Overflow weir crack chemical grouting hole arrangement structure
By chiseling a U-shaped groove at the overflow weir crack and setting a rough layer and a sealing layer, combined with grouting and injection hole structure, the problem of non-targeted grouting hole layout in the existing technology is solved, achieving efficient crack repair and structural stability improvement.
Patent Information
- Application Number
- CN202522500204.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-25
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-11-25
AI Technical Summary
The existing grouting hole layout lacks specificity and cannot effectively adapt to the seepage situation of the overflow weir cracks, resulting in unsatisfactory repair results.
A U-shaped groove is chiseled out along the crack, and a rough layer is set on the groove wall. A sealing layer is then filled in, and mortar is injected through the grouting pipe to form a grouting layer. Combined with the sealing layer and grouting holes, the seepage points are precisely treated to enhance sealing and repair effectiveness.
It improves the efficiency and quality of overflow weir crack repair, reduces water seepage, enhances structural integrity, and prevents cracks from developing further.
Smart Images

Figure CN225014079U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of crack treatment, and in particular to a chemical grouting hole arrangement structure for overflow weir cracks. Background Technology
[0002] Overflow weirs play a crucial role in water conservancy projects, and their proper utilization is indispensable for the development of these projects. With the continuous development of water conservancy, overflow weirs have demonstrated immense value in flood control, irrigation, and power generation. They effectively regulate water levels, ensuring the rational allocation and utilization of water resources in surrounding areas, and have a profound impact on agricultural production, industrial water use, and residential water supply. Among numerous water conservancy projects, the stable operation of overflow weirs is a key guarantee for the safety and efficiency of the entire project, and their performance directly relates to the comprehensive benefits of the water conservancy project.
[0003] There are several conventional methods for dealing with cracks in overflow weirs. Chemical grouting is a common approach, which involves injecting epoxy grout to seal the cracks and achieve repair. In addition, there are methods to reinforce the structure, such as adding external support components to enhance the overall stability of the overflow weir and reduce further crack development. Surface treatments for the cracks are also applied, such as applying protective layers, to prevent crack widening and increased seepage.
[0004] However, existing technologies have significant drawbacks. The current grouting hole layout lacks specificity and fails to consider the differences in seepage conditions in overflow weirs. Therefore, the grouting hole layout in existing technologies is relatively generic and cannot well adapt to the characteristics of overflow weir cracks, ultimately leading to unsatisfactory crack repair results. Utility Model Content
[0005] To address the above issues, this application provides a chemical grouting hole arrangement structure for overflow weir cracks.
[0006] This application provides a chemical grouting hole arrangement structure for overflow weir cracks, employing the following technical solution: An overflow weir crack chemical grouting hole arrangement structure includes a U-shaped groove chiseled along the crack direction, a sealing layer filled in the U-shaped groove, and a grouting layer formed after mortar is injected into the crack through a grouting pipe. The U-shaped groove is set at the seepage point, and the groove wall of the U-shaped groove is provided with a rough layer.
[0007] By adopting the above technical solution, a U-shaped groove is chiseled along the crack direction at the seepage point, which can precisely address the seepage situation of the overflow weir crack and improve the targeted nature of the repair. The rough layer on the wall of the U-shaped groove increases the friction and contact area between the sealing layer and the U-shaped groove wall, allowing the sealing layer to better bond with the U-shaped groove, enhancing the sealing effect and preventing grout leakage during grouting. Filling the U-shaped groove with a sealing layer can further seal the crack. Combined with injecting epoxy mortar into the crack through the grouting pipe to form a grouting layer, the crack is effectively sealed, improving the repair efficiency and quality of the overflow weir crack, reducing the impact of the crack on the structural integrity of the overflow weir, reducing the occurrence of seepage, and reducing the damage to the overflow weir caused by seepage.
[0008] Preferably, it further includes a sealing layer, which is applied to the concrete surfaces on both sides of the crack and extends to the upper surface of the sealing layer.
[0009] By adopting the above technical solution, the sealing layer is applied to the concrete surface on both sides of the crack and extends to the upper surface of the sealing layer, which can further prevent water seepage around the crack, improve the sealing and waterproofing of the crack repair, and thus improve the efficiency and quality of overflow weir crack repair.
[0010] Preferably, the method further includes a plurality of grouting holes spaced apart along the direction of the crack, wherein the grouting holes are cross-cut holes and the diameter of the cross-cut holes is greater than the width of the crack.
