Anti-settling composite structure for soft soil subgrade

The anti-settlement composite structure combining precast concrete subgrade and cast-in-place piles solves the problem of insufficient control of horizontal deformation and differential settlement in soft soil subgrades, realizes the overall stability of the structure and uniform load distribution, enhances connection strength and shear resistance, and prevents local damage.

CN225013899UActive Publication Date: 2026-11-24LULIANG BRANCH OF SHANXI PROVINCIAL HIGHWAY BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522574839.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-04
Publication Date
2026-11-24
Estimated Expiration
2035-12-04

AI Technical Summary

Technical Problem

Existing soft soil subgrades are relatively effective in controlling vertical settlement, but they are insufficient in controlling horizontal deformation and differential settlement. Furthermore, there is a lack of effective coordination between different treatment layers, leading to interface slippage and localized plastic failure.

Method used

The anti-settlement composite structure combines precast concrete roadbed with cast-in-place concrete piles. Through precise insertion of rectangular plugs and alignment slots, a sheet-pile composite system is formed. The design of steel mesh and grouting grooves enhances the connection strength and horizontal restraint.

Benefits of technology

It effectively controls uneven settlement of the roadbed, improves the overall stability and load diffusion capacity of the structure, limits horizontal deformation, avoids stress concentration, enhances the tensile and shear resistance of the connection, and ensures the smoothness of the road surface and the structural integrity for long-term use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225013899U_ABST
    Figure CN225013899U_ABST
Patent Text Reader

Abstract

This utility model discloses a composite structure for preventing settlement in soft soil subgrades. The subgrade includes: a precast concrete subgrade, with a first and a second convex / concave seat fixedly installed at one and the other ends respectively, and multiple precast concrete subgrades are assembled by interlocking the first and second convex / concave seats at adjacent ends; and cast-in-place concrete piles embedded in the soft soil, with rectangular inserts fixedly installed at their tops. These rectangular inserts are interlocked with multiple matrix-distributed alignment slots at the bottom of the precast concrete subgrades. This utility model, through the interlocking assembly of precast concrete subgrade units and the interlocking-grouting connection with the piles, forms a collaborative sheet-pile composite structure, effectively controlling the vertical and horizontal deformation of the soft soil subgrade and optimizing the load transfer path, thereby significantly improving the overall stability, uniformity, and bearing capacity of the subgrade.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to roadbeds, specifically a composite structure for preventing settlement in soft soil roadbeds. Background Technology

[0002] Existing soft soil subgrade treatments involve replacement and pile foundations, primarily controlling vertical settlement. However, these methods fall short in controlling horizontal deformation and differential settlement. Furthermore, when the load from the pavement is transferred to the soft soil layer through the subgrade, stress concentration is significant, easily leading to localized plastic failure. Additionally, the lack of effective coordination between different treatment layers (such as piles and fill, reinforcement materials and soil) results in interface slippage leading to overall failure. Utility Model Content

[0003] The purpose of this invention is to provide a composite structure for preventing settlement in soft soil subgrades, so as to overcome the above-mentioned shortcomings in the prior art.

[0004] To achieve the above objectives, this utility model provides the following technical solution: a composite structure for preventing settlement in soft soil subgrade, comprising: A precast concrete roadbed has a first convex and concave seat and a second convex and concave seat fixedly installed at one end and the other end, and multiple precast concrete roadbeds are assembled by embedding the first convex and concave seats and the second convex and concave seats at adjacent ends. The cast-in-place concrete piles are embedded in soft soil, and a rectangular plug is fixedly installed on the top of the pile. The rectangular plug is inserted into a plurality of alignment slots arranged in a matrix at the bottom of the precast concrete roadbed.

[0005] Preferably, a grouting groove is provided on the end face of the first concave-convex seat on the side of the precast concrete roadbed.

[0006] Preferably, the precast concrete roadbed includes a steel mesh, the portion of which extends to the exposed end face of the precast concrete roadbed located on the side of the second concave-convex seat is the outer edge of the outer steel bar; Preferably, the outer edge of the outer reinforcing bar has a rounded triangular structure, and there are multiple of them, which are distributed in a linear array.

[0007] Preferably, the steel mesh is provided with an outer edge of the inner steel bar that extends to one side of the precast concrete roadbed and has an exposed end face. The outer edge of the inner steel bar is located within the outer edge of the outer steel bar, and the two have the same outline and are both embedded in the grouting groove.

