Well perimeter anti-settlement structure and municipal well

By installing a first support ring and a second support ring structure around the well, the problem of short service life of the well perimeter anti-settlement structure is solved, resulting in a smooth road surface, extended service life, and reduced maintenance costs.

CN224997643UActive Publication Date: 2026-11-20CCFEB CIVIL ENG
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202522436708.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-18
Publication Date
2026-11-20
Estimated Expiration
2035-11-18

AI Technical Summary

Technical Problem

Existing well perimeter anti-settlement structures have a short service life, and unloading plates are prone to bending or breaking during long-term use, leading to roadbed settlement and a shortened service life.

Method used

The system employs a first support ring and a second support ring structure. The first support ring is fixed to the top surface of the road structure layer around the manhole, while the second support ring separates the roadbed into upper and lower parts in the middle of the roadbed. By using the support rings to separate the road structure layer from the roadbed, the cumulative effects of settlement are reduced, and the service life is extended.

Benefits of technology

It effectively prevents the road structure layer from settling with the subgrade, delays pavement settlement defects, improves pavement service life and reduces maintenance costs, increases the service life of support rings, and reduces soil particle loss.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224997643U_ABST
    Figure CN224997643U_ABST
Patent Text Reader

Abstract

The utility model discloses a kind of well perimeter anti-settling structure and municipal well, belong to municipal engineering technical field, by first support ring and second support ring are fixedly installed on shaft, by first support ring directly supporting road structure layer, the settlement of the roadbed below first support ring does not cause the influence to the road structure layer above first support ring, simultaneously, second support ring is located in the middle position of roadbed, by second support ring, the roadbed around shaft is divided into two parts, so that the settlement of the roadbed above second support ring and the roadbed below second support ring does not influence each other, the settlement of the roadbed above second support ring can be reduced, the service life of first support ring is increased, the service life of overall structure is improved, and the soil particle loss caused by time and water migration can be reduced by second support ring, further slow down the settlement of the roadbed above second support ring, further increase the service life of overall structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of municipal engineering technology, specifically to a well perimeter anti-settlement structure and a municipal well. Background Technology

[0002] The backfill soil around the manhole is prone to carrying away tiny soil particles under the flow of soil water, forming pores and voids. Under the influence of various factors, it will settle, and the subgrade will face the problem of increasing settlement over time. The roadbed is a semi-rigid material, which is prone to deformation under the combined action of the settlement of the lower subgrade and the pressure on the upper part, and then settles, eventually leading to the overall settlement of the manhole area, forming a "belly button" defect in the road surface. As can be seen from the above description, the main reason for the settlement of the roadbed around the manhole is the settlement of the subgrade.

[0003] Chinese invention patent application CN117803018A discloses a prefabricated manhole perimeter reinforcement component for anti-settlement manhole covers, comprising a limiting cylinder, a manhole perimeter reinforcement component disposed on the lower side of the limiting cylinder, a cover plate disposed on the limiting cylinder, and an anti-settlement manhole cover disposed on the limiting cylinder. By adopting this component and combining it with the provided construction technology, the construction process of anti-settlement manhole covers can be optimized, the problem of unevenness between the wide-side anti-settlement manhole cover and the road surface can be solved, the impact of human factors on construction can be reduced, and the construction quality can be improved. Current technology involves installing unloading plates on the manhole. These unloading plates separate the roadbed around the manhole from the subgrade. When the subgrade below the unloading plate settles, the unloading plate can also support the roadbed above it, thus ensuring that the roadbed does not settle and extending its service life. However, the settlement of the subgrade will gradually accumulate from bottom to top, which means that the settlement is greater at the top of the subgrade. This causes the subgrade below the unloading plate to quickly lose contact with the unloading plate. At this time, the vehicle load and the structural load of the roadbed above the unloading plate will all act on the unloading plate. In the long-term use, this will cause the unloading plate to bend or break, resulting in a short service life of the current manhole anti-settlement structure, which in turn leads to a short service life of the roadbed.

