A new and old roadbed lap joint structure
By installing a double-layer steel-plastic composite grid at the junction of the old and new roadbeds and optimizing the contact surface treatment, the problems of uneven settlement between the old and new roadbeds and insufficient material fusion were solved, thereby improving the stability and durability of the structure and reducing safety hazards and crack risks.
Patent Information
- Application Number
- CN202522325049.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-03
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-11-03
AI Technical Summary
In road expansion or repair projects, uneven settlement between the old and new roadbeds can lead to longitudinal cracking, insufficient material bonding, large differences in rigidity, and uneven settlement can cause height differences and dynamic impacts, posing safety risks and structural instability.
Double-layer steel-plastic composite grids are installed at the junction of new and old roadbeds. A frame is formed by cross-connection to enhance longitudinal and transverse interlocking. Combined with a roughening treatment layer and a surface cleaning layer, the contact surface is optimized. Locking bolts and high-strength steel wires are used to reinforce the joints to improve structural stability and durability.
It significantly improves the overall stability and durability of the new and old roadbed overlap structure, reduces safety hazards, enhances load distribution capacity, prevents cracks and damage, and improves driving smoothness and safety.
Smart Images

Figure CN225013908U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of roadbed and pavement construction engineering technology, and more specifically, to a structure for connecting new and old roadbeds. Background Technology
[0002] In road expansion or repair projects, the connection between the new road and the existing road is crucial. Because the old roadbed gradually stabilizes after long-term operation and load-bearing, the new roadbed inevitably undergoes post-construction settlement, resulting in uneven settlement between the old and new roadbeds. This can cause longitudinal cracking, which reflects onto the road surface, affecting future traffic safety and road lifespan. The main problems are as follows: 1. As old materials age, they expand, while new roadbed materials shrink after curing, resulting in increased deformation differences. This can easily lead to uncontrolled deformation and the formation of a crack propagation network.
[0003] 2. Insufficient integration of materials between the old and new roadbeds. After years of load-bearing capacity integration, the internal structure of the old roadbed is basically stable. After the newly constructed road surface is filled, there will be areas with significant differences in rigidity.
[0004] 3. When the settlement of the old and new roadbeds is uneven, there will be a large height difference (such as more than 0.8cm) at the joint between the old and new roadbeds. When a heavy vehicle passes over it, it will cause instantaneous dynamic impact. Improper slope transition can easily lead to vehicle bouncing, resulting in safety risks. Utility Model Content
[0005] Therefore, the purpose of this utility model is to design a new and old roadbed overlapping structure to construct an overall configuration of interconnected new and old roadbeds. Steel-plastic composite grids are added between the upper layer of the old roadbed and the base layer of the new roadbed, and between the base layer and the lower layer of the new roadbed at the junction of the new and old roadbeds. The steel-plastic composite grids are made into a frame by cross-connection to ensure that the composite grids play an interlocking role in both the longitudinal and transverse directions of the overall road, thereby improving the overall structural stability and durability of the new and old roadbed overlapping structure and reducing safety hazards.
[0006] This utility model provides a structure for connecting old and new roadbeds, which is installed at the connection between the old and new roadbeds. It includes: two layers of steel-plastic composite grids disposed between the subgrades of the old and new roadbeds. The two layers of steel-plastic composite grids are respectively embedded between the upper layer of the old roadbed and the base layer of the new roadbed, and between the base layer and the lower layer of the new roadbed. The steel-plastic composite grids are formed by several horizontal strips and several vertical strips that intersect each other perpendicularly, and the two ends of the vertical strips are respectively tied with steel bars.
[0007] This new and old roadbed overlap structure significantly improves overall stability and deformation resistance by laying double-layer steel-plastic composite geogrids at key locations and employing a specific binding and fixing method. The double-layer steel-plastic composite geogrids are embedded between different structural layers of the new and old roadbeds, effectively restraining soil displacement, enhancing the overall integrity of the roadbed, effectively reducing differential settlement between the two roadbeds, and ensuring overall structural stability. The longitudinal and transverse ribs (longitudinal and transverse bands) of the geogrid work together to produce a strong interlocking effect on the concrete, thereby significantly improving the roadbed's deformation resistance and reducing uneven settlement. The steel-plastic composite geogrid, with its intersecting transverse and longitudinal bands forming a mesh structure, can evenly distribute vehicle loads and stresses generated by the superstructure over a wider area of the soil, effectively dispersing loads, significantly reducing local stress in the overlap area of the new and old roadbeds, reducing stress concentration, and effectively preventing cracks and damage caused by stress concentration.