[0011] By adopting the above technical solution, multiple grouting holes are set at intervals along the crack direction, and the diameter of the grouting holes is larger than the crack width. The grouting holes can be used to precisely grout the crack, which improves the targeting of crack repair, adapts to the characteristics of overflow weir cracks, and improves repair efficiency and quality.
[0012] Preferably, it also includes sealing holes located at both ends of the crack.
[0013] By adopting the above technical solution, sealing holes are set at both ends of the crack to limit the further development of the crack, thereby improving the efficiency and quality of overflow weir crack repair.
[0014] Preferably, the bottom wall of the U-shaped groove is provided with a grouting hole, the grouting hole extends into the crack, and a support pipe is installed inside the grouting hole, the support pipe extending to the opening of the U-shaped groove.
[0015] By adopting the above technical solution, a support pipe extending to the U-shaped groove opening is set in the grouting hole, which can ensure the stability of the grouting process, provide support for the grouting operation, and further improve the quality of crack repair, so as to form a composite structure of surface sealing first and then internal filling.
[0016] Preferably, it also includes a plurality of oblique holes respectively disposed on both sides of the crack, wherein the lower end of the oblique holes is inclined toward the crack.
[0017] By adopting the above technical solutions, for areas with severe seepage, it is also necessary to add inclined holes in combination with filling holes, thereby improving the repair efficiency and quality of overflow weir cracks, better sealing the cracks, reducing seepage caused by cracks, and ensuring the integrity of the overflow weir structure.
[0018] Preferably, a plurality of the inclined holes are arranged in a quincunx pattern on both sides of the crack and are staggered from the grouting holes.
[0019] By adopting the above technical solution, the inclined holes are arranged in a quincunx pattern on both sides of the crack and staggered with the grouting holes, which enables the grouting to cover the crack area more comprehensively and evenly, improves the efficiency and quality of crack repair, better adapts to the characteristics of overflow weir cracks, and enhances the repair effect on cracks.
[0020] Preferably, the upper surface of the crack is ground down to be lower than the settling groove of the concrete on both sides of the crack, the settling groove is provided with a filling layer, the settling groove is connected to the U-shaped groove, the inclined hole and the grouting hole, and a connector is provided between two adjacent inclined holes, the connector being built into the settling groove.
[0021] By adopting the above technical solution, the upper surface of the crack is ground into a sinkhole lower than the concrete on both sides and a filling layer is set. The sinkhole is connected to the U-shaped channel, the inclined hole and the grouting hole, which allows the grout to flow better between the channels and fill the crack. At the same time, the connectors built into the sinkhole are set between adjacent inclined holes, which enhances the integrity and stability of the structure and effectively improves the repair effect and quality of the overflow weir crack.
[0022] In summary, this application has the following beneficial effects: 1. Chisel out a U-shaped groove along the direction of the crack. The U-shaped groove is set at the seepage point, which can be arranged according to the seepage situation, improving the efficiency and quality of crack repair. 2. The U-shaped groove has a roughened layer on its wall, which enhances the bonding force between the sealing layer and the U-shaped groove, and better seals the cracks; 3. The setting of grouting holes and inclined holes enables epoxy grout to be better injected into cracks, adapts to the characteristics of overflow weir cracks, and improves the repair effect. Attached Figure Description
[0023] Figure 1 This is a schematic diagram of the structure of Embodiment 1 of this application; Figure 2 This is a cross-sectional view of the U-shaped groove in Embodiment 1 of this application; Figure 3 This is a schematic diagram of the oblique hole in Embodiment 2 of this application; Figure 4 This is a cross-sectional view of the oblique hole in Embodiment 2 of this application; Figure 5 This is a schematic diagram of the structure of Embodiment 3 of this application; Figure 6 This is a cross-sectional view of the U-shaped groove in Embodiment 3 of this application; Figure 7 This is a structural schematic diagram of Embodiment 4 of this application; Figure 8 yes Figure 7 A magnified view of part A in the middle; Figure 9 This is a side view of the connector in Embodiment 4 of this application; Figure 10 yes Figure 9 A magnified view of part B in the diagram.
[0024] Explanation of reference numerals in the attached drawings: 1. Crack; 2. U-shaped groove; 21. Rough layer; 3. Sealing layer; 4. Grouting layer; 5. Sealing layer; 6. Grouting hole; 61. Support pipe; 7. Sealing hole; 8. Inclined hole; 9. Settling groove; 91. Filling layer; 10. Connector; 101. First connecting rod; 102. Second connecting rod; 103. Through ring; 104. Restricting ring. Detailed Implementation
[0025] The following is in conjunction with the appendix Figure 1 - Appendix Figure 10 This application will be described in further detail below.
