A water collecting structure of a cooling tower

By installing heating pipes and temperature controllers in the cooling tower's water collection tank, the problems of water freezing and debris blockage in low-temperature environments are solved, achieving convenient cleaning.

CN225000314UActive Publication Date: 2026-11-20WUXI ARK FLUID TECH
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202521985212.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-09-16
Publication Date
2026-11-20
Estimated Expiration
2035-09-16

AI Technical Summary

Technical Problem

Existing cooling tower water collection structures are prone to water freezing in low-temperature environments, have low cleaning efficiency and are easily clogged, and their open design makes them susceptible to the introduction of debris.

Method used

A heating element and a temperature controller are installed in the water collection tank. The heating element is operated by the temperature controller to prevent freezing, and a scraping device is provided to remove algae and prevent debris from entering.

Benefits of technology

It effectively prevents water from freezing, improves cleaning efficiency, prevents debris from clogging the system, and simplifies the cleaning process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225000314U_ABST
    Figure CN225000314U_ABST
Patent Text Reader

Abstract

The utility model discloses a water collecting structure of cooling tower, it includes the water collecting tank, the top fixed of water collecting tank is connected with the heat preservation frame through bolt, the inside fixed connection of heat preservation frame has fixed frame, the inside fixed connection of fixed frame has heating pipe, the outer wall fixed connection of heat preservation frame has temperature controller, the front surface inlay of temperature controller has display screen, the front surface inlay of temperature controller has button, the top of heat preservation frame is connected with the apron through the pivot, this kind of water collecting structure of cooling tower, through the heat preservation frame with heating pipe of bolt connection in the top of water collecting tank, like this can be in the case where temperature is lower, heating pipe emits heat, thereby prevents the water flow inside water collecting tank from freezing, and the scraper and the scraper rod that can scrape the inside of the device and treat the water collecting tank inner wall are equipped, prevent the growth of algae material.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the technical field of cooling tower water collection devices, specifically a water collection structure for a cooling tower. Background Technology

[0002] The water collection structure of a cooling tower is an important component of the cooling tower system. Its main function is to collect the water that has cooled down after passing through the packing and air through heat and mass exchange, and to transport it to the suction port of the circulating water pump to complete the entire circulating cooling process. The water collection structure plays a decisive role in ensuring the stable operation of the cooling tower, improving cooling efficiency, preventing water pump cavitation, and reducing water waste.

[0003] Existing technology patent document CN203785528U discloses a novel water collection tank structure for a closed-loop cooling tower, comprising at least one water collection tank unit. The water collection tank unit is rectangular and includes multiple side plates formed by splicing together and a base plate spliced ​​with the side plate unit. At least one of the side plates has a step, with one end of the step connected to the side plate and the other end connected to the base plate along its width. Compared to existing water collection tank structures, this invention reduces the volume of the water tank, thereby saving water resources. Furthermore, its stepped maintenance access design makes maintenance and cleaning of the water tank more convenient.

[0004] Although the device has many beneficial effects, it still has the following problems: When used in low-temperature environments, the water inside the collection tank may freeze, making it difficult to drain and use the water. Also, the open design of the collection tank allows external debris to enter, causing blockages in the water pipes. Furthermore, the device lacks a scraping device inside, so cleaning equipment is required to deal with algae growing on the inner wall of the tank, resulting in poor cleaning efficiency. Utility Model Content

[0005] The purpose of this section is to outline some aspects of the embodiments of this utility model and to briefly introduce some preferred embodiments. Simplifications or omissions may be made in this section, as well as in the abstract and title of this application, to avoid obscuring the purpose of these documents; however, such simplifications or omissions should not be used to limit the scope of this utility model.

[0006] 1. Technical problems to be solved:

[0007] To address the aforementioned issues, such as the water inside the collection tank freezing when used in low-temperature environments, hindering water drainage and use, the open design of the collection tank allowing external debris to enter and clog water pipes, and the lack of a scraping device inside the device requiring additional cleaning equipment to treat algae growth on the tank walls, resulting in poor cleaning efficiency.

[0008] Therefore, the purpose of this utility model is to provide a water collection structure for a cooling tower. By installing heating pipes inside the insulation frame and connecting them to the circuit board via a temperature controller, the heating pipes can be operated to generate heat, thereby heating the inside of the water collection tank and preventing the water inside the tank from freezing. Covering the tank with a cover plate can also prevent debris from falling into the water collection tank. Furthermore, by installing a scraping device inside the water collection tank, algae growing on the inner wall of the tank can be scraped off with a scraper and scraper, eliminating the need for additional tools and making cleaning convenient.

