A roof hoist for a tower
By using split-type conversion supports and high-strength alloy steel materials, the instability problem of roof-mounted equipment in the construction of super high-rise buildings was solved, achieving stable heightening of the tower and improved safety.
Patent Information
- Application Number
- CN202522609578.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-09
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-09
AI Technical Summary
Existing roof-mounted cranes cannot flexibly adapt to the construction needs of super high-rise buildings. The tower structure is unstable during the heightening process, posing safety hazards, especially the risk of swaying or overturning under high-altitude wind loads or dynamic loads.
The system adopts a split-type conversion bearing, combined with high-strength alloy steel materials and precision machining technology. Standard sections are added section by section through the conversion bearing, and professional jacking equipment and positioning devices are used to ensure the verticality of the tower body, enhance the anti-overturning ability, and reduce stress concentration.
It has achieved stability and safety in the construction of super high-rise buildings, avoiding tower swaying or overturning, meeting the construction needs of different heights, and reducing safety risks.
Smart Images

Figure CN225013015U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building construction technology, and in particular to a heightened tower roof crane. Background Technology
[0002] A roof-mounted crane is a lifting device installed on the roof or high-altitude platform of a building, mainly used for high-rise building construction, equipment installation and dismantling. Its core feature is that it achieves high-altitude hoisting through roof fixation, offering advantages such as high flexibility and saving ground space.
[0003] A search revealed Chinese patent CN202575758U, which discloses a roof crane, including a base with a rotating platform on the base. The rotating platform is connected to a power drive device that drives its rotation. A support platform is connected to one side of the rotating platform, and a winch device and a counterweight are installed on the support platform. A lifting arm is hinged to the upper part of the rotating platform, and a hook is installed at the other end of the lifting arm. The hook is connected to the winch device. A power device that drives the lifting arm to rotate around the hinge is installed between the lifting arm and the rotating platform. The roof crane has a small footprint, adjustable range, and can lift heavy objects through the winch device and lifting arm, meeting the requirements for dismantling tower cranes. All components of the roof crane can be installed and disassembled manually, making it easy to disassemble and assemble.
[0004] Based on the above search and existing technology, the findings were as follows: Existing patents rely solely on crane booms and rotary tables of fixed heights, which cannot flexibly adapt to the construction needs of super high-rise buildings. The tower structure is unstable during the heightening process, posing safety hazards, and is at risk of swaying or overturning under high-altitude wind loads or dynamic loads, thus having certain limitations. Utility Model Content
[0005] To address the aforementioned technical problems, this utility model proposes a roof-mounted crane for increasing the height of the tower body. By using specific conversion supports, the tower body can be effectively increased in height, meeting the needs of different construction heights.
[0006] The technical solution to achieve the purpose of this utility model is: a heightened tower roof crane, comprising the original tower body, standard sections, and roof beams, and also including auxiliary beams and conversion supports. The auxiliary beam is fixedly installed between the roof beams, and the original tower body is set on top of the auxiliary beam; The conversion support includes a lower support body fixedly installed on the top of the original tower body, and multiple upper support bodies are fixedly installed on the top of the lower support body.
[0007] Preferably, a tower crane foundation is fixedly installed at the bottom of the original tower body, and a foundation embedded part is fixedly installed at the bottom of the tower crane foundation. The foundation embedded part is located inside the auxiliary beam.
[0008] Preferably, multiple reinforcing members 2 are fixedly installed between the original tower body and the lower base body, and multiple reinforcing members 1 are fixedly installed between each upper base body and the lower base body.
[0009] Preferably, each of the upper seats has a connecting plate fixedly installed on both sides, and the connecting plate is fixedly connected to the standard section by high-strength bolts.
[0010] Compared with existing technologies, the significant advantages of this invention are: Firstly, this utility model adopts a split-type conversion support, combined with high-strength alloy steel materials and precision machining technology, to ensure the strength and rigidity of the connection parts, effectively distribute the load, and reduce stress concentration; a second reinforcement component is set between the original tower body and the lower support body, and a first reinforcement component is added between the upper support body and the lower support body, forming a multi-level reinforcement to prevent the tower body from swaying or tilting; the foundation embedded parts are embedded inside the auxiliary beam to enhance the overall anti-overturning capacity and adapt to the wind load and dynamic load of high-rise buildings.
[0011] Secondly, this utility model achieves the gradual addition of standard sections by converting the support, which can increase the height of the tower without replacing the main structure, meeting the construction needs of super high-rise buildings. It adopts professional jacking equipment and positioning devices to ensure the verticality of the tower during the heightening process and avoid safety hazards caused by tilting.