[0004] Based on this, this utility model designs a well perimeter anti-settlement structure and a municipal well to solve the above problems. Utility Model Content

[0005] This utility model provides a well perimeter anti-settlement structure and a municipal well to solve the technical problem of short service life of existing well perimeter anti-settlement structures.

[0006] According to one aspect of the present invention, a manhole perimeter anti-settlement structure is provided for installation on a manhole casing to support the road structure layer around the manhole casing. The manhole perimeter anti-settlement structure includes a first support ring and a second support ring. Both the first and second support rings are fixedly installed on the manhole casing. The first support ring is installed at a position flush with the top surface of the roadbed and is used to support the road structure layer around the manhole casing. The second support ring is positioned in the middle of the roadbed and is used to divide the roadbed around the manhole casing into upper and lower parts.

[0007] As a further embodiment of this utility model, the well shaft includes multiple annular cylinders, which are stacked axially to form the well shaft. The first support ring and the second support ring are used to be set at the splicing position of two adjacent cylinders.

[0008] As a further embodiment of this utility model, the inner walls of the first support ring and the second support ring are both set as annular surfaces with diameters matching the outer diameter of the cylinder. A connecting ring is fixedly provided on the annular surfaces of the first support ring and the second support ring. The connecting ring is used to clamp between two adjacent cylinders. The bottom surface of the connecting ring in the first support ring is higher than the bottom surface of the first support ring, and the bottom surface of the connecting ring in the second support ring is higher than the bottom surface of the second support ring.

[0009] As a further embodiment of this utility model, the top surface of the connecting ring installed inside the first support ring is lower than the top surface of the first support ring, and the top surface of the connecting ring installed inside the second support ring is lower than the top surface of the second support ring.

[0010] As a further embodiment of this utility model, the inner diameter of the connecting ring is not less than the inner diameter of the cylinder.

[0011] As a further embodiment of this utility model, the first support ring and the second support ring are circular rings, and both the first support ring and the second support ring are used to be coaxially arranged relative to the wellbore.

[0012] As a further embodiment of this utility model, the top surface of the first support ring is provided with a geogrid, which is used to extend radially outward along the well cylinder to the upper surface of the roadbed and support the road structure layer.

[0013] As a further embodiment of this utility model, the top surface of the second support ring is provided with geotextile and crushed stone layer from bottom to top, and the geotextile and crushed stone layer are used to extend outward along the radial direction of the well cylinder into the roadbed.

[0014] As a further embodiment of this utility model, the radial length from the inner ring surface to the outer ring surface of the first support ring and the second support ring is not greater than 1000mm, the axial height of the first support ring and the second support ring is not less than 200mm, and the axial height of the connecting ring is not less than 100mm.

[0015] A municipal well includes a well casing, and the municipal well also includes the aforementioned perimeter anti-settlement structure, which is installed on the outer perimeter of the well casing.

[0016] This utility model has the following beneficial effects: This invention, by fixing a first support ring and a second support ring to the manhole, directly supports the road structure layer through the first support ring. This prevents the settlement of the roadbed below the first support ring from affecting the road structure layer above it, thus preventing the road structure layer around the manhole from settling along with the roadbed. This ensures the smoothness of the road surface around the manhole, delays the appearance of "navel" defects, extends the service life of the road surface, and reduces later maintenance costs. Simultaneously, the second support ring is positioned in the middle of the roadbed, dividing the roadbed around the manhole into upper and lower parts. This ensures that the settlement of the roadbed above and below the second support ring does not affect each other, reducing the settlement of the roadbed above the second support ring. This allows the roadbed above the second support ring to provide support for the first support ring for a longer period, increasing the service life of the first support ring and improving the overall structure's service life. Furthermore, the second support ring reduces soil particle loss caused by time and water migration, further slowing down the settlement of the roadbed above the second support ring and further increasing the service life of the overall structure.

