Expansion pile formed by end sediment and bearing layer of reinforced pile and construction device

By using a compaction reinforcement technology that forms a three-layer composite reinforcement at the pile bottom, the problem of pile tip bearing capacity loss during bored pile construction has been solved, resulting in a significant improvement in pile tip bearing capacity and improved construction efficiency, economy, and environmental friendliness.

CN225014131UActive Publication Date: 2026-11-24SHANGHAI STRONG FOUND ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522389649.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-11
Publication Date
2026-11-24
Estimated Expiration
2035-11-11

AI Technical Summary

Technical Problem

Existing bored pile construction technologies suffer from issues such as pile tip bearing capacity loss, mud wall protection technology forming mud cake, long spiral borehole pressure grouting technology disturbing the bearing layer, and the effect of post-grouting technology at the pile tip uncertain.

Method used

The compaction reinforcement technology is adopted, which forms a three-layer composite reinforcement at the bottom of the pile: a compaction filler reinforcement zone, a bearing layer compaction zone, and a bearing layer squeezing zone. The compaction reinforcement is carried out by using hollow channel components and column hammer assemblies to form a dense compaction filler reinforcement zone and a bearing layer reinforcement layer.

Benefits of technology

It significantly increases the bearing capacity of pile ends by more than 30%, is efficient and economical to construct, reduces soil disturbance, adapts to complex strata, and enhances structural reliability and construction flexibility.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014131U_ABST
    Figure CN225014131U_ABST
Patent Text Reader

Abstract

This utility model belongs to the field of foundation construction technology, and discloses a structure for enlarged-base cast-in-place piles formed by compacting and reinforcing pile tip sediment and bearing stratum. The cast-in-place pile structure includes a concrete pile body, with a compaction reinforcement body connected to its bottom, comprising a three-layer composite structure: a top layer of compaction filler reinforcement embedded in the bearing stratum; a middle layer of bearing stratum compaction zone; and a bottom layer of bearing stratum compaction zone. Layered reinforcement enhances the bearing capacity of the pile tip. The supporting construction device includes: a hollow channel component whose bottom extends to the bearing stratum at the pile bottom; a column hammer that can be raised and lowered within the channel, with a hammer diameter adapted to the inner diameter of the channel and an impact protrusion or frustum-shaped impact surface at the bottom; and a mixer and feeding system for dispensing filler. During construction, filler is dispensed into the bearing stratum through the channel, and repeated impacts from the column hammer achieve simultaneous compaction of the filler, reinforcement of the bearing stratum, and formation of the compaction transition zone. This device can adapt to various geological conditions, effectively solves the problem of reinforcing weak bearing strata, and significantly improves the bearing capacity of a single pile.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of foundation construction technology for building engineering, specifically relating to a cast-in-place pile structure formed by compaction and reinforcement of the bearing layer, and also relating to a cast-in-place pile construction device based on the cast-in-place pile structure formed by compaction and reinforcement of the bearing layer. Background Technology

[0002] In urban construction and underground space development, pile foundations are a key foundation type for various municipal facilities and industrial and civil buildings. Among them, bored piles are one of the most commonly used pile types due to their wide applicability.

[0003] Currently, the mainstream drilling pile construction technologies mainly include: reverse circulation drilling rig mud wall forming and underwater concrete pouring technology, rotary drilling rig mud wall forming and underwater concrete pouring technology, and long spiral pre-drilling pressure grouting technology. However, these traditional technologies have significant common defects that seriously affect the performance of the pile tip bearing capacity.

[0004] Among these methods, mud wall protection technology (reverse circulation, rotary drilling) inevitably forms mud cake on the pile wall and produces sediment at the pile tip. The mud cake weakens the pile side friction, while the sediment forms a weak cushion layer, significantly reducing the bearing capacity of the pile tip. Although the long spiral borehole pressure grouting technology does not require mud wall protection and avoids the problems of mud cake and sediment, the spiral drill bit will disturb the soil of the bearing layer at the pile tip during drilling, which will also lead to a decrease in its bearing capacity.

