Multifunctional diversion tunnel structure

By designing a multifunctional diversion tunnel structure that integrates diversion, ecological water supply, water release, and flood discharge functions, the problem of underutilization of tunnel functions was solved, the amount of engineering work was reduced and flexible operation was achieved, the structure was optimized, and the flood discharge safety of the reservoir was ensured.

CN225014103UActive Publication Date: 2026-11-24POWERCHINA ZHONGNAN ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522710804.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-22
Publication Date
2026-11-24
Estimated Expiration
2035-12-22

AI Technical Summary

Technical Problem

In existing water conservancy and hydropower projects, the functions of many tunnels are not fully utilized, resulting in resource waste and increased engineering workload. There is an urgent need for a multi-functional integrated tunnel structure to improve utilization and reduce engineering costs.

Method used

Design a multifunctional diversion tunnel structure, including an inlet, a front section of the diversion tunnel, a gate well, a middle section of the diversion tunnel, a vertical shaft, a rear section of the diversion tunnel, and an energy dissipation section. Set up horizontal and vertical water flow channels, and arrange water discharge pipes and ecological pipes. The energy dissipation section includes a water discharge pipe energy dissipation section and a flood discharge orifice energy dissipation section. The integration of multiple functions is achieved through the coordinated control of gates and valves.

Benefits of technology

It significantly reduces the amount of excavation work for dedicated caverns, improves functional utilization, flexibly responds to different working conditions, optimizes the structure, ensures flood discharge safety, and reduces project investment and resource waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014103U_ABST
    Figure CN225014103U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of water conservancy and hydropower engineering technology, specifically disclosing a multifunctional diversion tunnel structure, including an inlet, a front section of the diversion tunnel, a gate well, a middle section of the diversion tunnel, a vertical shaft, a rear section of the diversion tunnel, and an energy dissipation section arranged sequentially. The inlet is provided with independent horizontal and vertical water flow channels, both of which are connected to the front section of the diversion tunnel. Water discharge pipes are arranged along the middle and rear sections of the diversion tunnel. Ecological pipes are also buried along the front, middle, and rear sections of the diversion tunnel. The energy dissipation section includes a water discharge pipe energy dissipation section and a flood discharge orifice energy dissipation section arranged in parallel. This utility model integrates multiple functions such as diversion, ecological water supply, water discharge, and flood discharge into a single tunnel, significantly reducing the amount of excavation work for dedicated tunnels and saving on project investment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of water conservancy and hydropower engineering technology, specifically to a multifunctional diversion tunnel structure. Background Technology

[0002] In water conservancy and hydropower projects, multiple tunnels are often constructed to meet the functional needs of different periods. During construction, temporary flow passage tunnels, such as diversion tunnels, are required to meet the requirements of flood diversion. During the permanent operation period, various types of tunnels are required to meet different needs: flood discharge outlets are required to meet the flood discharge requirements; venting tunnels are required to meet the requirements of pre-discharge and emptying; ecological pipes are installed to meet the requirements of ecological water diversion, etc.

[0003] The common practice is to set up multiple tunnels to meet different needs. However, this results in the underutilization of the functions of each tunnel. For example, diversion tunnels only play a short-term role during the construction period and remain idle during the long-term permanent operation, causing a great waste of functions and resources. At the same time, it also increases the amount of work and investment, which is not conducive to energy conservation and emission reduction.

[0004] Therefore, there is an urgent need for a tunnel structure that integrates multiple functions such as construction diversion, ecological water supply, reservoir emptying, pre-discharge, and tiered flood discharge, in order to improve the utilization rate of each functional part in the tunnel, simplify the structure, reduce the amount of engineering work, lower the project cost, and improve the flexibility of operation and scheduling. Utility Model Content

[0005] The technical problem to be solved by this utility model is to overcome the shortcomings of the existing technology and provide a simple, economical, and multifunctional diversion tunnel structure.

