Super-hydrophobic soil-cement macadam ecological field pavement structure

By using a superhydrophobic soil-bound gravel ecological field road structure, the problem of traditional field roads softening during the rainy season has been solved, achieving the effect of keeping the road surface dry and the structure stable on rainy days, while improving the micro-ecological environment.

CN225013907UActive Publication Date: 2026-11-24GUANGDONG YUEHE SPACE PLANNING TECH CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522830286.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-31
Publication Date
2026-11-24
Estimated Expiration
2035-12-31

AI Technical Summary

Technical Problem

Traditional field roads are prone to absorbing water and softening during the rainy season, leading to a sharp drop in load-bearing capacity and the appearance of problems such as mud, ruts, and potholes. Hardened road surfaces, on the other hand, block the natural infiltration path of surface water and disrupt the micro-ecological balance of farmland.

Method used

The ecological field pavement structure using superhydrophobic soil-bound gravel includes a soft base layer, a subbase layer, a superhydrophobic soil-bound gravel surface layer, a wear layer, and a vegetation layer. The superhydrophobic material prevents rainwater infiltration, and the vegetation layer improves the micro-ecological environment.

Benefits of technology

In continuous rainfall or high humidity conditions, the road surface remains dry and stable, improving the passage of agricultural machinery and personnel, extending the service life of the road, and improving the local micro-ecological environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225013907U_ABST
    Figure CN225013907U_ABST
Patent Text Reader

Abstract

This utility model discloses a superhydrophobic soil-bound gravel ecological field pavement structure, relating to the field of pavement structures. It includes: a soft base layer, a subbase layer laid on top of the soft base layer, a superhydrophobic soil-bound gravel surface layer laid on top of the subbase layer, an abrasion layer laid on top of the superhydrophobic soil-bound gravel surface layer, a protective layer laid on top of the abrasion layer, and a plant layer laid in the middle area of ​​the superhydrophobic soil-bound gravel surface layer. The soft base layer has a thickness of 25cm, the subbase layer has a thickness of 15cm, the superhydrophobic soil-bound gravel surface layer has a thickness of 8-15cm, the abrasion layer has a thickness of 1-3cm, and the protective layer has a thickness of 1cm. This utility model, through the superhydrophobic soil-bound gravel surface layer, gives the pavement excellent superhydrophobic properties, effectively preventing rainwater from seeping into the structural layer and avoiding mud, ruts, and structural damage caused by water absorption and softening.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of road structure technology, specifically to a superhydrophobic soil-cement-gravel ecological field road structure. Background Technology

[0002] Field roads are an indispensable infrastructure for agricultural production and rural life. They mainly refer to roads located inside or around agricultural production areas such as farmland, orchards, and vegetable gardens, used for the passage of agricultural machinery, transportation of agricultural products, and daily travel of farmers.

[0003] Traditional field roads often use compacted soil, mud-bound gravel, or simple concrete structures. Although these are inexpensive, the soil or ordinary mud-bound gravel surfaces are prone to absorbing water and softening during the rainy season, leading to a sharp drop in load-bearing capacity and problems such as mud, ruts, and potholes. This seriously affects the efficiency and safety of agricultural machinery. Hardened surfaces (such as cement or asphalt) have higher strength, but they block the natural infiltration path of surface water, exacerbate surface runoff and soil erosion, disrupt the micro-ecological balance of farmland, and lack vegetation cover, which is not conducive to biodiversity conservation and landscape harmony. Utility Model Content

[0004] The purpose of this invention is to provide a superhydrophobic soil-bound gravel ecological field road structure to solve the problem that the structure of traditional field roads in the prior art is easily eroded by the natural environment.

[0005] To achieve the above objectives, this utility model provides the following technical solution: a superhydrophobic soil-bound gravel ecological field pavement structure, comprising:

[0006] The soft base layer has a subbase layer on top, a superhydrophobic soil-bound gravel surface layer on top of the subbase layer, an abrasion layer on top of the superhydrophobic soil-bound gravel surface layer, a protective layer on top of the abrasion layer, and a plant layer in the middle area of ​​the superhydrophobic soil-bound gravel surface layer. The soft base layer is 25cm thick, the subbase layer is 15cm thick, the superhydrophobic soil-bound gravel surface layer is 8-15cm thick, the abrasion layer is 1-3cm thick, and the protective layer is 1cm thick.