[0005] To address the aforementioned issue of pile tip bearing capacity loss, the engineering community commonly employs "post-grouting technology" to compensate for it. However, this technology also has significant shortcomings. The diffusion of the grout in the soil is disordered, making it difficult to precisely control the reinforcement range and effect. Its effect on improving the pile foundation bearing capacity is uncertain and is greatly influenced by factors such as geological conditions, grout mix ratio, and grouting process.

[0006] In conclusion, engineering practice urgently requires a more direct, effective, and reliable method to reinforce the bearing stratum at the pile tip. Therefore, developing an innovative bored pile construction technology that can effectively implement physical compaction reinforcement of the bearing stratum at the pile tip is an urgent need in the current engineering field. Summary of the Invention

[0007] The first aspect of this utility model provides an enlarged-base cast-in-place pile that reinforces the pile end sediment and bearing layer by compaction. The pile is formed by filling material embedding and layered compaction technology to form a three-layer composite reinforcement, thereby simultaneously improving the pile end bearing capacity and the integrity of the bearing layer.

[0008] To achieve the above objectives, this utility model provides the following technical solution: This utility model discloses an enlarged-base cast-in-place pile formed by compaction reinforcement of pile tip sediment and bearing layer, comprising a concrete pile body, wherein a compaction reinforcement body is connected to the bottom of the concrete pile body, and the compaction of the compaction reinforcement body is controlled by the penetration of the compaction hammer; the compaction reinforcement body comprises a three-layer composite structure from top to bottom: The compacted filler reinforcement zone embedded in the bearing layer is composed of compacted filler.

[0009] The bearing layer compaction zone, located below the filler zone, is a reinforced layer formed by compaction of the original bearing layer.

[0010] The compacted zone of the bearing layer, which encloses the compacted zone of the bearing layer, is a transitional compacted layer formed by the compression of the bearing layer.

[0011] In addition to the above-mentioned technical features, this utility model has also made optimizations and improvements in the following aspects: As a preferred technical solution of this application, the filler in the compaction filler reinforcement zone is dry powder cement sand or dry crushed stone concrete aggregate with a particle size not greater than 50mm.

[0012] This application also provides a construction device for enlarged-base cast-in-place piles that compacts and reinforces pile tip sediment and bearing layer, including: a hollow channel component, a pile hammer assembly, and a filler delivery assembly.

[0013] The hollow channel component runs through the pile body, and its bottom opening extends to the bearing layer at the bottom of the pile.

[0014] The hammer assembly is vertically and flexibly installed inside the hollow channel component, and the diameter of the hammer assembly is adapted to the inner diameter of the hollow channel component.

[0015] The filler dispensing assembly is used to dispense filler into the hollow channel component.

[0016] As a preferred technical solution of this application, the hollow channel component is a hollow drill rod of a long spiral drill bit, and its bottom end is provided with an openable and closable gate.

[0017] As a preferred technical solution of this application, the hollow channel component is a steel casing for a driven pipe pile.

[0018] As a preferred technical solution of this application, the hollow channel component is a rear-insertion protective pipe that is inserted into the center of the uncured concrete pile in a reverse circulation drilling or rotary drilling rig bored pile.

[0019] As a preferred technical solution of this application, the bottom end of the steel casing is connected to a separable pile tip or end plate. The pile tip and the steel casing are detachably connected by a snap-fit ​​or embedding connection. The pile tip can be separated from the steel casing by impacting the pile hammer.

[0020] As a preferred technical solution of this application, the hollow channel component is a spiral tube or a rear-inserted protective tube. The spiral tube is a segmented steel pipe with spiral threads on the pipe wall and an open structure at the bottom, which is connected to the pile tip or end plate.

[0021] As a preferred technical solution of this application, the hammer assembly includes a hammer and a traction cable, the side wall of the hammer is provided with a vertical guide groove, and the bottom end of the hammer is a frustoconical impact surface.

