A long and large shield tail water treatment and sedimentation equipment

By adopting the design of partition plates, perforated flower walls and movable wall panels in the shield tunnel tailwater treatment equipment, efficient sedimentation treatment of shield tunnel tailwater is achieved, solving the problems of long time consumption and poor effect in the existing technology, and adapting to the needs of different construction speeds.

CN225006413UActive Publication Date: 2026-11-24CHINA RAILWAY SHISIJU GROUP CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522806574.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-30
Publication Date
2026-11-24
Estimated Expiration
2035-12-30

AI Technical Summary

Technical Problem

Existing technologies for treating tailwater sedimentation during tunnel boring machine (TBM) construction are time-consuming and ineffective, failing to meet construction schedule requirements, especially in urban areas where treatment sites are limited.

Method used

Design a sedimentation device for tailrace treatment of long shield tunnels. The sedimentation tank is divided into multiple sedimentation chambers by partition plates. Perforated flower walls and partition walls are used to gradually reduce the sedimentation rate. The sedimentation effect is improved by a water collection tank. The height of the partition walls can be adjusted by movable wall panels and lifting cylinders to adapt to different flow velocities.

Benefits of technology

By using multi-stage sedimentation chambers and dynamically adjusting the height of the partition walls, the sedimentation efficiency and purification effect of the effluent are significantly improved, ensuring efficient effluent treatment and adapting to different construction speeds.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225006413U_ABST
    Figure CN225006413U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of tailwater treatment technology for tunnel boring machines (TBMs), and particularly to a sedimentation device for tailwater treatment in long TBMs. It solves the problems of excessively long sedimentation time and poor sedimentation effect in existing technologies. The device first slows down the sedimentation process through a perforated wall, and then gradually sediments through multiple partition walls, effectively treating the tailwater discharged during TBM construction. It includes an elongated sedimentation tank. An inlet tank is located at the front end of the right-side tank, and a clean water tank is located at the front end of the left-side tank. At least one perforated wall is located within the right-side tank, with several water-passing perforations on its surface. At least one partition wall is located within both the right-side and left-side tanks, with the partition wall of the right-side tank located behind the perforated wall. The perforated wall and partition walls divide the sedimentation tank into multiple sedimentation chambers.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of tailwater treatment technology for tunnel boring machines, and particularly to a sedimentation device for tailwater treatment of long tunnel boring machines. Background Technology

[0002] As the mainstream technology in underground tunnel construction, the shield tunneling method plays a crucial role in the construction of ultra-long and ultra-large diameter tunnels. When a shield machine continuously excavates in such large tunnels, it generates a large amount of tailwater, which is discharged at an extremely rapid rate. This tailwater has a complex composition, containing not only a large number of suspended solid particles and additives, but also potentially small amounts of harmful substances.

[0003] Direct discharge of untreated tailwater can have serious negative consequences. In actual construction, sedimentation, centrifugation, and solidification are common tailwater treatment methods. Construction teams will choose one or more methods depending on the specific construction environment. Sedimentation, based on gravity, uses the density difference between suspended particles and water to achieve solid-liquid separation. Its advantages include the absence of complex equipment, low technical requirements for operators, and relatively simple operation. However, sedimentation is time-consuming and less effective; the treated tailwater is often difficult to discharge directly, and there are limited facilities for tailwater treatment in cities, which to some extent restricts the construction progress of tunnel boring machines. Utility Model Content

[0004] The technical problem to be solved by this utility model is to provide a sedimentation device for treating tailwater from long shield tunnels, which solves the problems of excessive sedimentation time and poor sedimentation effect in the prior art. The device first passes through a perforated flower wall to slow down the sedimentation, and then passes through multiple partition walls for gradual sedimentation, thus effectively treating the tailwater discharged from shield tunnel construction.

