Unit curtain wall fold line crossbeam connecting structure and fold line unit curtain wall
By using a connection method that combines precast steel castings with limiting slides, the problem of complex construction of the folded beam connection in unitized curtain walls is solved, achieving convenient disassembly and assembly and high-precision connection, thus improving construction quality and appearance.
Patent Information
- Application Number
- CN202522641515.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-12
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2035-12-12
AI Technical Summary
The existing construction methods for connecting the folded beams of unitized curtain walls are redundant and have poor control over processing quality. The traditional cutting and welding method is inconvenient to operate and the connection is unstable.
Precast steel castings are used to connect the zigzag beams, and the beams are precisely positioned by limiting slides and limiting grooves. Combined with bolts, nuts and machine screws, the precast steel castings are firmly connected to the beams, avoiding on-site cutting and welding.
It improves the ease of assembly and disassembly of the zigzag beam connection and the connection accuracy, ensures excellent appearance, simplifies construction operations, and enhances construction quality and reliability.
Smart Images

Figure CN224997844U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building curtain wall technology, and in particular to a unitized curtain wall zigzag beam connection structure and a zigzag unitized curtain wall. Background Technology
[0002] With the innovation of architectural design concepts, curtain wall shapes have shown a diversified development trend. Among them, the zigzag unitized curtain wall has been widely used because it can meet the three-dimensional shape requirements of building facades. The current construction method for connecting the horizontal beams at the zigzag position of unitized curtain walls in the industry generally adopts a "cutting and welding" process. The specific operation is as follows: according to the included angle of the zigzag unit panels, the metal insert is cut to fit the connection angle of the adjacent unit panels; then the cut insert is placed in the connection cavity of the adjacent unit panels, and the insert is fixed to the frame of the unit panel by arc welding or gas shielded welding to complete the connection. This process is redundant and has poor quality control. Utility Model Content
[0003] The technical problem this utility model aims to solve is to provide a unitized curtain wall with a zigzag horizontal beam connection structure and a zigzag unitized curtain wall. Two horizontal beams spliced at the zigzag joint are connected by precast steel castings, and the precast steel castings and horizontal beams are fastened with connectors. This method facilitates construction, ensures reliable assembly and disassembly, and results in a superior aesthetic appearance.
[0004] To solve the above-mentioned technical problems, the technical solution of this invention is as follows: This utility model embodiment proposes a unitized curtain wall zigzag beam connection structure, including: The first crossbeam has a first receiving cavity at one end that opens along its length. The second crossbeam has a second receiving cavity that opens along its length at one end. One end of the second crossbeam is connected to one end of the first crossbeam at a preset angle. The inner sidewalls of the first receiving cavity and the second receiving cavity are respectively provided with limiting slides that extend along the length. A precast steel casting has a bent structure. The bending angle of the precast steel casting matches the included angle between the first crossbeam and the second crossbeam. The first bent section of the precast steel casting is housed in the first receiving cavity, and the second bent section of the precast steel casting is housed in the second receiving cavity. The sides of the first bent section and the second bent section are respectively provided with limiting grooves that slide in cooperation with the corresponding limiting slides. Multiple connectors are provided, which respectively connect the first crossbeam to the first bent section of the precast steel casting and the second crossbeam to the second bent section of the precast steel casting.
[0005] Optionally, the top and bottom walls of the first and second accommodating cavities in the thickness direction are provided with a plurality of first through holes, and a plurality of corresponding second through holes are provided through the thickness direction of the precast steel casting. Multiple connectors, including: The bolt passes through a first through hole in the top and bottom walls of the first receiving cavity, and a second through hole corresponding to the first bent section of the precast steel casting; or, passes through a first through hole in the top and bottom walls of the second receiving cavity, and a second through hole corresponding to the second bent section of the precast steel casting. A nut is fastened to the end of the bolt that penetrates the bottom wall of the first or second receiving cavity.
[0006] Optionally, the first receiving cavity and the second receiving cavity have multiple first threaded holes on their two sidewalls in the width direction, and the precast steel casting has multiple corresponding second threaded holes on its two sidewalls in the width direction. Multiple connectors, including: The machine screw connects the side wall of the first receiving cavity to the corresponding side wall of the first bent section of the precast steel casting through a first threaded hole and a second threaded hole, or connects the side wall of the second receiving cavity to the corresponding side wall of the second bent section of the precast steel casting through a first threaded hole and a second threaded hole.
[0007] Optionally, the limiting slide is in multiple sets, each set of limiting slide includes a first limiting slide and a second limiting slide, the first limiting slide and the second limiting slide are respectively disposed on the top wall and / or bottom wall of the inner side wall of the first receiving cavity and the second receiving cavity.