[0008] Laying the geogrid between the upper and lower layers of the roadbed, as well as between the lower and lower layers, can enhance the friction and interlocking between the structural layers, strengthen the interlayer bond, prevent interlayer slippage, ensure that the roadbed layers are subjected to stress in a coordinated manner, and improve the structural durability.
[0009] The method of fixing the longitudinal strips by tying steel bars at both ends greatly enhances the anchoring force between the grid and the subgrade soil. Tying steel bars at both ends of the longitudinal strips enhances the anchoring effect and can effectively resist the possible slippage or peeling of the grid under stress, ensuring the reinforcement effect is long-lasting and stable.
[0010] Furthermore, high-strength steel wires are tied at the intersections of the horizontal and vertical strips, and the high-strength steel wires at each intersection form a reinforcing node. The reinforcing node has an approximately spherical structure, and the outer contour dimensions of each reinforcing node are consistent.
[0011] The tensile strength of the steel-plastic composite geogrid is borne by the warp and weft woven transverse and longitudinal strips (preferably steel wire material), which generate extremely high tensile modulus under low strain capacity. When vehicles pass and generate loads, the steel-plastic composite geogrid will generate extremely high tensile strength, playing an interlocking role in both the longitudinal and transverse directions of the overall road, greatly enhancing the overall stability, improving the strength of the road pavement structure, and reducing settlement and cracking in the overlapping area.
[0012] By binding high-strength steel wires at intersections to form an approximately spherical structure, the connection strength at the grid nodes can be effectively enhanced, significantly improving the node strength and overall integrity. This prevents problems such as weld cracking or rib slippage under stress. This reinforced node design allows the grid to work together better under longitudinal and transverse stress, improving the stability and load-bearing capacity of the overall structure.
[0013] The near-spherical structure of the reinforced joints, with their consistent external dimensions, optimizes stress distribution and deformation resistance, helping to evenly disperse stress concentration at the joints and more effectively transfer loads to the longitudinal and transverse ribs. This effectively reduces local deformation and enhances the geogrid's resistance to lateral displacement in projects such as soft soil foundation reinforcement. The consistent dimensions of the reinforced joints facilitate standardized construction. Preferably, U-shaped nail fixing and mesh overlapping methods ensure connection quality, reduce construction difficulty, and improve construction efficiency and reliability. This reinforced joint design represents a significant improvement in steel-plastic geogrid technology and is particularly suitable for highway and railway subgrade reinforcement and retaining wall construction projects where high joint strength is required. Furthermore, this structural design better adapts to machine compaction, reducing construction damage.
[0014] Furthermore, the reinforcing node is provided with a locking bolt, which is sleeved on the outside of the high-strength steel wire, and the high-strength steel wire is locked and fixed at the intersection of the horizontal and vertical strips by the locking bolt.
[0015] Locking bolts act directly on the high-strength steel wire, mechanically securing it to the intersection of nodes. This effectively prevents slippage or displacement of the wire under stress, ensuring the stability of the connection. Compared to connections relying solely on friction, mechanical locking provides more reliable anti-slip performance, improving connection reliability. The tightening action of the locking bolts increases the contact pressure between the high-strength steel wire and the transverse and longitudinal strips, thereby enhancing the overall load-bearing capacity and fatigue resistance at the node, strengthening the joint. This is particularly suitable for structural reinforcement applications requiring dynamic loads or long-term stress.
[0016] The installation and adjustment of locking bolts are relatively simple, allowing construction workers to quickly complete the tightening and fixing of nodes, making construction convenient and efficient. It also facilitates fine-tuning of nodes during construction, ensuring installation accuracy.
[0017] The locking bolt design can accommodate high-strength steel wires of different diameters and specifications, exhibiting strong versatility. Furthermore, this node type can be flexibly applied to reinforcement scenarios at various intersection angles, meeting the reinforcement needs of complex structures. Nodes secured with locking bolts allow for easier observation of bolt tightness during later maintenance and inspection, facilitating the timely detection and handling of loosening issues.
[0018] Furthermore, the surfaces of the horizontal and vertical strips are respectively provided with rough textures of different configurations, and the trajectory lines along the textures of the horizontal strip and the vertical strip are both curves.