[0007] Furthermore, the soft base layer is located below the field surface and is made of dry soil mixed with slaked lime.

[0008] Furthermore, the cushion layer is laid on top of the soft base layer, and the cushion layer is made of lime-soil mixed with quicklime.

[0009] Furthermore, the superhydrophobic soil-bound crushed stone surface layer is laid on top of the subbase layer, and the superhydrophobic soil-bound crushed stone surface layer is composed of superhydrophobic emulsion, soil, crushed stone, and slaked lime.

[0010] Furthermore, the plant layer is cultivated from evenly sown grass seeds.

[0011] Furthermore, the wear layer is composed of small stones, and the protective layer is composed of coarse sand.

[0012] Compared with existing technologies, the present invention provides a superhydrophobic soil-bound gravel ecological field road structure. Through the superhydrophobic soil-bound gravel surface layer, the road surface has excellent superhydrophobic properties, which can effectively prevent rainwater from seeping into the structural layer and avoid mud, ruts and structural damage caused by water absorption and softening. In continuous rainfall or high humidity environments, traditional field roads are often impassable due to severe water accumulation, while the superhydrophobic soil-bound gravel ecological field road of this application can still maintain a dry surface and structural stability, improve the passage and operation efficiency of agricultural machinery and personnel in rainy weather, and extend the service life of the road.

[0013] A plant layer is set in the middle area of ​​the superhydrophobic soil-bound gravel surface layer, and Zoysia japonica seeds are evenly sown. This not only uses the grass root network to consolidate the surface soil and prevent soil erosion, but also improves the local micro-ecological environment. Zoysia japonica is characterized by its tolerance to trampling, drought resistance, and well-developed root system. Its growth process helps to loosen the soil and increase the organic matter content, which indirectly promotes the growth of surrounding crops. At the same time, all materials used in the entire pavement structure are natural and have low environmental impact. The soil superhydrophobic emulsion is prepared from natural oils and natural soil-derived silica derivatives. It is non-toxic and harmless and does not pollute farmland soil and water. Attached Figure Description

[0014] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in this utility model. For those skilled in the art, other drawings can be obtained based on these drawings.

[0015] Figure 1 This is a schematic diagram of the overall structure provided for an embodiment of the present utility model.

[0016] Explanation of reference numerals in the attached figures:

[0017] 1. Soft base layer; 2. Subbase layer; 3. Superhydrophobic soil-bound gravel surface layer; 4. Wear layer; 5. Protective layer; 6. Plant layer. Detailed Implementation

[0018] To enable those skilled in the art to better understand the technical solution of this utility model, the present utility model will be further described in detail below with reference to the accompanying drawings.

[0019] As attached Figure 1 As shown:

[0020] Example 1:

[0021] This utility model provides a superhydrophobic soil-bound gravel ecological field pavement structure, including:

[0022] The soft base layer 1 is topped with a cushion layer 2, which is topped with a superhydrophobic soil-bound gravel surface layer 3. The superhydrophobic soil-bound gravel surface layer 3 is topped with an abrasion layer 4, which is topped with a protective layer 5. A plant layer 6 is laid in the middle area of ​​the superhydrophobic soil-bound gravel surface layer 3. The thickness of the soft base layer 1 is 25cm, the thickness of the cushion layer 2 is 15cm, the thickness of the superhydrophobic soil-bound gravel surface layer 3 is 15cm, the thickness of the abrasion layer 4 is 2cm, and the thickness of the protective layer 5 is 1cm.

[0023] Specifically, the soft base layer 1 is set below the field surface and is made of dry soil mixed with quicklime. The cushion layer 2 is laid on top of the soft base layer 1 and is made of lime-soil mixed with quicklime. The superhydrophobic soil-bound gravel surface layer 3 is laid on top of the cushion layer 2 and is made of gravel mixed with quicklime. The plant layer 6 is formed by uniformly sown grass seeds. The abrasion layer 4 is composed of small stones. The protective layer 5 is composed of coarse sand.