[0008] Optionally, the unitized curtain wall zigzag beam connection structure further includes: The top wall of the U-shaped reinforcement is connected to the first crossbeam and the second crossbeam respectively.
[0009] Optionally, when the connecting member includes bolts and nuts, the top wall of the U-shaped reinforcing member is respectively provided with a third through hole corresponding to the first through hole of the first receiving cavity and the second through hole of the first bent section of the precast steel casting, and a third through hole corresponding to the first through hole of the second receiving cavity and the second through hole of the second bent section of the precast steel casting; The bolt passes through the first through hole in the top and bottom walls of the first receiving cavity, the second through hole in the first bent section of the precast steel casting, and the corresponding third through hole in the top wall of the U-shaped reinforcement; or, it passes through the first through hole in the top and bottom walls of the second receiving cavity, the second through hole in the second bent section of the precast steel casting, and the corresponding third through hole in the top wall of the U-shaped reinforcement. A nut is fastened to the end of the bolt that penetrates the top wall of the U-shaped reinforcement.
[0010] Optionally, the precast steel casting includes: Middle section; The first end and the second end are respectively connected to both sides of the middle part along the width direction by a connecting part; Wherein, a limiting groove is formed between the connecting part and the middle part and the first end part and / or between the connecting part and the middle part and the second end part.
[0011] Optionally, the sides of the middle portion, the first end portion, and the second end portion are fitted to the corresponding sides of the first receiving cavity and the second receiving cavity.
[0012] Optionally, the first crossbeam and the second crossbeam are provided with upward openings and interconnected cavities; water guiding components are provided in the cavities.
[0013] This utility model embodiment also proposes a polygonal unit curtain wall, including the polygonal horizontal beam connection structure of the unit curtain wall as described above.
[0014] The above-described solution of this utility model has at least the following beneficial effects: The above-mentioned solution of this utility model embeds precast steel castings into the first receiving cavity of the first crossbeam and the second receiving cavity of the second crossbeam respectively, and accurately positions them through limiting slides and limiting grooves. The precast steel castings are further connected to the first receiving cavity and the precast steel castings are connected to the second receiving cavity respectively through connectors, avoiding the traditional on-site cutting and welding connection method, making the zigzag crossbeam connection structure easy to assemble and disassemble, convenient to operate, improving the connection accuracy of the zigzag crossbeam connection structure, and resulting in a better appearance. Attached Figure Description
[0015] Figure 1 This is a structural diagram of the assembled unitized curtain wall folded beam connection structure provided in this embodiment of the utility model; Figure 2 yes Figure 1 Side view of the central broken-line beam connection structure; Figure 3 yes Figure 1 Schematic diagram of the structure of precast steel castings; Figure 4 This is a schematic diagram of the cross-section of a precast steel casting; Figure 5 This is a schematic diagram of the first bent section of a precast steel casting; Figure 6 It is a 3D view of the assembled zigzag beam connection structure; Figure 7 This is a schematic diagram of one side of the assembled zigzag beam connection structure; Figure 8 This is a schematic diagram of the U-shaped reinforcing member in the installation of the zigzag beam connection structure in this utility model embodiment; Figure 9 This is a top view of a zigzag unit curtain wall after the installation of the zigzag beam connection structure provided in this embodiment of the utility model.
[0016] Explanation of reference numerals in the attached figures: 10. Crossbeam connection structure; 1. First crossbeam; 11. First receiving cavity; 2. Second crossbeam; 21. Second receiving cavity; 211. First through hole; 212. First threaded hole; 30. Cavity; 40. Water guide; 200. Limiting slide; 3. Precast steel casting; 3a. First bending section; 3b. Second bending section; 31. Middle part; 32. Connecting part; 33. First end; 34. Second end; 35. Second through hole; 36. Second threaded hole; 300. Limiting groove; 4. Connecting part; 41. Bolt; 42. Nut; 43. Machine screw; 5. U-shaped reinforcing part; 51. Top wall; 52. Elastic pad; 53. Third through hole; 6. Core sleeve; 7. Column; 71. Central column. Detailed Implementation
[0017] Exemplary embodiments of the present disclosure will now be described in more detail with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be implemented in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the disclosure to those skilled in the art.
