By introducing a lead screw drive and PLC controller connection module into the PCBA circuit board testing device, the problem of unstable automated sorting and transportation was solved, and the efficiency of automated sorting, transportation and testing was improved.

CN225007740UActive Publication Date: 2026-11-24DONGGUAN HONGCHUANGDA ELECTRONIC TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522726730.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-23
Publication Date
2026-11-24
Estimated Expiration
2035-12-23

AI Technical Summary

Technical Problem

Existing PCBA circuit board testing equipment lacks a precise automated classification mechanism, which leads to increased labor costs and errors due to manual differentiation of good and defective products. Furthermore, the lifting accuracy and stability of the connecting and transport structure are low, which can easily cause circuit boards to shift, jam, or fall, affecting testing efficiency.

Method used

The connecting module, controlled by a screw drive device, is combined with the conveyor lines for good and defective products to form a precise automated sorting and transfer structure. The PLC controller and position sensors enable precise connection of the connecting conveyor lines, avoiding human error and improving the lifting accuracy and stability of the connecting conveyor lines.

Benefits of technology

It achieves fully automated sorting and transfer of PCBA circuit boards, reducing labor costs, avoiding material mixing issues, improving testing efficiency and quality control, and ensuring the stability and accuracy of circuit boards during the transfer process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225007740U_ABST
    Figure CN225007740U_ABST
Patent Text Reader

Abstract

This utility model discloses a PCBA circuit board testing device, relating to the field of circuit board manufacturing technology. It includes an equipment cabinet, a testing host, a testing conveyor line, a testing station, a connection module, a good product conveyor line, and a defective product conveyor line. The testing conveyor line intermittently transports PCBA circuit boards. The testing station at the top of the equipment cabinet contains cylinder-driven testing probes that can precisely connect to the test points on the circuit boards. The connection module drives the connection conveyor line to rise and fall via a motor, lead screw, and synchronous wheel transmission kit, achieving precise connection with the good / defective product conveyor lines. This device eliminates the need for manual sorting, reducing labor costs and the risk of material mixing. Furthermore, the lead screw drive structure improves connection stability, avoids circuit board transfer problems, and effectively improves testing efficiency and quality control. It is suitable for batch testing scenarios of PCBA circuit boards.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of circuit board manufacturing technology, and in particular to a PCBA circuit board testing device. Background Technology

[0002] In the PCBA (Printed Circuit Board Assembly) production process, performance testing is a crucial step in ensuring product quality. Specialized equipment is needed to test core indicators such as circuit continuity, component function, and signal transmission to screen out qualified products. Currently, most mainstream PCBA testing devices adopt an integrated "transport-testing" structure, but this has significant limitations in practical applications. On the one hand, some devices lack a precise automated classification mechanism, requiring manual differentiation of good and bad products after testing. This not only increases labor costs but also makes it easy for human error to cause mixing, affecting subsequent production processes. On the other hand, the few devices with classification functions often use cylinders to directly drive their connecting and transferring structures, resulting in low lifting accuracy and poor connection stability. This can easily lead to circuit board misalignment, jamming, or even falling, causing a decrease in testing efficiency. Utility Model Content

[0003] To address the technical problems existing in the background art, this utility model proposes a PCBA circuit board testing device.

[0004] This utility model proposes a PCBA circuit board testing device, including an equipment cabinet and a testing host. A testing conveyor line is installed inside the equipment cabinet. The conveying section of the testing conveyor line carries several PCBA circuit boards, and the testing conveyor line can intermittently convey the PCBA circuit boards. The device is characterized by a testing station installed on the top of the equipment cabinet for testing the PCBA circuit boards. A connection module is provided at the outlet of the testing conveyor line. The outlet of the connection module is respectively provided with a good product conveyor line and a defective product conveyor line. The connection module includes a screw drive device, the output end of which is connected to the connection conveyor line to drive the connection conveyor line to connect with the good product conveyor line or the defective product conveyor line.

[0005] Furthermore, the test station includes a base plate installed on the top of the equipment cabinet, a cylinder is installed at the top of the base plate, the telescopic end of the cylinder extends to the bottom of the base plate and is connected to an electrical board, a carrier plate is installed at the bottom of the electrical board, and a test probe is connected to the bottom of the carrier plate.

