A heat energy recovery system for preparing recycled hot water by using CIP waste hot water

By designing the CIP waste hot water heat energy recovery system, the problems of high heating pressure and acid and alkali corrosion of heat pumps were solved. It achieved efficient recovery of waste heat fluid and automated control of hot water, ensuring the sterilization quality of hot water and the protection of equipment.

CN225000271UActive Publication Date: 2026-11-20ANGEL YEAST(PUER) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522769693.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-26
Publication Date
2026-11-20
Estimated Expiration
2035-12-26

AI Technical Summary

Technical Problem

The problems of high heating pressure, waste heat fluid temperature, and hot water quality pollution caused by acid and alkali corrosion in existing hot water preparation processes have not been effectively solved.

Method used

A heat recovery system for CIP wastewater hot water was designed, including components such as a wastewater tank, plate heat exchanger, shell-and-tube heat exchanger, and steam ejector. The system realizes automated heat recovery, heating, and insulation processes through a control system, avoiding acid and alkali corrosion and ensuring hot water quality.

Benefits of technology

It achieves efficient recycling of waste heat fluid, reduces heat pump pressure, ensures the sterilization temperature and quality of hot water, avoids equipment corrosion and pollution, and improves control precision and automation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225000271U_ABST
    Figure CN225000271U_ABST
Patent Text Reader

Abstract

The utility model discloses a kind of heat energy recovery systems for preparing recycled hot water using CIP waste hot water, including the wastewater tank for recycling CIP waste hot water, waste heat fluid level gauge is equipped in the wastewater tank, when waste heat fluid level gauge monitors that liquid level reaches set value, and heat energy recovery module and primary heating module are started by control system, and heat preservation heating module and hot water pump are closed;Heat energy recovery module includes plate heat exchanger, one end of plate heat exchanger is input waste heat fluid by waste heat fluid pump, another end of plate heat exchanger is input soft water by soft water adjusting valve, soft water flows into primary heating module after temperature rise in plate heat exchanger;Hot water tank is equipped with hot water tank liquid level probe, when hot water tank liquid level probe monitors that liquid level reaches set value, and heat energy recovery module and primary heating module are closed by control system, and heat preservation heating module is opened;Waste heat fluid is carried out heat energy recovery, and the quality of hot soft water is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of heat energy recovery technology, and in particular to a heat energy recovery system that uses CIP waste hot water to prepare recycled hot water. Background Technology

[0002] The basic principle of heat recovery is to use a heat exchanger to indirectly or directly contact a higher-temperature waste heat fluid with a lower-temperature fluid to be heated, thereby transferring heat from the waste heat source to the medium to be heated, without the two mixing. This process follows the second law of thermodynamics and aims to maximize the utilization of the energy's "grade" (temperature level).

[0003] The application of heat recovery technology is extremely wide, covering almost all fields that generate waste heat; however, the utilization of low-grade waste heat is relatively limited. Currently, the existing methods for preparing hot water from soft water to meet sterilization requirements require heating to at least 85°C. Soft water also needs a heat pump to improve its grade. The heat pump has a high heating pressure, and the heat in the waste heat fluid is not utilized, resulting in a waste of heat energy.

[0004] Furthermore, the heat exchange media used in the current production process are mostly acids and alkalis, which inevitably corrode the heat exchange equipment and cause waste heat fluid to contaminate soft water, posing a potential quality hazard. Utility Model Content

[0005] This invention provides a heat energy recovery system for preparing recycled hot water using CIP waste hot water, aiming to solve the problems mentioned above in existing hot water preparation processes, such as high heating pressure of heat pumps, waste of waste heat fluid temperature, and pollution of hot water quality caused by corrosion of heat exchange equipment by acids and alkalis.