[0022] Based on the above description of the technical content, the technical effects of this application are specifically reflected in the following aspects: 1. Significantly improves pile tip bearing capacity By constructing a three-layer composite reinforcement (compacted filler reinforcement zone + bearing layer compaction zone + bearing layer squeezing zone) in the bearing stratum at the bottom of the pile, the bearing capacity of the pile tip is increased by more than 30%, effectively solving the problem of reinforcing the bearing stratum of pile foundations in soft soil areas.

[0023] 2. Construction efficiency and economy Equipment reuse: The hollow channel of the drilling equipment can be used directly for compaction and reinforcement without additional drilling, simplifying the process.

[0024] Shorter construction period: Hole drilling, reinforcement, and grouting are completed in one integrated process, reducing the time required for process changeover.

[0025] Cost reduction: Avoid investment in specialized reinforcement equipment; materials (graded crushed stone / aggregate) are inexpensive and readily available.

[0026] 3. Minimal Disturbance Green Construction By isolating the surrounding soil with a casing / spiral pipe, disturbance to the soil around the pile is reduced; The compaction zone forms a natural transition layer, preventing damage to the soil structure of the bearing layer and meeting environmental protection construction requirements.

[0027] 4. Adaptable to complex strata For soft soil strata: steel casing combined with separable pile tips enables soil squeezing and sinking, preventing borehole collapse; For mud wall protection applications: the spiral pipe serves both as a wall protection channel and a packing channel, ensuring effective compaction.

[0028] 5. Enhanced structural reliability The three-layer reinforcement structure forms a stepped strength distribution: the surface dense fill provides rigid support; the middle layer of undisturbed soil compaction layer preserves the integrity of the bearing layer; and the outer compaction transition zone disperses stress and reduces the risk of settlement.

[0029] 6. High process flexibility This application is applicable to a variety of construction methods: spiral drill rod direct impact method, casing insertion and compaction method, casing sinking and excavation method, and casing with pile tip squeezing and sinking method, which can be adapted to different engineering scenarios.

[0030] In summary, this compaction-reinforced bearing layer grouting pile technology brings significant innovation and improvement to the field of pile foundation engineering by improving the bearing capacity of the pile foundation end, achieving high efficiency in pile end reinforcement construction, reducing construction costs, realizing the goal of green construction of pile foundations with minimal disturbance, enhancing the stability of pile foundations, and providing diversified construction methods. Attached Figure Description

[0031] Figure 1 This application provides a schematic diagram of the structure of the hollow drill pipe, which provides a column hammer and a filling channel to reinforce the bearing layer through compaction. Figure 2 This application presents a schematic diagram of the structure of a bored cast-in-place pile where a protective casing is inserted to provide a channel for the hammer and filler material, thereby compacting and reinforcing the bearing layer. Figure 3 This application provides a structural schematic diagram of the steel casing, including the column hammer and filling channel, which are compacted to reinforce the bearing layer. Figure 4 This application presents a schematic diagram of the soil structure extracted from the inside of the steel casing using a bucket drill. Figure 5 This application includes a schematic diagram of a sealed pile tip driven into a casing structure. Figure 6 This application presents a structural schematic diagram of an enlarged-base cast-in-place pile designed to compact and reinforce the pile tip sediment and bearing layer. Figure 7 This application presents a schematic diagram of the structure of the casing and the spiral drilling for soil extraction. Figure 8 This application presents a schematic diagram of a drilling and hole-forming structure using mud slurry wall protection. Figure 9 This application presents a schematic diagram of the structure after a spiral tube is placed inside the drilling hole for mud wall protection.