[0019] The design of setting curved patterns on the surface of the horizontal and vertical strips can improve the friction coefficient between the steel-plastic composite grating and the road base layer.
[0020] Preferably, the ribs are pressed into a rough texture through a surface treatment process, which increases the interlocking effect between the grid and the soil, prevents slippage, and ensures the stability of the reinforced structure.
[0021] The rough texture of the surface increases the friction coefficient between the grid and the soil, making it suitable for projects such as soft soil foundation reinforcement and road crack prevention. It can effectively disperse load stress and extend service life.
[0022] Furthermore, the new and old roadbed overlapping structure also includes: a roughening treatment layer disposed on the upper part of the upper layer of the old roadbed, the thickness of the roughening treatment layer being 1 / 5 to 1 / 3 of the upper layer of the old roadbed.
[0023] Setting a roughening layer in the joint structure between new and old roadbeds can enhance the adhesion and integrity between them, solving the problem of weak connection caused by differences in material properties and uneven settlement. The roughening process removes the smooth layer on the surface of the old roadbed, forming an uneven, rough surface, which significantly increases the contact area between the new and old materials and increases the roughness of the contact surface.
[0024] Furthermore, this rough surface is more conducive to the penetration and anchoring of adhesive materials (such as asphalt binders), thereby forming a stronger mechanical interlocking effect, improving bond strength, and effectively reducing the risk of cracking and delamination at the joint. Good bonding performance promotes stress transfer, which helps vehicle loads and temperature stresses to be transferred more evenly in the joint area, avoiding stress concentration and improving the overall stability and durability of the road surface.
[0025] Furthermore, the new and old roadbed overlapping structure also includes: a clearing layer set on the slope surface of the old roadbed, the thickness of which is 1 / 6 to 1 / 5 of the roadbed thickness at the junction of the old and new roadbeds.
[0026] The clearing layer placed on the slope of the old roadbed in the overlapping structure of the new and old roadbeds can effectively reduce the physical isolation between the new and old roadbeds by removing the loose surface soil on the slope of the old roadbed and laying a clearing layer of a certain thickness, so that the two can be better integrated into a whole, thereby reducing uneven settlement caused by poor bonding.
[0027] The application of a surface clearing layer helps to drain water from the slope surface, prevents water accumulation at the joints, and improves drainage performance, thereby avoiding roadbed instability or "spring" phenomenon caused by water softening the foundation.
[0028] Clearing the surface layer provides a good working surface for subsequent filling and compaction operations, ensuring that the newly filled material can fully contact the old roadbed slope, facilitating compaction operations, achieving the required density through compaction, and reducing post-construction settlement differences.
[0029] By optimizing the treatment of the joint, stress concentration caused by the difference in settlement between new and old road surfaces can be reduced, effectively preventing reflective cracks in the pavement structure.
[0030] Furthermore, the surface of the reinforcing bar is coated with a rust inhibitor layer.
[0031] The rust inhibitor layer effectively prevents corrosive substances such as water, oxygen, and chloride ions from contacting the reinforcing steel, thereby inhibiting rust formation. Migratory rust inhibitors can also simultaneously inhibit both cathodic and anodic corrosion processes in the reinforcing steel, providing a dual anti-corrosion mechanism and more comprehensive protection. By reducing steel corrosion, the safety and durability of concrete structures are significantly improved, extending the service life of buildings.
[0032] Furthermore, when the new and old roadbed overlapping structures are laid between the old and new roadbeds, the top surfaces of all the old and new roadbeds that make up the upper surface of the entire road are flush.
[0033] A flush roadbed top surface avoids bumps or "jumping" caused by elevation differences, significantly improving driving smoothness and comfort. A flush roadbed top surface also facilitates smooth connection of the drainage system, optimizes drainage performance, and prevents water accumulation from eroding the roadbed. A smooth road surface also reduces traffic safety hazards caused by elevation differences.
[0034] Preferably, standardized processes such as layered filling and compaction testing can be adopted to ensure the quality of roadbed filling and provide a foundation for a level road surface.