[0018] like Figures 1 to 8 As shown, an embodiment of this utility model proposes a unitized curtain wall folded-line beam connection structure, including: The first crossbeam 1 has a first receiving cavity 11 that opens along its length at one end; The second crossbeam 2 has a second receiving cavity 21 with an opening along its length at one end. One end of the second crossbeam 2 is connected to one end of the first crossbeam 1 at a preset angle. The inner walls of the first receiving cavity 11 and the second receiving cavity 21 are respectively provided with limiting slides 200 extending along the length. The precast steel casting 3 has a bent structure. The bending angle of the precast steel casting 3 matches the included angle of the first crossbeam 1 and the second crossbeam 2. The first bent section 3a of the precast steel casting 3 is housed in the first receiving cavity 11, and the second bent section 3b of the precast steel casting 3 is housed in the second receiving cavity 21. The sides of the first bent section 3a and the second bent section 3b are respectively provided with limiting grooves 300 that slide in cooperation with the corresponding limiting slides 200. Multiple connectors 4 are provided, which respectively connect the first crossbeam 1 to the first bent section 3a of the precast steel casting 3 and the second crossbeam 2 to the second bent section 3b of the precast steel casting 3.
[0019] In this embodiment of the utility model, the fold line position of the fold line type unit curtain wall horizontal beam is formed by the first horizontal beam 1 and the second horizontal beam 2, which are joined together according to the preset fold line angle of the curtain wall. One end of the first horizontal beam 1 and the second horizontal beam 2 are respectively inclined at a preset angle. After one end of the first horizontal beam 1 and one end of the second horizontal beam 2 are connected by a prefabricated steel casting 3, the included angle formed is the preset fold line angle. The first receiving cavity 11 and the second receiving cavity 2 are connected. The prefabricated steel casting 3 is precisely injection molded into a bent structure according to the preset fold line angle of the horizontal beam, forming a prefabricated standardized steel casting. The bending angle of the prefabricated steel casting 3 matches the included angle of the first horizontal beam 1 and the second horizontal beam 2. The shape of the prefabricated steel casting 3 also matches the first receiving cavity 11 and the second receiving cavity 21 to ensure that the prefabricated steel casting 3 is completely embedded in the first receiving cavity 11 and the second receiving cavity 21, thereby achieving precise installation. The two bent sections of the precast steel casting 3 are respectively embedded in the first receiving cavity 11 and the second receiving cavity 21 to connect the first crossbeam 1 and the second crossbeam 2. The first bent section 3a of the precast steel casting 3 is further tightened to the first crossbeam 1, and the second bent section 3b is further tightened to the second crossbeam 2 via connectors 4, making the connection between the first crossbeam 1 and the second crossbeam 2 more secure. In this embodiment, multiple connectors connect the first receiving cavity 11 to the first bent section 3a of the precast steel casting 3, and the second receiving cavity 21 to the second bent section 3b of the precast steel casting 3. The precast steel casting 3, i.e., the standardized steel casting, can be prefabricated in a factory and coated with an anti-corrosion coating; the material of the precast steel casting 3 is selected from steel of the appropriate grade.
[0020] The installation process of the zigzag beam connection structure in this embodiment includes: precisely prefabricating standardized steel castings, namely prefabricated steel castings 3, according to the angle of the zigzag beams of the zigzag unit curtain wall; precisely positioning the limiting groove 300 of the first bent section 3a of the prefabricated steel casting 3 with the limiting slide 200 in the first receiving cavity 11 of the first beam 1, and sliding the first bent section 3a into the first receiving cavity 11 of the first beam 1; and precisely positioning the limiting groove 300 of the second bent section 3b of the prefabricated steel casting 3 with the limiting slide 200 in the first receiving cavity 11 of the first beam 1. The groove 300 corresponds to the limiting slide 200 in the second receiving cavity 21 of the second crossbeam 2. The second bent section 3b is slidably inserted into the second receiving cavity 21 of the second crossbeam 2. Each side of the precast steel casting 3 fits against the side of the corresponding receiving cavity. After the precast steel casting 3 is precisely assembled in the first receiving cavity 11 and the second receiving cavity 21, the first bent section 3a of the precast steel casting 3 and the first crossbeam 1, and the second bent section 3b and the second crossbeam 2 are respectively fastened by multiple connectors 4.
[0021] In this embodiment, the standardized pre-cast steel part 3 can be precisely prefabricated in the factory according to the angle of the fold line position and the preset bending angle. The first crossbeam 1 and the second crossbeam 2 can be pre-assembled with the pre-cast steel part 3 in the factory. The crossbeam connection structure is easy, quick and precise to disassemble and assemble, avoiding the angle deviation caused by on-site cutting and processing of the core in the traditional method, eliminating welding defects such as weld beads, false welds and air holes caused by welding operations, and ensuring the appearance consistency of the fold line shape of the curtain wall.
[0022] like Figure 3 and Figure 7 As shown, in an optional embodiment of the present invention, the top and bottom walls of the first receiving cavity 11 and the second receiving cavity 21 in the thickness direction have a plurality of first through holes 211, and a plurality of corresponding second through holes 35 are respectively provided through the thickness direction of the precast steel casting 3.
