A boiler water working fluid sampling device

By installing a traction pipe and a sampling pipe inside the boiler water delivery pipeline, and utilizing a dual-guide structure to reduce flow velocity and seal the system, the problem of damage to the boiler water sampling device due to high-speed flow was solved, achieving stable sampling and equipment protection.

CN225000795UActive Publication Date: 2026-11-20ZHANGJIAGANG JIANGNENG INSTR MECHANICAL EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522151700.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-10-11
Publication Date
2026-11-20
Estimated Expiration
2035-10-11

AI Technical Summary

Technical Problem

Existing boiler water working fluid sampling devices are easily damaged by impact during high-flow-rate boiler water transportation, resulting in a reduced service life.

Method used

A boiler water working medium sampling device was designed. By setting up a traction pipe and a sampling pipe in the boiler water delivery pipeline, the flow rate is reduced by a dual guiding structure, and leakage is prevented by a sealing structure, so as to achieve stable sampling of boiler water.

Benefits of technology

It effectively protects the sampling device, avoids damage caused by the impact of high-speed flowing boiler water, and improves the service life and sampling timeliness of the sampling equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225000795U_ABST
    Figure CN225000795U_ABST
Patent Text Reader

Abstract

The utility model relates to a boiler water sampling equipment technical field discloses a boiler water working quality sampling device, including the boiler water delivery pipe, the inside installation of boiler water delivery pipe has first connecting pipe, the outside installation of first connecting pipe has the traction pipeline, the middle part swing sleeve joint of traction pipeline has second connecting pipe, the outside fixed limit board of second connecting pipe, the outside sleeve joint of second connecting pipe has the round clamp cover, the inside fixed connection of second connecting pipe has the sampling pipe. The boiler water working quality sampling device, through the third connecting pipe sleeve joint in the outside of second connecting pipe, when the equipment stops the sampling of boiler water, rotates the round clamp cover, and the round clamp cover drives the third connecting pipe to stop and sample the pipe alignment, and the spring pushes the sealing plug to move outward at the same time, ensures the sealing of third connecting pipe inside, under the action of double seal, avoids the leakage when the boiler water sampling.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the technical field of boiler water sampling equipment, specifically a boiler water working fluid sampling device. Background Technology

[0002] During boiler operation, in addition to strict monitoring of steam quality, there are also strict requirements for boiler water quality. This requires that the samples extracted from the main water source be representative. After real-time sampling and analysis, the power plant adjusts the steam-water medium in a timely manner based on the sample quality to ensure the normal operation of the boiler and turbine. Key factors of the sampling system include: sampling point, material selection, system design, sampling time, sampling frequency, and the process of properly maintaining sample integrity before sample analysis.

[0003] Boiler water working medium refers to the working medium that realizes energy conversion and transfer. The boiler water working medium in a boiler is water and steam. The boiler relies on the phase change from water to steam to complete the entire process of heat absorption, heat transfer and work. Therefore, using boiler water and steam as a medium to carry heat out to do work, this medium is called boiler water working medium. In actual operation, in order to ensure that the quality of boiler water working medium meets the standards, it is necessary to conduct regular sampling tests on boiler water working medium.

[0004] Typically, when sampling and testing boiler water inside a boiler, a hole is made on the outside of the boiler water delivery pipe, and a sealed structure is designed to control the extraction device to extend into the boiler water delivery pipe so that the boiler water inside can be extracted. However, during the transmission of boiler water inside the pipe, the flow velocity of the boiler water is relatively high, which causes the sampling device to be impacted and damaged when it extends into the boiler water delivery pipe, resulting in a reduction in the service life of the sampling equipment. Therefore, we propose a boiler water working fluid sampling device. Utility Model Content

[0005] To address the shortcomings of existing boiler water working fluid sampling devices, this utility model provides a boiler water working fluid sampling device, which is equipped with a traction pipe installed inside a first connecting pipe. When boiler water is transported into the traction pipe, a sampling pipe is installed inside the traction pipe. Through dual guidance, the flow rate of boiler water transported into the third connecting pipe is reduced, thereby reducing damage to the extraction device and solving the problems mentioned in the background art.