[0035] Compared with the prior art, the beneficial effects of this utility model's new and old roadbed overlapping structure are as follows: The new and old roadbed overlapping structure provided by this utility model is simple and reasonable, with strong integrity. It constructs an integrated configuration of new and old roadbeds that are connected to each other. Steel-plastic composite grids are added between the upper layer of the old roadbed and the base layer of the new roadbed, as well as between the base layer and the lower layer of the new roadbed. The steel-plastic composite grids are made into a frame by cross-connection, which ensures that the composite grids play an interlocking role in both the longitudinal and transverse directions of the overall road, effectively improving the overall structural stability and durability of the new and old roadbed overlapping structure, reducing safety hazards; and it has good applicability and has a wide range of application prospects. Attached Figure Description
[0036] Various other advantages and benefits will become apparent to those skilled in the art upon reading the following detailed description of preferred embodiments. The accompanying drawings are for illustrative purposes only and are not intended to limit the scope of the invention. Furthermore, the same reference numerals denote the same parts throughout the drawings. In the drawings: Figure 1This is a cross-sectional structural diagram of the new and old roadbed overlapping structure according to an embodiment of the present utility model; Figure 2 This is a schematic diagram of the planar structure of the steel-plastic composite grid according to an embodiment of the present utility model.
[0037] The markings in the attached figure are as follows: 1. Old roadbed, 2. New roadbed, 3. Steel-plastic composite grid, 31. Horizontal strip, 32. Longitudinal strip, 33. Reinforced node, 4. Roughening treatment layer, 5. Surface cleaning layer. Detailed Implementation
[0038] Exemplary embodiments of the present disclosure will now be described in more detail with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be implemented in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the disclosure to those skilled in the art. It should be noted that, unless otherwise specified, embodiments and features of the present invention can be combined with each other. The present invention will now be described in detail with reference to the accompanying drawings and embodiments.
[0039] In the description of this utility model, it should be noted that the terms "inner" and "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed or operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model.
[0040] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the term "connection" should be interpreted broadly. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be a connection within two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.
[0041] The embodiments of this utility model will be described in detail below with reference to the accompanying drawings: This utility model embodiment provides a joint structure for the old and new roadbeds 1, which is installed at the connection between the old roadbed 1 and the new roadbed 2, including a structure set between the subgrade of the old roadbed 1 and the new roadbed 2 (e.g., Figure 1 As shown, two layers of steel-plastic composite geogrid 3 are embedded between the upper layer of the old roadbed 1 and the base layer of the new roadbed 2, and between the base layer and the lower layer of the new roadbed 2, respectively; as shown. Figure 2As shown, the steel-plastic composite grid 3 is formed by several transverse strips 31 and several longitudinal strips 32 intersecting perpendicularly. Reinforcing bars are tied to both ends of the longitudinal strips 32. A rust inhibitor layer is applied to the surface of the reinforcing bars. This rust inhibitor layer effectively prevents corrosive substances such as water, oxygen, and chloride ions from contacting the reinforcing bars, inhibiting rust formation. The migratory rust inhibitor can also simultaneously inhibit both cathodic and anodic corrosion processes of the reinforcing bars, providing a dual anti-corrosion mechanism and more comprehensive protection. By reducing reinforcing bar corrosion, the safety and durability of the concrete structure are significantly improved, extending the building's service life. This new and old roadbed 1 overlapping structure significantly improves overall stability and deformation resistance by laying double-layer steel-plastic composite grid 3 at key locations and using a specific binding and fixing method. The double-layer steel-plastic composite grid 3 is embedded between different structural layers of the new and old roadbed 1, effectively constraining soil displacement, enhancing the integrity of the roadbed, effectively reducing differential settlement between the new and old roadbed 1, and ensuring overall structural stability. The longitudinal and transverse ribs (longitudinal bands 32 and transverse bands 31) of the geogrid work together to create a strong interlocking effect on the concrete, thereby significantly improving the roadbed's resistance to deformation and reducing uneven settlement. The steel-plastic composite geogrid 3, with its intersecting transverse bands 31 and longitudinal bands 32 forming a mesh structure, evenly distributes vehicle loads and stresses generated by the superstructure over a wider area of the soil, effectively dispersing the load and significantly reducing local stress in the overlap area between the old and new roadbeds 1. This reduces stress concentration and effectively prevents cracks and damage caused by stress concentration. Laying the geogrid between the upper and lower layers of the roadbed, as well as between the lower and upper layers, strengthens the friction and interlocking between structural layers, enhances interlayer bonding, prevents interlayer slippage, ensures coordinated stress distribution across all roadbed layers, and improves structural durability. The method of fixing the longitudinal bands 32 with reinforcing bars at both ends greatly enhances the anchorage force between the geogrid and the roadbed soil. The reinforcing bars at both ends of the longitudinal bands 32 enhance the anchorage effect, effectively resisting possible slippage or peeling of the geogrid under stress, ensuring the long-lasting and stable reinforcement effect.