[0024] As shown above, the soft base layer 1 is located below the field surface, with a thickness of 25cm. It consists of dry soil mixed with 8% slaked lime. The addition of slaked lime improves the performance of the soil, enhances the stability and strength of the soft base layer 1, and provides a solid foundation support for the entire road structure. The subbase layer 2 is located above the soft base layer 1, with a thickness of 15cm. It is composed of soil mixed with 12% lime. The reasonable ratio of lime and soil further enhances the load-bearing capacity and deformation resistance of the subbase layer 2, effectively dispersing the load transmitted from the road surface and reducing the pressure on the soft base layer 1. The superhydrophobic soil is well-bonded. The crushed stone surface layer 3, with a thickness of 15cm, is laid on top of the subbase layer 2. This superhydrophobic soil-bound crushed stone surface layer 3 is made by mixing soil, crushed stone, slaked lime, and superhydrophobic materials. This soil superhydrophobic emulsion is a water-based nanoemulsion prepared from natural oils and silica derivatives found in natural soil. When mixed with soil, it removes water-absorbing hydroxyl groups from the soil, forming a nanoporous microparticle structure, thereby greatly increasing the water droplet contact angle. This gives the superhydrophobic soil-bound crushed stone surface layer 3 superhydrophobic properties, effectively preventing rainwater infiltration and protecting the road structure. The plant layer 6 is placed on top of the superhydrophobic soil... The middle area of ​​the mud-bound gravel surface layer 3 is formed by evenly sowing grass seeds. Zoysia japonica seeds are selected because they are highly adaptable, have a well-developed root system, and can grow well in this road surface environment. The plant layer 6 not only serves to stabilize the soil and protect the slope but also enhances the ecological and aesthetic appeal of the road surface and promotes the balance of the farmland ecosystem. The abrasion layer 4, located above the superhydrophobic mud-bound gravel surface layer 3, consists of even finer stones and is 2cm thick. Its main function is to resist wear and tear from vehicle traffic and natural factors, protect the underlying structure, and extend the road surface's lifespan. This extends the lifespan of the road surface and improves driving comfort. The protective layer 5 is placed above the wear layer 4 and consists of coarse sand with a thickness of 1cm. Before laying, a layer of superhydrophobic soil emulsion is sprayed and mixed with coarse sand to further enhance the superhydrophobic properties of the road surface. The texture of the coarse sand can provide a certain degree of protection for the wear layer 4, preventing it from being excessively eroded by external factors. Together with the superhydrophobic soil emulsion, it provides comprehensive protection for the road surface. After the road surface construction is completed, it is compacted again, and the compaction degree should be 85%-98%.

[0025] Construction requirements:

[0026] 1. The roadbed should have sufficient strength, stability, resistance to deformation, and durability, and its surface should be flat;

[0027] 2. A test section should be constructed before road construction. The length of the test section should be 10 m to 50 m. Based on the test section's test indicators, the control requirements for construction should be clarified. Construction safety should be carried out in accordance with the relevant provisions of JTG F90.

[0028] 3. Before construction, all necessary equipment and temporary sites for the plant mixing method should be prepared.

[0029] Construction preparation:

[0030] 1. Before construction, sampling tests should be conducted on the soil materials of the road surface layer of the project, and a test report should be issued based on the test results;

[0031] 2. Sufficient dry soil should be stockpiled according to the designed road length before surface layer construction;

[0032] 3. Before construction, construction zones should be rationally divided according to the project site size and the distribution of planned roads, and a scientific construction organization plan should be formulated to ensure the continuity of construction.

[0033] 4. To prevent erosion from rainfall during the drying and curing period of the surface layer, it is advisable to prepare recyclable agricultural film before the surface layer construction.