[0005] This utility model is achieved through the following technical solution: A sedimentation device for treating tailwater from a long shield tunnel includes an elongated sedimentation tank. A partition plate is provided along the length of the sedimentation tank. The front end of the partition plate is integrally connected to the front side of the inner wall of the sedimentation tank. An opening is reserved at the rear end of the partition plate and the rear side of the inner wall of the sedimentation tank. The partition plate divides the left and right sides of the sedimentation tank. The front end of the right pool is provided with a water inlet pool, the front end of the left pool is provided with a water purification pool, the right pool is provided with at least one perforated flower wall, the perforated flower wall is provided with several water passage holes on the wall surface, and both the right pool and the left pool are provided with at least one partition wall, the partition wall of the right pool is located behind the perforated flower wall. The perforated flower wall and partition wall divide the sedimentation tank into multiple sedimentation chambers.

[0006] Furthermore, there are two perforated flower walls and two partition walls, which divide the sedimentation tank into five sedimentation chambers.

[0007] Furthermore, the height of the partition wall gradually decreases along the direction of the tailwater flow.

[0008] Furthermore, it also includes multiple parallel water collection tanks, which are located in the sedimentation chamber near the water purification tank. The front end of the water collection tank passes through the rear side wall of the water purification tank and communicates with the water purification tank. The top edge of the water collection tank is provided with several serrated diversion ports.

[0009] Furthermore, the bottom of the water collection tank is fixed inside the sedimentation chamber by a support rod.

[0010] Furthermore, the partition wall includes a base wall disposed within the sedimentation tank, and a movable wall panel capable of vertical movement is slidably connected within the base wall. A passageway is provided at the top of the sedimentation tank, and multiple lifting cylinders are installed on the passageway. The movable end of each lifting cylinder penetrates the bottom plate of the passageway downwards and is connected to the top of the movable wall panel.

[0011] Furthermore, a water inlet pipe is provided at the top of the side wall of the water inlet pool, and a flow sensor is installed inside the water inlet pipe.

[0012] The beneficial effects achieved by this utility model compared with the prior art are as follows: 1. The partition plate separates the left and right sides of the sedimentation tank, thereby increasing the sedimentation path of the tailwater. The perforated flower wall and partition wall divide the sedimentation tank into multiple sedimentation chambers. The tailwater of the tunnel boring machine first passes through the perforated flower wall to slow down, and then enters each sedimentation chamber through multiple partition walls and is fully settled in them. After sedimentation and purification, the tailwater enters the clean water tank. This utility model effectively treats the tailwater discharged from the tunnel boring machine. 2. The height of the partition wall gradually decreases along the flow of the tailwater, which allows the tailwater to smoothly enter the next sedimentation chamber. 3. The top edge of the water collection tank is equipped with several serrated diversion ports, which can slow down the flow of the settled water into the water purification tank after it passes through the water collection tank, thereby improving the sedimentation effect. 4. The adjustable wall panel height can change the height of the partition wall, and the height of the partition wall can be adjusted according to the inflow velocity of the tailwater to ensure the sedimentation effect. Attached Figure Description

[0013] Figure 1 This is a three-dimensional schematic diagram of the tailwater treatment sedimentation equipment for long shield tunnels described in this utility model; Figure 2 for Figure 1 Enlarged schematic diagram of structure A in the middle; Figure 3 This is a top view schematic diagram of the tailrace water treatment sedimentation equipment of the long shield tunnel described in this utility model; Figure 4 This is a schematic diagram of the partition wall described in this utility model; Figure 5 This is the control structure diagram of the controller; In the diagram: 1. Sedimentation tank, 11. Left side tank, 12. Right side tank, 2. Partition plate, 3. Opening, 4. Inlet tank, 5. Clean water tank, 6. Partition wall, 61. Base wall, 62. Movable wall panel, 63. Lifting cylinder, 7. Perforated flower wall, 8. Water collection trough, 9. Passageway, 10. Inlet pipe. Detailed Implementation

[0014] The technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the scope of protection of this application.

[0015] In the description of the utility model, it should be understood that the terms "front", "rear", "up", "down", "left", "right", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing the utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the utility model.