[0042] High-strength steel wires are tied at the intersections of the transverse and longitudinal bands 31 and 32, forming a reinforced node at each intersection. The reinforced node 33 is an approximately spherical structure, with each node having the same external dimensions. The tensile strength of the steel-plastic composite geogrid is borne by the warp and weft woven transverse and longitudinal bands 31 and 32 of the steel wire material, generating extremely high tensile modulus under low strain. When vehicle traffic generates loads, the steel-plastic composite geogrid 3 exhibits extremely high tensile strength, simultaneously playing an interlocking role in both the longitudinal and transverse directions of the overall road, greatly enhancing overall stability, improving the strength of the road surface structure, and reducing settlement and cracking in overlapping areas. By tying high-strength steel wires at the intersections to form an approximately spherical structure, the connection strength at the grid nodes is effectively enhanced, significantly improving node strength and integrity, preventing weld cracking or rib slippage under stress. This reinforced node design allows the geogrid to work better collaboratively under longitudinal and transverse forces, improving the overall structural stability and load-bearing capacity.
[0043] The near-spherical structure of the reinforced joints features consistent external dimensions, optimizing stress distribution and deformation resistance. This helps to evenly disperse stress concentration at the joints, allowing for more effective load transfer to the longitudinal and transverse ribs. It effectively reduces local deformation and enhances the geogrid's resistance to lateral displacement in soft soil foundation reinforcement and other projects. The consistent dimensions of the reinforced joint 33 facilitate standardized construction. This design represents a significant improvement in steel-plastic geogrid technology, particularly suitable for highway and railway subgrade reinforcement and retaining wall construction projects where high joint strength is required. The reinforced joint 33 is equipped with locking bolts, which are fitted onto the outside of the high-strength steel wire. The high-strength steel wire is locked and fixed at the intersection of the transverse band 31 and the longitudinal band 32 by the locking bolts. The locking bolts act directly on the high-strength steel wire, mechanically securing it to the joint intersection and preventing slippage or displacement under stress, ensuring the stability of the joint connection. Compared to connections relying solely on friction, mechanical locking provides more reliable anti-slip performance and improves connection reliability. The tightening action of the locking bolts increases the contact pressure between the high-strength steel wire and the transverse and longitudinal bands 31 and 32, thereby improving the overall load-bearing capacity and fatigue resistance of the joint and enhancing its strength. This is particularly suitable for structural reinforcement scenarios requiring dynamic loads or long-term stress. The installation and adjustment of the locking bolts are relatively simple, allowing construction personnel to quickly complete the tightening and fixing of the joint, making construction convenient and efficient. It also facilitates fine-tuning of the joint during construction to ensure installation accuracy. The locking bolts are adaptable to high-strength steel wires of different diameters and specifications, offering strong versatility. Joints fixed with locking bolts make it easier to observe the bolt tightness during later maintenance and inspection, facilitating the timely detection and handling of loosening issues.
[0044] The surfaces of the transverse bands 31 and longitudinal bands 32 are respectively provided with rough textures of different configurations. The trajectory lines of the textures in both the transverse bands 31 and longitudinal bands 32 are curved. The curved textures on the surfaces of the transverse and longitudinal bands 31 and 32 increase the friction coefficient between the steel-plastic composite geogrid 3 and the road base layer. By pressing the ribs into a rough texture through surface treatment, the interlocking effect between the geogrid and the soil is increased, preventing slippage and ensuring the stability of the reinforced structure. Furthermore, the rough surface texture increases the friction coefficient at the contact surface between the geogrid and the soil, making it suitable for soft soil foundation reinforcement, pavement crack prevention, and other projects. It can effectively distribute load stress and extend service life.
[0045] A roughened layer 4, with a thickness one-quarter that of the old subgrade's upper layer, is installed on the upper part of the old subgrade's upper layer. This roughened layer 4, installed in the overlapping structure of the old and new subgrades 1, enhances the adhesion and integrity between them, resolving the connection weakness caused by differences in material properties and uneven settlement. The roughening process removes the smooth layer from the old subgrade surface, creating an uneven, rough surface that significantly increases the contact area between the old and new materials and increases the surface roughness. Furthermore, this rough surface facilitates the penetration and anchoring of adhesive materials (such as asphalt binder), resulting in stronger mechanical interlocking, improved bond strength, and effectively reduced risk of cracking and delamination at the joint. Good adhesion promotes stress transfer, helping to distribute vehicle loads and temperature stress more evenly in the joint area, avoiding stress concentration, and improving the overall stability and durability of the pavement.