[0006] To solve the above-mentioned technical problems, the technical solution adopted by this utility model is as follows: A heat energy recovery system for preparing recycled hot water using CIP waste water includes a wastewater tank for recycling CIP waste water. The wastewater tank is equipped with a waste heat fluid level gauge. When the waste heat fluid level gauge detects that the liquid level has reached a set value, the heat energy recovery module and the primary heating module are activated through the control system, and the heat preservation heating module and the hot water pump are shut down. The heat recovery module includes a plate heat exchanger. Waste heat fluid is input into one end of the plate heat exchanger through a waste heat fluid pump, and soft water is input into the other end of the plate heat exchanger through a soft water regulating valve. The soft water and the waste heat fluid exchange heat in the plate heat exchanger. After being heated in the plate heat exchanger, the soft water flows into the first-stage heating module. The primary heating module includes a shell-and-tube heat exchanger. Steam is input into one end of the shell-and-tube heat exchanger through a steam regulating valve, and heated soft water is input into the other end of the shell-and-tube heat exchanger. The heated soft water and steam exchange heat in the shell-and-tube heat exchanger, and the heated soft water is then passed into a hot water tank for storage. The hot water tank is equipped with a hot water tank level probe. When the hot water tank level probe detects that the liquid level has reached the set value, the control system shuts down the heat recovery module and the first-stage heating module, and turns on the heat preservation heating module. The heat preservation and heating module includes a steam ejector and a hot water tank temperature probe located inside the hot water tank. The steam ejector inputs steam through its steam valve. The hot water tank temperature probe is linked to the steam ejector valve through a control system, and the control system keeps time. After the heat preservation time is up, the hot water pump is turned on to supply water to the system.

[0007] Preferably, the waste heat fluid enters the drain module after heat exchange in the plate heat exchanger. The drain module includes a main pipe connected to the waste heat fluid outlet of the plate heat exchanger, and a branch is connected in parallel on the other side of the main pipe. One branch is connected to the exhaust gas treatment system through the exhaust gas drain valve, and the other branch is connected to the drain well through the drain valve.

[0008] Preferably, the main pipe is equipped with a waste heat fluid temperature probe to monitor the temperature of the waste heat fluid after heat exchange, and the exhaust gas drain valve and the sewage valve are linked with the waste heat fluid temperature probe through the control system. When the waste heat fluid temperature probe detects a temperature higher than the set value, the exhaust gas drain valve opens and the sewage drain valve closes. When the waste heat fluid temperature probe detects that the temperature is not higher than the set value, the exhaust gas drain valve closes and the sewage drain valve opens.

[0009] Preferably, the condensate from the steam heat exchanger after steam heat exchange is incorporated into the softened water after secondary heating through a steam trap.

[0010] Preferably, the input end of the soft water regulating valve is equipped with a soft water flow meter to monitor the soft water flow, and the soft water flow meter is linked with the soft water regulating valve through the control system.

[0011] Preferably, the shell-and-tube heat exchanger is equipped with a temperature and conductivity probe at the soft water output end to monitor the temperature and conductivity of the soft water after secondary heating.

[0012] Preferably, the temperature conductivity probe is linked with the heat recovery module and the primary heating module through a control system; When the temperature is below 85℃, the temperature conductivity probe increases the flow rate of the steam regulating valve in the first-stage heating module through the control system; when the temperature is above 95℃, the temperature conductivity probe decreases the flow rate of the steam regulating valve in the first-stage heating module through the control system. When the conductivity is greater than 10 μs / cm for more than 10 seconds, the control system shuts down the heat recovery module and the primary heating module.

[0013] Preferably, during heat preservation, the temperature of the hot water tank temperature probe is set to 85°C. When the temperature detected by the hot water tank temperature probe is lower than 85°C, the hot water tank temperature probe opens the steam valve of the steam injector through the control system to heat the water until the temperature is not lower than 85°C, and the control system keeps time for a heat preservation time of not less than 30 minutes.