[0032] In the diagram: 100, reinforced bearing body; 101, compaction filler reinforcement zone; 102, bearing stratum compaction zone; 103, bearing stratum compaction zone; 200, long auger drill bit; 201, hollow drill rod; 202, auger blade; 300, column hammer; 301, filler; 400, steel casing; 401, cylindrical bucket; 402, pile tip; 403, mixer; 500, cast-in-place concrete pile; 600, borehole wall; 601, borehole casing; 602, wall protection mud; 603, bottom of borehole; 604, auger pipe; 700, rear-inserted casing. Detailed Implementation

[0033] The preferred embodiments of the present invention will be described below with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are for illustration and explanation only and are not intended to limit the present invention.

[0034] I. Explanation of descriptive terms used in this utility model The embodiments provided in conjunction with the technical solutions of this utility model are intended to make the present utility model more thorough and complete, and to fully express the scope of the present utility model to those skilled in the art. It should be noted that unless otherwise specifically stated by the present utility model, the relative arrangement of components described in these embodiments should be interpreted as merely exemplary, and not as a limitation on the technical solutions of the present utility model.

[0035] In this utility model, the use of directional terms such as "upper," "lower," "left," "right," "bottom," and "top" is defined relative to the directions shown in the accompanying drawings and is used only to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly. These or other directional terms should not be construed as restrictive terms.

[0036] In this utility model, the terms "a," "an," "a kind," "the," and similar words used do not indicate quantity limitation and can represent singular or plural. The terms "comprising," "including," "having," and any variations thereof used in this utility model are intended to cover non-exclusive inclusion; the terms "first," "second," "third," etc., used in this utility model are merely to distinguish similar objects and do not represent a specific ordering of objects.

[0037] In this invention, when a specific device is described as being located between a first device and a second device, an intermediary device may or may not exist between the specific device and the first or second device. When a specific device is described as being connected to other devices, the specific device may be directly connected to the other devices without an intermediary device, or it may not be directly connected to the other devices but may have an intermediary device.

[0038] Furthermore, this utility model does not discuss in detail the technologies and equipment known to those skilled in the art, but where appropriate, such technologies and equipment should be considered part of the specification.

[0039] II. The core technical problem to be solved by the technical solution of this application Existing bored pile construction technologies have many problems. Mainstream technologies, such as reverse circulation drilling rig mud wall forming and underwater concrete pouring, and rotary drilling rig mud wall forming and underwater concrete pouring, inevitably result in mud cake formation on the pile wall and sediment buildup at the pile tip due to the use of mud wall protection. The mud cake weakens the pile's side friction, and the sediment forms a weak cushion layer, significantly reducing the pile tip bearing capacity.

[0040] While the long spiral pre-drilling and pressure grouting concrete technology eliminates the need for mud slurry wall protection, avoiding mud skin and sediment problems, the drilling of the spiral drill bit disturbs the bearing stratum soil at the pile tip, leading to a decrease in bearing capacity. Although the engineering community widely adopts "post-grouting technology at the pile tip" to compensate for the loss of pile tip bearing capacity, the grout in this technology diffuses randomly in the soil, making it difficult to accurately control the reinforcement range and effect. The effect on improving the bearing capacity of the pile foundation is uncertain and is greatly affected by factors such as geological conditions, grout mix ratio, and grouting process.

[0041] Therefore, engineering practice urgently needs a more direct, effective and reliable method to reinforce the bearing layer at the pile tip.

[0042] III. Based on the above problems, this utility model specifically provides a technical solution to solve these problems. The following describes a specific embodiment with reference to... Figures 1-9 As shown, the technical solution, working principle and technical effects of this utility model are described in detail.

[0043] Example 1: Construction of compaction-reinforced cast-in-place piles based on hollow drill rods (I) Cast-in-place pile structure In this embodiment, the enlarged-base cast-in-place pile with compaction reinforcement for pile tip sediment and bearing layer includes a concrete pile body, and a compaction reinforcement is connected to the bottom of the concrete pile body. The compaction reinforcement consists of a three-layer composite structure from top to bottom: Compacted filler reinforcement zone 101: Graded crushed stone is used as compacted filler 301, with the crushed stone particle size controlled at 30mm (not greater than 50mm), and it is evenly filled above the bearing layer at the bottom of the pile to form a compacted filler reinforcement zone.