[0006] Furthermore, a first guide rod is symmetrically arranged inside the substrate, the substrate slides relative to the first guide rod, and the bottom end of the first guide rod is connected to the electrical board.

[0007] Furthermore, the connection module includes a connection cabinet, and the lead screw drive device is installed inside the connection cabinet.

[0008] Furthermore, the lead screw drive device includes a motor installed at the top of the connecting cabinet and a lead screw rotatably connected inside the connecting cabinet. The drive end of the motor and the lead screw are driven by a synchronous pulley transmission kit. The lead screw is externally threaded to a lifting seat, and the connecting conveyor line is installed inside the lifting seat.

[0009] Furthermore, the synchronous pulley transmission kit includes a driving synchronous pulley mounted on the motor drive end, a driven synchronous pulley mounted on the top of the lead screw, and a synchronous belt connected to the outside of the driving and driven synchronous pulleys to drive the lead screw to rotate.

[0010] Furthermore, a second guide rod is symmetrically installed inside the connection cabinet, and the second guide rod is slidably connected to the lifting seat.

[0011] The beneficial effects of this utility model are as follows: By setting a connecting module controlled by a lead screw drive device at the outlet of the test conveyor line, and combining it with two conveyor lines for good and defective products, a precise automated classification and transfer structure is formed. This not only eliminates the need for manual differentiation between good and defective products, significantly reducing labor costs, but also avoids the problem of mixed materials caused by human error. At the same time, compared with the traditional cylinder-driven connecting structure, the lead screw drive combined with the guide rod design can significantly improve the lifting accuracy and connection stability of the connecting conveyor line, effectively preventing the circuit board from shifting, jamming, or falling during the transfer process, ensuring the smoothness of the entire process of "transfer, testing, and classification", and thus improving the overall efficiency and quality control level of PCBA circuit board testing. Attached Figure Description

[0012] Figure 1 This is a schematic diagram of the structure of this utility model; Figure 2 This is a half-sectional view of the present invention; Figure 3 This is a schematic diagram of the test station structure in this utility model; Figure 4 This is a schematic diagram of the connection module in this utility model.

[0013] In the diagram: 1. Equipment cabinet; 2. Test host; 3. Test conveyor line; 4. PCBA circuit board; 5. Test station; 51. Substrate; 52. Cylinder; 53. First guide rod; 54. Electrical board; 55. Carrier board; 56. Test probe; 6. Connection module; 61. Connection cabinet; 62. Motor; 63. Lead screw; 64. Lifting seat; 65. Connection conveyor line; 66. Synchronous pulley drive kit; 67. Second guide rod; 7. Good product conveyor line; 8. Defective product conveyor line. Detailed Implementation