[0023] like Figure 2 As shown, multiple connectors 4 include: Bolt 41, the bolt 41 penetrates the first through hole 211 through the top and bottom walls of the first receiving cavity 11 and the second through hole 35 corresponding to the first bent section 3a of the precast steel casting 3, or, penetrates the first through hole 211 through the top and bottom walls of the second receiving cavity 21 and the second through hole 35 corresponding to the second bent section 3b of the precast steel casting 3. Nut 42 is fastened to the end of the bolt 41 that passes through the bottom wall of the first receiving cavity 11 or the second receiving cavity 21.
[0024] In this embodiment, when the connector 4 includes multiple bolts 41 and nuts 42, each bolt 41 passes through the first through hole 211 in the top and bottom walls of the first receiving cavity 11 in the thickness direction, and the corresponding second through hole 35 in the first bent section 3a of the precast steel casting 3, the first through hole 211 in the top and bottom walls of the second receiving cavity 21 in the thickness direction, and the second through hole 35 in the thickness direction of the precast steel casting 3. Each nut 42 is fastened to the bolt end in the bottom wall of the first receiving cavity 11 and the bolt end in the bottom wall of the second receiving cavity 21. The multiple bolts 41 and nuts 42 can be evenly arranged along the width and / or length direction of the beam.
[0025] In this embodiment, bolts 41 and nuts 42 are used to fasten the precast steel casting 3 of the bent structure to one end of the first crossbeam 1 and the first crossbeam 2 to connect the two folded crossbeams, making the crossbeam connection structure easy to disassemble and assemble, simple to operate, and improving disassembly and assembly efficiency.
[0026] like Figure 5 and Figure 6As shown, in an optional embodiment of the present invention, the first receiving cavity 11 and the second receiving cavity 21 have multiple first threaded holes 212 on the two side walls in the width direction, and the precast steel casting 3 has multiple corresponding second threaded holes 36 on the two side walls in the width direction. like Figure 2 As shown, the multiple connectors 4 also include: The machine screw 43 connects the side wall of the first receiving cavity 11 to the corresponding side wall of the first bent section 3a of the precast steel casting 3 through the first threaded hole 212 and the second threaded hole 36, or connects the side wall of the second receiving cavity 21 to the corresponding side wall of the second bent section 3b of the precast steel casting 3 through the first threaded hole 212 and the second threaded hole 36.
[0027] In this embodiment, when the connector 4 also includes multiple threaded pins 43, the threaded pins 43 are respectively threaded to the first threaded hole 212 of the first receiving cavity 11 and the corresponding second threaded hole 36 of the side wall of the first bent section 3a of the precast steel casting 3; and, to connect the first threaded hole 212 of the second receiving cavity 21 and the second threaded hole 36 of the side wall of the second bent section 3b of the precast steel casting 3.
[0028] In this embodiment, the countersunk stainless steel screw 43 is used. The screw 43 can also play a role in pre-positioning. After the precast steel casting 3 is fully embedded in the first receiving cavity 11 and the second receiving cavity 21, and the sides of the precast steel casting 3 are flush with the sides of the corresponding receiving cavities, the screw 43 initially positions the side wall of the first receiving cavity 11 with the side wall of the first bent section 3a of the precast steel casting 3 and the side wall of the second receiving cavity 21 with the side wall of the second bent section 3b of the precast steel casting 3, but does not completely lock it, leaving room for fine adjustment. The precast steel casting 3 is finely adjusted until it is qualified, and then the screw 43 is tightened for fixation. Then, the nuts 42 are tightened on the top and bottom walls of the first receiving cavity 11 and the second receiving cavity 21 in the thickness direction, as well as the corresponding through holes of the precast steel casting 3 in the thickness direction, for final fixation. During the fixation process, the surface of the beam profile is observed in real time to avoid deformation of the beam profile due to overtightening.
[0029] like Figure 6 and Figure 7 As shown, in an optional embodiment of the present invention, the limiting slide 200 is in multiple sets, and each set of limiting slide 200 includes a first limiting slide and a second limiting slide. The first limiting slide and the second limiting slide are respectively disposed on the top wall and / or bottom wall of the inner sidewall of the first receiving cavity 11 and the second receiving cavity 21.
[0030] It should be noted that the inner walls of the first receiving cavity 11 and the second receiving cavity 21 are respectively provided with multiple sets of limiting slides 200. The two limiting slides of each set of limiting slides 200 can be both set on the top wall of the inner wall of the first receiving cavity 11 and the second receiving cavity 21, or the two limiting slides can be both set on the bottom wall of the inner wall of the first receiving cavity 11 and the second receiving cavity 21, or the two limiting slides can be set on the top wall and the bottom wall of the inner wall of the first receiving cavity 11 and the second receiving cavity 21 respectively. The number and position of the limiting slides in specific applications can be adjusted according to the actual situation.