[0044] Bearing layer compaction zone 102: Located below the compaction filler reinforcement zone 101, it is formed by compacting the original bearing layer and then compacting it with subsequent construction equipment to form a reinforced layer with certain strength and stability, thereby improving the bearing capacity.

[0045] Bearing layer compaction zone 103: Encloses the bearing layer compaction zone. During construction, the bearing layer is subjected to compression to form a transitional compaction layer, which further enhances the bearing capacity of the pile bottom.

[0046] (ii) Construction equipment Hollow channel component: Hollow drill rod 201 is selected, with an openable and closable gate at its bottom end. During drilling, the hollow drill rod 201 not only serves as a guide but also provides a channel for subsequent compaction and filler material placement.

[0047] Before construction, the hollow drill rod 201 is inserted through the pile hole, with the bottom opening extending to the bearing layer at the bottom of the pile. When it is necessary to put in the fill material, the gate is opened and closed after the filling is completed to prevent the fill material from leaking.

[0048] Piston Hammer Assembly: The piston hammer 300 is vertically mounted inside the hollow drill rod 201. The diameter of the hammer assembly is adapted to the inner diameter of the hollow drill rod 201 to ensure that the piston hammer 300 moves smoothly up and down inside the drill rod.

[0049] The bottom of the 300 column hammer is equipped with an impact boss, the diameter of which is larger than the diameter of the middle part of the hammer body. This design can increase the impact force distribution range during compaction and improve the compaction effect.

[0050] The hammer assembly also includes a traction cable for raising and lowering the hammer, thereby controlling the lifting and lowering of the hammer 300. The bottom of the hammer 300 has a frustoconical impact surface, which helps to concentrate the impact force and better compact the filler and bearing layer.

[0051] The filler material feeding assembly consists of a mixer 403 and a feeding pipe. After the mixer 403 mixes the graded crushed stone evenly, the filler material 301 is transported to the top inlet of the hollow drill rod 201 through the feeding pipe. The filler material slides down the inner wall of the drill rod to the bottom of the pile.

[0052] (III) Construction Process Drilling: Use hollow drill rod 201 to drill a pile hole at the predetermined position, to the designed pile bottom bearing layer depth.

[0053] Filling material placement: Open the gate at the bottom of the hollow drill rod 201 and put the graded crushed stone filler 301 into the hollow drill rod 201 through the filler placement component. The filler falls into the bottom of the pile under the action of gravity.

[0054] Compacting the fill material: Raise the column hammer 300 to a certain height, and then let it fall freely to compact the fill material 301 at the bottom of the pile, forming a compacted fill material reinforcement zone 101.

[0055] Compacting the bearing layer: Continue raising and lowering the hammer 300 to compact the bearing layer, transforming the original bearing layer into a compacted bearing layer zone 102, while simultaneously compressing the bearing layer to form a squeezed bearing layer zone 103. Repeat the raising and lowering of the hammer multiple times until the required compaction effect is achieved.

[0056] Concrete pouring: After the compaction operation is completed, the hollow drill rod 201 is removed and concrete is poured into the pile hole to form a concrete pile body.

[0057] Specifically, such as Figure 1As shown, a long spiral drill bit 200 is used to drill a hole at the pile location. Near the hole opening, the upper part of the hollow drill rod 201 is removed. Using the central channel of the hollow drill rod 201, a column hammer 300 is inserted. Simultaneously, the gate at the bottom of the hollow drill rod 201 is opened, and filler material 301 is inserted from the hole opening into the central channel of the hollow drill rod 201. The column hammer 300 is used to impact the filler material 301 below the pile bottom, forming a reinforced bearing body 100 composed of a compacted filler reinforcement zone 101, a bearing layer compaction zone 102, and a bearing layer squeezing zone 103 below the pile end. Finally, the spiral blades 202 are used to lift and remove the soil from the hole. Simultaneously, concrete is injected through the central channel of the hollow drill rod 201 to fill the borehole, forming a cast-in-place concrete pile 500. The reinforcing cage inside the pile can be inserted using a vibration method, forming a structure as shown in the diagram. Figure 6 The cast-in-place pile and bearing body are shown.

