the reverse construction method and connecting the steel pipe column caps with the main load-bearing structure to form a temporary force transmission structure, the problem of damage to the main floor slab and beams during the soil extraction process in the reverse construction method was solved, and the construction safety and efficiency were improved.

CN224997642UActive Publication Date: 2026-11-20CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522587677.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-05
Publication Date
2026-11-20
Estimated Expiration
2035-12-05

AI Technical Summary

Technical Problem

In reverse construction, the damage to the main floor slabs and beams caused by soil extraction is a problem, especially when a complete load-bearing structure has not been formed, making it difficult to guarantee the safety and efficiency of soil extraction machinery operations.

Method used

Design a temporary steel platform that connects to the main load-bearing structure via steel pipe column caps to form a small temporary force transmission structure. Use pads, supporting main beams, and supporting secondary beams to form a planar support frame to support the outriggers of the soil extraction equipment, thus simplifying the soil extraction construction steps.

Benefits of technology

By directly connecting the main load-bearing components to form a temporary force transmission structure, the soil extraction and construction steps are simplified, and construction safety and efficiency are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224997642U_ABST
    Figure CN224997642U_ABST
Patent Text Reader

Abstract

The utility model relates to a kind of temporary steel platform in topsoil machine work is conducive to in cover and dig reverse construction method, comprising: steel pipe column cap, detachably fixed at the top of reverse construction method steel pipe column, steel pipe column cap includes U type clamping slot and the bracing plate connected with U type clamping slot;Packing plate, fixedly arranged at the top of steel pipe column cap;Supporting main beam, fixedly connected above packing plate;Supporting secondary beam, welded fixedly in the web area of supporting main beam, and supporting main beam and supporting secondary beam jointly constitute a plane support frame;Wherein, the supporting leg of topsoil equipment is supported on the plane support frame formed by supporting main beam and supporting secondary beam.The utility model directly connects through steel pipe column cap and main force component, and a small temporary force transmission structure is formed through packing plate, supporting main beam and supporting secondary beam, the supporting leg of topsoil equipment can be fixed on plane support frame, and the construction steps of topsoil in cover and dig reverse construction are simplified.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the technical field of building construction, and in particular to a temporary steel platform that facilitates the operation of a soil extraction machine in top-down construction. Background Technology

[0002] The reverse construction method is a construction approach suitable for ultra-deep basement high-rise buildings, where construction is carried out layer by layer from the ground floor downwards. This method helps control the impact of foundation pit deformation on the surrounding environment during construction. For ultra-deep basement projects in complex surrounding environments, it can effectively ensure the safety of surrounding buildings, structures, and nearby roads, pipelines, and other building facilities.

[0003] Because reverse construction employs a top-down, layer-by-layer construction method, when the next layer of soil is excavated, the portion below the outer wall beam of the basement of the previous layer has not yet been constructed. Therefore, the upper layer structure cannot yet form a box-shaped structure, and the floor load cannot be transferred to the main load-bearing structure through the floor slab. During the reverse excavation process, the soil extraction location needs to be reinforced to facilitate the operation of soil extraction machinery. Therefore, designing a temporary steel platform that facilitates the operation of soil extraction machinery is particularly important. Utility Model Content

[0004] This utility model aims to address the shortcomings of existing technologies and overcome the damage to the main floor slabs and beams during the reverse construction process. It provides a temporary steel platform that facilitates the operation of the excavator in the cut-and-cover construction method. Before a complete force transmission structure is fully formed, the temporary steel platform is connected to the main load-bearing structure, which facilitates the operation of the cut-and-cover excavator.

[0005] To achieve the above objectives, this utility model adopts the following technical solution:

[0006] A temporary steel platform for use by excavators in top-down construction (cut-and-cover method) includes:

[0007] A steel pipe column cap is detachably fixed to the top of a reverse-construction steel pipe column. The steel pipe column cap includes a U-shaped groove and a support plate connected to the U-shaped groove.

