A water conservancy dam body construction operation platform

By combining a wire winding machine and an elastic belt, the problem of multi-position construction of the construction platform on the inclined sidewall of the dam was solved, ensuring the stability and safety of the suspended platform and improving the convenience and safety of construction.

CN224997953UActive Publication Date: 2026-11-20ZHEJIANG YONGQING CONSTRUCTION ENGINEERING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202522440409.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-18
Publication Date
2026-11-20
Estimated Expiration
2035-11-18

AI Technical Summary

Technical Problem

The existing construction operation platform cannot carry out multi-position construction on the inclined sidewall of the trapezoidal dam without damaging the dam body, and lacks anti-slip measures, causing the construction platform to sway in high winds, affecting construction safety.

Method used

A wire winding machine is used to control the length and angle of the wire. Combined with elastic bands and arc-shaped long strip clamps, the position and tilt angle of the construction basket are adjusted to ensure that the basket is vertical. The elastic bands are tightly connected to the dam body to increase friction, and ventilation holes are set to reduce wind resistance.

Benefits of technology

This enabled flexible adjustment and stability of the construction scaffold on the dam sidewall, improving construction safety and convenience, reducing the risk of platform swaying, and enhancing the safety of construction personnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224997953U_ABST
    Figure CN224997953U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of water conservancy dam construction, concretely is a kind of water conservancy dam body construction operation platform, the upper portion of construction basket is provided with fixing frame, the upper portion of fixing frame is synchronously slidably provided with multiple steel wire winding machines, steel wire is connected and set on the winding roller of each steel wire winding machine, one end of multiple steel wires is fixedly connected with the multiple-point balance position of the upper end surface of construction basket respectively, the side of construction basket is fixedly connected and is provided with elastic belt, multiple arc long strip clamping pieces are arranged on the inclined outer side wall of elastic belt.The utility model is provided with steel wire winding machine, steel wire and universal wheel etc. component, can be wound multiple steel wires by multiple steel wire winding machines, to control the length of each steel wire, form the arbitrary adjustment of the position of construction basket, can also adjust the inclination angle of construction basket, so that construction basket keeps vertical state, and it is convenient for worker to stand in construction basket and operate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of water conservancy dam construction technology, and in particular relates to a water conservancy dam construction operation platform. Background Technology

[0002] After the main body of the dam is completed, when further construction is carried out on the dam body, in order to ensure the strength of the dam body itself, it is not possible to build scaffolding on the inclined side walls of the dam body. Therefore, there is an urgent need for a more convenient and safe dam body construction operation platform to carry out the subsequent construction work of the dam body.

[0003] Patent application CN202320725242.1 discloses a construction operation platform for a water conservancy dam, comprising a dam body, an electromagnetic drive device fixedly installed on the top of the dam body, a telescopic rod movably installed inside the electromagnetic drive device, a limit strip fixedly installed on the left side wall of the telescopic rod, and the outer left side of the limit strip movably engaging with the inner left side of the electromagnetic drive device, a servo motor fixedly installed at the top front end of the telescopic rod, and the output end of the servo motor movably scraping through the bottom of the telescopic rod, a lead screw fixedly installed at the output end of the servo motor, and an automatic lifting platform mechanism provided on the outer wall of the lead screw. By setting up the automatic lifting platform mechanism, the automatic lifting platform mechanism can automatically raise and lower the construction platform, giving the lifting construction platform the function of self-adjusting height, which can facilitate workers to carry out construction on the dam body from all directions, reduce construction risks, and improve the convenience of water conservancy dam construction.

[0004] Existing technologies, by using components such as lifting construction platforms, facilitate construction operations at different heights on the dam body, but still have shortcomings: First, when carrying out construction operations on the inclined sidewalls of a trapezoidal dam, the existing construction operation platform cannot perform attached and multi-position construction operations without damaging the dam body. Secondly, when carrying out construction operations on the sidewalls of higher dams, the existing construction operation platform lacks anti-slip features between itself and the dam body. This causes the operation platform to sway when encountering strong winds, affecting the normal construction work and also affecting the personal safety of construction workers. Utility Model Content

[0005] To overcome the shortcomings of existing technologies, this utility model provides a construction operation platform for hydraulic dams. Through the inclusion of components such as steel wires, multiple steel wire winding machines can be used to wind multiple steel wires, thereby controlling the length of each wire. This allows for arbitrary adjustment of the position of the construction platform while also adjusting its tilt angle to maintain a vertical position. Furthermore, the inclusion of components such as elastic bands allows for adjustment of the elastic band's tilt angle, ensuring a tight fit between the inclined end face of the elastic band and the dam body. This increases the friction between the construction platform and the dam, enhancing the safety of the operation platform.

