A connecting structure of a newly-added structure of a residential elevator and an original structure
By using a combination of connecting angle steel, anchor bolts, horizontal angle steel, vertical angle steel, rubber pads, and cement filling layers, the problem of settlement misalignment in the connection between the new structure and the original structure when adding elevators to existing residential buildings is solved, achieving safe passage and cost reduction.
Patent Information
- Application Number
- CN202522764622.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-26
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2035-12-26
AI Technical Summary
When adding elevators to existing residential buildings, the new structure is connected to the original structure. Differential settlement can cause misalignment, affecting traffic safety and increasing construction costs.
The new structure employs a combination of connecting angle steel, anchor bolts, horizontal angle steel, vertical angle steel, rubber pads, matching connectors, and cement filling layers. Through the movable connection of the rubber pads and the constraint of the connecting steel plates, the free settlement and translational torsion of the new structure are restricted, thereby reducing construction costs.
It effectively prevents misalignment between the new structure and the original structure due to settlement differences, improves traffic safety, significantly reduces construction costs, and simplifies design calculations.
Smart Images

Figure CN224997764U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of building construction engineering technology, and in particular relates to structural technology for elevator installation in residential buildings. Background Technology
[0002] With the arrival of an aging population, many older residential buildings lack elevators, making it difficult for the elderly to go up and down stairs. To address this issue, my country is actively promoting the installation of elevators in existing residential buildings.
[0003] The new structures added to existing residential buildings for elevator installation, whether made of concrete or steel, have a large height-to-width ratio and relatively weak overall structural rigidity. To meet the design standards' requirements regarding displacement angle, displacement ratio, and torsion, the structural cross-section must be enlarged and the amount of material used must be increased. This significantly increases construction costs, hinders the progress of elevator installation in residential buildings, and restricts the implementation of this beneficial project.
[0004] Generally, the total mass of elevator installation projects in residential buildings is less than the total mass of the existing building, usually not exceeding 5%. According to relevant engineering construction standards, in this case, if the new structure is integrated with the original structure, the impact of horizontal seismic and wind loads on the original structure can be disregarded. Furthermore, since the lateral stiffness of the new structure is much smaller than that of the original structure, there is no possibility that the new structure will share the horizontal seismic and wind loads. Therefore, the horizontal seismic and wind loads of the new structure can be transferred to the original structure, and the new structure no longer needs to bear these loads. This simplifies the calculation and design of the new structure, significantly reduces the cross-sectional dimensions and material usage of the new structural components, and significantly lowers construction costs, thus facilitating the implementation of elevator installation projects in existing residential buildings.
[0005] However, if the new structure is connected to the original structure as a single unit, the settlement of the new structure will create a differential settlement between them, leading to engineering quality problems such as damage, cracking, and air and water leaks at the connection. To solve this problem, the connection between the new and original structures must allow the new structure to settle freely, while its horizontal translation and torsion are constrained by the original structure. Currently, there are various connection methods, including using bolts with elongated round holes. However, the presence of a differential settlement will cause misalignment between the new and original structures, making it easy for pedestrians to trip and affecting traffic safety.
[0006] There is currently no good technical solution to these problems, so a new technical solution is urgently needed. Utility Model Content
[0007] The technical problem to be solved by this utility model is to provide a connection scheme between the new structure and the original structure of a residential elevator installation, which solves the problems in the connection between the new structure and the original structure of a residential elevator installation. It can satisfy the constraint and restriction of the horizontal translation and torsion of the new structure on the original structure, while allowing the new structure to settle freely relative to the original structure, and also prevent misalignment after the new structure has a settlement difference with the original structure. At the same time, it can ensure the safety of the new structure and the original structure, and significantly reduce the construction cost.
[0008] A connection structure between a new structure and the original structure for adding an elevator to a residential building is disclosed. This structure connects the new structure to the original structure, the original stair landing slab, and a passageway opening. The original structure is the existing structure of the residential building to which the elevator needs to be added. The original stair landing slab is the floor staircase slab or stair landing slab of the existing residential building to which the elevator needs to be added. The passageway opening is an opening created in the existing residential building to which the elevator needs to be added, allowing passage between the original structure and the new structure. The structure is characterized by including the new structure, connecting angle steel, anchor bolts, horizontal angle steel, vertical angle steel, rubber pads, mating connectors, connecting steel plates, and a cement filling layer.
[0009] The number of connecting angle steels is two. The bottom surfaces of the two connecting angle steels are connected to the original stair platform board through the anchor bolts and structural adhesive. The sides of the connecting angle steels are connected to the sides of the passage opening through structural adhesive.