[0006] To solve the above-mentioned technical problems, the present invention adopts the following technical solution: A multifunctional diversion tunnel structure includes an inlet, a front section of the diversion tunnel, a gate well, a middle section of the diversion tunnel, a vertical shaft, a rear section of the diversion tunnel, and an energy dissipation section arranged in sequence. The inlet is provided with a horizontal water flow channel and a vertical water flow channel, both of which are connected to the front section of the diversion tunnel. Water discharge pipes are arranged along the middle and rear sections of the diversion tunnel. The front end of the water discharge pipe is connected to the front section of the diversion tunnel, and the rear end of the water discharge pipe is connected to the energy dissipation section. An ecological pipe is also buried along the front section, middle section and rear section of the diversion tunnel. The front end of the ecological pipe is connected to the vertical water flow channel and the rear end of the ecological pipe is connected to the energy dissipation section. The energy dissipation section includes an energy dissipation section for the water discharge pipe and an energy dissipation section for the flood discharge orifice, which are arranged in parallel.

[0007] As a further improvement to the above technical solution: The end of the energy dissipation section of the water discharge pipe is equipped with a valve for adjusting the flow rate.

[0008] As a further improvement to the above technical solution: The gate well is also connected to the middle section of the diversion tunnel, and an emergency maintenance gate is installed inside the gate well.

[0009] As a further improvement to the above technical solution: The diameter of the rear section of the drain pipe is smaller than the net width of the middle section of the diversion tunnel.

[0010] As a further improvement to the above technical solution: The diameter of both the front and rear sections of the drain pipe is not less than 2m.

[0011] As a further improvement to the above technical solution: The inner diameter of the ecological pipe is less than 0.5m.

[0012] As a further improvement to the above technical solution: The front section of the water discharge pipe is buried in the middle section of the diversion tunnel, and the rear section of the water discharge pipe and the ecological pipe are buried in the bottom slab or side wall of the tunnel.

[0013] As a further improvement to the above technical solution: The middle section of the diversion tunnel also serves as the front section of the water discharge pipe.

[0014] As a further improvement to the above technical solution: A vertical baffle is also installed at the end of the energy dissipation section of the water discharge pipe; A transverse retaining wall is also provided between the energy dissipation section of the water discharge pipe and the energy dissipation section of the flood discharge orifice. The transverse retaining wall is used to separate the energy dissipation section of the water discharge pipe from the energy dissipation section of the flood discharge orifice and to keep the outlet of the water discharge pipe in a submerged outflow state.

[0015] As a further improvement to the above technical solution: The shaft is also connected to the rear section of the diversion tunnel, and the inlet elevation of the shaft is higher than the inlet elevation of the vertical water flow channel.

[0016] Compared with the prior art, the beneficial effects of this utility model are: (1) High integration and economy: The present invention provides a multifunctional diversion tunnel structure, including an inlet, a front section of the diversion tunnel, a gate well, a middle section of the diversion tunnel, a vertical shaft, a rear section of the diversion tunnel, and an energy dissipation section arranged in sequence. The inlet is provided with independent horizontal and vertical water flow channels, both of which are connected to the front section of the diversion tunnel. Water discharge pipes are arranged along the middle and rear sections of the diversion tunnel, with the front end of the water discharge pipe connected to the front section of the diversion tunnel and the rear end of the water discharge pipe connected to the energy dissipation section. Ecological pipes are also buried along the front, middle, and rear sections of the diversion tunnel, with the front end of the ecological pipe connected to the vertical water flow channel and the rear end of the ecological pipe connected to the energy dissipation section. The energy dissipation section includes a water discharge pipe energy dissipation section and a flood discharge orifice energy dissipation section arranged in parallel. By integrating multiple functions such as diversion, ecological water supply, water release, and flood discharge into a single tunnel, the amount of excavation work for dedicated caverns is significantly reduced, saving on project investment.