[0017] In addition to the objectives, features, and advantages described above, this utility model has other objectives, features, and advantages. The present utility model will now be described in further detail with reference to the figures. Attached Figure Description

[0018] The accompanying drawings, which form part of this application, are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an undue limitation of the present invention. In the drawings: Figure 1 This is a schematic diagram of the overall structure of this utility model.

[0019] Legend: 1. First support ring; 2. Second support ring; 3. Subgrade; 4. Road structure layer; 5. Cylinder; 6. Connecting ring; 7. Geogrid; 8. Geotextile; 9. Crushed stone layer. Detailed Implementation

[0020] The embodiments of the present invention will be described in detail below with reference to the accompanying drawings. However, the present invention can be implemented in many different ways as defined and covered below.

[0021] Please see Figure 1This utility model provides a technical solution: a manhole perimeter anti-settlement structure, used to be installed on the manhole to support the road structure layer 4 around the manhole. The manhole perimeter anti-settlement structure includes a first support ring 1 and a second support ring 2. The first support ring 1 and the second support ring 2 are both used to be fixedly installed on the manhole. The first support ring 1 is used to be installed at a position flush with the top surface of the roadbed 3 and is used to support the road structure layer 4 around the manhole. The second support ring 2 is used to be located in the middle of the roadbed 3 and is used to divide the roadbed 3 around the manhole into upper and lower parts. This invention involves fixing a first support ring 1 and a second support ring 2 to the manhole cover. The top surface of the first support ring 1 is flush with the top surface of the roadbed 3, meaning the top surface of the first support ring 1 can support the bottom surface of the road structure layer 4. Because the first support ring 1 is fixedly connected to the manhole cover, it maintains its current height even when the roadbed 3 below it settles, providing stable support to the road structure layer 4 above it. This ensures that the road structure layer 4 above the first support ring 1 will not settle. By separating the road structure layer 4 above the first support ring 1 from the roadbed 3 below it, the settlement of the roadbed 3 below the first support ring 1 will not affect the road structure layer 4 above it. This ensures that the road structure layer 4 above the first support ring 1 remains at the same height as the manhole cover, delaying the appearance of a "navel" on the road surface. During the time of the "eye" defect, the second support ring 2 is located in the middle of the roadbed 3, which vertically divides the roadbed 3 around the well into upper and lower parts. The settlement of the roadbed 3 above and below the second support ring 2 does not affect each other. The settlement of the roadbed 3 below the second support ring 2 will not overlap with the settlement of the roadbed 3 above the second support ring 2. The settlement of the roadbed 3 located between the first support ring 1 and the second support ring 2 is slower. The roadbed 3 above the second support ring 2 takes longer to completely separate from the first support ring 1 due to the settlement, which can provide support for the first support ring 1 and the road structure layer 4 above it for a longer time, thus improving the service life of the overall structure. At the same time, the second support ring 2 can reduce the loss of soil particles caused by time and water migration, further slowing down the settlement of the roadbed 3 above the second support ring 2, and further increasing the service life of the overall structure. This invention, by fixing a first support ring 1 and a second support ring 2 onto the manhole, allows the first support ring 1 to directly support the road structure layer 4. This prevents settlement of the roadbed 3 below the first support ring 1 from affecting the road structure layer 4 above it, thus preventing the road structure layer 4 around the manhole from settling along with the roadbed 3. This ensures a smooth road surface around the manhole, delays the appearance of "belly button" defects, extends the service life of the road surface, and reduces later maintenance costs. Meanwhile, the second support ring 2 is positioned in the middle of the roadbed 3, further supporting the manhole... The roadbed 3 around the cylinder is divided into upper and lower parts, so that the settlement of the roadbed 3 above the second support ring 2 and the roadbed 3 below the second support ring 2 do not affect each other. This can reduce the settlement of the roadbed 3 above the second support ring 2, so that the roadbed 3 above the second support ring 2 can provide support for the first support ring 1 for a longer time, increase the service life of the first support ring 1, and improve the service life of the overall structure. At the same time, the second support ring 2 can reduce the loss of soil particles caused by time and water migration, further slow down the settlement of the roadbed 3 above the second support ring 2, and further increase the service life of the overall structure. Specifically, the well shaft includes multiple annular cylinders 5, which are stacked axially to form the well shaft. The first support ring 1 and the second support ring 2 are used to be set at the splicing position of two adjacent cylinders 5. like Figure 1 As shown, the well casing is formed by stacking multiple annular cylinders 5 vertically. When installing the cylinders 5, the first support ring 1 is placed on the top surface of the well casing, and then a new cylinder 5 is placed on the first support ring 1, thereby achieving the fixed installation of the first support ring 1 on the well casing. The second support ring 2 is installed between the cylinders 5 in the same way. It is more convenient to install the first support ring 1 and the second support ring 2 without damaging the well casing.