[0014] Preferably, during water supply, the hot water tank temperature probe is linked with the steam valve of the steam ejector and the hot water pump through the control system. When the temperature detected by the hot water tank temperature probe is lower than 85°C, the hot water tank temperature probe shuts off the hot water pump through the control system and opens the steam valve of the steam ejector to heat the water until the temperature is not lower than 85°C. Then, the control system restarts the hot water pump and closes the steam valve of the steam ejector.

[0015] Preferably, the control system is an industrial PLC control system.

[0016] The beneficial effects of this utility model are: 1. This patent utilizes the heat energy of waste heat fluid for primary heating of soft water, and then uses steam to reheat it to the required temperature for insulation through a shell-and-tube heat exchanger, thereby reducing the pressure of the heat pump and recovering heat energy. 2. Ensure the temperature of the insulation and the outlet water, and ensure the quality of sterilization and the temperature of the supplied water; 3. It is automated, enabling automatic heat exchange, water replenishment, heat preservation, and pollution prevention, thus improving the degree of control. The heat exchange and water output are interlocked to control the heat preservation time. 4. The steam control of the shell-and-tube heat exchanger adopts a steam regulating valve, which can regulate the amount of steam while ensuring a slight positive pressure in the hot water tank to prevent backflow and contamination. 5. The temperature and conductivity probe can monitor the outlet water temperature and conductivity, ensuring the quality of the hot soft water and preventing waste heat fluid from corroding the heat exchange device and causing pollution to the hot soft water. Attached Figure Description

[0017] Figure 1 This is a schematic diagram of the system connection of this utility model; In the diagram: 1. Waste heat fluid pump; 2. Tail gas drain valve; 3. Waste heat fluid temperature probe; 4. Drain valve; 5. Shell and tube heat exchanger; 6. Plate heat exchanger; 7. Soft water regulating valve; 8. Soft water flow meter; 9. Temperature conductivity probe; 10. Steam ejector steam valve; 11. Hot water tank temperature probe; 12. Hot water pump; 13. Hot water tank level probe; 14. Steam trap; 15. Steam regulating valve; 16. Waste heat fluid level gauge. Detailed Implementation

[0018] The embodiments will be further described below with reference to the accompanying drawings.

[0019] like Figure 1 As shown in the preferred embodiment 1, a heat energy recovery system for preparing recycled hot water using CIP waste water includes a wastewater tank for recycling CIP waste water. The wastewater tank is equipped with a waste heat fluid level gauge 16. When the waste heat fluid level gauge 16 detects that the liquid level has reached a set value, the heat energy recovery module and the first-stage heating module are started through the control system, and the heat preservation heating module and the hot water pump 12 are turned off. The heat recovery module includes a plate heat exchanger 6. Waste heat fluid is input into one end of the plate heat exchanger 6 through a waste heat fluid pump 1, and soft water is input into the other end of the plate heat exchanger 6 through a soft water regulating valve 7. The soft water and the waste heat fluid exchange heat in the plate heat exchanger 6. After being heated in the plate heat exchanger 6, the soft water flows into the first-stage heating module. The primary heating module includes a shell-and-tube heat exchanger 5. Steam is input into one end of the shell-and-tube heat exchanger 5 through a steam regulating valve 15, and heated soft water is input into the other end of the shell-and-tube heat exchanger 5. The heated soft water and steam exchange heat in the shell-and-tube heat exchanger 5, and the heated soft water is then passed into a hot water tank for storage. The hot water tank is equipped with a hot water tank level probe 13. When the hot water tank level probe 13 detects that the liquid level has reached the set value, the heat recovery module and the first-stage heating module are shut down through the control system, and the heat preservation heating module is turned on. The heat preservation and heating module includes a steam ejector and a hot water tank temperature probe 11 located inside the hot water tank. The steam ejector inputs steam through the steam ejector steam valve 10. The hot water tank temperature probe 11 is linked with the steam ejector steam valve 10 through the control system and is timed by the control system. After the heat preservation time is up, the hot water pump 12 is turned on to supply water to the system.