[0008] Preferably, one end of the precast concrete roadbed is provided with a boring groove, and the outer edge of the inner reinforcing bar is distributed within the boring groove.

[0009] Preferably, the top of the precast concrete roadbed has at least two injection ports that communicate with the grouting groove from the upper surface.

[0010] Preferably, the alignment slot has at least two relatively distributed inner surfaces that fit against the opposite two sides of the rectangular connector, and otherwise maintains a predetermined distance. The mating surfaces of the two adjacent rows of alignment slots and the rectangular connectors are opposite.

[0011] Preferably, the grouting groove has a connecting slot that passes through the same row of rectangular plug bodies in sequence.

[0012] In the above technical solution, the anti-settlement composite structure for soft soil subgrade provided by this utility model has the following beneficial effects: 1. This system combines previously discrete prefabricated units into a continuous, rigid superstructure. Simultaneously, the bottom of the prefabricated roadbed is precisely connected to the pre-embedded piles via alignment slots, forming a "slab-pile" composite system. This ensures that the upper load can be effectively transferred and distributed to the lower pile foundation through the rigid slab, greatly improving the coordinated stress distribution between different treatment layers (piles, roadbed slab, and fill replacement area), avoiding overall failure due to interface slippage, and significantly improving the overall stability and load diffusion capacity of the structure.

[0013] 2. It effectively resists and disperses uneven settlement (differential settlement) of the roadbed, ensuring the smoothness of the road surface. At the same time, the reliable connection between the rigid plate and the pile foundation, as well as the interlocking action formed by the concave-convex interlocking between prefabricated units and the grouting, together provide strong horizontal restraint and shear resistance, which can effectively limit the horizontal deformation and displacement of soft soil roadbed under load or lateral earth pressure, overcoming the shortcomings of traditional methods in controlling horizontal deformation.

[0014] 3. Cast-in-place concrete piles serve as the primary vertical supports, directly transferring most of the load to deeper, better-quality soil or rock layers. Precast concrete subgrade acts as a bearing platform, evenly distributing the pavement load across multiple piles, avoiding stress concentration that occurs when loads are transferred through soft soil layers. The specific tolerance design between the rectangular connector and the alignment slot (partial side contact, partial gaps) ensures accurate installation and positioning while providing space for grout flow. The resulting grout filling layer further adjusts contact stress, resulting in smoother load transfer and effectively reducing the risk of localized plastic failure.

[0015] 4. By setting the outer edges of the outer and inner reinforcing bars extending into the grouting groove, and then encasing them in high-performance concrete mortar after grouting, a robust reinforced concrete connection joint is formed. This significantly improves the tensile, shear, and fatigue resistance of the connection between adjacent precast units, ensuring the integrity of the joint and the overall structure under long-term use. The rounded triangular or other irregularly shaped cross-sections of the reinforcing bars enhance the mechanical interlocking force with the grouting material. Attached Figure Description

[0016] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in this utility model. For those skilled in the art, other drawings can be obtained based on these drawings.

[0017] Figure 1 A schematic diagram of the overall structure provided for an embodiment of this utility model; Figure 2 This is a schematic diagram of the structure of the second concave-convex seat provided in an embodiment of the present utility model; Figure 3 A schematic diagram of the structure of an explosion provided for an embodiment of this utility model; Figure 4 This is a schematic diagram of the cross-sectional structure provided for an embodiment of the present utility model.

[0018] Explanation of reference numerals in the attached figures: 1. Precast concrete subgrade; 11. Alignment slot; 12. Grouting groove; 14. Outer edge of outer reinforcing bar; 15. Outer edge of inner reinforcing bar; 16. Injection port; 17. Connecting slot; 18. Boring slot; 2. First concave-convex seat; 3. Second concave-convex seat; 4. Cast-in-place concrete pile; 41. Rectangular plug body. Detailed Implementation

[0019] To enable those skilled in the art to better understand the technical solution of this utility model, the present utility model will be further described in detail below with reference to the accompanying drawings.

[0020] Please see Figure 1-4 This utility model provides a technical solution comprising two main parts: a precast concrete roadbed 1 and cast-in-place concrete piles 4.