[0009] 2. Technical Solution:

[0010] To solve the above-mentioned technical problems, according to one aspect of the present invention, the present invention provides the following technical solution:

[0011] A water collection structure for a cooling tower includes a water collection tank. An insulation frame is bolted to the top of the water collection tank. A fixing frame is fixedly connected inside the insulation frame. A heating tube is fixedly connected inside the fixing frame. A temperature controller is fixedly connected to the outer wall of the insulation frame. A display screen and a button are embedded in the front of the temperature controller. A cover plate is connected to the top of the insulation frame via a pivot. An opening / closing handle is fixedly connected to the top of the cover plate. A snap-fit ​​block is fixedly connected to the front of the cover plate. A slotted block engages with the surface of the snap-fit ​​block. The insulation frame is fixedly connected to the back of the slotted block. The heating tube is electrically connected to a circuit board via a connecting wire. The circuit board is electrically connected to the temperature controller via a connecting wire. The temperature controller is electrically connected to another circuit board via a connecting wire. The other circuit board is electrically connected to the display screen and the button via a connecting wire. The temperature controller is electrically connected to an external distribution box via a connecting wire. The distribution box is electrically connected to an external control panel via a connecting wire. A second sliding groove is fixedly connected to the inner wall of the water collection tank.

[0012] In a preferred embodiment of the water collection structure of a cooling tower according to this utility model, a first slider is slidably connected inside the second slide groove, a scraper is fixedly connected to the top of the first slider, a crossbar is fixedly connected to the top of the scraper, a second movable handle is fixedly connected to the top of the crossbar, a third slide groove is provided on the side of the scraper, a second slider is slidably connected inside the third slide groove, a scraper is fixedly connected to the side of the second slider, and a first movable handle is fixedly connected to the front of the scraper.

[0013] As a preferred embodiment of the water collection structure of the cooling tower of this utility model, the surface of the water collection tank is fixedly connected with an anti-corrosion outer frame, and the inside of the water collection tank is provided with a first sliding groove. The anti-corrosion outer frame can prevent corrosion from occurring on the surface of the water collection tank.

[0014] In a preferred embodiment of the water collection structure of a cooling tower according to this utility model, a sliding rod is slidably connected inside the first sliding groove, and a filter plate is fixedly connected to the side of the sliding rod. The filter plate can be easily replaced by using the sliding rod slidably connected inside the first sliding groove.

[0015] As a preferred embodiment of the water collection structure of the cooling tower of this utility model, the bottom of the water collection tank is fixedly connected to a water suction pool, and the front of the water suction pool is fixedly connected to a first connecting flange. The water suction pool is an important part of the entire water collection structure, and its main function is to receive the cooling water dripping from the packing.

[0016] As a preferred embodiment of the water collection structure of the cooling tower of this utility model, the side of the water collection tank is connected to a second connecting flange by bolts, and the inside of the second connecting flange is fixedly connected to a water inlet pipe. Through various water pipes with different functions, water can be conveniently introduced, drained, and excessive water overflow can be prevented.

[0017] As a preferred embodiment of the water collection structure of a cooling tower according to the present invention, an overflow pipe is fixedly connected to the side of the water collection tank, and a drain pipe is fixedly connected to the bottom of the water collection tank.

[0018] 3. Beneficial effects:

[0019] Compared with the prior art, the beneficial effects of this utility model are:

[0020] The water collection structure of this cooling tower is as follows: an insulation frame is bolted to the top of the water collection tank, and a heating pipe is installed inside the insulation frame. When the device needs to be used in low-temperature weather, the circuit board inside the temperature controller can be activated by pressing a button and an electrical signal will be transmitted. The temperature controller will then activate the heating pipe, which will heat up and keep the temperature inside the water collection tank from freezing. At the same time, when the heating pipe is in use, the cover plate can be closed to slow down the heat dissipation and prevent debris from falling into the water collection tank.