[0008] A base plate is fixedly installed on the top of the column cap of the steel pipe column;

[0009] Support the main beam and fix it to the top of the pad;

[0010] The secondary supporting beams are welded and fixed to the web area of ​​the main supporting beams. Together, the main supporting beams and the secondary supporting beams form a planar supporting frame.

[0011] The outriggers of the soil extraction equipment are supported on a planar support frame formed by the main support beam and the secondary support beam.

[0012] The U-shaped slot of the steel pipe column cap is inserted upside down into the top of the reverse construction steel pipe column and supported on the top plate of the main structure. Several support plates are welded between the two U-shaped slots.

[0013] The base plate is welded to the top of the steel pipe column cap.

[0014] The main support beam and the base plate are connected by bolts.

[0015] Specifically, it also includes ramp base plates, which overlap between the top slab of the main structure and the planar support frame, used to allow earthmoving equipment to travel to the planar support frame. The bottom length of the ramp base plate is a multiple of the vertical distance between the top slab of the main structure and the planar support frame.

[0016] In particular, soil extraction equipment can also be vertically hoisted and installed using tower cranes.

[0017] The beneficial effects of this utility model are: the utility model directly connects the steel pipe column cap to the main load-bearing components, and forms a small temporary force transmission structure through the pad plate, the main support beam and the secondary support beam. The outriggers of the soil extraction equipment can be fixed on the planar support frame, which simplifies the construction steps of soil extraction in the top-down construction of the cover-cut. Attached Figure Description

[0018] Figure 1 This is a schematic diagram of the elevation of the temporary steel platform during the top-down construction method of this utility model;

[0019] Figure 2 This is a schematic diagram of the temporary steel platform during the top-down construction method of this utility model;

[0020] In the diagram: 1-Main structure top slab; 2-Reverse construction steel pipe column; 3-Steel pipe column cap; 4-Plate; 5-Main supporting beam; 6-Secondary supporting beam; 7-Soil extraction equipment;

[0021] 31-U-shaped slot; 32-Support plate;

[0022] The following will describe in detail the embodiments of this utility model with reference to the accompanying drawings. Detailed Implementation

[0023] The principles and features of this utility model are described below with reference to the accompanying drawings. The embodiments described are for illustrative purposes only and are not intended to limit the scope of this utility model. The utility model is described more specifically in the following paragraphs by way of example with reference to the accompanying drawings. The advantages and features of this utility model will become clearer from the following description. It should be noted that the drawings are all in a very simplified form and use non-precise proportions, and are only used to facilitate and clarify the illustration of the embodiments of this utility model.

[0024] It should be noted that when a component is described as "fixed to" another component, it can be directly on the other component or may have a component in between. When a component is considered "connected to" another component, it can be directly connected to the other component or may have a component in between. When a component is considered "set on" another component, it can be directly set on the other component or may have a component in between. The terms "vertical," "horizontal," "left," "right," and similar expressions used in this document are for illustrative purposes only.

[0025] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains. The terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.

[0026] The present invention will be further described below with reference to the accompanying drawings and embodiments:

[0027] In the reverse-construction support system, the reverse-construction steel pipe column 2 serves as the main structural load-bearing component, while the traditional ring beam and top slab act as force-transferring components to transfer external loads. However, during the reverse-construction excavation process, an excavation opening is required, which prevents the force-transferring components from forming a closed structure, and the excavation machinery operation will affect the safety of the structure.

[0028] To address this situation, this utility model designs a temporary steel platform that facilitates the operation of excavators during top-down excavation construction, such as... Figures 1 to 2 As shown, it includes a steel pipe column cap 3, a base plate 4, a main supporting beam 5, and a secondary supporting beam 6.

[0029] The steel pipe column cap 3 is detachably fixed to the top of the reverse construction steel pipe column 2. The steel pipe column cap 3 includes a U-shaped slot 31 and a support plate 32 connected to the U-shaped slot 31.

[0030] The U-shaped slot 31 of the steel pipe column cap 3 is inserted upside down into the top of the reverse construction steel pipe column 2 and supported on the main structure top plate 1. Several support plates 32 are welded between the two U-shaped slots 31.