[0021] The precast concrete roadbed 1 is a precast reinforced concrete slab, the length and width of which are designed according to construction transportation and hoisting capabilities. A first convex-concave seat 2 (e.g., a protrusion) is fixedly installed at one end along its length, and a second convex-concave seat 3 (e.g., a groove matching the first convex-concave seat 2) is fixedly installed at the other end. Multiple precast concrete roadbeds 1 are assembled on-site by interlocking the first convex-concave seats 2 and second convex-concave seats 3 at adjacent ends, thereby splicing them into a continuous roadbed slab body. A grouting groove 12 is also provided on the end face of the precast concrete roadbed 1 located at the end of the first convex-concave seat 2. After two adjacent roadbed units are spliced, the grouting groove 12, together with the corresponding end face (or another groove) of the adjacent unit, forms a closed cavity. At least two injection ports 16 are provided on the top of the precast concrete roadbed 1. These injection ports 16 extend downwards from the upper surface and communicate with the grouting groove 12 for subsequent injection of grout.

[0022] A steel mesh 13 is pre-embedded inside the precast concrete subgrade 1. Part of the longitudinal main reinforcement bars of this steel mesh 13 extend outwards from the end face of the second concave-convex seat 3, forming the outer edge of the outer reinforcement bar 14. In this embodiment, the outer edge of the outer reinforcement bar 14 has a rounded triangular cross-section, consists of multiple bars arranged in a linear array along the width of the slab to increase the contact area and interlocking force with the grouting material. Simultaneously, another part of the longitudinal main reinforcement bars (or additional short bars) of the steel mesh 13 extend outwards from the same end face (i.e., the end of the second concave-convex seat 3), forming the inner edge of the outer reinforcement bar 15. The inner edge of the outer reinforcement bar 15 is located within the contour enclosed by the outer edge of the outer reinforcement bar 14, and its cross-sectional contour is consistent with that of the outer edge of the outer reinforcement bar 14 (e.g., also a rounded triangular shape), but slightly smaller in size. A boring groove 18 is also provided on the end face of the precast concrete subgrade 1, and the inner edge of the outer reinforcement bar 15 is distributed within this boring groove 18. When two roadbed units are spliced, the outer edge 14 of the outer reinforcing bar and the outer edge 15 of the inner reinforcing bar at this end will be inserted into the grouting groove 12 of the adjacent unit.

[0023] At the bottom of the precast concrete roadbed 1, multiple alignment slots 11 are provided in a rectangular matrix. These alignment slots 11 are used to connect with the lower piles.

[0024] The cast-in-place concrete pile 4 is a vertical reinforcement formed by pre-drilling holes and pouring concrete in soft soil foundation. A rectangular connector 41 is fixedly installed at its top. This rectangular connector 41 is typically cast integrally with the pile 4, and its cross-sectional dimensions are slightly smaller than the alignment slots 11 at the bottom of the precast concrete subgrade 1. The key design feature is that at least two opposing inner surfaces of the alignment slots 11 (e.g., two surfaces along the longitudinal direction of the road) are designed to fit tightly against the corresponding two surfaces of the rectangular connector 41 to provide primary lateral positioning and constraint; while the other two surfaces (e.g., two surfaces along the transverse direction of the road) maintain a predetermined distance from the rectangular connector 41, forming gaps. Furthermore, the tight-fitting surfaces of adjacent rows of alignment slots 11 and rectangular connectors 41 are opposite. For example, the connectors 41 of the first row of piles fit against the alignment slots 11 on the longitudinal side, with a gap on the transverse side; the adjacent second row of piles, however, fits against the second row on the transverse side, with a gap on the longitudinal side. This staggered fit design ensures proper positioning while providing a continuous grout flow channel around the top of all piles.

[0025] A connecting slot 17 is also provided on the bottom wall of the grouting groove 12. The connecting slot 17 passes through the corresponding area at the top of all the rectangular plugs 41 in the same row (along the longitudinal direction of the roadbed) in the vertical direction, or passes through the path connecting the bottom of the grouting groove 12 with the space below, so that the interior of the grouting groove 12 is connected to the gap between all the alignment slots 11 and the rectangular plugs 41.

[0026] The assembly and construction process is as follows: First, cast-in-place concrete piles 4 are constructed on-site according to the design location, ensuring that the rectangular plug-in body 41 at the top is accurately positioned and at the same elevation.

[0027] Then, using lifting equipment, the precast concrete roadbed 1 is hoisted above the pile column and slowly lowered so that the rectangular plug 41 at the top of the pile column is precisely inserted into the corresponding alignment slot 11 at the bottom of the precast roadbed.