[0021] The water collection structure of this type of cooling tower: through the second sliding groove fixedly connected inside the water collection tank, the inner wall surface of the water collection plate can be scraped off by the crossbar and the first slider sliding scraper, so as to scrape off the algae attached to the inner wall of the water collection tank. The scraper can also scrape off the inner side wall of the water collection plate. There is no need to carry additional cleaning tools for cleaning, and the cleaning effect is good. Attached Figure Description

[0022] To more clearly illustrate the technical solutions of the embodiments of this utility model, the present utility model will be described in detail below with reference to the accompanying drawings and detailed embodiments. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort. Among them:

[0023] Figure 1 This is a schematic diagram of the overall structure of the water collection structure of a cooling tower according to the present invention;

[0024] Figure 2 This is a schematic diagram of the anti-corrosion frame structure of the water collection structure of a cooling tower according to the present invention;

[0025] Figure 3 This is a schematic diagram of the water collection tank structure of a cooling tower according to the present invention;

[0026] Figure 4 This is a schematic diagram of the water intake pool structure of a cooling tower according to the present invention;

[0027] Figure 5 This is a schematic diagram of the insulation frame structure of the water collection structure of a cooling tower according to the present invention;

[0028] Figure 6 This is a schematic diagram of the sliding rod structure of the water collection structure of a cooling tower according to the present invention.

[0029] The following are the labels in the diagram: 1. Water collection tank; 2. Corrosion-resistant outer frame; 3. Overflow pipe; 4. Drain pipe; 5. Inlet pipe; 6. Suction tank; 7. First connecting flange; 8. Second connecting flange; 9. First slide groove; 10. Slide rod; 11. Filter plate; 12. Insulation frame; 13. Temperature controller; 14. Display screen; 15. Button; 16. Fixing frame; 17. Heating tube; 18. Cover plate; 19. Opening handle; 20. Buckle block; 21. Slot block; 22. Second slide groove; 23. First slider; 24. Scraper rod; 25. Third slide groove; 26. Second slider; 27. Crossbar; 28. Scraper; 29. ​​First moving handle; 30. Second moving handle. Detailed Implementation

[0030] To make the above-mentioned objectives, features and advantages of this utility model more apparent and understandable, the specific embodiments of this utility model will be described in detail below with reference to the accompanying drawings.

[0031] This utility model is described in detail with reference to the schematic diagrams. When describing the embodiments of this utility model, for ease of explanation, the cross-sectional views illustrating the device structure may be partially enlarged, not adhering to the usual scale. Furthermore, the schematic diagrams are merely examples and should not be construed as limiting the scope of protection of this utility model. In actual manufacturing, the three-dimensional spatial dimensions of length, width, and depth should be included.

[0032] The orientation or positional relationship indicated in the terminology is based on the orientation or positional relationship shown in the accompanying drawings and is only for the convenience of describing the present invention and simplifying the description. It is not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention.

[0033] The term "connection method" should be interpreted broadly. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be a connection within two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0034] The embodiments of this utility model will now be described in further detail with reference to the accompanying drawings.

[0035] This utility model provides an overall structural schematic diagram of a water collection structure embodiment for a cooling tower, including:

[0036] Please see Figures 1-6This embodiment of a cooling tower water collection structure includes a water collection tank 1. An insulation frame 12 is bolted to the top of the water collection tank 1. The insulation frame 12 prevents the heat emitted by the heating pipe 17 from dissipating too quickly, maintaining a relatively even temperature inside the water collection tank 1. A fixing frame 16 is welded inside the insulation frame 12, and the heating pipe 17 is bolted to the inside of the fixing frame 16. The heating pipe 17 dissipates heat, preventing the temperature inside the water collection tank 1 from becoming too low and preventing the water inside the water collection tank 1 from freezing. A temperature controller 13 is welded to the outer wall of the insulation frame 12. A display screen 14 is embedded in the front of the temperature controller 13, and a button 15 is also embedded in the front of the temperature controller 13. Pressing the button 15 connects the circuit board inside the temperature controller 13 and transmits electrical signals, allowing operation of the temperature controller 13. The display screen 14 also transmits electrical signals through the circuit board inside the temperature controller 13, displaying temperature data. The insulation frame... The top of the 12 is connected to a cover plate 18 via a pivot. The cover plate 18 can seal the water collection tank 1, preventing debris from falling into the tank and clogging the water pipes. An opening and closing handle 19 is welded to the top of the cover plate 18. A snap-fit ​​block 20 is welded to the front of the cover plate 18, and a slot block 21 engages with the surface of the snap-fit ​​block 20. The insulation frame 12 is welded to the back of the slot block 21. The cooperation between the slot block 21 and the opening block allows the cover plate 18 to be tightly assembled, ensuring good sealing. Heating element 17 is electrically connected to a circuit board via a connecting wire. The circuit board is electrically connected to the temperature controller via a connecting wire. The temperature controller is electrically connected to another circuit board via a connecting wire. The other circuit board is electrically connected to the display screen 14 and the button 15 via a connecting wire. The temperature controller is electrically connected to an external distribution box via a connecting wire. The distribution box is electrically connected to an external control panel via a connecting wire. The control panel refers to a control device with a control switch. A second sliding groove 22 is fixedly connected to the inner wall of the water collection tank 1.