[0006] To achieve the above objectives, this utility model provides the following technical solution: a construction operation platform for a water conservancy dam, including a construction basket, a fixed frame above the construction basket, and multiple wire winding machines synchronously sliding above the fixed frame. Each wire winding machine has a winding roller with a wire wound and connected. One end of the multiple wires is fixedly connected to multiple balance positions on the upper surface of the construction basket. An elastic belt is fixedly connected to one side of the construction basket, and multiple arc-shaped long strip clips are provided on the inclined outer wall of the elastic belt.

[0007] Optionally, an elastic belt is fixedly connected to one side of the construction scaffold, a first support roller is slidably arranged between the elastic belt and the construction scaffold, and a second support roller is fixedly arranged below the first support roller between the elastic belt and the construction scaffold.

[0008] Optionally, one side of the construction scaffold is slidably equipped with multiple casters.

[0009] Optionally, the upper end face of the fixing frame is provided with a first sliding groove, and each wire winding machine is slidably engaged with a second slider inside the first sliding groove below it, and each second slider is fixedly connected to the wire winding machine above it.

[0010] Optionally, a lead screw is rotatably provided inside the first slide groove, and each of the second sliders is threadedly connected to the lead screw.

[0011] Optionally, a long plate is provided between the construction scaffold and the fixed frame. A U-shaped frame is slidably engaged on one side of the long plate. A rotating shaft is fixedly provided inside the U-shaped frame. A guide pulley is rotatably provided on one side of each steel wire outside the rotating shaft. Each guide pulley rotates and abuts against its adjacent steel wire.

[0012] Optionally, multiple ventilation holes are provided on multiple outer side walls of the construction scaffold.

[0013] Optionally, one side of the elastic band is provided with an elongated hole on the side wall of the construction scaffold. A fixed roller is detachably installed inside the construction scaffold on one side of the elongated hole. One end of the elastic band passes through the elongated hole and is fixedly connected to the outer circular surface of the fixed roller. An installation groove is provided below the elongated hole on the side wall of the construction scaffold. An installation locking strip is slidably engaged inside the installation groove. The other end of the elastic band is fixedly connected to one side wall of the installation locking strip.

[0014] In summary, compared with existing technologies, the beneficial effects of this solution are as follows: (1) By setting up components such as wire winding machine, wire and caster wheel, this utility model can wind multiple wires by multiple wire winding machines, thereby controlling the length of each wire, so as to make arbitrary adjustment of the position of the construction basket and adjust the tilt angle of the construction basket, so as to keep the construction basket in a vertical state, which is convenient for workers to stand and work inside the construction basket. (2) By setting up components such as elastic belt, arc-shaped long strip clip and ventilation holes, this utility model can adjust the tilt angle of the elastic belt so that the tilted end face of the elastic belt can form a tight contact with the dam body, thereby increasing the friction between the construction basket and the dam body and increasing the safety of the operating platform. At the same time, by setting up multiple ventilation holes, the ventilation performance of the construction basket is increased, which can reduce the wind resistance of the construction basket, reduce the weight of the construction basket and improve the safety performance of the operating platform. Attached Figure Description

[0015] Figure 1 This is a perspective view of the present utility model; Figure 2 This is the front view of the present invention; Figure 3 for Figure 2 A three-dimensional cross-sectional view at point AA; Figure 4 for Figure 1 Enlarged view of a section at point B; Figure 5 for Figure 3 A magnified view of a section at point C. Figure 6 for Figure 1 Enlarged view of a section at point D; Figure 7 for Figure 1 A magnified view of a section at point E in the middle; Figure 8 This is a perspective view of the construction suspended platform components in this utility model; Figure 9 for Figure 8 A magnified view of a section at point F in the middle; Figure 10This is an external protective diagram of the first lead screw component of this utility model.

[0016] In the diagram: 10. Construction hoist; 11. Fixing frame; 12. Wire winding machine; 13. First slide groove; 14. Second slider; 15. Lead screw; 16. Wire; 17. Long plate; 18. U-shaped frame; 19. Rotating shaft; 20. Guide pulley; 21. Second slide groove; 22. Second slider; 23. First lead screw; 24. Universal wheel; 25. Level; 26. Partition; 27. Elastic belt; 28. First support roller; 29. ​​Second support roller; 30. Rotating connecting block; 31. Second lead screw; 32. Arc-shaped long strip clamp; 33. Ventilation hole; 35. Long hole; 36. Fixing roller; 37. Fixing clip; 38. Installation slide groove; 39. Installation clip strip. Detailed Implementation

[0017] To enable those skilled in the art to better understand the present invention, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention.