[0010] The transverse angle steel is welded to the connecting angle steel;
[0011] The horizontal angle steel is welded to the connecting steel plate, and vertical angle steel is welded to both ends of the horizontal angle steel. The inner wall of the vertical angle steel is provided with a rubber pad; and a cement filling layer is provided between the horizontal angle steel and the outer wall of the original structure.
[0012] Rubber pads are provided on the inner walls of both legs of the vertical angle steel;
[0013] The mating connector is installed on the new structure and is mated and connected to the connecting steel plate.
[0014] The vertical angle steel is connected to the rubber pad by adhesive bonding.
[0015] The outer surface of the rubber pad is in close contact with the newly added structure.
[0016] The mating connector is a steel structural component installed on the newly added structure.
[0017] The connecting component is a pre-embedded steel component installed in the concrete structure of the newly added structure.
[0018] The connecting steel plate is a steel plate that connects the transverse angle steel and the mating connector, and the width of the connecting steel plate is greater than 200mm.
[0019] The vertical angle steel is perpendicular to the horizontal angle steel. The outer wall of one leg of the vertical angle steel is welded to the end of the horizontal angle steel, and the outer wall of the other leg is connected to the cement filling layer.
[0020] The connecting angle steel is welded to the connecting steel plate.
[0021] The cement filling layer uses cement-based materials, including cement-based grouting material, cement-based injection grout, cement mortar and concrete; the cement filling layer fills the gap between the transverse angle steel and the original structure, and is fixedly connected to the transverse angle steel and the original structure.
[0022] The mating connector is a steel connector, which is fixedly installed on the new structure and is mated with the connecting steel plate.
[0023] Through the above design scheme, this utility model can bring the following beneficial effects: by constraining the connecting steel plate, the translational displacement and torsion of the new structure away from the original structure are restricted; by the movable connection between the rubber pad on the outer side of the vertical angle steel and the new structure, the translational displacement of the new structure close to the original structure is restricted, and the translational displacement of horizontal misalignment between the new structure and the original structure is restricted; by the movable connection between the rubber pad on the outer side of the vertical angle steel and the original structure, the new structure can settle freely relative to the original structure; when the settlement difference is small, because the width of the connecting steel plate is large and the vertical rotation angle of the connecting steel plate is small, the connecting steel plate will not generate internal forces that would damage the connecting structure, the new structure, and the original structure;
[0024] The buffering effect of the rubber pads on the outside of the vertical angle steel can prevent destructive collisions between the new structure and the original structure due to external forces; through the connection of the connecting parts, the translation and torsion of the new structure are constrained by the original structure, and the horizontal force borne by the new structure is transferred to the original structure. The design of the new structure can ignore the influence of horizontal forces, which can significantly reduce the construction cost of the new structure; the connecting steel plate also serves as a walkway slab for the connecting section. Attached Figure Description
[0025] The present invention will be further described below with reference to the accompanying drawings and specific embodiments:
[0026] Figure 1 This is a plan view of the connection between the newly added structure and the original structure in this utility model;
[0027] Figure 2 This is a partial enlarged view (A) of the connection between the new structure and the original structure in this invention.
[0028] Figure 3 This is a schematic diagram of the AA section of the plane connecting the new structure and the original structure in this invention.
[0029] Figure 4 This is a BB cross-sectional view of the enlarged portion of the plane at the connection point between the newly added structure and the original structure.
[0030] In the diagram, 101-original structure, 102-original stair platform slab, 103-passage opening, 201-new structure, 202-connecting angle steel, 203-anchor bolt, 204-horizontal angle steel, 205-vertical angle steel, 206-rubber pad, 207-fitting connector, 208-connecting steel plate, 209-cement filling layer. Detailed Implementation
[0031] The present application is explained with reference to the accompanying drawings: A connection structure between a new structure and the original structure for adding an elevator to a residential building is used to connect the new structure 201 with the original structure 101, the original stair platform slab 102, and the passage opening 103; the original structure 101 is the structure of the existing residential building for which an elevator needs to be added; the original stair platform slab 102 is the floor stair structure slab or stair landing structure slab of the existing residential building for which an elevator needs to be added; the passage opening 103 is an opening made in the existing residential building for which an elevator needs to be added, for passage between the original structure 101 and the new structure 201; its features include: a new structure 201, connecting angle steel 202, anchor bolts 203, horizontal angle steel 204, vertical angle steel 205, rubber pads 206, mating connectors 207, connecting steel plates 208, and a cement filling layer 209;
[0032] The number of connecting angle steels 202 is two. The bottom surfaces of the two connecting angle steels 202 are connected to the original stair platform plate 102 through the anchor bolts 203 and structural adhesive. The sides of the connecting angle steels 202 are connected to the sides of the passage opening 103 through structural adhesive.