[0037] It is worth noting that, in order to facilitate the scraping operation on the inner wall of the water-collecting plant, specifically, a first slider 23 is slidably connected inside the second sliding groove 22. A scraper 24 is welded to the top of the first slider 23. By pulling or pushing the second moving handle 30, the scraper 24 can be moved. One side of the scraper 24 is in contact with one side of the water-collecting tank 1, thereby enabling the scraping operation on the currently contacted surface. A crossbar 27 is welded to the top of the scraper 24, and a second moving handle 30 is welded to the top of the crossbar 27. A third sliding groove 25 is opened on the side of the scraper 24. The third chute 25 is internally connected to a second slider 26, and a scraper 28 is fixedly connected to the side of the second slider 26. A first movable handle 29 is welded to the front of the scraper 28. After the crossbar 27 is moved to a position where it cannot move, that is, when the crossbar 27 is close to the inner side wall of the water collection tank 1, the scraper 28 can be moved by the first movable handle 29. The scraper 28 moves up and down, and the top of the scraper 28 has an inverted triangular structure, which can easily scrape off algae or attached impurities from the inner side wall of the water collection tank 1. After scraping off, the debris can be picked up by the staff with tongs, making cleaning relatively convenient.

[0038] Next, in order to prevent the surface of the water collection tank 1 from being corroded under long-term water ingress, specifically, the surface of the water collection tank 1 is welded with an anti-corrosion outer frame 2, which is made of aluminum alloy. Through the isolation effect of aluminum alloy and water, water flow is directly prevented from adhering to the surface of the water collection tank 1. The inside of the water collection tank 1 is provided with a first sliding groove 9.

[0039] Meanwhile, to facilitate the installation of the filter plate 11, specifically, a slide rod 10 is slidably connected inside the first slide groove 9, and the filter plate 11 is welded to the side of the slide rod 10.

[0040] Furthermore, in order to maintain the water collection effect of the water collection structure, specifically, a water suction tank 6 is welded to the bottom of the water collection tank 1, and a first connecting flange 7 is fixedly connected to the front of the water suction tank 6 by bolts.

[0041] It is worth noting that, in order to facilitate the connection of various water pipes, specifically, the side of the water collection tank 1 is bolted to a second connecting flange 8, and the inside of the second connecting flange 8 is welded to a water inlet pipe 5.

[0042] Finally, in order to maintain the water flow rate inside the water collection tank 1 at a suitable capacity, specifically, an overflow pipe 3 is welded to the side of the water collection tank 1, and a drain pipe 4 is welded to the bottom of the water collection tank 1.

[0043] In addition, the circuits, electronic components and modules involved in this utility model are all existing technologies, which can be fully implemented by those skilled in the art, and need not be elaborated upon. The content protected by this utility model does not involve any improvement to the internal structure and method.

[0044] Combination Figures 1-6 The water collection structure of a cooling tower according to this embodiment is used in the following specific process:

[0045] 1: When using the water collection structure of this type of cooling tower, the device needs to be installed on the required cooling tower first. After installation, connect the overflow pipe 3, the inlet pipe 5, the drain pipe 4 to the first connecting flange 7 on the front of the water intake tank 6 and it can be put into use. The water flow inside the water collection tank can be kept at a suitable value through the action of each water pipe, without being too much or too little.

[0046] 2: When the temperature is low during use, the device can be started and powered on through the control panel. Then, by pressing button 15, the circuit board is connected and an electrical signal is transmitted, which also connects the circuit board of heating tube 17, so that heating tube 17 emits heat to prevent the temperature inside the water collection tank 1 from getting too low. When in use, the cover plate 18 is closed, which can prevent debris in the air from falling into the water collection tank 1 and also prevent the heat from dissipating too quickly when using heating tube 17, thus providing a better heat preservation effect.