[0017] (2) Flexible operation: Through the coordinated control of gates, valves and different inlets, it can flexibly cope with various working conditions from the construction period to the operation period, including normal water supply, ecological water release, pre-discharge, flood discharge and equipment maintenance.

[0018] (3) Structural optimization: By setting vertical baffles and horizontal retaining walls, the energy dissipation section effectively reduces the scouring of the lateral retaining walls, and by creating a submerged outflow state, the required length of the energy dissipation section is shortened, further optimizing the structure and improving reliability and economy.

[0019] (4) Reliable function: It realizes the graded and joint operation of the flood discharge surface outlet and the flood discharge bottom outlet, ensuring the safety of flood discharge of the reservoir under different water level conditions. Attached Figure Description

[0020] Figure 1 This is a front view of a multifunctional diversion tunnel structure during the construction phase, according to an embodiment of the present utility model. Figure 2 for Figure 1 The multi-functional diversion tunnel structure is shown in the top view during the construction period; Figure 3 This is a front view of the multifunctional diversion tunnel structure during operation, as shown in the embodiment. Figure 4 for Figure 3 The multi-functional diversion tunnel structure is shown in the top view during operation; Figure 5 for Figure 3 AA cross-section view.

[0021] In the diagram: 1. Inlet; 2. Front section of diversion tunnel; 3. Middle section of diversion tunnel; 4. Shaft; 5. Rear section of diversion tunnel; 6. Energy dissipation section; 7. Vertical water flow channel; 8. Horizontal water flow channel; 9. Rear section of discharge pipe; 10. Ecological pipe; 11. Concrete; 12. Base slab; 13. Side wall; 14. Valve; 15. Front section of discharge pipe; 16. Gate well; 17. Emergency maintenance gate; 18. Discharge pipe; 19. Energy dissipation section of discharge pipe; 20. Energy dissipation section of flood discharge orifice; 21. Vertical baffle; 22. Horizontal retaining wall. Detailed Implementation

[0022] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0023] like Figure 1-5 As shown, this embodiment provides a multifunctional diversion tunnel structure, including an inlet 1, a diversion tunnel front section 2, a gate well 16, a diversion tunnel middle section 3, a vertical shaft 4, a diversion tunnel rear section 5, and an energy dissipation section 6 arranged sequentially. The inlet 1 is provided with independent horizontal water flow channels 8 and vertical water flow channels 7, both of which are connected to the diversion tunnel front section 2. A water discharge pipe 18 is arranged along the diversion tunnel middle section 3 and the diversion tunnel rear section 5. The front end of the water discharge pipe 18 is connected to the diversion tunnel front section 2, and the rear end of the water discharge pipe 18 is connected to the energy dissipation section 6. An ecological pipe 10 is also buried along the diversion tunnel front section 2, the diversion tunnel middle section 3, and the diversion tunnel rear section 5. The front end of the ecological pipe 10 is connected to the vertical water flow channel 7, and the rear end of the ecological pipe 10 is connected to the energy dissipation section 6. The energy dissipation section 6 includes a water discharge pipe energy dissipation section 19 and a flood discharge orifice energy dissipation section 20 arranged in parallel.

[0024] Through the above configuration, the multifunctional diversion tunnel structure of this embodiment integrates multiple functions such as diversion, ecological water supply, water release, and flood discharge into one tunnel, which significantly reduces the amount of excavation work for dedicated caverns and saves on project investment.

[0025] The end of the energy dissipation section 19 of the water discharge pipe is equipped with a valve 14 for regulating the flow rate. The gate well 16 is also connected to the middle section 3 of the diversion tunnel, and an emergency maintenance gate 17 is installed in the gate well 16. Through the coordinated control of the emergency maintenance gate 17, the valve 14, and the different inlets 1, various operating conditions from the construction period to the operation period can be flexibly handled, including normal water supply, ecological water release, pre-discharge, flood discharge, and equipment maintenance.