[0034] Equipment requirements:

[0035] 1. Excavators and bulldozers: used for roadbed excavation and leveling;

[0036] 2. Rotary tiller or soil stabilization mixer: used for breaking up soil and mixing materials in road surface mixing construction;

[0037] 3. Road grader: Used for initial and fine leveling of road surfaces;

[0038] 4. Water trucks or spraying equipment: used for spraying superhydrophobic materials;

[0039] 5. Road roller (6 t ~ 8 t): Used for initial compaction of surface layer mixture;

[0040] 6. Road roller (18 t~22 t): Used for compacting roadbed and pavement;

[0041] 7. Soil crusher: Used for crushing and screening soil materials;

[0042] 8. Mixing equipment: used for centralized mixing;

[0043] 9. Paver: Used for paving road surface mixtures;

[0044] 10. Dump trucks or self-dumping tractors: used for short-distance transportation of road mixtures.

[0045] Roadbed construction:

[0046] 1. During construction, weeds, silt, stagnant water, and humus within the road width area should be thoroughly removed;

[0047] 2. The roadbed leveling should be carried out according to the design cross-section and elevation requirements to prevent under-excavation and over-excavation;

[0048] 3. The roadbed should not have phenomena such as frost heave, springiness, peeling, undulation, or water accumulation. After compaction by a 6t to 8t road roller, the wheel track depth should not exceed 5 mm.

[0049] 4. Side ditches should be reserved on the outer side of the roadbed to drain rainwater and prevent the roadbed from being soaked in water;

[0050] 5. After the subgrade construction inspection is passed, the pavement construction should be carried out continuously. If the pavement cannot be laid continuously, water should be sprinkled to keep the subgrade surface moist and vehicles should be prohibited from passing through.

[0051] Surface layer construction:

[0052] 1. The surface layer construction should select different construction techniques according to weather conditions and construction season. The construction methods are divided into road mixing method and plant mixing method.

[0053] 2. During non-flood seasons, on consecutive sunny days, when the construction site is dry and the soil moisture content meets the construction requirements, the road mixing method should be adopted for construction.

[0054] 3. Plant mixing method should be used for construction during the flood season or during periods of intermittent rainfall.

[0055] The road mixing method construction process includes the following:

[0056] 1. Surveying and setting out: Before the surface layer construction, set up index stakes on both sides of the formed roadbed. The index stakes should be clearly marked to indicate the design height of the edge of the pavement structure layer. Stakes should be set every 15 m to 20 m on straight sections of the route and every 10 m to 15 m on curved sections.

[0057] 2. Spreading the soil: The prepared dry soil should be spread in sufficient thickness and width. After spreading the soil, branches, turf and large particles should be removed from the soil. Use a rotary tiller or soil stabilizer to break the soil to the required particle size and then use a grader to initially level the surface soil.

[0058] 3. Spread crushed stone and quicklime. The crushed stone added to the surface soil should have sufficient strength and wear resistance. Spread the crushed stone and quicklime evenly on the soil surface according to the design requirements, and then mix them thoroughly and evenly with a rotary tiller or stabilized soil mixer.

[0059] 4. Spraying and mixing superhydrophobic materials: Mix and dilute the superhydrophobic emulsion concentrate with water in a ratio of 1:6 to 1:8. It is advisable to use a pressure or spray nozzle water truck to spray the mixture evenly on the road surface. It is advisable to divide the spraying into 2 to 3 times. After each spraying, a rotary tiller or stabilized soil mixer should be used to mix the mixture to ensure that the mixture is fully moistened and the color is uniform.

[0060] 5. Initial compaction and shaping: After the super-hydrophobic soil-cement aggregate mixture is evenly mixed, grass seeds should be evenly sown manually in the middle of the wheel tracks on the road surface. After initial leveling with a grader, a 6t-8t pneumatic tire roller should be used for initial compaction, and then the surface should be leveled and shaped with a grader.

[0061] 6. Compaction: The shaped mixture structure layer should be compacted at its optimum moisture content using an 18-22 t roller across the full width. The first two passes should be at a low speed of 1.5 km / h to 1.7 km / h, followed by 2.0 km / h to 2.5 km / h, combined with vibratory compaction. If the mixture is too wet, it should be allowed to dry before compaction. Compaction should result in no obvious wheel tracks and should not exhibit springiness, looseness, or peeling.