[0026] This application discloses a chemical grouting hole arrangement structure for overflow weir cracks.
[0027] Example 1: A chemical grouting hole arrangement structure for overflow weir cracks, referring to Figure 1 , Figure 2 It includes a U-shaped groove 2 chiseled along the direction of crack 1, a sealing layer 3 filled in the U-shaped groove 2, and a grouting layer 4 formed after mortar is injected into crack 1 through a grouting pipe.
[0028] The U-shaped groove 2 is placed in areas with severe seepage. Specifically, the U-shaped groove 2 can be 8cm wide at the top, 5cm wide at the bottom, and 5cm deep, with its length determined by the extent of the seepage. The groove wall of the U-shaped groove 2 has a roughened layer 21, which is formed by grinding using appropriate equipment. The sealing layer 3 used needs to be a sealant compatible with epoxy mortar, such as polysulfide sealant or polyurethane sealant. When caulking, the sealant should be full and dense, with the surface flush with the concrete surface. After caulking, grouting is performed using embedded pipes. The spacing between the grouting pipes is determined based on the condition of crack 1, generally 30-50cm. Epoxy grout is used as the grouting material, and the grouting pressure is controlled at 0.2-0.3MPa. Grouting continues until no more grout enters crack 1.
[0029] Furthermore, it also includes a sealing layer 5, which is applied to the concrete surfaces on both sides of the crack 1 and extends to the upper surface of the sealing layer 3. The sealing layer 5 is formed mainly after the grouting is completed, the crack surface is ground and cleaned, and epoxy putty is applied 1-2 times for sealing treatment. After solidification, the sealing layer 5 is formed.
[0030] Furthermore, for areas without water seepage, the system may include multiple grouting holes 6 spaced along the direction of crack 1 and sealing holes 7 located at both ends of crack 1. In this embodiment, the grouting holes 6 are cross-cut holes, with a diameter larger than the width of crack 1. It should be noted that during grouting, the surface of the crack and a 15-20cm area on both sides should be ground and cleaned first. Loose concrete skin and protruding parts should be removed using a wire brush or grinder to make the surface smooth and clean.
[0031] It should be noted that drilling is performed using an electric hammer or pneumatic drill. After drilling, the hole should be promptly cleaned of powder and debris with pressurized water. The grouting pipes used are connected to Φ5mm PU transparent plastic pipes via plastic nozzles. Epoxy mortar is used for pipe embedding. The joints are first sealed with quick-setting cementitious material, then filled tightly with epoxy mortar. Epoxy putty is then applied to seal the joint surface. After sealing, each grouting nozzle is recorded and numbered.
[0032] The implementation principle of the chemical grouting hole arrangement structure for overflow weir cracks in this embodiment is as follows: This embodiment uses a combination of structures such as U-shaped groove 2, sealing layer 3, sealing layer 5, grouting hole 6, and plugging hole 7 to make a reasonable arrangement for the characteristics of overflow weir crack 1. The U-shaped groove 2 is set at the seepage point to accurately deal with the seepage problem, the sealing layer 3 prevents grout leakage, and the sealing layer 5 protects crack 1 from external influences.
[0033] Example 2: Reference Figure 3 , Figure 4 The difference from Embodiment 1 is that, when the seepage area is relatively large, this embodiment also includes several inclined holes 8 respectively set on both sides of the crack 1. The lower end of the inclined holes 8 is inclined towards the crack 1, and the several inclined holes 8 are arranged in a quincunx pattern on both sides of the crack 1, and are staggered with the grouting holes 6. The inclined holes 8 are drilled at a vertical distance of 15cm from the crack 1, with an angle of 35°, and the spacing between the holes on each side is 40cm. The hole depth exceeds the crack 1 by 115cm. To limit the further development of the crack, holes are drilled and sealed at both ends of the crack 1. The holes are drilled using an electric hammer or pneumatic drill, with a hole diameter of Φ12mm. After drilling, the powder and debris inside the hole are washed away with pressurized water in time.
[0034] The inclined holes 8 further improve the efficiency and quality of overflow weir crack 1 repair, and represent a significant improvement and enhancement compared to the lack of targeted grouting hole 6 arrangement structure in existing technologies.