[0047] 3. When the water collection structure needs maintenance, the water inside must be drained first. After draining the water, the scraper 24 can be moved by pushing or pulling the second moving handle 30. One side of the scraper 24 is attached to one side of the water collection tank 1, so that the currently attached surface can be scraped. After the crossbar 27 is moved to the position where it cannot move, that is, when the crossbar 27 is close to the inner side wall of the water collection tank 1, the scraper 28 can be moved by the first moving handle 29. The scraper 28 moves up and down, and the top of the scraper 28 has an inverted triangular structure, which can easily scrape off algae or attached impurities from the inner side of the water collection tank 1. After scraping, the debris can be picked up by the staff with tongs. The cleaning is relatively convenient and no additional scraping tools are required.

[0048] Although the present invention has been described above with reference to embodiments, various modifications can be made and components can be replaced with equivalents without departing from the scope of the present invention. In particular, as long as there is no structural conflict, the features in the embodiments disclosed in this invention can be combined with each other in any way. The lack of an exhaustive description of these combinations in this specification is merely for the sake of brevity and resource conservation. Therefore, the present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.

Claims

1. A water collection structure for a cooling tower, characterized in that, The system includes a water collection tank (1), the top of which is fixedly connected to an insulation frame (12) by bolts. A fixing frame (16) is fixedly connected inside the insulation frame (12), and a heating tube (17) is fixedly connected inside the fixing frame (16). A temperature controller (13) is fixedly connected to the outer wall of the insulation frame (12). A display screen (14) is embedded in the front of the temperature controller (13), and a button (15) is embedded in the front of the temperature controller (13). A cover plate (18) is connected to the top of the insulation frame (12) via a pivot. An opening and closing handle (19) is fixedly connected to the top of the cover plate (18), and a buckle block (2) is fixedly connected to the front of the cover plate (18). 0), the surface of the buckle block (20) is snapped with a slot block (21), the back of the slot block (21) is fixedly connected to the heat insulation frame (12), the heating tube (17) is electrically connected to a circuit board through a connecting line, the circuit board is electrically connected to the temperature controller (13) through a connecting line, the temperature controller (13) is electrically connected to another circuit board through a connecting line, the other circuit board is electrically connected to the display screen (14) and the button (15) through a connecting line, the temperature controller (13) is electrically connected to an external distribution box through a connecting line, the distribution box is electrically connected to an external control panel through a connecting line, and the inner wall of the water collection tank (1) is fixedly connected with a second sliding groove (22).

2. The water collection structure of the cooling tower according to claim 1, characterized in that, The second slide groove (22) is slidably connected to the inside of the first slider (23), the top of the first slider (23) is fixedly connected to the scraper (24), the top of the scraper (24) is fixedly connected to the crossbar (27), the top of the crossbar (27) is fixedly connected to the second moving handle (30), the side of the scraper (24) is provided with a third slide groove (25), the inside of the third slide groove (25) is slidably connected to the second slider (26), the side of the second slider (26) is fixedly connected to the scraper (28), and the front of the scraper (28) is fixedly connected to the first moving handle (29).

3. The water collection structure of the cooling tower according to claim 2, characterized in that, The surface of the water collection tank (1) is fixedly connected to an anti-corrosion outer frame (2), and the inside of the water collection tank (1) is provided with a first sliding groove (9).

4. The water collection structure of the cooling tower according to claim 3, characterized in that, The first slid groove (9) is slidably connected to a slide rod (10), and a filter plate (11) is fixedly connected to the side of the slide rod (10).

5. The water collection structure of the cooling tower according to claim 4, characterized in that, The bottom of the water collection tank (1) is fixedly connected to a water suction tank (6), and the front of the water suction tank (6) is fixedly connected to a first connecting flange (7).

6. The water collection structure of the cooling tower according to claim 5, characterized in that, The side of the water collection tank (1) is connected to a second connecting flange (8) by bolts, and the water inlet pipe (5) is fixedly connected inside the second connecting flange (8).

7. The water collection structure of the cooling tower according to claim 6, characterized in that, An overflow pipe (3) is fixedly connected to the side of the water collection tank (1), and a drain pipe (4) is fixedly connected to the bottom of the water collection tank (1).

Citation Information

Patent Citations

  • Novel water collecting channel structure of closed cooling tower

    CN203785528U