[0022] Specifically, the inner walls of the first support ring 1 and the second support ring 2 are both set as annular surfaces with a diameter matching the outer diameter of the cylinder 5. A connecting ring 6 is fixedly provided on the annular surfaces of the first support ring 1 and the second support ring 2. The connecting ring 6 is used to clamp between two adjacent cylinders 5. The bottom surface of the connecting ring 6 in the first support ring 1 is higher than the bottom surface of the first support ring 1, and the bottom surface of the connecting ring 6 in the second support ring 2 is higher than the bottom surface of the second support ring 2, so that the annular surface in the middle of the first support ring 1 and the second support ring 2 can abut against the outer surface of the cylinder 5. like Figure 1As shown, both the first support ring 1 and the second support ring 2 have annular surfaces with diameters matching the outer diameter of the cylinder 5. A connecting ring 6 is installed on the annular surface. When installing the first support ring 1 and the second support ring 2, the connecting ring 6 is positioned between two adjacent cylinders 5, thus forming a fixed connection between the first support ring 1 and the second support ring 2 and the cylinder 5. At the same time, the bottom surfaces of the first support ring 1 and the second support ring 2 are both lower than the connecting ring 6 installed at their centers, so that the annular surfaces between the first support ring 1 and the second support ring 2 can abut against the outer surface of the cylinder 5. The cylinder 5 can apply a horizontal supporting force to the annular surfaces between the first support ring 1 and the second support ring 2, thereby increasing the bending resistance of the first support ring 1 and the second support ring 2. It also plays a positioning role, so that the first support ring 1 and the second support ring 2 can always remain coaxial with the cylinder 5 below them during installation and subsequent use. Furthermore, the top surface of the connecting ring 6 installed inside the first support ring 1 is lower than the top surface of the first support ring 1, and the top surface of the connecting ring 6 installed inside the second support ring 2 is lower than the top surface of the second support ring 2. like Figure 1 As shown, the top surface of the first support ring 1 and the top surface of the second support ring 2 are both higher than the connecting ring 6 installed at their center, so that the annular surface in the middle of the first support ring 1 and the second support ring 2 can abut against the outer surface of the cylinder 5 above them, so that the first support ring 1 and the second support ring 2 can be positioned with the cylinder 5 above them, ensuring the stability of the first support ring 1 and the second support ring 2 during installation and subsequent use. Furthermore, the inner diameter of the connecting ring 6 is not less than the inner diameter of the cylinder 5 to prevent the connecting ring 6 from protruding from the inner surface of the well shaft and to ensure the flatness of the inner surface of the well shaft. Preferably, the inner diameter of the connecting ring 6 matches the inner diameter of the cylinder 5. When the connecting ring 6 is installed between the cylinders 5, the inner surface of the connecting ring 6 is adjacent to the inner surface of the cylinder 5, so that the final inner surface of the well shaft is flat and without gaps.