[0018] Example 1: like Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 6 As shown, a construction operation platform for a hydraulic dam includes a construction basket 10. A fixed frame 11 is installed above the construction basket 10 and fixed to the top of the dam. Multiple wire winding machines 12 are synchronously slidably installed above the fixed frame 11. Each wire winding machine 12 has a winding roller with a wire 16 wound and connected. One end of the multiple wires 16 is fixedly connected to multiple balance positions on the upper surface of the construction basket 10. Multiple casters 24 are slidably installed on one side of the construction basket 10. When the construction basket 10 is moved, the multiple wire winding machines 12 are simultaneously activated to synchronously wind the multiple wires 16, causing the construction basket 10 to slide vertically. Horizontal movement of the multiple wire winding machines 12 causes the multiple wires 16 and the construction basket 10 to move horizontally. This allows for the adjustment of the horizontal position of the construction scaffold 10, and subsequently, the adjustment of its construction position on one side of the dam. The sliding contact between multiple casters 24 and the dam sidewall prevents friction between the scaffold 10 and the dam, improving the flexibility of the scaffold 10. Each caster 24 has a first lead screw 23 rotatably connected to one side. One end of the first lead screw 23 passes through the scaffold 10 and is threadedly connected to its sidewall. After the dam is moved, rotating the output ends of the multiple first lead screws 23 drives the casters 24 to move horizontally, thus adjusting the distance between the casters 24 and the scaffold 10 at different positions. This facilitates timely adjustment of the horizontal state of the scaffold 10, improving the safety of workers inside the scaffold 10.

[0019] Furthermore, such as Figure 5 and Figure 6 As shown, an elastic band 27 is provided on one side of the construction scaffold 10. The elastic band 27 is made of elastic wear-resistant damping material, such as polyurethane elastomer. It has the characteristics of wide hardness range (Shore A10 - Shore D75), excellent wear resistance (2-10 times that of natural rubber), and strong fatigue resistance. The damping coefficient has a large adjustable range (0.1-0.6). In actual construction use, the inclined sidewall of the elastic band 27 can abut against the inclined sidewall of the dam. Through the friction between the elastic band 27 and the dam, a stable abutment and fixation of the construction scaffold 10 on one side of the dam can be formed.

[0020] A first support roller 28 is slidably disposed between the elastic band 27 and the construction scaffold 10. A second support roller 29 is fixedly disposed below the first support roller 28 between the elastic band 27 and the construction scaffold 10. Rotary connecting blocks 30 are rotatably connected to both ends of the first support roller 28 and the second support roller 29. A second screw rod 31 is rotatably connected to one side of each of the rotating connecting blocks 30 on both sides of the first support roller 28. The rotating connecting blocks 30 on both sides of the second support roller 29 are fixedly connected to the side wall of the construction scaffold 10, forming a rotational fixation of the second support roller 29. One end of the second screw rod 31 passes through the side wall of the construction scaffold 10 and is threadedly connected to the side wall of the construction scaffold 10. The two supports rollers are adjusted by synchronous rotation. The second lead screw 31 can extend its length on one side of the construction basket 10, thereby adjusting the horizontal distance between the first support roller 28 and the construction basket 10. This provides elastic support for the elastic band 27 and also allows for adjustment of the tilt angle of the elastic band 27 between the first support roller 28 and the second support roller 29. In actual construction operations, the tilt angle of the elastic band 27 between the first support roller 28 and the second support roller 29 can be adjusted according to the tilt of the dam body. This ensures that while maintaining the horizontal state of the construction basket 10, the elastic band 27 can be more tightly bonded to the dam body, resulting in greater friction and greater stability of the construction basket 10.

[0021] It should be noted that when the construction basket 10 is moved horizontally, the first support roller 28 and the second support roller 29 can be moved closer to the construction basket 10 by rotating multiple second lead screws 31, so that the elastic belt 27 can be contracted, so that the elastic belt 27 is separated from the dam body, and the contact friction between the elastic belt 27 and the construction basket 10 is prevented from affecting the position movement of the construction basket 10.