[0006] This utility model provides the following technical solution: a boiler water working medium sampling device, including a boiler water conveying pipe, a first connecting pipe installed inside the boiler water conveying pipe, a traction pipe installed outside the first connecting pipe, a second connecting pipe movably sleeved in the middle of the traction pipe, a limit plate fixed outside the second connecting pipe, a circular sleeve sleeved outside the second connecting pipe, a sampling pipe fixedly connected inside the second connecting pipe, a third connecting pipe fixed outside the circular sleeve, and an extraction syringe for sampling boiler water installed at the end of the third connecting pipe.

[0007] Preferably, a first sealing sleeve is fitted over the connection between the boiler water supply pipe and the first connecting pipe for sealing, and the boiler water supply pipe is connected inside the boiler.

[0008] Preferably, the second connecting pipe is movably sleeved with a second sealing sleeve covering the outside of the traction pipe, and the outside of the traction pipe is movably sleeved with a threaded sleeve threaded onto the outside of the second sealing sleeve.

[0009] Preferably, the circular jacket is fitted over the outside of the second connecting tube, and a sealing sleeve is provided between the sampling tube and the circular jacket.

[0010] Preferably, both ends of the traction pipe extend into the interior of the first connecting pipe, the openings at both ends of the traction pipe extend into the interior of the first connecting pipe, and the ends of the traction pipe remain parallel to the interior of the first connecting pipe.

[0011] Preferably, the third connecting tube has an opening inside, which is connected to the sampling tube, and the sampling tube is installed obliquely inside the second connecting tube.

[0012] Preferably, a spring and a sealing plug are installed inside the third connecting tube, and a pin is installed at the extraction port at the front end of the extraction syringe, wherein the pin is in contact with the outside of the sealing plug.

[0013] Compared with existing boiler water working fluid sampling devices, this utility model has the following advantages: 1. The boiler water working medium sampling device is connected to the outside of the second connecting pipe through the third connecting pipe. When the device stops sampling the boiler water, the circular jacket is rotated. The circular jacket drives the third connecting pipe to stop aligning with the sampling pipe. At the same time, the spring pushes the sealing plug to move outward to ensure the seal inside the third connecting pipe. Under the action of double sealing, leakage is avoided when sampling boiler water.

[0014] 2. This boiler water working fluid sampling device extends into the first connecting pipe via a traction pipe, which pulls the boiler water flowing inside the first connecting pipe while ensuring that the pulled boiler water decelerates. Simultaneously, the sampling pipe extends into the second connecting pipe, where it again decelerates the boiler water to ensure continuous flow. This means that boiler water can be sampled in real time as it flows, improving the timeliness of boiler water sampling and avoiding impact damage to the sampling equipment when high-speed boiler water is extracted. Attached Figure Description

[0015] Figure 1 This is a schematic diagram of the main structure of the present utility model; Figure 2 This is a schematic cross-sectional view of the main body of this utility model; Figure 3 This is a cross-sectional view of the sampling structure of this utility model in the sampling state; Figure 4 This is a schematic diagram of the sealed state of the sampling structure of this utility model; Figure 5 This utility model Figure 1 Enlarged structural diagram at point A in the middle; Figure 6 This utility model Figure 2 Enlarged structural diagram at point B.

[0016] In the diagram: 1. Boiler water delivery pipe; 2. First connecting pipe; 3. First sealing sleeve; 4. Traction pipe; 5. Second connecting pipe; 6. Second sealing sleeve; 7. Threaded sleeve; 8. Limiting plate; 9. Sampling tube; 10. Circular jacket; 11. Third connecting pipe; 12. Spring; 13. Sealing plug; 14. Extraction syringe. Detailed Implementation

[0017] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0018] Please see Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 and Figure 6A boiler water working medium sampling device includes a boiler water delivery pipe 1, a first connecting pipe 2 installed inside the boiler water delivery pipe 1, and a traction pipe 4 installed outside the first connecting pipe 2. Both ends of the traction pipe 4 extend into the interior of the first connecting pipe 2. When boiler water flows inside the first connecting pipe 2, some boiler water can be transferred to the interior of the traction pipe 4. Due to the bend structure of the traction pipe 4, the flow rate of the boiler water is reduced. A second connecting pipe 5 is movably sleeved in the middle of the traction pipe 4. A limit plate 8 is fixed outside the second connecting pipe 5. A circular jacket 10 is sleeved outside the second connecting pipe 5. A sampling pipe 9 is fixedly connected to the inner side of the second connecting pipe 5. The sampling pipe 9 extracts the boiler water inside the second connecting pipe 5. A third connecting pipe 11 is fixed outside the circular jacket 10. An extraction syringe 14 for sampling boiler water is installed at the end of the third connecting pipe 11. The extraction syringe 14 performs sampling treatment on the boiler water.