[0033] The transverse angle steel 204 is welded to the connecting angle steel 202;
[0034] The transverse angle steel 204 is welded to the connecting steel plate 208. Vertical angle steels 205 are welded to both ends of the transverse angle steel 204. Rubber pads 206 are provided on the inner wall of the vertical angle steel 205. A cement filling layer 209 is provided between the transverse angle steel 204 and the outer wall of the original structure 101.
[0035] Rubber pads 206 are provided on the inner walls of both legs of the vertical angle steel 205;
[0036] The mating connector 207 is provided on the new structure 201, and the mating connector 207 is mated and connected with the connecting steel plate 208.
[0037] The vertical angle steel 205 and the rubber pad 206 are connected by adhesive bonding.
[0038] The outer surface of the rubber pad 206 is in close contact with the new structure 201; and the contact is sliding, which allows the new structure 201 to sink freely relative to the original structure 101.
[0039] The mating connector 207 is a steel structural component installed on the newly added structure 201.
[0040] The mating connector 207 is a pre-embedded steel component installed in the concrete structure of the newly added structure 201.
[0041] The connecting steel plate 208 is a steel plate that connects the transverse angle steel 204 and the mating connector 207, and the width of the connecting steel plate 208 is greater than 200mm.
[0042] The vertical angle steel 205 is perpendicular to the horizontal angle steel 204. The outer wall of one leg of the vertical angle steel 205 is welded to the end of the horizontal angle steel 204, and the outer wall of the other leg is connected to the cement filling layer 209.
[0043] The connecting angle steel 202 is welded to the connecting steel plate 208.
[0044] The cement filling layer 209 is made of cement-based materials, including cement-based grouting material, cement-based injection grout, cement mortar and concrete; the cement filling layer 209 fills the gap between the transverse angle steel 204 and the original structure 101, and is fixedly connected to the transverse angle steel 204 and the original structure 101.
[0045] The mating connector 207 is a steel connector, which is fixedly installed on the new structure 201. The mating connector 207 is mated and connected with the connecting steel plate 208.
[0046] The connecting steel plate 208 also serves as a walkway for the connecting section.
[0047] The outer side of the rubber pad 206 is in close contact with the new structure 201 and is vertically slidable.
[0048] The vertical angle steel 205 is perpendicular to the horizontal angle steel 204. The outer wall of one leg of the vertical angle steel 205 is welded to the end of the horizontal angle steel 204, and the outer wall of the other leg is connected to the cement filling layer 209.
[0049] like Figure 1As shown, the connecting angle steel 202 is formed by two sections of angle steel in an L shape. The sides of the long and short sections are connected to the sides of the passage opening 103 and the inner side of the original structure 101 by structural adhesive. The bottom surfaces of the long and short sections are connected to the original stair platform 102 by the anchor bolts 203 and structural adhesive. Each connecting angle steel 202 is equipped with two or more anchor bolts 203.
[0050] The shape of the mating connector 207 matches that of the connecting steel plate 208, which is used to connect the new structure 201 with the connecting steel plate 208, ensuring the unobstructed passage of the ground between the new structure 201 and the original structure 101.
[0051] A method for implementing a connection structure between a new elevator installation in a residential building and the original structure includes the following steps, which are performed sequentially:
[0052] Step 1: Construction of New Structures
[0053] The new structure 201 is constructed using traditional methods. The structural components on both sides of the new structure 201 are close to the original structure 101. A matching connector 207 for welding connection with the connecting steel plate 208 is set on the side of the new structure 201 near the original structure 101.
[0054] Step 2: Constructing the new connection structure
[0055] At the corresponding position of the connecting angle steel 202, remove the mortar plaster layer of the original stair platform 102, install anchor bolts 203, apply structural adhesive to the contact surface between the connecting angle steel 202 and the original structure 101, and fasten the connecting angle steel 202 to the work position through the anchor bolts 203.
[0056] The vertical angle steel 205 is welded to the end of the horizontal angle steel 204, and the rubber pad 206 is pasted on the inner side of the two legs of the vertical angle steel 205. The horizontal angle steel 204 assembly with the vertical angle steel 205 and the rubber pad 206 is placed in the work position. The outer side of the rubber pad 206 is in close contact with the inner side and end of the original structure 101, and there is a vertical sliding contact between the rubber pad 206 and the original structure 101.