[0014] Reference Figure 1-4The present invention proposes a PCBA circuit board testing device, including an equipment cabinet 1 and a test host 2. The test host 2 provides core control and data processing support for the testing of PCBA circuit boards 4 (the specific structure of the test host 2 and how to perform the test are well known to those skilled in the art and will not be described in detail here; the data interface of the test host 2 is connected to the test probe 56 through a wire harness). The equipment cabinet 1 is equipped with a test conveyor line 3. The conveying section of the test conveyor line 3 carries several PCBA circuit boards 4 to be tested, and the test conveyor line 3 adopts an intermittent conveying method, which can accurately convey the PCBA circuit boards 4 to the test station in sequence, creating stable conditions for subsequent testing operations. Test station 5 is installed on the top of equipment cabinet 1. Test station 5 is the core working component for realizing the performance testing of PCBA circuit board 4. Test station 5 is specifically composed of substrate 51, cylinder 52, first guide rod 53, electrical board 54, carrier board 55 and test probe 56. The substrate 51 is fixedly installed on the top of equipment cabinet 1 to provide the mounting base for other components of test station 5. The top of substrate 51 is equipped with cylinder 52. The telescopic end of cylinder 52 extends to the bottom of substrate 51 and is connected to electrical board 54 (electrical board 54 serves as insulation). Cylinder 52 serves as a power source and can drive electrical board 54 to move up and down. Carrier board 55 is installed at the bottom of electrical board 54. Test probe 56 is connected to the bottom of carrier board 55. Test probe 56 corresponds to the test point of PCBA circuit board 4 and is used to contact the circuit board and collect test data. The substrate 51 is symmetrically provided with first guide rods 53. The substrate 51 slides relative to the first guide rods 53, and the bottom end of the first guide rods 53 is connected to the electrical board 54. When the cylinder 52 drives the electrical board 54 to move up and down, the first guide rods 53 can provide guidance for the movement of the electrical board 54, prevent the electrical board 54 from deviating during the movement, and ensure that the test probes 56 can accurately connect to the test points of the PCBA circuit board 4, thereby improving the test accuracy. The outlet of the test conveyor line 3 is equipped with a connecting module 6. The outlet of the connecting module 6 is connected to the good product conveyor line 7 and the defective product conveyor line 8 respectively. It is used to classify and transport the PCBA circuit boards 4 after testing according to the test results. The connecting module 6 includes a connecting cabinet 61, a screw drive device, a connecting conveyor line 65 and a second guide rod 67. The connecting cabinet 61 provides installation and protection space for internal components. The screw drive device is installed inside the connecting cabinet 61 and is the power mechanism to realize the position switching of the connecting conveyor line 65. The lead screw drive device is specifically composed of a motor 62, a lead screw 63, a lifting seat 64, and a synchronous pulley transmission kit 66. The motor 62 is installed at the top of the connecting cabinet 61, and the lead screw 63 is rotatably connected inside the connecting cabinet 61. The drive end of the motor 62 and the lead screw 63 are transmitted through the synchronous pulley transmission kit 66. The synchronous pulley transmission kit 66 includes a driving synchronous pulley installed at the drive end of the motor 62, a driven synchronous pulley installed at the top of the lead screw 63, and a synchronous belt connected to the outside of the driving and driven synchronous pulleys. After the motor 62 starts, it drives the lead screw 63 to rotate through the synchronous pulley transmission kit 66. The lifting seat 64 is threadedly connected to the outside of the lead screw 63. The connecting conveyor line 65 is installed inside the lifting seat 64. When the lead screw 63 rotates, it drives the lifting seat 64 to move up and down along the axis of the lead screw 63, thereby driving the connecting conveyor line 65 to rise and fall synchronously, so as to achieve precise connection with the good product conveyor line 7 or the defective product conveyor line 8. The inside of the connecting cabinet 61 is symmetrically equipped with second guide rods 67. The second guide rods 67 are slidably connected to the lifting seat 64. When the lifting seat 64 moves up and down with the lead screw 63, the second guide rods 67 can restrict the rotation of the lifting seat 64, ensuring that the lifting seat 64 moves smoothly, thereby ensuring the stability of the connection between the connecting conveyor line 65 and the good product conveyor line 7 and the defective product conveyor line 8, and preventing the circuit board from falling or shifting during the transfer process. The working process of this device is as follows: The PCBA circuit board 4 to be tested is placed on the test conveyor line 3. The test conveyor line 3 intermittently conveys the circuit board to the area below the test station 5. Then, the cylinder 52 drives the electrical board 54 to move downward, causing the test probe 56 to contact the test point of the PCBA circuit board 4. The test host 2 simultaneously collects and analyzes the test data. After the test is completed, the test conveyor line 3 conveys the circuit board to the connecting conveyor line 65. According to the judgment result of the test host 2, the motor 62 starts and drives the connecting conveyor line 65 to rise and fall through the lead screw drive device, so that the connecting conveyor line 65 connects with the good product conveyor line 7 or the defective product conveyor line 8. Finally, the connecting conveyor line 65 conveys the circuit board to the corresponding conveyor line, completing the classification and transfer.