[0026] In this embodiment, the drain pipe 18 includes a front section 15 and a rear section 9, wherein the diameter of the rear section of the drain pipe 18 is smaller than the net width of the middle section 3 of the guide hole.

[0027] The diameter of both the front and rear sections of the drain pipe 18 is not less than 2m.

[0028] The front section of the water discharge pipe 18 is buried in the middle section 3 of the diversion tunnel, and the rear section of the water discharge pipe 18 and the ecological pipe 10 are buried in the bottom slab 12 or side wall 13 of the tunnel.

[0029] The middle section 3 of the diversion tunnel also serves as the front section of the water discharge pipe 18.

[0030] The inner diameter of the ecological pipe 10 is less than 0.5m.

[0031] A vertical baffle 21 is also provided at the end of the energy dissipation section 19 of the discharge pipe; a transverse baffle wall 22 is also provided between the energy dissipation section 19 of the discharge pipe and the energy dissipation section 20 of the flood discharge orifice. The transverse baffle wall 22 is used to separate the energy dissipation section 19 of the discharge pipe from the energy dissipation section 20 of the flood discharge orifice and to keep the outlet of the discharge pipe 18 in a submerged outflow state. By setting the vertical baffle 21 and the transverse baffle wall 22, the energy dissipation section 6 effectively reduces the scouring of the lateral baffle wall, and shortens the required length of the energy dissipation section 6 by creating a submerged outflow state, further optimizing the structure and improving reliability and economy.

[0032] The vertical shaft 4 is also connected to the rear section 5 of the diversion tunnel, and the inlet elevation of the vertical shaft 4 is higher than the inlet elevation of the vertical water flow channel 7.

[0033] The construction and usage methods of the multifunctional diversion tunnel structure in this embodiment are as follows: 1. Construction Phase: Complete the excavation of the tunnel structure, including inlet 1, front section 2 of the diversion tunnel, gate shaft 16, middle section 3 of the diversion tunnel, vertical shaft 4, rear section 5 of the diversion tunnel, and energy dissipation section 6; bury the rear section 9 of the discharge pipe (diameter less than 2m) and the ecological pipe 10 (diameter less than 0.5m) into the bottom slab 12 or sidewall 13 of the rear section 5 of the diversion tunnel; water flows horizontally from inlet 1 into the water flow channel 8, flows sequentially through the front section 2 of the diversion tunnel, gate shaft 16, middle section 3 of the diversion tunnel, vertical shaft 4, and rear section 5 of the diversion tunnel, and is finally discharged through the energy dissipation section 6, thus realizing the diversion function; 2. Sealing period: seal the horizontal water flow channel 8 of inlet 1, close the emergency maintenance gate 17 in gate well 16; bury the front section 15 of the discharge pipe in the middle section 3 of the diversion tunnel, and connect it to the rear section 9 of the discharge pipe in the rear section 5 of the diversion tunnel; finally, backfill the gap between the front section 15 of the discharge pipe and the middle section 3 of the diversion tunnel with concrete 11. 3. Normal operation period: Open the emergency maintenance gate 17 and close the valve 14 at the end of the drain pipe 18; water flows in from the vertical water flow channel 7 of the inlet 1 and flows out automatically through the ecological pipe 10 to achieve ecological water supply; at this time, the drain pipe 18 does not work. 4. Pre-discharge or maintenance emptying period: Open the emergency maintenance gate 17, open the valve 14 at the end of the discharge pipe 18, and the discharge pipe 18 will work to realize the reservoir pre-discharge or maintenance emptying function; 5. Flood season: Open the emergency maintenance gate 17 and open the valve 14 at the end of the discharge pipe 18; at this time, the discharge pipe 18 works as the bottom outlet for flood discharge; when the flood level exceeds the inlet of the vertical shaft 4, the water flows in from the vertical shaft 4, and discharges through the rear section 5 of the diversion tunnel and the energy dissipation section 6 to realize the function of the flood discharge surface outlet. At this time, the flood discharge surface outlet and the flood discharge bottom outlet work together. 6. Maintenance period: Close the emergency maintenance gate 17 and stop the operation of the water discharge pipe 18; if there is a flood and the water level exceeds the entrance of the vertical shaft 4, the water will enter from the vertical shaft 4 and pass through the diversion tunnel section 5 and the energy dissipation section 6 for flood discharge. At this time, the diversion tunnel section 5 alone acts as the flood discharge outlet.