[0035] Example 3: Reference Figure 5 , Figure 6 The difference from Embodiment 1 is that a grouting hole 6 is provided on the bottom wall of the U-shaped groove 2, extending into the crack 1. A support pipe 61 is installed inside the grouting hole 6, extending to the opening of the U-shaped groove 2, thus forming a composite barrier structure that is first surface-sealed and then internally grouted. The support pipe 61 is generally made of metal, possessing sufficient strength to withstand the pressure of the grouting material. It is circular in shape, and the pipe diameter is determined according to the actual situation.
[0036] Example 4: Reference Figure 7 , Figure 8 The difference from Embodiment 1 is that the upper surface of the crack 1 is ground down to the level of the settling groove 9 of the concrete on both sides of the crack 1. The settling groove 9 is filled with a filling layer 91. The settling groove 9 is connected to the U-shaped groove 2, the inclined hole 8 and the grouting hole 6. A connector 10 is provided between two adjacent inclined holes 8. The connector 10 is built into the settling groove 9.
[0037] It should be noted that after the filler layer 91 is filled, the sealing layer 5 is applied, such as... Figure 9 As shown.
[0038] Reference Figure 8 , Figure 9 and Figure 10 The connector 10 may specifically include a first connecting rod 101 inserted into the inclined hole 8, a horizontally arranged second connecting rod 102, a through ring 103 disposed at the end of the second connecting rod 102, and a limiting ring 104 threadedly connected to the first connecting rod 101. The through ring 103 is slidably sleeved on the first connecting rod 101 and limited by the limiting ring. Alternatively, it may specifically include a first connecting rod 101 inserted into the inclined hole 8 and a steel wire rope fixedly wound around two adjacent first connecting rods 101. Compared to the second connecting rod 102, the processing of the steel wire rope is relatively simple, and the limiting ring can also prevent the steel wire rope from detaching from the first connecting rod 101. By adding the connector 10, the overall integrity and stability of the structure are enhanced, effectively improving the repair effect and quality of the overflow weir crack 1.
[0039] The above are all preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.
Claims
1. A chemical grouting hole arrangement structure for overflow weir cracks, characterized in that: It includes a U-shaped groove (2) chiseled along the direction of the crack (1), a sealing layer (3) filled in the U-shaped groove (2), and a grouting layer (4) formed after mortar is injected into the crack (1) through a grouting pipe. The U-shaped groove (2) is located at the seepage point, and the groove wall of the U-shaped groove (2) is provided with a rough layer (21).
2. The overflow weir crack chemical grouting hole arrangement structure according to claim 1, characterized in that: It also includes a sealing layer (5) for coating the concrete surfaces on both sides of the crack (1) and extending to the upper surface of the sealing layer (3).
3. The overflow weir crack chemical grouting hole arrangement structure according to claim 1, characterized in that: It also includes a plurality of grouting holes (6) spaced apart along the direction of the crack (1), wherein the grouting holes (6) are cross-cut holes and the diameter of the cross-cut holes is greater than the width of the crack (1).
4. The overflow weir crack chemical grouting hole arrangement structure according to claim 1, characterized in that: It also includes sealing holes (7) set at both ends of the crack (1).
5. The overflow weir crack chemical grouting hole arrangement structure according to claim 1, characterized in that: The bottom wall of the U-shaped groove (2) is provided with a grouting hole (6), which extends into the crack (1). The grouting hole (6) is equipped with a support pipe (61), which extends to the opening of the U-shaped groove (2).
6. The overflow weir crack chemical grouting hole arrangement structure according to claim 3, characterized in that: It also includes several inclined holes (8) respectively set on both sides of the crack (1), with the lower end of the inclined holes (8) inclined towards the crack (1).
7. The overflow weir crack chemical grouting hole arrangement structure according to claim 6, characterized in that: Several of the inclined holes (8) are arranged in a quincunx pattern on both sides of the crack (1) and are staggered from the grouting holes (6).
8. The overflow weir crack chemical grouting hole arrangement structure according to claim 6, characterized in that: The upper surface of the crack (1) is ground down to the level of the settling groove (9) of the concrete on both sides of the crack (1). The settling groove (9) is filled with a filling layer (91). The settling groove (9) is connected to the U-shaped groove (2), the inclined hole (8) and the grouting hole (6). A connector (10) is provided between two adjacent inclined holes (8). The connector (10) is built into the settling groove (9).