[0031] like Figure 6 and Figure 7 As shown, in an optional embodiment of this example, the limiting slide 200 can be provided in two sets. One set of two limiting slides 200 is spaced apart on the top walls of the first receiving cavity 11 and the second receiving cavity 21, while the other set of two limiting slides 200 is spaced apart on the bottom walls of the first receiving cavity 11 and the second receiving cavity 21. The limiting slides 200 located on the top walls are positioned opposite to the corresponding limiting slides 200 located on the bottom walls. Figure 4 As shown, the outer surface of the precast steel casting 3 is provided with a limiting groove 300 corresponding to the limiting slide 200. The limiting groove 300 of the precast steel casting 3 can be positioned and slidably installed through the limiting slide 200 in the receiving cavity, making the installation convenient and precise.
[0032] like Figure 2 and Figure 8 As shown, in an optional embodiment of this utility model, the unitized curtain wall folded-line beam connection structure further includes: The top wall 51 of the U-shaped reinforcing member 5 is connected to the first crossbeam 1 and the second crossbeam 2 respectively.
[0033] In this embodiment, the top wall 51 of the U-shaped reinforcing member 5 can be threadedly connected to the bottom wall of the first crossbeam 1 and the second crossbeam 2 respectively by screws, further connecting the first crossbeam 1 and the second crossbeam 2 together. The top wall 51 of the U-shaped reinforcing member 5 is tightly fitted to the bottom wall surface of the first crossbeam 1 and the second crossbeam 2, so that the force is evenly distributed at the connection between the U-shaped reinforcing member 5 and the first crossbeam 1 and the second crossbeam 2.
[0034] In a specific embodiment of this utility model, the top wall 51 of the U-shaped reinforcing member 5 is provided with a third through hole 53 corresponding to the first through hole 211 of the first receiving cavity 11 and the second through hole 35 of the first bent section 3a of the precast steel casting 3, and a third through hole 53 corresponding to the first through hole 211 of the second receiving cavity 21 and the second through hole 35 of the second bent section 3b of the precast steel casting 3.
[0035] The bolt 41 penetrates the first through hole 211 through the top and bottom walls of the first receiving cavity 11, the second through hole 35 of the first bent section 3a of the precast steel casting 3, and the corresponding third through hole 53 of the top wall 51 of the U-shaped reinforcement 5; or, it penetrates the first through hole 211 through the top and bottom walls of the second receiving cavity 21, the second through hole 35 of the second bent section 3b of the precast steel casting, and the corresponding third through hole 53 of the top wall 51 of the U-shaped reinforcement 5; the nut 42 is fastened to the end of the bolt 41 that penetrates the top wall 51 of the U-shaped reinforcement 5.
[0036] In this embodiment, the connecting member 4, namely the bolt 41, sequentially passes through the first through hole 211 in the top wall of the first receiving cavity 11, the second through hole 35 in the first bent section 3a of the precast steel casting 3, the first through hole 211 in the bottom wall of the first receiving cavity 11, and the corresponding third through hole 53 in the top wall of the U-shaped reinforcing member 5. The nut 42 is threadedly fastened to the end of the bolt 41 that passes through the third through hole 53 in the top wall 51 of the U-shaped reinforcing member 5. The bolt 41 sequentially passes through the first through hole 211 in the top wall of the second receiving cavity 21, the second through hole 35 in the second bent section 3b of the precast steel casting 3, the first through hole 211 in the bottom wall of the second receiving cavity 21, and the corresponding third through hole 53 in the top wall 51 of the U-shaped reinforcing member 5. The nut 42 is threadedly fastened to the end of the bolt 41 that passes through the third through hole 53 in the top wall 51 of the U-shaped reinforcing member 5.
[0037] like Figure 2 As shown, in an optional embodiment of the present invention, the unitized curtain wall folded beam connection structure further includes: an elastic pad 52, disposed between the nut 42 and the top wall of the U-shaped reinforcing member 5, or between the top wall 51 of the U-shaped reinforcing member 5 and the first beam 1 and the second beam 2.
[0038] In this embodiment, the elastic pad 52 increases the stability and tightening force of the bolt connection between the U-shaped reinforcing member 5 and the first crossbeam 1 and the second crossbeam 2.
[0039] like Figure 4 As shown, in an optional embodiment of this utility model, the precast steel casting 3 includes: Middle section 31; The first end 33 and the second end 34 are respectively connected to both sides of the middle part 31 along the width direction by the connecting part 32; Wherein, a limiting groove 300 is formed between the connecting part 32 and the middle part 31 and the first end part 33 and / or between the connecting part 32 and the middle part 31 and the second end part 34.