[0020] The liquid level condition for starting heat preservation can be set to be greater than 1 / 2 of the hot water pump's 12-hour capacity, ensuring that there is always water for heat preservation for more than half an hour.

[0021] The waste heat fluid enters the sewage discharge module after heat exchange in the plate heat exchanger 6. The sewage discharge module includes a main pipe connected to the waste heat fluid outlet of the plate heat exchanger 6. A branch is connected in parallel on the other side of the main pipe. One branch is connected to the exhaust gas treatment system through the exhaust gas drain valve 2, and the other branch is connected to the sewage discharge well through the sewage discharge valve 4.

[0022] The main pipe is equipped with a waste heat fluid temperature probe 3 to monitor the temperature of the waste heat fluid after heat exchange, and the tail gas drain valve 2 and the drain valve 4 are both linked with the waste heat fluid temperature probe 3 through the control system. When the waste heat fluid temperature probe 3 detects that the temperature is higher than the set value, the exhaust gas drain valve 2 opens and the drain valve 4 closes. When the waste heat fluid temperature probe 3 detects a temperature not higher than the set value, the exhaust gas drain valve 2 closes and the sewage discharge valve 4 opens. In some special fields, the waste heat fluid temperature probe 3 can be used to determine the temperature of the waste heat fluid for other purposes. If the temperature is still relatively high, it can enter the exhaust gas treatment system; if the temperature is low, it can be directly discharged into the sewage discharge well.

[0023] The condensate from the steam in the shell-and-tube heat exchanger 5 is incorporated into the softened water after secondary heating via a steam trap 14, thus avoiding water waste.

[0024] The soft water regulating valve 7 is equipped with a soft water flow meter 8 at its input end to monitor the soft water flow. The soft water flow meter 8 is linked with the soft water regulating valve 7 through a control system.

[0025] The shell-and-tube heat exchanger 5 is equipped with a temperature and conductivity probe 9 at the soft water output end to monitor the temperature and conductivity of the soft water after secondary heating.

[0026] The temperature conductivity probe 9 is linked with the heat recovery module and the primary heating module through the control system. When the temperature is below 85℃, the temperature conductivity probe 9 increases the flow rate of the steam regulating valve 15 in the first-stage heating module through the control system. When the temperature is above 95℃, the temperature conductivity probe 9 decreases the flow rate of the steam regulating valve 15 in the first-stage heating module through the control system. This controls the temperature of the hot water after heating, avoids heat energy waste, and ensures the temperature requirements for subsequent heat preservation, reducing the pressure on the heat preservation and heating module. The heat preservation and heating module mainly plays an auxiliary role in maintaining the temperature.

[0027] When the conductivity exceeds 10 μs / cm for more than 10 seconds, the control system shuts down the heat recovery module and the primary heating module. Soft water typically has a conductivity of 0. When the conductivity exceeds 10 μs / cm for more than 10 seconds, a malfunction in the heat recovery process is highly likely. For example, in applications where the waste heat fluid has a high conductivity, typically >10000 μs / cm, the plate heat exchanger 6 may experience perforation.

[0028] During heat preservation, the set temperature of the hot water tank temperature probe 11 is 85℃. When the temperature detected by the hot water tank temperature probe 11 is lower than 85℃, the hot water tank temperature probe 11 opens the steam valve 10 of the steam ejector through the control system to heat the water until the temperature is not lower than 85℃, and the control system times the temperature. The heat preservation time is not less than 30 minutes. The heat preservation is to meet the sterilization conditions of the hot water.

[0029] During water supply, the hot water tank temperature probe 11 is linked with the steam valve 10 of the steam ejector and the hot water pump 12 through the control system. When the temperature detected by the hot water tank temperature probe 11 is lower than 85℃, the hot water tank temperature probe 11 shuts down the hot water pump 12 through the control system and opens the steam valve 10 of the steam ejector to heat the water until the temperature is not lower than 85℃. Then, the control system restarts the hot water pump 12 and closes the steam valve 10 of the steam ejector, ensuring that the temperature of the outlet water is not lower than 85℃.