[0015] The specific process for the above-mentioned classification and transfer is as follows: After PCBA circuit board 4 completes testing, the testing host 2 analyzes the collected test data (such as continuity, voltage stability, signal transmission efficiency, etc.) and generates a "good" or "defective" judgment result. This judgment signal is transmitted to the core control unit of the device, namely the PLC controller, in real time. The PLC controller then executes the corresponding classification and transfer instructions based on the judgment result. The specific process is as follows: (1) If the test host 2 determines that the current PCBA circuit board 4 is a good product, it will send a "good product transfer" trigger signal to the PLC controller. After receiving the signal, the PLC controller will immediately retrieve the preset "good product conveying program", generate a control command for the motor 62 to rotate forward, and simultaneously activate the standby state of the connecting conveyor line 65 (the conveying direction is consistent with the exit direction of the test conveyor line 3). (1.1) The PLC controller sends a forward rotation start signal to the motor 62, and the motor 62 starts to rotate forward after being powered on; (1.2) The drive end of the motor 62 drives the active synchronous pulley in the synchronous pulley transmission kit 66 to rotate. The active synchronous pulley transmits power to the driven synchronous pulley at the top of the lead screw 63 through the synchronous belt, thereby driving the lead screw 63 to rotate forward along its own axis. (1.3) Since the lead screw 63 and the lifting seat 64 are connected by threads, and the lifting seat 64 is restricted by the second guide rod 67 symmetrically installed inside the connecting cabinet 61 (it can only move along the axial direction and cannot rotate synchronously with the lead screw 63), when the lead screw 63 rotates in the forward direction, it will generate an upward axial thrust, which will push the lifting seat 64 to rise smoothly along the second guide rod 67. (1.4) The connecting conveyor line 65 installed inside the lifting seat 64 rises synchronously with the lifting seat 64. The PLC controller collects the speed data in real time through the encoder of the motor 62 and calculates the rising height of the lifting seat 64. At the same time, the position sensor (such as photoelectric sensor) preset inside the connecting cabinet 61 will detect the height position of the connecting conveyor line 65 in real time. When the conveying surface of the connecting conveyor line 65 is flush with the conveying surface of the good product conveyor line 7 and the center lines of the two are completely aligned, the position sensor sends an "arrival signal" to the PLC controller. (1.5) After receiving the “position signal”, the PLC controller immediately sends a stop command to the motor 62. The motor 62 is powered off and stops rotating. The screw drive device stops operating, and the connecting conveyor line 65 stops precisely at the position where it connects with the good product conveyor line 7. (1.6) While controlling the motor 62 to stop, the PLC controller sends a start signal to the connecting conveyor line 65, and the connecting conveyor line 65 is powered on and runs (the conveying speed is consistent with the good product conveyor line 7 to avoid jamming when the circuit board is transferred). At this time, the test conveyor line 3 has transported the good PCBA circuit board 4 to the entrance end of the connecting conveyor line 65. The connecting conveyor line 65 smoothly transports the circuit board to the good product conveyor line 7, and the good product conveyor line 7 transfers it to the subsequent packaging or assembly process. (1.7) When the good PCBA circuit board 4 completely leaves the connecting conveyor line 65 (when the photoelectric sensor at the end of the connecting conveyor line 65 cannot detect the circuit board), the PLC controller sends a stop signal to the connecting conveyor line 65 and generates a reverse command for the motor 62 to drive the connecting conveyor line 65 to descend to the initial position (the height at which it connects with the outlet of the test conveyor line 3) and wait for the test result of the next PCBA circuit board 4.

[0016] (2) If the test host 2 determines that the current PCBA circuit board 4 is a defective product (such as having problems such as short circuit, component failure, or abnormal signal), it will send a "defective product transfer" trigger signal to the PLC controller. After receiving the signal, the PLC controller will retrieve the preset "defective product conveying program", generate a control command for the motor 62 to reverse, and activate the standby state of the connecting conveyor line 65 (the conveying direction remains unchanged, only the subsequent height adjustment is different from the good product process); (2.1) The PLC controller sends a reverse start signal to the motor 62. After the motor 62 is powered on, it starts to reverse, driving the active synchronous pulley, synchronous belt and driven synchronous pulley in the synchronous pulley transmission kit 66 to rotate in the opposite direction, thereby driving the lead screw 63 to reverse along its own axis. (2.2) When the lead screw 63 reverses, it generates a downward axial force on the lifting seat 64. The lifting seat 64 descends smoothly along the second guide rod 67, and the connecting conveyor line 65 descends synchronously with the lifting seat 64. (2.3) The PLC controller monitors the descent height of the connecting conveyor line 65 in real time through the encoder of motor 62 and the position sensor inside the connecting cabinet 61. When the conveying surface of the connecting conveyor line 65 is flush with the conveying surface of the defective product conveyor line 8 and the center lines of the two are aligned, the position sensor sends an "arrival signal" to the PLC controller. The PLC controller immediately controls motor 62 to stop rotating, and the connecting conveyor line 65 stops precisely at the position where it connects with the defective product conveyor line 8. (2.4) The PLC controller sends a start signal to the connecting conveyor line 65, and the connecting conveyor line 65 runs at a speed matched with the defective product conveyor line 8. After the test conveyor line 3 transports the defective PCBA circuit board 4 to the connecting conveyor line 65, the connecting conveyor line 65 smoothly transfers it to the defective product conveyor line 8, and the defective product conveyor line 8 transports it to a dedicated defective product temporary storage area for subsequent manual re-inspection or rework. (2.5) When the defective PCBA circuit board 4 completely leaves the connecting conveyor line 65, the PLC controller controls the connecting conveyor line 65 to stop running, and at the same time instructs the motor 62 to rotate forward, driving the connecting conveyor line 65 to rise to the initial position, waiting for the next sorting and transfer instruction.