[0040] In this embodiment, the first end portion 33 and the second end portion 34 are respectively connected to the middle portion 31 via the connecting portion 32. The middle portion 31, the first end portion 33, and the second end portion 34 can be closed cavities. A limiting groove 300 is formed between the connecting portion 32 and the middle portion 31 and the first end portion 33 and / or between the connecting portion 32 and the middle portion 31 and the second end portion 34. The middle portion 31, the connecting portion 32, the first end portion 33, and the second end portion 34 in this embodiment can be configured according to actual conditions, so that the limiting groove 300 corresponds to the limiting slide 200.
[0041] In a specific embodiment of this utility model, the sides of the middle part 31, the first end part 33 and the second end part 34 are in contact with the corresponding sides of the first receiving cavity 11 and the second receiving cavity 21.
[0042] It should be noted that the two sides of the middle part 31 along the thickness direction of the precast steel casting 3 are respectively attached to the top wall and bottom wall of the first receiving cavity 11 and the second receiving cavity 21, and the first end part 33 and the second end part 34 are respectively attached to the top wall, bottom wall and side wall of the first receiving cavity 11 and the second receiving cavity 21 along the thickness direction of the precast steel casting 3 and along the outer side wall along the width direction of the precast steel casting 3.
[0043] like Figure 2 As shown, in an optional embodiment of this utility model, an upwardly opening and a cavity 30 communicating with each other are provided above the first crossbeam 1 and the second crossbeam 2; a water guide 40 is provided inside the cavity 30. In this embodiment, the cross-section of the cavity 30 can be a U-shaped structure, and the corresponding water guide 40 can be arranged close to the inner wall of the cavity.
[0044] like Figure 9 As shown, in this embodiment, the span of the zigzag unit is 2.1 meters, containing three turning nodes. The beams at the turning points are spliced, and the processing and assembly of the beams at the turning points using traditional cutting, inserting, and welding methods is difficult. The precast steel casting 3 in this embodiment is used to connect the beams at the turning points, resulting in the zigzag beam connection structure 10. This beam connection structure is easy and quick to assemble and disassemble. The precast steel casting 3 is precisely inserted into the first receiving cavity 11 and the second receiving cavity 21 of the first beam 1 and the second beam 2, thereby improving the accuracy of the beam connection at the zigzag position of the unit curtain wall, ensuring stable construction quality, and ultimately achieving the goals of excellent architectural decoration appearance, convenient on-site construction operation, and reliable and durable installation quality, further enhancing the overall decorative value and socio-economic benefits of the building.
[0045] The specific implementation process is as follows: Based on the processing drawing of the polygonal unit curtain wall, the dimensional parameters of the precast steel casting 3 are determined, and the standardized steel casting, i.e., the precast steel casting 3, is precisely precast by the factory according to the preset angle.
[0046] Compressed air is used to purge the steel casting installation adaptation area of the crossbeam at the unit body fold line position and the groove of the crossbeam profile installation slot for the first time to remove surface dust and debris. Then, the inner wall and inner surface of the groove are wiped with a lint-free cloth. The installation slot is the crossbeam receiving cavity, including the first receiving cavity 11 and the second receiving cavity 21.
[0047] After cleaning, a laser line projector is used to mark the installation reference line and bolt hole positions of the precast steel casting 3 on the surface of the unit beam profile.
[0048] Carefully place the precast steel casting 3 into the pre-reserved installation groove at the fold line. Ensure it is fully embedded and flush with the unitized curtain wall beam profile.
[0049] The limiting groove 300 of the first bent section 3a of the precast steel casting 3 is aligned with the limiting slide 200 of the first receiving cavity 11, and the first bent section 3a is slid into the first receiving cavity 11; the limiting groove 300 of the second bent section 3b of the precast steel casting 3 is aligned with the limiting slide 200 of the second receiving cavity 21, and the second bent section 3b is slid into the second receiving cavity 21, and each side of the precast steel casting 3 is fitted with each side of the corresponding receiving cavity.
[0050] Initial positioning of the unit beam profile was achieved using machine screws 43, but not completely locked, leaving room for fine-tuning. The installation position of the precast steel casting 3 was then verified using a laser rangefinder and an angle gauge. After fine-tuning to the acceptable level, the machine screws 43 were tightened for final fixation.
