A wind power mixed tower concrete section parallel steel wire finished cable supplementing and cable withdrawing tool

By designing tooling with adjustable support mechanisms and precision force measuring units suitable for wind turbine hybrid towers, the problems of spatial adaptability and cable angle mismatch in wind turbine hybrid tower construction were solved, cable torsion and rebound were avoided, and the safety and convenience of construction were improved.

CN224998003UActive Publication Date: 2026-11-20JIANGSU LUHAI ENG TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522564040.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-03
Publication Date
2026-11-20
Estimated Expiration
2035-12-03

AI Technical Summary

Technical Problem

Existing bridge prestressed construction equipment cannot adapt to the narrow space and complex cable angle distribution of wind turbine hybrid towers, and lacks anti-rebound structure, resulting in construction difficulties and safety hazards.

Method used

A tooling system including an adjustable support mechanism, an anti-torsion tensioning component, and a precision force measuring unit was designed. The adjustable support mechanism is adapted to the space of the wind power hybrid tower, the guide groove and guide slider restrict torsion, the precision force measuring unit monitors the tension force, and the buffer cylinder slowly releases the load.

Benefits of technology

It enables flexible adaptation of the tooling within the wind turbine tower, preventing cable twisting and springback, and ensuring construction safety and ease of operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224998003U_ABST
    Figure CN224998003U_ABST
Patent Text Reader

Abstract

The utility model discloses a kind of wind power mixed tower concrete section parallel steel wire finished product cable supplementing and withdrawing tool, including adjustable support mechanism, anti-twist tensioning assembly and accurate force measuring unit, anti-twist tensioning assembly is set in adjustable support mechanism top, using the utility model scheme, 1 strong adaptability: adjustable support mechanism is adapted to wind power mixed tower narrow space and different angle cable body by telescopic arm and angle adjustment hinge, solve the problem that bridge tooling "can not be installed, not accurate";Anti-twist reliable: the cooperation of guide groove and guide block, limit the circumferential rotation in cable body tensioning / withdrawing process, avoid parallel steel wire stress concentration due to torsion;Safety controllable: accurate force measuring unit real-time monitoring tensioning force, avoid over-tensioning or under-tensioning;Safety unloading assembly is realized by buffer cylinder and return spring Load slowly release, prevent cable body rebound causes safety accident while operating conveniently.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of wind power mixed tower prestressed engineering technology. More specifically, this utility model relates to a tooling for tensioning and untensioning of parallel steel wire finished cables in the concrete section of a wind power mixed tower. Background Technology

[0002] In bridge engineering, the tensioning of prestressed steel strands often employs a combination structure of "jacks + anchor positioning frames + force measuring devices," while cable unloading is achieved smoothly through "unloading valves + buffer devices." However, this type of tooling has the following shortcomings and cannot be directly applied to wind turbine hybrid towers: 1. Poor spatial adaptability: The construction space for prestressed bridges is open, and the tooling is large; while the internal space of the concrete section of the wind turbine tower is narrow (mostly 3-5m in diameter), making it difficult to install and operate the existing bridge tooling. 2. Mismatched cable angles: Bridge steel strands are mostly arranged horizontally or at a small angle, and the tooling supports are at a fixed angle; the parallel steel wire finished cables of wind turbine hybrid towers are distributed radially along the tower wall, and the angle between the cable and the tower wall is 15°-45°. Fixed-angle tooling can easily cause the cable to twist. 3. Insufficient safety redundancy: The load transfer path is clear when the bridge cables are unloaded. The anchorage depth of the cable body of the wind turbine hybrid tower is relatively shallow. Sudden unloading can easily cause the cable body to rebound. Existing bridge tooling lacks a targeted anti-rebound structure. Utility Model Content

[0003] The technical problem to be solved by this utility model is to provide a tooling for tensioning and untensioning of parallel steel wire finished cables in the concrete section of a wind power mixed tower, which can solve the problems of poor spatial adaptability, mismatched cable angles, and insufficient safety redundancy.