[0017] Throughout the entire sorting and transfer process, the PLC controller precisely controls the motor 62 and the connecting conveyor line 65, combined with real-time feedback from position sensors and encoders, to ensure the connection accuracy (error ≤ 0.5mm) between the connecting conveyor line 65 and the target conveyor line (good / defective products). This prevents the circuit boards from shifting, falling, or getting stuck during the transfer process, while also achieving fully automated connection of "testing-judgment-sorting" and improving the overall operating efficiency of the testing device.

[0018] The above description is only a preferred embodiment of the present utility model, but the protection scope of the present utility model is not limited thereto. Any equivalent substitutions or changes made by those skilled in the art within the technical scope disclosed in the present utility model, based on the technical solution and the inventive concept of the present utility model, should be included within the protection scope of the present utility model.

Claims

1. A PCBA circuit board testing device, comprising an equipment cabinet (1) and a testing host (2), wherein a testing conveyor line (3) is installed inside the equipment cabinet (1), the conveying section of the testing conveyor line (3) carries a plurality of PCBA circuit boards (4), and the testing conveyor line (3) is capable of intermittently conveying the PCBA circuit boards (4), characterized in that, The top of the equipment cabinet (1) is equipped with a test station (5) to test the PCBA circuit board (4). The outlet of the test conveyor line (3) is provided with a connection module (6). The outlet of the connection module (6) is respectively provided with a good product conveyor line (7) and a defective product conveyor line (8). The connection module (6) includes a screw drive device. The output end of the screw drive device is connected to the connection conveyor line (65) to drive the connection conveyor line (65) to connect with the good product conveyor line (7) or the defective product conveyor line (8).

2. The PCBA circuit board testing device according to claim 1, characterized in that, The test station (5) includes a base plate (51) installed on the top of the equipment cabinet (1). A cylinder (52) is installed on the top of the base plate (51). The telescopic end of the cylinder (52) extends to the bottom of the base plate (51) and is connected to an electrical board (54). A carrier plate (55) is installed at the bottom of the electrical board (54). A test probe (56) is connected to the bottom of the carrier plate (55).

3. The PCBA circuit board testing device according to claim 2, characterized in that, The substrate (51) is symmetrically provided with a first guide rod (53) inside. The substrate (51) slides relative to the first guide rod (53). The bottom end of the first guide rod (53) is connected to the electrical board (54).

4. The PCBA circuit board testing device according to claim 1, characterized in that, The connection module (6) includes a connection cabinet (61), and the screw drive device is installed inside the connection cabinet (61).

5. The PCBA circuit board testing device according to claim 4, characterized in that, The lead screw drive device includes a motor (62) installed at the top of the connecting cabinet (61) and a lead screw (63) rotatably connected inside the connecting cabinet (61). The drive end of the motor (62) and the lead screw (63) are driven by a synchronous wheel transmission kit (66). The lead screw (63) is externally threaded to a lifting seat (64), and the connecting conveyor line (65) is installed inside the lifting seat (64).

6. The PCBA circuit board testing device according to claim 5, characterized in that, The synchronous pulley drive assembly (66) includes an active synchronous pulley mounted on the drive end of the motor (62), a driven synchronous pulley mounted on the top of the lead screw (63), and a synchronous belt connected to the outside of the active and driven synchronous pulleys to drive the lead screw (63) to rotate.