[0034] This embodiment ensures the safety of flood discharge from the reservoir under different water level conditions by using graded and combined operation of the flood discharge surface outlets and the flood discharge bottom outlets.

[0035] The above description is merely a preferred embodiment of this utility model, and the protection scope of this utility model is not limited to the above embodiments. For those skilled in the art, improvements and modifications obtained without departing from the technical concept of this utility model should also be considered within the protection scope of this utility model.

Claims

1. A multifunctional diversion tunnel structure, comprising, in sequence, an inlet, a front section of the diversion tunnel, a gate shaft, a middle section of the diversion tunnel, a vertical shaft, a rear section of the diversion tunnel, and an energy dissipation section, characterized in that: The inlet is provided with a horizontal water flow channel and a vertical water flow channel, both of which are connected to the front section of the diversion tunnel; Water discharge pipes are arranged along the middle and rear sections of the diversion tunnel. The front end of the water discharge pipe is connected to the front section of the diversion tunnel, and the rear end of the water discharge pipe is connected to the energy dissipation section. An ecological pipe is also buried along the front section, middle section and rear section of the diversion tunnel. The front end of the ecological pipe is connected to the vertical water flow channel and the rear end of the ecological pipe is connected to the energy dissipation section. The energy dissipation section includes an energy dissipation section for the water discharge pipe and an energy dissipation section for the flood discharge orifice, which are arranged in parallel.

2. The multifunctional diversion tunnel structure according to claim 1, characterized in that, The end of the energy dissipation section of the water discharge pipe is equipped with a valve for adjusting the flow rate.

3. The multifunctional diversion tunnel structure according to claim 1, characterized in that, The gate well is also connected to the middle section of the diversion tunnel, and an emergency maintenance gate is installed inside the gate well.

4. The multifunctional diversion tunnel structure according to claim 1, characterized in that, The diameter of the rear section of the drain pipe is smaller than the net width of the middle section of the diversion tunnel.

5. The multifunctional diversion tunnel structure according to claim 1, characterized in that, The diameter of both the front and rear sections of the drain pipe is not less than [1] 2m.

6. The multifunctional diversion tunnel structure according to claim 1, characterized in that, The inner diameter of the ecological pipe is less than 0.5m.

7. The multifunctional diversion tunnel structure according to claim 1, characterized in that, The front section of the water discharge pipe is buried in the middle section of the diversion tunnel, and the rear section of the water discharge pipe and the ecological pipe are buried in the bottom slab or side wall of the tunnel.

8. The multifunctional diversion tunnel structure according to claim 1, characterized in that, The middle section of the diversion tunnel also serves as the front section of the water discharge pipe.

9. The multifunctional diversion tunnel structure according to claim 1, characterized in that, A vertical baffle is also installed at the end of the energy dissipation section of the water discharge pipe; A transverse retaining wall is also provided between the energy dissipation section of the water discharge pipe and the energy dissipation section of the flood discharge orifice. The transverse retaining wall is used to separate the energy dissipation section of the water discharge pipe from the energy dissipation section of the flood discharge orifice and to keep the outlet of the water discharge pipe in a submerged outflow state.

10. The multifunctional diversion tunnel structure according to claim 1, characterized in that, The shaft is also connected to the rear section of the diversion tunnel, and the inlet elevation of the shaft is higher than the inlet elevation of the vertical water flow channel.