[0004] To achieve the above objectives, the technical solution adopted by this utility model is as follows: a tooling for tensioning and untensioning parallel steel wire finished cables in the concrete section of a wind turbine hybrid tower, comprising an adjustable support mechanism, an anti-torsion tensioning component, and a precision force measuring unit, wherein the anti-torsion tensioning component is installed on top of the adjustable support mechanism, wherein: The adjustable support mechanism includes a base, a telescopic arm, and an angle adjustment hinge; the base is connected to the inner wall of the wind turbine tower by expansion bolts, one end of the telescopic arm is hinged to the base, and the other end is connected to the anti-torsion tensioning component by the angle adjustment hinge. The anti-torsion tensioning assembly includes a tensioning jacket, a guide slider, and a jack. The inner wall of the tensioning jacket is provided with a guide groove that matches the finished parallel steel wire cable. The guide slider is embedded in the guide groove and fits against the cable anchor head. The jack is located at the end of the tensioning jacket away from the cable, and its piston rod is connected to the guide slider, which can push the cable along the axial direction of the guide groove.

[0005] This utility model discloses a tooling for tensioning and untensioning of finished parallel steel wire cables in the concrete section of a wind power hybrid tower. The angle adjustment hinge is equipped with a fixing locking bolt, which can fix the cable body to an appropriate angle of 15°-45°.

[0006] This utility model discloses a tooling for tensioning and untensioning of parallel steel wire finished cables in the concrete section of a wind power hybrid tower. The telescopic arm is equipped with a hydraulic push rod, which can achieve length adjustment from 0 to 500 mm.

[0007] This utility model discloses a tooling for tensioning and untensioning of parallel steel wire finished cables in the concrete section of a wind power mixed tower. The precision force measuring unit includes a pressure sensor and a digital display screen. The pressure sensor is located between the piston rod of the jack and the guide slider. The digital display screen is fixed to the outer wall of the tensioning jacket and is connected to the pressure sensor through a wire to display the tension force value in real time.

[0008] Compared with the prior art, the present invention has the following advantages: 1. High adaptability: The adjustable support mechanism, through telescopic arms and angle adjustment hinges, can adapt to the narrow space of wind power hybrid towers and cables at different angles, solving the problem of "cannot fit or be aligned" of bridge equipment; 2. Reliable anti-torsion: The cooperation between the guide groove and the guide slider restricts the circumferential rotation of the cable during tensioning / untensioning, avoiding stress concentration in the parallel steel wires due to torsion; 3. Safe and controllable: The precise force measuring unit monitors the tension force in real time to avoid over-tensioning or under-tensioning; the safety unloading component releases the load slowly through a buffer cylinder and a return spring to prevent the cable from rebounding and causing safety accidents. 4. Easy to operate: The modular design of each component allows for disassembly and installation, adapting to the narrow operating space inside the hybrid tower and reducing the labor intensity of construction personnel.

[0009] The present invention will be described in more detail below with reference to the accompanying drawings and embodiments. Attached Figure Description

[0010] The following is a brief explanation of the contents of each of the accompanying drawings and the markings in the drawings: Figure 1 This is a schematic diagram of the present invention; The following are marked in the diagram: 1. Base; 2. Telescopic arm; 3. Angle adjustment hinge; 4. Tensioning jacket; 5. Guide slider; 6. Jack; 7. Guide groove; 8. Pressure sensor; 9. Digital display screen; 10. Cable body. Detailed Implementation

[0011] The following description, with reference to the accompanying drawings, further details the specific implementation methods of this utility model, including the shape and structure of each component, the relative positions and connections between the parts, the function and working principle of each part, the manufacturing process, and the operation and use methods, so as to help those skilled in the art to have a more complete, accurate, and in-depth understanding of the utility model concept and technical solution.