[0046] A topsoil layer 5 is installed on the slope surface of the old roadbed 1. The thickness of the topsoil layer 5 is 1 / 5 of the subgrade thickness at the junction of the old roadbed 1 and the new roadbed 2. The topsoil layer 5, installed on the slope surface of the old roadbed 1 in the overlapping structure of the old and new roadbeds 1, effectively reduces the physical isolation between the old and new roadbeds 1 by removing loose surface soil and laying a certain thickness of topsoil layer 5, allowing them to better integrate into a whole and reducing uneven settlement caused by poor bonding. The topsoil layer 5 helps to drain water from the slope surface, preventing moisture accumulation at the junction, improving drainage performance, and thus avoiding roadbed instability or "springing" phenomena caused by water softening the foundation. The topsoil layer 5 provides a good working surface for subsequent filling and compaction operations, ensuring that the newly filled material is in full contact with the slope of the old roadbed 1, facilitating compaction operations, achieving the design required density through compaction, and reducing post-construction settlement differences. By optimizing the treatment of the joint, stress concentration caused by the difference in settlement between new and old road surfaces is reduced, effectively preventing reflective cracks in the pavement structure.
[0047] When the new and old roadbed 1 overlap structures are laid between the old roadbed 1 and the new roadbed 2, the top surfaces of all the old and new roadbeds that make up the entire road surface are flush. Standard processes such as layered filling and compaction testing are adopted to ensure the quality of the roadbed filling, providing a foundation for a flush road surface. A flush roadbed top surface avoids bumps or "jumping" caused by elevation differences, significantly improving driving smoothness and comfort. A flush roadbed top surface facilitates smooth connection of the drainage system, optimizes drainage performance, and prevents water accumulation from eroding the roadbed. A smooth road surface also reduces traffic safety hazards caused by elevation differences.
[0048] The construction process in this embodiment includes the following steps in practical application: (a) Excavation of steps: Remove topsoil and insufficiently compacted fill within a certain depth of the old road slope. The original roadbed slope must be excavated into steps, allowing for an effective interlocking of the old and new roadbeds and facilitating the treatment of soft soil in the widened section. The step width must meet the needs of paving and compaction equipment operation to facilitate mechanized construction. The excavation method involves first cutting the slope (1:0.5), then excavating 1.0m steps, without setting an inward angle. The slope cutting must meet the stability requirements of the existing roadbed during construction. This increases the contact area at the junction of the old and new roadbeds, enhancing the shear resistance of the junction.
[0049] (II) Selection of filling materials: Under the influence of its own weight, road surface, and vehicle loads, the old roadbed has been largely compacted, while the new roadbed, despite rigorous compaction, still experiences subsequent deformation. Therefore, the selection of filling materials significantly impacts the effective settlement of the roadbed. In this embodiment, all filling materials are the same as those used in the old roadbed, and materials with good permeability are selected.
[0050] The new roadbed is constructed from bottom to top as follows: base course, tack coat, seal coat, lower layer, tack coat, and upper layer. The base course, situated above the subgrade, is the main load-bearing layer of the pavement, composed of semi-rigid materials (such as cement-stabilized materials), and bears the load transfer and support functions of the pavement.
[0051] A tack coat is sprayed onto the base layer surface, using emulsified or liquid asphalt. It penetrates the pores of the base layer to enhance the adhesion of the surface layer and prevent moisture infiltration. This should be applied immediately after the base layer has been compacted, and the penetration depth should reach 5-10mm.
[0052] Sealing layers are divided into top seal (above the topcoat) and bottom seal (below the topcoat), and their main function is to seal surface voids and provide waterproofing. The bottom seal is usually applied using a thin slurry to prevent rainwater erosion of the substrate.
[0053] The lower asphalt layer, which is in direct contact with the base layer, bears the shear stress from vehicle loads and prevents reflective cracking from propagating to the base layer. The material must possess shear and deformation resistance.
[0054] The tack coat is used to enhance the adhesion between adjacent asphalt layers or between an asphalt layer and a cement concrete pavement. It is typically applied on the day the surface layer is laid and uses fast-cracking modified emulsified asphalt.