[0051] The machine screw 43 is used to initially connect the first threaded hole 212 of the first receiving cavity 11 with the corresponding second threaded hole 36 of the first bent section 3a of the precast steel casting 3, and the first threaded hole 212 of the second receiving cavity 21 with the corresponding second threaded hole 36 of the second bent section 3b of the precast steel casting 3. The machine screw 43 is not completely locked. The precast steel casting 3 is then finely adjusted and the machine screw 43 is tightened to fix it.
[0052] On the outer side of the connection between the precast steel casting 3 and the unit beam profile, a U-shaped reinforcing member 5 is installed according to the processing drawing requirements. The U-shaped reinforcing member 5 must fit tightly against the surface of the beam profile. The top of the U-shaped reinforcing member 5 is temporarily fixed to the bottom wall profile of the first beam 1 and the second beam 2 by spot welding to form an anti-deformation support. Bolts 41 and nuts 42 are used for final fixing. During the fixing process, the surface of the beam profile is observed in real time to avoid overtightening and deformation of the profile.
[0053] After the U-shaped reinforcing member 5 is temporarily fixed to the bottom wall of the first crossbeam 1 and the second crossbeam 2, one set of bolts 41 passes through the first through hole 211 of the first receiving cavity 11, the second through hole 35 corresponding to the first bent section 3a of the precast steel casting 3, and the third through hole 53 of the U-shaped reinforcing member 5. Another set of bolts 41 passes through the first through hole 211 of the second receiving cavity 21, the second through hole 35 corresponding to the second bent section 3b of the precast steel casting 3, and the third through hole 53 of the U-shaped reinforcing member 5. While tightening the bolts 41 at the end of the bolts below the top wall of the U-shaped reinforcing member 5 with nuts 42, observe the surface of the crossbeam and tighten to the appropriate position to complete the installation.
[0054] This utility model also provides a polygonal unitized curtain wall, including: the polygonal crossbeam connection structure of the unitized curtain wall as described above.
[0055] In this embodiment, when assembling the zigzag beam connection structure, the specifications, models, and geometric dimensions of the standardized steel castings to be installed are checked one by one based on the detailed design drawings and connection node details of the zigzag unit curtain wall, including the fit clearance between the precast steel castings and the beams, and the coordinates of the bolt holes. The precast steel castings are then connected to the corresponding first and second beams, facilitating easy assembly and disassembly with high installation accuracy. Whether the precast steel castings and beams are pre-assembled in the factory or installed on-site, the operation is more convenient and the installation quality is more reliable.
[0056] In this embodiment, the zigzag unit curtain wall also includes: a hollow core 6 with openings at both ends, which is fitted onto the outside of the U-shaped reinforcing member 5, and the side wall of the core 6 is connected to the two side walls opposite to the U-shaped reinforcing member 5 by fasteners.
[0057] In this embodiment, the U-shaped reinforcing member has multiple connecting threaded holes on its opposite side walls, and the sleeve 6 and the U-shaped reinforcing member 5 have corresponding connecting threaded holes on their corresponding side walls. The U-shaped reinforcing member 5 and the sleeve 6 are connected by fastening screws passing through the corresponding connecting threaded holes.
[0058] In this embodiment, the zigzag unit curtain wall further includes: a column 7, which is sleeved on the outside of the core 6, and the exterior-facing sidewall is connected to the exterior-facing sidewall of the core 6. A central column 71 is provided in the central area of the exterior-facing sidewall of the column 7, and the central column 71 is connected to the column 7 by a thermal insulation strip.
[0059] The sleeve core 6 is provided with vertically extending reinforcing ribs at intervals with the adjacent and opposite outer side walls facing the outside, and the reinforcing ribs contact the inner side wall of the column. The surface shapes of the sleeve core 6 and the column 7 facing the outside match the angle of the crossbeam.
[0060] The above description is the preferred embodiment of this utility model. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the principle of this utility model, and these improvements and modifications should also be considered within the protection scope of this utility model.
Claims
1. A unitized curtain wall zigzag beam connection structure, characterized in that, include: The first crossbeam (1) has a first receiving cavity (11) with an opening along its length direction at one end. The second crossbeam (2) has a second receiving cavity (21) with an opening along its length at one end. One end of the second crossbeam (2) is connected to one end of the first crossbeam (1) at a preset angle. The inner walls of the first receiving cavity (11) and the second receiving cavity (21) are respectively provided with limiting slides (200) extending along the length. The precast steel casting (3) has a bent structure. The bending angle of the precast steel casting (3) matches the included angle between the first crossbeam (1) and the second crossbeam (2). The first bent section (3a) of the precast steel casting (3) is housed in the first receiving cavity (11), and the second bent section (3b) of the precast steel casting (3) is housed in the second receiving cavity (21). The sides of the first bent section (3a) and the second bent section (3b) are respectively provided with limiting grooves (300) that slide in cooperation with the corresponding limiting slides (200). Multiple connectors (4) are respectively connected to the first crossbeam (1) and the first bent section (3a) of the precast steel casting (3) and the second crossbeam (2) and the second bent section (3b) of the precast steel casting (3).