[0012] like Figure 1 The illustrated fixture for tensioning and untensioning parallel steel wire precast cables in the concrete section of a wind turbine tower includes an adjustable support mechanism, an anti-torsion tensioning component, and a precision force measuring unit. The anti-torsion tensioning component is located on top of the adjustable support mechanism. The adjustable support mechanism includes a base 1, a telescopic arm 2, and an angle adjustment hinge 3. The base 1 is connected to the inner wall of the wind power tower by expansion bolts. One end of the telescopic arm 2 is hinged to the base 1, and the other end is connected to the anti-torsion tensioning component through the angle adjustment hinge 3. The angle adjustment hinge 3 is equipped with a fixing locking bolt, which can fix the cable body 10 to an appropriate angle of 15°-45°. The telescopic arm 2 is equipped with a hydraulic push rod, which can achieve length adjustment of 0-500mm.

[0013] The anti-torsion tensioning assembly includes a tensioning jacket 4, a guide slider 5, and a jack 6. The inner wall of the tensioning jacket 4 is provided with a guide groove 7 that matches the finished parallel steel wire cable. The guide slider 5 is embedded in the guide groove 7 and fits against the anchor head of the cable body 10. The jack 6 is located at the end of the tensioning jacket 4 away from the cable body 10, and its piston rod is connected to the guide slider 5, which can push the cable body 10 axially along the guide groove 7.

[0014] The precision force measurement unit includes a pressure sensor 8 and a digital display screen 9. The pressure sensor 8 is located between the piston rod of the jack 6 and the guide slider 5. The digital display screen 9 is fixed to the outer wall of the tension jacket 4 and is connected to the pressure sensor 8 through wires to display the tension force value in real time.

[0015] Working principle and method 1. Start jack 6 and apply a pre-jacking force equal to the existing tension of cable 10 to make the anchor head locking nut of cable 10 stress-free, and then remove the locking nut; 2. Close the oil inlet valve of jack 6 and open the unloading valve. Through the damping effect of the buffer cylinder and the return spring, the pressure of jack 6 will slowly decrease (pressure reduction rate ≤ 0.5MPa / s). 3. When the pressure sensor 8 displays a force value of 0, confirm that the cable 10 is completely unloaded and pull the cable 10 out of the anchoring end; 4. Disassemble all components of the tooling and complete the cable unwinding.

[0016] The present invention has been described above with reference to the accompanying drawings. Obviously, the specific implementation of the present invention is not limited to the above-described manner. Any non-substantial improvements made using the inventive concept and technical solution of the present invention, or the direct application of the inventive concept and technical solution to other situations without modification, are all within the protection scope of the present invention.

Claims

1. A tooling for tensioning and untensioning parallel steel wire precast cables in the concrete section of a wind turbine tower, characterized in that, It includes an adjustable support mechanism, an anti-torsion tensioning component, and a precision force measuring unit. The anti-torsion tensioning component is located on top of the adjustable support mechanism, wherein: The adjustable support mechanism includes a base, a telescopic arm, and an angle adjustment hinge; the base is connected to the inner wall of the wind turbine tower by expansion bolts, one end of the telescopic arm is hinged to the base, and the other end is connected to the anti-torsion tensioning component by the angle adjustment hinge. The anti-torsion tensioning assembly includes a tensioning jacket, a guide slider, and a jack. The inner wall of the tensioning jacket is provided with a guide groove that matches the finished parallel steel wire cable. The guide slider is embedded in the guide groove and fits against the cable anchor head. The jack is located at the end of the tensioning jacket away from the cable, and its piston rod is connected to the guide slider, which can push the cable along the axial direction of the guide groove.

2. The tooling for tensioning and untensioning parallel steel wire finished cables in the concrete section of a wind turbine tower according to claim 1, characterized in that, The angle adjustment hinge is fixed with a locking bolt, which can fix the cable body at an adaptation angle of 15°-45°.

3. The tooling for tensioning and untensioning parallel steel wire finished cables in the concrete section of a wind turbine tower according to claim 1, characterized in that, The telescopic arm is equipped with a hydraulic push rod, which can be adjusted in length from 0 to 500 mm.

4. The tooling for tensioning and untensioning parallel steel wire precast cables in the concrete section of a wind turbine tower according to claim 1, characterized in that, The precision force measuring unit includes a pressure sensor and a digital display screen; the pressure sensor is located between the jack piston rod and the guide slider, and the digital display screen is fixed to the outer wall of the tension jacket and connected to the pressure sensor through wires to display the tension force value in real time.