[0012] This invention solves the problems of existing patents that rely solely on crane booms and rotary tables of fixed heights, which cannot flexibly adapt to the construction needs of super high-rise buildings, and whose tower structures are unstable during the heightening process, posing safety hazards and risks of swaying or overturning under high-altitude wind loads or dynamic loads. Attached Figure Description
[0013] The present invention will be further explained below with reference to the accompanying drawings and embodiments: Figure 1 This is a schematic diagram of the roof-mounted suspension structure for the heightened tower provided by this utility model; Figure 2 This is a schematic diagram of the completed tower crane foundation installation provided by this utility model; Figure 3 This is a schematic diagram of the structural components of the tower crane foundation provided by this utility model; Figure 4 This is a three-dimensional structural diagram of the conversion support provided by this utility model; Figure 5 This is a side view schematic diagram of the conversion support structure provided by this utility model.
[0014] Explanation of reference numerals in the attached figures: 1. Original tower body; 2. Standard section; 3. Transition support; 4. Roof beam; 5. Auxiliary beam; 6. Tower crane foundation; 601. Foundation embedded parts; 7. Upper body; 701. Reinforcement component one; 702. Connecting plate; 8. Lower body; 801. Reinforcement component two. Detailed Implementation
[0015] The present invention will now be described in detail, and the technical solutions in the embodiments of the present invention will be clearly and completely described. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present invention.
[0016] This utility model provides an improved roof-mounted crane with a heightened tower. The technical solution of this utility model is as follows: like Figures 1-5 As shown, a heightened roof crane includes the original tower body 1, standard section 2, and roof beam 4, effectively increasing the height of the tower body and raising the lifting height of the roof crane to meet the needs of higher-rise building construction. It also includes auxiliary beam 5 and transfer support 3. The auxiliary beam 5 is fixedly installed between the roof beams 4, and the original tower body 1 is set on top of the auxiliary beam 5, making the overall structure solid and sturdy, and avoiding safety hazards; The conversion support 3 includes a lower support body 8 fixedly installed on the top of the original tower body 1, and multiple upper support bodies 7 fixedly installed on the top of the lower support body 8. The material of the conversion support 3 is high-strength alloy steel, which is precision machined and heat treated to ensure that it has sufficient strength and rigidity.
[0017] Furthermore, a tower crane foundation 6 is fixedly installed at the bottom of the original tower body 1, and a foundation embedded part 601 is fixedly installed at the bottom of the tower crane foundation 6. The foundation embedded part 601 is set inside the auxiliary beam 5, and uses high-strength alloy steel and precision machining technology to ensure the stability and reliability of the structure and reduce the safety risks during construction.
[0018] As a further embodiment of this utility model, multiple reinforcing members 801 are fixedly installed between the original tower body 1 and the lower base body 8, and multiple reinforcing members 701 are fixedly installed between each upper base body 7 and the lower base body 8, which strengthens the stability of the connection between the components and improves the safety of construction.
[0019] Furthermore, each upper body 7 is fixedly installed with a connecting plate 702 on both sides. The connecting plate 702 is fixedly connected to the standard section 2 by high-strength bolts, which facilitates installation, reduces construction time and labor costs, and improves construction efficiency.
[0020] The specific working method is as follows: First, the original tower body 1 is raised to the predetermined height and fixed. Then, the lower support body 8 of the conversion support 3 is precisely aligned and connected to the top of the original tower body 1 to ensure a firm and reliable connection. Next, the standard section 2 is connected to the original tower body 1 through the upper support body 7 of the conversion support 3. The standard section 2 is added section by section to the required height, and both the upper support body 7 and the lower support body 8 are equipped with connection interfaces. During the addition process, professional jacking equipment and positioning devices are used to ensure the overall verticality and stability of the tower body. Finally, after the tower body is heightened, a comprehensive inspection and debugging of the tower body is carried out to ensure its safety performance.
[0021] The technical means disclosed in this utility model are not limited to those described above, but also include technical solutions composed of equivalent substitutions of the above technical features. Matters not covered in this utility model are common knowledge to those skilled in the art.
Claims
1. A high-rise roof hanger, comprising a primary tower (1), a standard section (2) and a roof beam (4), characterized in that: Also includes: Auxiliary beam (5), the auxiliary beam (5) is fixedly installed between the roof beams (4), and the original tower body (1) is set on top of the auxiliary beam (5); The conversion support (3) includes a lower support body (8) fixedly installed on the top of the original tower body (1), and multiple upper support bodies (7) are fixedly installed on the top of the lower support body (8).
2. The roof hanger of claim 1, wherein: The bottom of the original tower body (1) is fixedly installed with a tower crane foundation (6), and the bottom of the tower crane foundation (6) is fixedly installed with a foundation embedded part (601), which is located inside the auxiliary beam (5).
3. The roof hanger of claim 1, wherein: Multiple reinforcing members (801) are fixedly installed between the original tower body (1) and the lower base body (8), and multiple reinforcing members (701) are fixedly installed between each upper base body (7) and the lower base body (8).
4. A roof hanger for a taller tower according to any one of claims 1-3, characterized in that: Each of the upper body (7) is fixedly installed with a connecting plate (702) on both sides, and the connecting plate (702) is fixedly connected to the standard section (2) by high-strength bolts.
Citation Information
Patent Citations
Roof covering lift
CN202575758U