2. The unitized curtain wall zigzag beam connection structure according to claim 1, characterized in that, The first receiving cavity (11) and the second receiving cavity (21) are provided with a plurality of first through holes (211) in the thickness direction of the top and bottom walls, and a plurality of corresponding second through holes (35) are provided through the thickness direction of the precast steel casting (3). Multiple connectors (4), including: Bolt (41), the bolt (41) penetrates the first through hole (211) through the top and bottom walls of the first receiving cavity (11), and the corresponding second through hole (35) of the first bent section (3a) of the precast steel casting (3), or, penetrates the first through hole (211) through the top and bottom walls of the second receiving cavity (21), and the corresponding second through hole (35) of the second bent section (3b) of the precast steel casting (3); Nut (42) is fastened to the end of the bolt (41) that penetrates the bottom wall of the first receiving cavity (11) or the second receiving cavity (21).
3. The unitized curtain wall zigzag beam connection structure according to claim 2, characterized in that, The first receiving cavity (11) and the second receiving cavity (21) have multiple first threaded holes (212) on their two side walls in the width direction, and the precast steel casting (3) has multiple corresponding second threaded holes (36) on its two side walls in the width direction. Multiple connectors (4) also include: A machine screw (43) is used to connect the side wall of the first receiving cavity (11) to the corresponding side wall of the first bent section (3a) of the precast steel casting (3) through a first threaded hole (212) and a second threaded hole (36), or to connect the side wall of the second receiving cavity (21) to the corresponding side wall of the second bent section (3b) of the precast steel casting (3) through a first threaded hole (212) and a second threaded hole (36).
4. The unitized curtain wall zigzag beam connection structure according to claim 1, characterized in that, The limiting slide (200) is in multiple sets, and each set of limiting slide includes a first limiting slide and a second limiting slide. The first limiting slide and the second limiting slide are respectively disposed on the top wall and / or bottom wall of the inner side wall of the first receiving cavity (11) and the second receiving cavity (21).
5. The unitized curtain wall zigzag beam connection structure according to claim 1 or 2, characterized in that, The unitized curtain wall zigzag beam connection structure further includes: U-shaped reinforcing member (5), the top wall (51) of which is connected to the first crossbeam (1) and the second crossbeam (2) respectively.
6. The unitized curtain wall zigzag beam connection structure according to claim 5, characterized in that, When the connector (4) includes a bolt (41) and a nut (42), the top wall (51) of the U-shaped reinforcing member (5) is respectively provided with a third through hole (53) corresponding to the first through hole (211) of the first receiving cavity (11) and the second through hole (35) of the first bent section (3a) of the precast steel casting (3), and a third through hole (53) corresponding to the first through hole (211) of the second receiving cavity (21) and the second through hole (35) of the second bent section (3b) of the precast steel casting (3). The bolt (41) penetrates the first through hole (211) of the top and bottom walls of the first receiving cavity (11), the second through hole (35) of the first bent section (3a) of the precast steel casting (3), and the corresponding third through hole (53) of the top wall (51) of the U-shaped reinforcement (5), or penetrates the first through hole (211) of the top and bottom walls of the second receiving cavity (21), the second through hole (35) of the second bent section (3b) of the precast steel casting (3), and the corresponding third through hole (53) of the top wall (51) of the U-shaped reinforcement (5); Nut (42) is fastened to the end of the top wall (51) of the U-shaped reinforcement (5) through which the bolt (41) passes.
7. The unitized curtain wall zigzag beam connection structure according to claim 1, characterized in that, The precast steel casting (3) includes: Middle section (31); The first end (33) and the second end (34) are connected to both sides of the middle part (31) along the width direction by a connecting part (32); Wherein, a limiting groove (300) is formed between the connecting part (32) and the middle part (31) and the first end (33) and / or between the connecting part (32) and the middle part (31) and the second end (34).
8. The unitized curtain wall zigzag beam connection structure according to claim 7, characterized in that, The sides of the middle part (31), the first end (33) and the second end (34) are in contact with the corresponding sides of the first receiving cavity (11) and the second receiving cavity (21).
9. The unitized curtain wall zigzag beam connection structure according to claim 1, characterized in that, The first crossbeam (1) and the second crossbeam (2) are provided with upward openings and interconnected cavities (30); water guides (40) are provided inside the cavities (30).
10. A polygonal unit curtain wall, characterized in that, Includes the unitized curtain wall zigzag beam connection structure as described in any one of claims 1 to 9.