[0019] Please see Figure 2 A first sealing sleeve 3 is fitted over the connection between the boiler water supply pipe 1 and the first connecting pipe 2 for sealing. The boiler water supply pipe 1 is connected to the inside of the boiler. When the boiler water flows through the boiler water supply pipe 1, the boiler water can be transported to the inside of the first connecting pipe 2. At the same time, the first sealing sleeve 3 is fitted over the connection between the boiler water supply pipe 1 and the first connecting pipe 2 to seal the outside of the connection.

[0020] Please see Figure 6 The second connecting pipe 5 is movably sleeved with a second sealing sleeve 6 covering the outside of the traction pipe 4. The outside of the traction pipe 4 is movably sleeved with a threaded sleeve 7 threaded on the outside of the second sealing sleeve 6. By installing the second connecting pipe 5 inside the traction pipe 4, adjusting the outside of the two ends of the second connecting pipe 5 to install the second sealing sleeve 6, the second sealing sleeve 6 is sleeved on the outside of the traction pipe 4. At the same time, adjusting the position of the threaded sleeve 7 installed on the outside of the traction pipe 4, the threaded sleeve 7 is threaded on the outside of the second sealing sleeve 6. That is, the second sealing sleeve 6 and the threaded sleeve 7 are mutually tightened and limited, ensuring the controllability, sealing and convenience of the second connecting pipe 5 when installed inside the traction pipe 4.

[0021] Please see Figure 6 A circular jacket 10 is fitted onto the outside of the second connecting pipe 5. A sealing sleeve is provided between the sampling pipe 9 and the circular jacket 10. The circular jacket 10 is fitted onto the outside of the second connecting pipe 5, and the sampling pipe 9 installed outside the second connecting pipe 5 limits the movement trajectory of the circular jacket 10. At the same time, a sealing sleeve is installed between the sampling pipe 9 and the circular jacket 10, so the position of the circular jacket 10 outside the sampling pipe 9 can be adjusted, and its sealing performance is ensured.

[0022] Please see Figure 2 Both ends of the traction pipe 4 extend into the interior of the first connecting pipe 2, and the openings at both ends of the traction pipe 4 extend into the interior of the first connecting pipe 2. The ends of the traction pipe 4 are kept parallel to the interior of the first connecting pipe 2. After the boiler water is transported to the interior of the first connecting pipe 2 by the boiler water conveying pipe 1 through the two ends of the traction pipe 4, the boiler water is transported to the interior of a set of traction pipes 4 through the first connecting pipe 2 and discharged from the interior of another set of traction pipes 4. The traction pipe 4 drives the filtered water back into the interior of the first connecting pipe 2. Through the bends and small-diameter pipes of the traction pipe 4, the flow rate of the boiler water is reduced, so as to avoid the high-speed flow of boiler water affecting the sampling. During the sampling process, the boiler water is kept in a continuous flow state to ensure that the sampling device can process water at a constant speed.

[0023] Please see Figure 3 and Figure 4 The third connecting pipe 11 has an opening inside, which is connected to the sampling pipe 9. The sampling pipe 9 is installed obliquely inside the second connecting pipe 5. The third connecting pipe 11 has an opening inside, and the opening inside the third connecting pipe 11 is connected to the sampling pipe 9. After the second connecting pipe 5 is installed inside the traction pipe 4, the boiler water is transported to the second connecting pipe 5. The sampling pipe 9 guides the filtered water through and discharges it. At the same time, an extraction device is installed outside the third connecting pipe 11 to sample the boiler water. When the circular jacket 10 is rotated, the third connecting pipe 11 and the sampling pipe 9 are misaligned, which prevents the transmission of boiler water and ensures that the boiler water remains in a flowing state inside the pipe.