[0023] Specifically, the vertical projection of the first support ring 1 and the second support ring 2 can be any shape, as long as the first support ring 1 and the second support ring 2 protrude from the outer surface of the wellbore along the radial direction of the wellbore. like Figure 1 As shown, in some examples, the first support ring 1 and the second support ring 2 are circular rings, and the diameters of the first support ring 1 and the second support ring 2 are larger than the outer diameter of the manhole, so that the first support ring 1 and the second support ring 2 can extend beyond the outer surface of the manhole radially, so that the first support ring 1 can support the road structure layer 4 around the manhole, and the second support ring 2 can divide the roadbed 3 around the manhole into upper and lower parts. Preferably, the first support ring 1, the second support ring 2 and the manhole are coaxially arranged, so that the part of the first support ring 1 and the second support ring 2 protruding from the outer surface of the manhole is circular, forming a regular support area around the manhole. Specifically, the top surface of the first support ring 1 is provided with a geogrid 7, which is used to extend radially outward along the well to the upper surface of the roadbed 3 and support the road structure layer 4. like Figure 1 As shown, a geogrid 7 is provided on the top surface of the first support ring 1. The outer diameter of the geogrid 7 is larger than that of the first support ring 1. The top surface of the geogrid 7 is in contact with the road structure layer 4. Through the friction between the geogrid 7 and the road structure layer 4, the local load is dispersed and transferred to a larger area of ​​soil. The load of the road structure layer 4 above the first support ring 1 can be dispersed to the roadbed 3 around the first support ring 1, which can effectively reduce the load on the first support ring 1 and improve the service life of the first support ring 1. The geogrid 7 is embedded in the soil, and through the frictional interlocking and passive impedance between its mesh and soil particles, it effectively transfers and disperses the load stress applied to the soil to a larger area.

[0024] Specifically, the top surface of the second support ring 2 is provided with geotextile 8 and crushed stone layer 9 from bottom to top. The geotextile 8 and crushed stone layer 9 are used to extend outward along the radial direction of the well shaft into the roadbed 3. like Figure 1 As shown, the top surface of the second support ring 2 is provided with geotextile 8, and a crushed stone layer 9 is provided above the geotextile 8. The crushed stone layer 9 and the geotextile 8 work together to form a filter layer, which can effectively block soil particles from being lost with the water flow while ensuring drainage, and further reduce the settlement of the roadbed 3 above the second support ring 2.

[0025] Specifically, the first support ring 1 and the second support ring 2 are prefabricated and can be directly placed in the designated position during construction without affecting the normal progress of construction.

[0026] Specifically, the radial length from the inner ring surface to the outer ring surface of the first support ring 1 and the second support ring 2 is not greater than 1000mm, the axial height of the first support ring 1 and the second support ring 2 is not less than 200mm, and the axial height of the connecting ring 6 is not less than 100mm. If the diameter of the first support ring 1 and the second support ring 2 is too large, the load during use will be too high. In order to ensure the stability of the first support ring 1 and the second support ring 2, the radial length from the inner ring surface to the outer ring surface of the first support ring 1 and the second support ring 2 shall not be greater than 1000mm. At the same time, the axial height of the first support ring 1 and the second support ring 2 shall not be less than 200mm, so as to ensure that the first support ring 1 and the second support ring 2 have a certain load-bearing capacity. The axial height of the connecting ring 6 is not less than 100mm. The loads on the first support ring 1 and the second support ring 2 will be transmitted to the wellbore through the connecting ring 6. Therefore, the axial height of the connecting ring 6 is not less than 100mm to ensure that the connecting ring 6 can stably transmit the load. A municipal well includes a well casing and a surrounding anti-settlement structure. The surrounding anti-settlement structure is installed on the outer periphery of the well casing and can effectively delay the time when the road surface develops "belly button" defects and improve the service life of the road surface.

[0027] During the work, the first support ring 1 and the second support ring 2 are prefabricated first, and then the construction of the roadbed 3 begins. During the construction of the roadbed 3, the manhole is slowly increased in height along with the roadbed 3. When the roadbed 3 reaches the installation height of the second support ring 2, the installation area of ​​the second support ring 2 is excavated downward around the manhole. Then the second support ring 2 is installed. After the second support ring 2 is installed, geotextile 8 and crushed stone layer 9 are laid on the second support ring 2. After the layout is completed, backfilling and compaction of the roadbed 3 continues. After the roadbed 3 is backfilled and compacted to the elevation of the roadbed 3, the installation area of ​​the first support ring 1 is excavated in reverse around the manhole. Then the first support ring 1 is installed. After the first support ring 1 is installed, geogrid 7 is laid on the first support ring 1. After the roadbed 3 is accepted, the road structure layer 4 is constructed.