[0022] Furthermore, such as Figure 6 , Figure 5 and Figure 7As shown, elongated holes 35 are provided on one side of the elastic band 27 on the side wall of the construction scaffold 10. A fixed roller 36 is detachably installed inside the construction scaffold 10 on one side of the elongated hole 35. Fixed fasteners 37 are fixedly installed at both ends of the fixed roller 36 on the inner side wall of the construction scaffold 10. The fixed roller 36 is detachably connected to the fixed fasteners 37 on both sides by bolts. One end of the elastic band 27 passes through the elongated hole 35 and is fixedly connected to the outer surface of the fixed roller 36. Below the elongated hole 35, the construction scaffold 10... Each side wall is provided with a mounting groove 38, and a mounting clip 39 is provided inside the mounting groove 38 for sliding engagement. The other end of the elastic band 27 is fixedly connected to one side wall of the mounting clip 39. After long-term use, the elastic band 27 needs to be replaced periodically. At this time, it is necessary to first disassemble the fixed roller 36 and the fixed clip 37, and then remove the mounting clip 39 from the inside of the mounting groove 38, thereby completing the disassembly of the elastic band 27 and replacing it with a new elastic band 27.

[0023] Furthermore, such as Figure 8 and Figure 9 As shown, multiple arc-shaped elongated clips 32 are provided on the inclined outer wall of the elastic band 27. These clips 32 are evenly arranged in a row on the side wall of the elastic band 27. The cross-section of each arc-shaped clip 32 is a downward-opening hook shape, and one end of each clip is fixedly connected to the inclined side wall of the elastic band 27. The arrangement of these multiple arc-shaped clips 32 allows for multi-point local contact between the elastic band 27 and the dam body when they come into contact. While ensuring the frictional force between the elastic band 27 and the arc-shaped clips 32, the wear of the arc-shaped clips 32 can also replace the wear of the elastic band 27, increasing the elastic band 27's frictional strength. The service life of the 7 is extended. When the wire rewinder 12 malfunctions and the wire 16 slides down and elongates, the construction basket 10 will slide down due to the lack of tension from the wire 16. At this time, multiple arc-shaped long strip clamps 32 slide down with the construction basket 10 and generate friction with the dam body. This causes multiple arc-shaped long strip clamps 32 to flip up and form strip-shaped anti-slip strips between the elastic belt 27 and 10. These strips can act as wear parts between the construction basket 10 and the elastic belt 27, reducing the speed of the construction basket 10's descent. They can also extend the friction wear time between the elastic belt 27 and the construction basket 10, providing more time for rescue and effectively increasing the chances of survival for the workers.

[0024] Furthermore, such as Figure 1 and Figure 4As shown, the upper end face of the fixed frame 11 is provided with a first slide groove 13. Each wire winding machine 12 is slidably engaged with a second slider 14 inside the first slide groove 13. Each second slider 14 is fixedly connected to the wire winding machine 12 above it. A lead screw 15 is rotatably arranged inside the first slide groove 13. Each second slider 14 is threadedly connected to the lead screw 15. A servo motor for driving the lead screw 15 to rotate is provided on one side of the fixed frame 11. The servo motor drives the lead screw 15 to rotate, thereby driving multiple second sliders 14, wire winding machines 12 and wires 16 to perform horizontal sliding adjustment, forming a horizontal position adjustment of the construction basket 10. In addition, although the lead screw 12 is in an open state in the attached figure, in actual operation, a dust cover and a lubrication structure can be selectively placed on the outside of the lead screw 12 to avoid the influence of dust on the movement of the lead screw and ensure transmission stability.

[0025] Furthermore, such as Figure 1 and Figure 7 As shown, a long plate 17 is provided between the construction scaffold 10 and the fixed frame 11. In actual use, the long plate 17 is fixed at the angle between the top end face of the dam body and the inclined side wall, so that multiple guide pulleys 20 on one side of the long plate 17 can slide and guide the steel wire 16. A U-shaped frame 18 is slidably engaged on one side of the long plate 17. A second sliding groove 21 is provided on one side wall of the long plate 17. A second slider 22 is slidably disposed inside the second sliding groove 21. The second slider 22 is fixedly connected to the U-shaped frame 18. The second slide 21 and the second slider 22 are configured to fix the U-shaped frame 18 and other components to slide stably on one side of the long plate 17. A rotating shaft 19 is fixedly installed inside the U-shaped frame 18. A guide pulley 20 is rotatably installed on one side of each steel wire 16 outside the rotating shaft 19. Each guide pulley 20 rotates and abuts against its adjacent steel wire 16. The arrangement of multiple guide pulleys 20 forms a guiding transmission effect on multiple steel wires 16, reducing the wear of the steel wires 16 during winding and horizontal movement.