[0016] Example 1 like Figure 1-2As shown in the figure, this embodiment discloses a sedimentation device for treating tailwater from a long shield tunnel. It mainly includes a long sedimentation tank 1 constructed in a suitable area. In this embodiment, the sedimentation tank 1 has an overall length of 56m, a depth of 3.5m, and a width of 10m, capable of treating a maximum of 1900 cubic meters of tailwater. A partition plate 2 is constructed along the length of the sedimentation tank 1. The front end of the partition plate 2 is integrated with the front inner wall of the sedimentation tank 1, and an opening 3 is reserved at the rear end of the partition plate 2 and the rear inner wall of the sedimentation tank 1. The partition plate 2 connects the left side tank 11 and the right side tank 12 of the sedimentation tank 1. This design increases the sedimentation path of the tailwater and improves the sedimentation effect. An inlet tank 4 is constructed at the front end of the right side tank 12, and a purification tank 5 is constructed at the front end of the left side tank 11. The purification tank 5 is used to receive the purified water after sedimentation. Two perforated flower walls 7 are constructed within the right-side pool 12. Each perforated flower wall 7 has several water-passing perforations; in this embodiment, six rows of perforations are sufficient. The core function of the perforated flower walls 7 is to achieve uniform water distribution by controlling the flow velocity (0.10-0.20 m / s) through the perforations. In this embodiment, a partition wall 6 is constructed within both the right-side pool 12 and the left-side pool 11. The partition wall 6 of the right-side pool 12 is located behind the perforated flower wall 7, and its height gradually decreases along the direction of the tailwater flow to facilitate tailwater flow. It is worth noting that the number of partition walls 6 and perforated flower walls 7 can be increased or decreased according to actual needs. The perforated flower walls 7 and partition walls 6 divide the sedimentation tank 1 into five sedimentation chambers, sequentially designated as the first sedimentation chamber, second sedimentation chamber, third sedimentation chamber, fourth sedimentation chamber, and fifth sedimentation chamber along the tailwater flow direction.

[0017] To ensure that the settled water enters the water purification tank slowly and evenly, multiple parallel water collection troughs 8 are installed in the sedimentation chamber near the water purification tank 5 (the fifth sedimentation chamber in this embodiment). The front end of each water collection trough 8 passes through the upper end of the rear wall of the water purification tank 5 and communicates with the water purification tank 5. The water collection trough 8 has a rectangular structure, and several serrated diversion ports are evenly distributed along its top edge. To fix the water collection troughs, a support rod is fixed to the bottom of the water collection trough 8, and the lower end of the support rod is fixed inside the sedimentation chamber.

[0018] The specific working process of the tailrace water treatment sedimentation equipment for long shield tunnels described in this embodiment is as follows: like Figure 3As shown, the tailwater from the tunnel boring machine (TBM) is transported to the intake pool. As the water level in the intake pool rises, it then enters the first sedimentation chamber for sedimentation. Simultaneously, after being slowed down by the first perforated partition wall, it flows evenly into the second sedimentation chamber, and then again through the second perforated partition wall before flowing evenly into the third sedimentation chamber. Finally, it overflows from the first partition wall into the fourth sedimentation chamber, and then from the second partition wall into the fifth sedimentation chamber. The TBM tailwater first passes through the perforated partition wall for slowing down, then through multiple partition walls into various sedimentation chambers where it undergoes thorough sedimentation. After purification in the fifth sedimentation chamber, the tailwater enters the clean water tank, where the water is relatively cleaner than the tailwater and is then transported to subsequent equipment for further treatment. This method effectively treats the tailwater discharged during TBM construction, improving the sedimentation effect.

[0019] Example 2 Because the discharge rate of the tunnel boring machine's tailrace water varies, we need to adjust the height of the partition wall accordingly to ensure effective sedimentation. Figure 4 As shown, this embodiment discloses a sedimentation device for tailrace water treatment of long shield tunnels. When constructing the partition wall, the partition wall 6 includes a base wall 61 set in the sedimentation tank 1. A vertical cavity is reserved on the top surface of the base wall 61, and a movable wall plate 62 that can be raised and lowered is slidably connected inside the base wall 61.

[0020] A passageway 9 is constructed on the top of the sedimentation tank 1 using metal plates. Four lifting cylinders 63 are installed on the passageway 9. The fixed bases of the lifting cylinders 63 are installed on the passageway 9, and the movable ends of the lifting cylinders 63 penetrate the bottom plate of the passageway 9 with their downward facing direction. Two lifting cylinders 63 form a group, and the movable ends of the two lifting cylinders 63 are fixedly connected to the top of the movable wall panel 62. In this embodiment, the lifting cylinders 63 can be selected as hydraulic cylinders or electric cylinders.