[0057] Weld the transverse angle steel 204 to the connecting angle steel 202, fill the gap between the transverse angle steel 204 and the original structure 101 with cement filling layer 209 and smooth the surface.
[0058] The connecting steel plate 208 is placed in the work station and welded to the transverse angle steel 204 and the mating connector 207 respectively. The connecting steel plate 208 also serves as a walkway plate. The connection between the new structure for adding an elevator to the residential building and the original structure is completed.
[0059] The above description is merely a specific embodiment of this utility model, but the protection scope of this utility model is not limited thereto. Any modifications, equivalent substitutions, and improvements made by those skilled in the art within the scope of the technology disclosed in this utility model, and within the spirit and principles of this utility model, should be included within the protection scope of this utility model. Furthermore, all content not described in detail in this specification belongs to the prior art known to those skilled in the art.
Claims
1. A connection structure between a new structure and an existing structure for adding an elevator to a residential building, used to connect the new structure (201) with the existing structure (101), the existing stair landing slab (102), and a passageway opening (103); wherein the existing structure (101) is the structure of the existing residential building for which an elevator needs to be added; the existing stair landing slab (102) is the floor stair structure slab or stair landing structure slab of the existing residential building for which an elevator needs to be added; and the passageway opening (103) is an opening made in the existing residential building for which an elevator needs to be added, for passage between the existing structure (101) and the new structure (201); characterized in that: This includes the new structure (201), connecting angle steel (202), anchor bolts (203), horizontal angle steel (204), vertical angle steel (205), rubber pads (206), mating connectors (207), connecting steel plates (208), and cement filling layer (209); The number of connecting angle steels (202) is two. The bottom surfaces of the two connecting angle steels (202) are connected to the original stair platform plate (102) through the anchor bolts (203) and structural adhesive. The side surfaces of the connecting angle steels (202) are connected to the side surfaces of the passage opening (103) through structural adhesive. The transverse angle steel (204) is welded to the connecting angle steel (202); The transverse angle steel (204) is welded to the connecting steel plate (208), and vertical angle steel (205) is welded to both ends of the transverse angle steel (204). The inner wall of the vertical angle steel (205) is provided with a rubber pad (206); and a cement filling layer (209) is provided between the transverse angle steel (204) and the outer wall of the original structure (101). The inner walls of both legs of the vertical angle steel (205) are provided with rubber pads (206); The mating connector (207) is installed on the new structure (201), and the mating connector (207) is mated and connected with the connecting steel plate (208).
2. The connection structure between the new structure and the original structure for adding an elevator to a residential building, as described in claim 1, is characterized in that: The vertical angle steel (205) and the rubber pad (206) are connected by adhesive bonding.
3. The connection structure between the new structure and the original structure for adding an elevator to a residential building, as described in claim 1, is characterized in that: The outer surface of the rubber pad (206) is in close contact with the new structure (201).
4. The connection structure between the new structure and the original structure for adding an elevator to a residential building, as described in claim 1, is characterized in that: The mating connector (207) is a steel structural component installed on the new structure (201).
5. The connection structure between the new structure and the original structure for adding an elevator to a residential building according to claim 1, characterized in that: The mating connector (207) is a pre-embedded steel component installed in the concrete structure of the newly added structure (201).
6. The connection structure between the new structure and the original structure for adding an elevator to a residential building according to claim 1, characterized in that: The connecting steel plate (208) is a steel plate that connects the transverse angle steel (204) and the mating connector (207), and the width of the connecting steel plate (208) is greater than 200mm.
7. The connection structure between the new structure and the original structure for adding an elevator to a residential building according to claim 1, characterized in that: The vertical angle steel (205) is perpendicular to the horizontal angle steel (204). The outer wall of one leg of the vertical angle steel (205) is welded to the end of the horizontal angle steel (204), and the outer wall of the other leg is connected to the cement filling layer (209).
8. The connection structure between the new structure and the original structure for adding an elevator to a residential building according to claim 1, characterized in that: The connecting angle steel (202) is welded to the connecting steel plate (208).
9. The connection structure between the new structure and the original structure for adding an elevator to a residential building according to claim 1, characterized in that: The cement filling layer (209) is made of cement-based materials, including cement-based grouting material, cement-based injection grout, cement mortar and concrete; the cement filling layer (209) fills the gap between the transverse angle steel (204) and the original structure (101), and it is fixedly connected to the transverse angle steel (204) and the original structure (101).
10. The connection structure between the new structure and the original structure for adding an elevator to a residential building according to claim 1, characterized in that: The mating connector (207) is a steel connector, which is fixedly installed on the new structure (201). The mating connector (207) is mated and connected with the connecting steel plate (208).