[0062] 7. Laying the wearing course: After the road surface is compacted, the graded wearing course and protective course should be evenly spread manually, and then a super hydrophobic material should be sprayed on the surface. The spraying should be even and without omissions. After spraying, the road roller should be used to flatten the wearing course.

[0063] 8. Sun-drying and curing: After the wear layer is laid, the road should be closed to allow it to dry naturally. If it rains during the curing period, it should be covered with a film for protection. The curing period in sunny weather should not be less than 7 days.

[0064] 9. Shoulder backfilling: During the maintenance period, manual backfilling of the shoulders should be carried out, and proper connection treatment between the road surface edge and the shoulder should be ensured.

[0065] The plant-mixed concrete construction process includes the following:

[0066] 1. Surveying and setting out: Before the surface layer construction, set up index stakes on both sides of the formed roadbed. The index stakes should be clearly marked to indicate the design height of the edge of the pavement structure layer. Stakes should be set every 15 m to 20 m on straight sections of the route and every 10 m to 15 m on curved sections.

[0067] 2. Select a mixing site. The mixing site should preferably be located within the project area and should be adjacent to the soil material area. Dry soil materials should be covered with waterproof tarpaulins.

[0068] 3. Centralized mixing: Calculate the amount of superhydrophobic diluent to be added to each hopper of material based on the capacity of the mixing machine hopper and the moisture content of the soil, to ensure that the mixture is fully moistened until the color of the mixture is uniform.

[0069] 4. Transportation: Transport the well-mixed material to the construction site using dump trucks or self-dumping tractors.

[0070] 5. Paving: Asphalt concrete pavers or stabilized soil pavers should be used for paving the mixture. The production capacity of the mixing plant and the paver should be matched. The paver should pave continuously. If the production capacity of the mixing plant is small, the paver should pave at a low speed to reduce the situation where the paver stops to wait for materials.

[0071] 6. The shaping, compaction, abrasion course laying, drying and curing of the surface mixture shall be carried out in accordance with the road mixing method.

[0072] The foregoing description only illustrates certain exemplary embodiments of the present invention. Undoubtedly, those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.

Claims

1. A superhydrophobic soil-bound gravel ecological field pavement structure, characterized in that, include: A soft base layer (1) is provided with a cushion layer (2) at the top of the soft base layer (1), a superhydrophobic soil-bound gravel surface layer (3) is provided at the top of the cushion layer (2), an abrasion layer (4) is provided at the top of the superhydrophobic soil-bound gravel surface layer (3), a protective layer (5) is provided at the top of the abrasion layer (4), and a plant layer (6) is provided in the middle area of ​​the superhydrophobic soil-bound gravel surface layer (3). The soft base layer (1) is 25cm thick, the cushion layer (2) is 15cm thick, the superhydrophobic soil-bound gravel surface layer (3) is 8-15cm thick, the abrasion layer (4) is 1-3cm thick, and the protective layer (5) is 1cm thick.

2. The superhydrophobic soil-bound gravel ecological field pavement structure according to claim 1, characterized in that, The soft base layer (1) is set below the field surface and is made of dry soil mixed with slaked lime.

3. The superhydrophobic soil-bound gravel ecological field road structure according to claim 1, characterized in that, The cushion layer (2) is laid on top of the soft base layer (1), and the cushion layer (2) is made of lime-soil mixed with quicklime.

4. The superhydrophobic soil-bound gravel ecological field pavement structure according to claim 1, characterized in that, The superhydrophobic soil-cement-gravel surface layer (3) is laid on top of the subbase layer (2). The superhydrophobic soil-cement-gravel surface layer (3) is made of superhydrophobic emulsion, soil, gravel and quicklime.

5. The superhydrophobic soil-bound gravel ecological field pavement structure according to claim 1, characterized in that, The plant layer (6) is formed by uniformly sown grass seeds.

6. The superhydrophobic soil-bound gravel ecological field pavement structure according to claim 1, characterized in that, The wear layer (4) is composed of small stones, and the protective layer (5) is composed of coarse sand.