[0055] The top layer is located on the top of the road surface and is in direct contact with the wheels. Its functions include anti-skid, wear resistance, resistance to high-temperature deformation, and improvement of driving comfort. SMA (soil-permeable asphalt pavement) structure is commonly used to improve driving safety in rainy weather.
[0056] (III) Controlling roadbed compaction: Before roadbed filling, a test section should be prepared according to specifications. The optimal moisture content of the materials, loose-lay thickness, type and combination of compaction equipment, number of compaction passes, and compaction speed should be strictly controlled to ensure all indicators reach their optimal state and the compaction degree meets design requirements. For widening transition sections, the compaction width must be strictly controlled. When excavating steps in the old roadbed is limited, the requirements can be met by laying protective walkways, etc., to ensure the roadbed compaction degree meets the specified standards.
[0057] During construction, compaction should be carried out in layers, controlling the thickness and compaction degree of each layer to improve the compaction standard. Compaction should be carried out using a heavy-duty roller (≥25t), with dual drive and dual vibration. The thickness of the compacted loose section should not exceed 30cm, and the compaction degree must meet the requirements of the new standard, with emphasis on the junction between the old and new subgrades. After each layer is compacted, the surface should be smooth and level.
[0058] The embankment filling rate should be controlled during roadbed construction. When the filling rate is too fast, the foundation strength cannot develop quickly enough, easily leading to significant shear deformation. During construction, slow-filling standards should be followed, with ground settlement not exceeding 10mm per day and horizontal slope displacement rate not exceeding 5mm per day.
[0059] The technical solution of this utility model has been described above with reference to the preferred embodiments shown in the accompanying drawings. However, it will be readily understood by those skilled in the art that the protection scope of this utility model is obviously not limited to these specific embodiments. Without departing from the principle of this utility model, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will all fall within the protection scope of this utility model.
[0060] The above description is merely a preferred embodiment of this utility model and is not intended to limit the scope of this utility model. Various modifications and variations can be made to this utility model by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the protection scope of this utility model.
Claims
1. A structure for connecting old and new roadbeds, characterized in that, The paving is installed at the junction of the old roadbed and the new roadbed, comprising: two layers of steel-plastic composite grids set between the subgrades of the old roadbed and the new roadbed, the two layers of steel-plastic composite grids being respectively embedded between the upper layer of the old roadbed and the base layer of the new roadbed, and between the base layer and the lower layer of the new roadbed; the steel-plastic composite grids are formed by several transverse strips and several longitudinal strips intersecting each other perpendicularly, and the two ends of the longitudinal strips are respectively tied with steel bars.
2. The structure for connecting old and new roadbeds according to claim 1, characterized in that, High-strength steel wires are tied at the intersections of the horizontal and vertical strips, and each high-strength steel wire at each intersection forms a reinforcing node. The reinforcing node has an approximately spherical structure, and the outer contour dimensions of each reinforcing node are consistent.
3. The new and old roadbed overlapping structure according to claim 2, characterized in that, The reinforcing node is equipped with a locking bolt, which is sleeved on the outside of the high-strength steel wire. The high-strength steel wire is locked and fixed at the intersection of the horizontal and vertical strips by the locking bolt.
4. The structure for connecting old and new roadbeds according to claim 1, characterized in that, The surfaces of the horizontal and vertical strips are respectively provided with rough textures of different configurations, and the trajectory lines of the textures of the horizontal strips and the longitudinal strips are both curves.
5. The structure for connecting old and new roadbeds according to claim 2, characterized in that, The new and old roadbed overlapping structure also includes: a roughened layer disposed on the upper part of the upper layer of the old roadbed, the thickness of the roughened layer being 1 / 5 to 1 / 3 of the upper layer of the old roadbed.
6. The structure for connecting old and new roadbeds according to claim 1, characterized in that, The structure for connecting the old and new roadbeds also includes a clearing layer on the slope surface of the old roadbed, the thickness of which is 1 / 6 to 1 / 5 of the thickness of the roadbed at the junction of the old and new roadbeds.
7. The structure for connecting old and new roadbeds according to claim 1, characterized in that, The surface of the reinforcing bars is coated with a rust inhibitor layer.
8. The structure for connecting old and new roadbeds according to claim 1, characterized in that, When the new and old roadbed overlapping structure is laid between the old and new roadbeds, the top surfaces of all the old and new roadbeds that make up the upper surface of the entire road are flush.