[0021] like Figure 5 As shown, in order to monitor the flow rate of the tailwater discharged from the tunnel boring machine, an inlet pipe 10 is installed on the top of the side wall of the inlet pool 4, and a flow sensor is installed inside the inlet pipe 10. The outlet end of the inlet pipe 10 is located in the first sedimentation chamber, and the inlet end is connected to the tailwater discharge outlet of the tunnel boring machine through a pipe.

[0022] To achieve automatic monitoring and adjustment, a controller is also included, which establishes an electrical connection between the flow sensor and the control terminal of the lifting cylinder 63 and the controller. When the flow sensor detects that the flow velocity in the inlet pipe 10 is higher than the set value, the controller sends a signal to control the retraction of the lifting cylinder 63, raising the movable wall plate and thus increasing the height of the entire partition wall, thereby deepening the sedimentation area and ensuring the sedimentation effect; conversely, the controller controls the lifting cylinder 63 to extend, lowering the movable wall plate and thus reducing the height of the entire partition wall, adapting to different flow velocities of tailwater and taking into account sedimentation efficiency.

Claims

1. A long and large shield tail water treatment and sedimentation apparatus, characterized by, The sedimentation tank (1) is long and narrow. A partition plate (2) is provided in the sedimentation tank (1) along its length. The front end of the partition plate (2) is connected to the front side of the inner wall of the sedimentation tank (1) as a whole. An opening (3) is reserved between the rear end of the partition plate (2) and the rear side of the inner wall of the sedimentation tank (1). The partition plate (2) connects the left side (11) and the right side (12) of the sedimentation tank (1). The front end of the right pool (12) is provided with an inlet pool (4), the front end of the left pool (11) is provided with a purification pool (5), the right pool (12) is provided with at least one perforated flower wall (7), the perforated flower wall (7) is provided with several water passage holes, the right pool (12) and the left pool (11) are both provided with at least one partition wall (6), the partition wall (6) of the right pool (12) is located behind the perforated flower wall (7); The perforated flower wall (7) and partition wall (6) divide the sedimentation tank (1) into multiple sedimentation chambers.

2. The long large shield tail water treatment and sedimentation equipment according to claim 1, characterized in that, There are two perforated flower walls (7) and two partition walls (6). The perforated flower walls (7) and partition walls (6) divide the sedimentation tank (1) into five sedimentation chambers.

3. The long large shield tail water treatment and sedimentation equipment according to claim 2, characterized in that, Along the flow of the tailwater, the height of the partition wall (6) gradually decreases.

4. The tailrace water treatment sedimentation equipment for long shield tunnels according to claim 2, characterized in that, It also includes multiple parallel water collection tanks (8), which are located in the sedimentation chamber near the water purification tank (5). The front end of the water collection tank (8) passes through the rear side wall of the water purification tank (5) and is connected to the water purification tank (5). The top edge of the water collection tank (8) is provided with several serrated diversion ports.

5. The tailrace water treatment sedimentation equipment for long shield tunnels according to claim 4, characterized in that, The bottom of the water collection tank (8) is fixed inside the sedimentation chamber by a support rod.

6. The tailrace water treatment sedimentation equipment for long shield tunnels according to claim 2, characterized in that, The partition wall (6) includes a base wall (61) installed in the sedimentation tank (1), and a movable wall panel (62) that can be raised and lowered is slidably connected in the base wall (61). A passageway (9) is provided at the top of the sedimentation tank (1), and multiple lifting cylinders (63) are installed on the passageway (9). The movable end of the lifting cylinder (63) passes through the bottom plate of the passageway (9) and is connected to the top of the movable wall panel (62).

7. The long shield tunnel tailrace water treatment sedimentation equipment according to any one of claims 1-6, characterized in that, The top of the side wall of the water inlet pool (4) is provided with a water inlet pipe (10), and a flow sensor is provided inside the water inlet pipe (10).