[0030] The control system is an industrial PLC control system. Existing industrial PLC control systems within the factory can be used to achieve control and timing.

[0031] The working principle of this utility model: This heat recovery technology has functions such as heat recovery, heating, pollution detection, and automatic start-stop. When the waste heat fluid is collected to a certain level, the waste heat fluid level gauge 16 determines the level and controls the waste heat fluid pump 1 to run. At the same time, the soft water regulating valve 7 is opened, and the soft water flow meter 8 controls the soft water regulating valve 7 to reach the set flow rate. Heat energy recovery begins through the plate heat exchanger 6. The purpose of the steam regulating valve 15 is usually to regulate the steam flow. This technology requires steam to be supplied to maintain a slight positive pressure in the hot water tank and cannot completely block the steam. Therefore, the temperature conductivity probe 9 maintains a high temperature, usually above 85°C, when heat recovery stops, and the steam regulating valve 15 is in the closed state. When heat recovery begins, the temperature of the temperature conductivity probe 9 will drop to 85°C. At this time, the control steam regulating valve 15 will open to heat the recovered hot water to above 85°C through the shell-and-tube heat exchanger 5. At the same time, the temperature conductivity probe will determine the conductivity of the recovered hot water. When the conductivity is >10μs / cm for more than 10 seconds, the entire system will stop. This is because the application scenario of this technology is that the waste heat fluid has a high conductivity, usually >10000μs / cm. Soft water usually has a conductivity of 0. Check whether the plate heat exchanger 6 is perforated. During heat recovery, the hot water pump 12 is locked and stopped as soon as the soft water regulating valve 7 is opened to prevent the recovered hot water from being used while it is being supplied, thus failing to reach the heat preservation time. After the soft water regulating valve 7 is closed, the hot water tank level probe 13 and hot water tank temperature probe 11 determine whether the usage conditions have been met. If the temperature is not right, the hot water tank temperature probe 11 controls the steam valve 10 of the steam ejector to heat the hot water in the storage tank with the steam ejector. After the usage conditions are met, the hot water pump 12 is turned on to pump the recovered hot water to the usage location.

Claims

1. A heat energy recovery system for preparing recycled hot water from CIP wastewater, comprising a wastewater tank for recycling CIP wastewater, characterized in that, The wastewater tank is equipped with a waste heat fluid level gauge (16). When the waste heat fluid level gauge (16) detects that the liquid level has reached the set value, the heat recovery module and the first-level heating module are started through the control system, and the heat preservation heating module and the hot water pump (12) are turned off. The heat recovery module includes a plate heat exchanger (6). One end of the plate heat exchanger (6) is fed with waste heat fluid through a waste heat fluid pump (1), and the other end of the plate heat exchanger (6) is fed with soft water through a soft water regulating valve (7). The soft water and the waste heat fluid exchange heat in the plate heat exchanger (6). The soft water flows into the first-stage heating module after being heated in the plate heat exchanger (6). The primary heating module includes a shell-and-tube heat exchanger (5). Steam is input into one end of the shell-and-tube heat exchanger (5) through a steam regulating valve (15), and heated soft water is input into the other end of the shell-and-tube heat exchanger (5). The heated soft water and steam exchange heat in the shell-and-tube heat exchanger (5), and the heated soft water is then passed into a hot water tank for storage. The hot water tank is equipped with a hot water tank level probe (13). When the hot water tank level probe (13) detects that the liquid level has reached the set value, the heat recovery module and the first-level heating module are shut down through the control system, and the heat preservation heating module is turned on. The heat preservation and heating module includes a steam ejector and a hot water tank temperature probe (11) located inside the hot water tank. The steam ejector inputs steam through the steam ejector steam valve (10). The hot water tank temperature probe (11) is linked with the steam ejector steam valve (10) through the control system and is timed by the control system. After the heat preservation time is up, the hot water pump (12) is turned on to supply water to the system.