[0024] Please see Figure 6 The third connecting pipe 11 is equipped with a spring 12 and a sealing plug 13. The extraction port at the front end of the extraction syringe 14 is equipped with a push pin, which is in contact with the outside of the sealing plug 13. The spring 12 and the sealing plug 13 are installed in the third connecting pipe 11. Under normal conditions, the spring 12 pushes the sealing plug 13 to move outward, that is, the sealing plug 13 blocks the inside of the third connecting pipe 11, thus forming a counterflow structure to prevent boiler water leakage. Therefore, after the extraction syringe 14 is installed inside the third connecting pipe 11, the push pin installed at the front end of the extraction syringe 14 pushes open the sealing plug 13, that is, the extraction port formed at the front end of the extraction syringe 14 can extract boiler water from the inside of the third connecting pipe 11.

[0025] Working principle: In use, the first connecting pipe 2 is installed inside the boiler water delivery pipe 1, where the boiler water delivery pipe 1 guides and transmits boiler water. A first sealing sleeve 3 is fitted around the boiler water delivery pipe 1 and the first connecting pipe 2, sealing the connection. When boiler water flows inside the boiler water delivery pipe 1, it is delivered to the traction pipe 4, and can be discharged through the other side of the traction pipe 4. Under normal conditions, the spring 12 installed inside the third connecting pipe 11 pushes the sealing plug 13 outwards, ensuring the sealing performance inside the third connecting pipe 11. The circular clamp 1 is rotated... 0. The third connecting pipe 11 and the sampling pipe 9 are misaligned to prevent boiler water from flowing through the double protection. When sampling is required, the extraction syringe 14 is inserted into the third connecting pipe 11. The extraction syringe 14 pushes the sealing plug 13 to open. The circular jacket 10 is rotated to align the sampling pipe 9 with the third connecting pipe 11. The sampling pipe 9 pulls the boiler water transmitted inside the second connecting pipe 5 to control the boiler water to be delivered into the third connecting pipe 11. That is, the extraction syringe 14 can sample the boiler water flowing into the third connecting pipe 11. After sampling, the circular jacket 10 is rotated to prevent continuous output of boiler water.

[0026] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A boiler water working fluid sampling device, comprising a boiler water conveying pipe (1), wherein a first connecting pipe (2) is installed inside the boiler water conveying pipe (1), and a traction pipe (4) is installed outside the first connecting pipe (2), characterized in that: The middle of the traction pipe (4) is movably connected to a second connecting pipe (5), a limiting plate (8) is fixed to the outside of the second connecting pipe (5), a circular sleeve (10) is sleeved to the outside of the second connecting pipe (5), a sampling pipe (9) is fixedly connected to the inside of the second connecting pipe (5), a third connecting pipe (11) is fixed to the outside of the circular sleeve (10), and an extraction syringe (14) for sampling boiler water is installed at the end of the third connecting pipe (11).

2. The boiler water working fluid sampling device according to claim 1, characterized in that: The boiler water supply pipe (1) and the first connecting pipe (2) are connected to a first sealing sleeve (3) for sealing. The boiler water supply pipe (1) is connected to the inside of the boiler.

3. The boiler water working fluid sampling device according to claim 1, characterized in that: The second connecting pipe (5) is movably sleeved with a second sealing sleeve (6) covering the outside of the traction pipe (4), and the outside of the traction pipe (4) is movably sleeved with a threaded sleeve (7) threadedly installed on the outside of the second sealing sleeve (6).

4. The boiler water working fluid sampling device according to claim 1, characterized in that: The circular jacket (10) is fitted onto the outside of the second connecting tube (5), and a sealing sleeve is provided between the sampling tube (9) and the circular jacket (10).

5. A boiler water working fluid sampling device according to claim 1, characterized in that: The two ends of the traction pipe (4) extend into the interior of the first connecting pipe (2), the openings at both ends of the traction pipe (4) extend into the interior of the first connecting pipe (2), and the ends of the traction pipe (4) remain parallel to the interior of the first connecting pipe (2).

6. A boiler water working fluid sampling device according to claim 1, characterized in that: The third connecting tube (11) has an opening inside, which is connected to the sampling tube (9). The sampling tube (9) is installed obliquely inside the second connecting tube (5).

7. A boiler water working fluid sampling device according to claim 1, characterized in that: The third connecting tube (11) is equipped with a spring (12) and a sealing plug (13). The extraction port at the front end of the extraction syringe (14) is equipped with a pin, wherein the pin is in contact with the outside of the sealing plug (13).