[0031] The spacing of the U-shaped slots 31 and the dimensions of the support plates 32 are customized according to the dimensions of the reverse construction steel pipe columns 2.

[0032] The support plate 32 can be tilted to form a stable triangular support structure, etc.

[0033] The pad 4 is fixedly installed on the top of the steel pipe column cap 3; the pad 4 and the top of the steel pipe column cap 3 are fixed by welding.

[0034] The main support beam 5 is fixedly connected to the top of the pad 4; the main support beam 5 and the pad 4 are connected by bolts.

[0035] The secondary support beam 6 is welded and fixed to the web area of ​​the main support beam 5. The main support beam 5 and the secondary support beam 6 together form a planar support frame.

[0036] Among them, the outriggers of the soil extraction equipment 7 are supported on the planar support frame formed by the main support beam 5 and the secondary support beam 6.

[0037] The elevation difference between the temporary construction platform's planar support frame and the main structure's top slab 1 can be mitigated by adding a ramp pad to allow the soil-boring equipment 7 to travel to the planar support frame. The bottom length of the ramp pad is 3.5 times the vertical distance between the main structure's top slab 1 and the planar support frame to ensure the safe movement of the soil-boring equipment 7.

[0038] Alternatively, vertical transportation equipment such as tower cranes can be used to lift the soil extraction equipment 7 to the designated location.

[0039] This utility model directly connects the steel pipe column cap 3 to the main load-bearing components, and forms a small temporary force transmission structure through the pad plate 4, the main support beam 5, and the secondary support beam 6. The legs of the soil extraction equipment 7 can be fixed on the planar support frame, which simplifies the soil extraction construction steps in the top-down construction of the cover-cut.

[0040] The present invention has been described above with reference to the accompanying drawings. Obviously, the specific implementation of the present invention is not limited to the above-described manner. Any improvements made using the inventive concept and technical solution of the present invention, or direct application to other situations without modification, are all within the protection scope of the present invention.

Claims

1. A temporary steel platform for use by a soil extractor in top-down construction, characterized in that, include: The column cap (3) of the steel pipe column is detachably fixed to the top of the reverse construction steel pipe column (2). The column cap (3) of the steel pipe column includes a U-shaped slot (31) and a support plate (32) connected to the U-shaped slot (31). The pad (4) is fixedly installed on the top of the column cap (3) of the steel pipe column; The main beam (5) is fixedly connected to the top of the pad (4); The secondary support beam (6) is welded and fixed to the web area of ​​the main support beam (5). The main support beam (5) and the secondary support beam (6) together form a planar support frame. The legs of the soil extraction equipment (7) are supported on the planar support frame formed by the main support beam (5) and the secondary support beam (6).

2. The temporary steel platform for excavator operation in the top-down construction method according to claim 1, characterized in that, The U-shaped slot (31) of the steel pipe column cap (3) is inserted upside down into the top of the reverse construction steel pipe column (2) and supported on the main structure top plate (1). Several support plates (32) are welded between the two U-shaped slots (31).

3. The temporary steel platform for excavator operation in the top-down construction method according to claim 1, characterized in that, The pad (4) is welded to the top of the steel pipe column cap (3).

4. The temporary steel platform for facilitating the operation of a soil extractor in the top-down construction method according to claim 1, characterized in that, The main beam (5) and the pad (4) are connected by bolts.

5. A temporary steel platform for excavator operation in top-down construction according to claim 1, characterized in that, It also includes a ramp pad, which overlaps between the top plate (1) of the main structure and the planar support frame, and is used to allow the soil removal equipment (7) to travel to the planar support frame.

6. A temporary steel platform for excavator operation in top-down construction according to claim 5, characterized in that, The length of the bottom surface of the slope pad is 3.5 times the vertical distance between the top plate of the main structure (1) and the planar support frame.

7. A temporary steel platform for excavator operation in top-down construction according to claim 1, characterized in that, The soil extraction equipment (7) is vertically hoisted and installed using tower crane equipment.