2. The heat energy recovery system for preparing recycled hot water using CIP wastewater according to claim 1, characterized in that, The waste heat fluid enters the sewage discharge module after heat exchange through the plate heat exchanger (6). The sewage discharge module includes a main pipe connected to the waste heat fluid outlet of the plate heat exchanger (6). A branch is connected in parallel on the other side of the main pipe. One branch is connected to the tail gas treatment system through the tail gas drain valve (2), and the other branch is connected to the sewage discharge well through the sewage discharge valve (4).

3. A heat energy recovery system for preparing recycled hot water using CIP wastewater according to claim 2, characterized in that, The main pipe is equipped with a waste heat fluid temperature probe (3) to monitor the temperature of the waste heat fluid after heat exchange, and the tail gas drain valve (2) and the sewage valve (4) are linked with the waste heat fluid temperature probe (3) through the control system. When the waste heat fluid temperature probe (3) detects that the temperature is higher than the set value, the exhaust gas drain valve (2) opens and the drain valve (4) closes. When the waste heat fluid temperature probe (3) detects that the temperature is not higher than the set value, the exhaust gas drain valve (2) is closed and the sewage valve (4) is opened.

4. A heat energy recovery system for preparing recycled hot water using CIP wastewater according to claim 1, characterized in that, The condensate from the steam heat exchanger (5) is incorporated into the softened water after secondary heating through the steam trap (14).

5. A heat energy recovery system for preparing recycled hot water using CIP wastewater according to claim 1, characterized in that, The soft water regulating valve (7) is equipped with a soft water flow meter (8) at its input end to monitor the soft water flow. The soft water flow meter (8) is linked with the soft water regulating valve (7) through the control system.

6. A heat energy recovery system for preparing recycled hot water using CIP wastewater according to claim 1, characterized in that, The shell-and-tube heat exchanger (5) is equipped with a temperature and conductivity probe (9) at the soft water output end to monitor the temperature and conductivity of the soft water after secondary heating.

7. A heat energy recovery system for preparing recycled hot water using CIP wastewater according to claim 6, characterized in that, The temperature conductivity probe (9) is linked with the heat recovery module and the primary heating module through the control system; When the temperature is below 85°C, the temperature conductivity probe (9) increases the flow rate of the steam regulating valve (15) in the first-stage heating module through the control system. When the temperature is above 95°C, the temperature conductivity probe (9) decreases the flow rate of the steam regulating valve (15) in the first-stage heating module through the control system. When the conductivity is greater than 10 μs / cm for more than 10 seconds, the control system shuts down the heat recovery module and the primary heating module.

8. A heat energy recovery system for preparing recycled hot water using CIP wastewater according to claim 1, characterized in that, During heat preservation, the set temperature of the hot water tank temperature probe (11) is 85°C. When the temperature monitored by the hot water tank temperature probe (11) is lower than 85°C, the hot water tank temperature probe (11) opens the steam valve (10) of the steam injector through the control system to heat until the temperature is not lower than 85°C, and the heat preservation time is not less than 30 minutes through the control system.

9. A heat energy recovery system for preparing recycled hot water using CIP wastewater according to claim 1, characterized in that, During water supply, the hot water tank temperature probe (11) is linked with the steam valve (10) of the steam ejector and the hot water pump (12) through the control system. When the temperature detected by the hot water tank temperature probe (11) is lower than 85°C, the hot water tank temperature probe (11) shuts down the hot water pump (12) through the control system and opens the steam valve (10) of the steam ejector to heat until the temperature is not lower than 85°C. The control system then restarts the hot water pump (12) and closes the steam valve (10) of the steam ejector.

10. A heat energy recovery system for preparing recycled hot water using CIP wastewater according to any one of claims 1 to 9, characterized in that, The control system is an industrial PLC control system.