[0026] Furthermore, such as Figure 6 As shown, multiple ventilation holes 33 are provided on multiple outer side walls of the construction scaffold 10. The provision of multiple ventilation holes 33 increases the ventilation performance of the construction scaffold 10, reduces the wind resistance of the construction scaffold 10, reduces the weight of the construction scaffold 10, and improves the safety performance of the operating platform.

[0027] It should be noted that the electric push cylinders inside the construction scaffold 10 can all be powered by external wires. Furthermore, during actual operation, levels can be placed at various points on the outside of the construction scaffold 10 to detect any tilting or swaying, thereby assisting in controlling the specific output actions of the wire winding machine 12.

[0028] like Figure 10As shown, in actual use, the construction platform is equipped with folding ring sleeves on the outside of threaded parts such as the first lead screw 23 and the second lead screw 31 to prevent dust from sticking to the thread surface and to protect the accuracy of the thread and its normal use.

[0029] Finally, the screw rod, wire winding machine, caster wheel, and wire in the hydraulic dam construction operation platform of this utility model are all purchased from the market. Technical personnel in this industry only need to install and operate it according to the accompanying instruction manual, without requiring any creative work from those skilled in the art.

[0030] It should be noted that the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a product or system comprising a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a product or system. Without further limitation, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the product or system that includes said element.

[0031] The foregoing description illustrates and describes several preferred embodiments of this application. However, as previously stated, it should be understood that this application is not limited to the forms disclosed herein and should not be construed as excluding other embodiments. It can be used in various other combinations, modifications, and environments, and can be altered within the scope of the application concept described herein through the foregoing teachings or techniques or knowledge in related fields. Any modifications and variations made by those skilled in the art that do not depart from the spirit and scope of this application should be within the protection scope of the appended claims.

Claims

1. A construction operation platform for a hydraulic dam, comprising a construction basket (10), characterized in that, A fixed frame (11) is provided above the construction scaffold (10). Multiple wire winding machines (12) are synchronously slidably arranged above the fixed frame (11). Each wire winding machine (12) has a wire (16) wound and connected on its winding roller. One end of the multiple wires (16) is fixedly connected to multiple balance positions on the upper surface of the construction scaffold (10). An elastic band (27) is fixedly connected to one side of the construction scaffold (10). Multiple arc-shaped long strip clips (32) are provided on the inclined outer wall of the elastic band (27).

2. The hydraulic dam construction operation platform according to claim 1, characterized in that, A first support roller (28) is slidably disposed between the elastic band (27) and the construction basket (10), and a second support roller (29) is fixedly disposed below the first support roller (28) between the elastic band (27) and the construction basket (10).

3. The hydraulic dam construction operation platform according to claim 2, characterized in that, The construction scaffold (10) is equipped with multiple casters (24) on one side.

4. The hydraulic dam construction operation platform according to claim 1, characterized in that, The upper end face of the fixed frame (11) is provided with a first sliding groove (13), and each wire winding machine (12) is provided with a second slider (14) slidably engaged inside the first sliding groove (13) below it. Each second slider (14) is fixedly connected to the wire winding machine (12) above it.

5. The hydraulic dam construction operation platform according to claim 4, characterized in that, The first slide (13) is rotatably equipped with a lead screw (15), and each second slider (14) is threadedly connected to the lead screw (15).

6. The hydraulic dam construction operation platform according to claim 1, characterized in that, A long plate (17) is provided between the construction basket (10) and the fixed frame (11). A U-shaped frame (18) is slidably snapped onto one side of the long plate (17). A rotating shaft (19) is fixedly provided inside the U-shaped frame (18). A guide pulley (20) is rotatably provided on one side of each steel wire (16) outside the rotating shaft (19). Each guide pulley (20) rotates and abuts against its adjacent steel wire (16).

7. The hydraulic dam construction operation platform according to claim 1, characterized in that, Multiple ventilation holes (33) are provided on the multiple outer side walls of the construction basket (10).

8. The hydraulic dam construction operation platform according to claim 2, characterized in that, One side of the elastic band (27) is provided with an elongated hole (35) on the side wall of the construction basket (10). A fixed roller (36) is detachably provided inside the construction basket (10) on one side of the elongated hole (35). One end of the elastic band (27) passes through the elongated hole (35) and is fixedly connected to the outer circular surface of the fixed roller (36). Below the elongated hole (35), an installation groove (38) is provided on the side wall of the construction basket (10). An installation locking strip (39) is slidably engaged inside the installation groove (38). The other end of the elastic band (27) is fixedly connected to one side wall of the installation locking strip (39).

Citation Information

Patent Citations

  • Water conservancy dam body construction operation platform

    CN219569509U