[0028] Repeat this process, laying adjacent precast concrete subgrade 1, and aligning the first convex-concave seat 2 (or second convex-concave seat 3) at one end with the first convex-concave seat 2 (or second convex-concave seat 3) at the other end of the laid subgrade. At this time, the outer edge 14 and inner edge 15 of the outer reinforcing steel bar of the later laid subgrade will be inserted into the grouting groove 12 of the first laid subgrade.

[0029] Once a certain number of roadbed units (such as a construction section) are assembled, grouting connection work can be carried out. First, high-strength cement mortar or fine aggregate concrete with excellent fluidity is injected through the injection port 16 at the top of the precast concrete roadbed 1. The grout is poured into the grouting groove 12, filling the gaps between exposed reinforcing bars, and flows downwards through the connecting slot 17, gradually filling the gaps reserved between all rectangular plug-in bodies 41 and the alignment slots 11.

[0030] About 15 minutes after the grouting begins (the time can be adjusted according to the initial setting of the grout), after the fluid grout has initially filled the space, concrete mixture with an appropriate amount of gravel is poured through the injection port 16 to further fill and compact the main space of the grouting trench 12.

[0031] Finally, the grouting material is vibrated through the injection port 16 or the pre-reserved holes to ensure that every corner is filled with the grouting material and achieves compaction. After the grouting material reaches the design strength, the adjacent precast concrete subgrades 1 and the subgrades and piles are connected by the grouting body and steel bars to form a rigid whole.

[0032] After that, the pavement layer (asphalt) can be laid on the composite structure.

[0033] The foregoing description only illustrates certain exemplary embodiments of the present invention. Undoubtedly, those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.

Claims

1. A composite structure for preventing settlement in soft soil subgrade, characterized in that, include: A precast concrete roadbed (1) has a first concave-convex seat (2) and a second concave-convex seat (3) fixedly installed at one end and the other end respectively, and multiple precast concrete roadbeds (1) are assembled by the first concave-convex seat (2) and the second concave-convex seat (3) at adjacent ends. The cast-in-place concrete pile (4) is embedded in the soft soil and a rectangular plug (41) is fixedly installed on its top. The rectangular plug (41) is plugged into a plurality of matrix-distributed alignment slots (11) opened at the bottom of the precast concrete roadbed (1).

2. The anti-settlement composite structure for soft soil subgrade according to claim 1, characterized in that, A grouting groove (12) is provided on the end face of the first concave-convex seat (2) on the side of the precast concrete roadbed (1).

3. The anti-settlement composite structure for soft soil subgrade according to claim 2, characterized in that, The precast concrete roadbed (1) includes a steel mesh, the portion of which extends to the exposed end face of the precast concrete roadbed (1) located on the side of the second concave-convex seat (3) is the outer edge of the outer steel bar (14).

4. The anti-settlement composite structure for soft soil subgrade according to claim 3, characterized in that, The outer edge of the outer steel bar (14) is a rounded triangular structure, and there are multiple of them, which are distributed in a linear array.

5. A composite structure for preventing settlement in soft soil subgrade according to claim 4, characterized in that, The steel mesh is provided with an outer edge (15) of the inner steel bar that extends to one side of the precast concrete roadbed (1) with the end face exposed. The outer edge of the inner steel bar (15) is located within the outer edge of the outer steel bar (14), and the two have the same outline and are both embedded in the grouting groove (12).

6. The anti-settlement composite structure for soft soil subgrade according to claim 5, characterized in that, One end of the precast concrete roadbed (1) is provided with a boring groove (18), and the outer edge (15) of the inner steel bar is distributed in the boring groove (18).

7. A composite structure for preventing settlement in soft soil subgrade according to claim 5, characterized in that, The top of the precast concrete roadbed (1) has at least two injection ports (16) that are connected to the grouting groove (12) from the upper surface.

8. The anti-settlement composite structure for soft soil subgrade according to claim 1, characterized in that, The alignment slot (11) has at least two relatively distributed inner surfaces that fit against the opposite two sides of the rectangular plug (41), and otherwise maintains a predetermined distance. The mating surfaces of the adjacent rows of alignment slots (11) and rectangular plugs (41) are opposite.

9. A composite structure for preventing settlement in soft soil subgrade according to claim 5, characterized in that, The grouting groove (12) has a connecting slot (17) that passes through the same row of rectangular plugs (41) in sequence.