[0028] The above are merely preferred embodiments of this utility model and are not intended to limit the scope of this utility model. Various modifications and variations can be made to this utility model by those skilled in the art. Any modifications, equivalent substitutions, or improvements made within the spirit and principles of this utility model should be included within the protection scope of this utility model.

[0029] Finally, it should be noted that in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes the element.

Claims

1. A well perimeter anti-settlement structure, used for installation on the well casing to support the road structure layer (4) around the well casing, characterized in that: The well perimeter anti-settlement structure includes a first support ring (1) and a second support ring (2). Both the first support ring (1) and the second support ring (2) are used to be fixedly installed on the well. The first support ring (1) is used to be installed at a position flush with the top surface of the roadbed (3) and to support the road structure layer (4) around the well. The second support ring (2) is used to be located in the middle of the roadbed (3) and to divide the roadbed (3) around the well into upper and lower parts.

2. The well perimeter anti-settlement structure according to claim 1, characterized in that: The well shaft includes multiple annular cylinders (5), which are stacked axially to form the well shaft. The first support ring (1) and the second support ring (2) are used to be set at the splicing position of two adjacent cylinders (5).

3. The well perimeter anti-settlement structure according to claim 2, characterized in that: The inner walls of the first support ring (1) and the second support ring (2) are both set as annular surfaces with a diameter matching the outer diameter of the cylinder (5). A connecting ring (6) is fixedly provided on the annular surfaces of the first support ring (1) and the second support ring (2). The connecting ring (6) is used to clamp between two adjacent cylinders (5). The bottom surface of the connecting ring (6) in the first support ring (1) is higher than the bottom surface of the first support ring (1), and the bottom surface of the connecting ring (6) in the second support ring (2) is higher than the bottom surface of the second support ring (2).

4. The well perimeter anti-settlement structure according to claim 3, characterized in that: The top surface of the connecting ring (6) installed inside the first support ring (1) is lower than the top surface of the first support ring (1), and the top surface of the connecting ring (6) installed inside the second support ring (2) is lower than the top surface of the second support ring (2).

5. The well perimeter anti-settlement structure according to claim 3, characterized in that: The inner diameter of the connecting ring (6) is not less than the inner diameter of the cylinder (5).

6. The well perimeter anti-settlement structure according to claim 1, characterized in that: The first support ring (1) and the second support ring (2) are circular rings, and both the first support ring (1) and the second support ring (2) are used to be coaxially arranged relative to the wellbore.

7. The well perimeter anti-settlement structure according to claim 1, characterized in that: The top surface of the first support ring (1) is provided with a geogrid (7), which is used to extend radially outward along the well to the upper surface of the roadbed (3) and support the road structure layer (4).

8. The well perimeter anti-settlement structure according to claim 1, characterized in that: The top surface of the second support ring (2) is provided with geotextile (8) and crushed stone layer (9) from bottom to top. The geotextile (8) and crushed stone layer (9) are used to extend outward along the radial direction of the well cylinder into the roadbed (3).

9. A well perimeter anti-settlement structure according to claim 3, characterized in that: The radial length from the inner ring surface to the outer ring surface of the first support ring (1) and the second support ring (2) is not greater than 1000mm, the axial height of the first support ring (1) and the second support ring (2) is not less than 200mm, and the axial height of the connecting ring (6) is not less than 100mm.

10. A municipal well, comprising a well shaft, characterized in that: The municipal well also includes the well perimeter anti-settlement structure as described in any one of claims 1-9, wherein the well perimeter anti-settlement structure is installed on the outer perimeter of the well shaft.