[0058] Example 2: Construction of compaction-reinforced cast-in-place piles based on steel casing (I) Cast-in-place pile structure Similar to Example 1, the cast-in-place pile structure includes a concrete pile body and a compaction reinforcement at the bottom. The compaction reinforcement consists of a compaction filler reinforcement zone 101, a bearing layer compaction zone 102, and a bearing layer compaction zone 103. The compaction filler reinforcement zone 101 uses concrete aggregate as filler 301 with a particle size of 40mm (not greater than 50mm).

[0059] (ii) Construction equipment Hollow channel component: A steel casing 400 is used, with an open bottom and a continuous cylindrical structure on the sidewalls. A detachable pile tip 402 is connected to the bottom of the steel casing 400, and the pile tip 402 is detachably connected to the steel casing 400 via a snap-fit ​​connection. During construction, the pile tip 402 is first connected to the steel casing 400, and then it is driven into the pile hole until it reaches the bearing stratum at the bottom of the pile.

[0060] Plunger Assembly: The plunger 300 is vertically mounted within the steel casing 400, and the diameter of the hammer assembly is adapted to the inner diameter of the steel casing 400. The side wall of the plunger 300 has vertical guide grooves to ensure stability during lifting and lowering. The bottom of the plunger 300 has a frustum-shaped impact surface with an impact boss; the diameter of the boss is larger than the diameter of the middle part of the hammer body. The plunger assembly also includes a traction cable for controlling the lifting and lowering of the plunger 300.

[0061] Filler material delivery assembly: Consists of mixer 403 and feeding pipe. After the mixer 403 mixes the concrete aggregate evenly, the filler material 301 is transported to the top inlet of the steel casing 400 through the feeding pipe. The filler material enters the casing and slides down to the bottom of the pile.

[0062] (III) Construction Process Sinking the casing: Drill a pile hole at the predetermined position using drilling equipment, and sink the steel casing 400 connected to the pile tip 402 into the pile hole until it reaches the bearing layer at the bottom of the pile.

[0063] Adding filler: Turn on the mixer 403 and add concrete aggregate filler 301 into the steel casing 400 through the filler feeding component.

[0064] Compacting filler: The column hammer 300 is lifted to a certain height by traction steel cable and then falls freely to compact the filler 301 at the bottom of the pile. At the same time, it exerts a squeezing effect on the bearing layer to form the compacted filler reinforcement zone 101.

[0065] Compacting the bearing layer: Continue to raise and lower the column hammer 300 to compact the bearing layer, forming the bearing layer compaction zone 102 and the bearing layer squeezing zone 103.

[0066] Separating the pile tip: After the compaction operation is completed, the pile tip 402 is separated from the steel casing 400 by means of a clip.

[0067] Concrete pouring: Pull out the steel casing 400mm and pour concrete into the pile hole to form a concrete pile body.

[0068] Specifically, for some weak strata, in order to achieve compaction of the bearing layer at the bottom of the pile and improve its bearing capacity, the method of sinking the casing to guide the borehole is adopted.

[0069] like Figure 3 As shown, vibration penetrates the steel casing 400 deep into the stratum, bringing it to the design elevation. Then, an auger drill 202 is used to remove the soil inside the steel casing 400, as shown. Figure 7 As shown; another method is to use a cylindrical bucket 401 to remove the soil inside the steel casing 400, such as Figure 4 As shown.

[0070] like Figure 5 As shown, the steel casing 400 and the separable pile tip 402 are vibrated and driven into the foundation soil by squeezing the soil to reach the design elevation.

[0071] Then, a hammer 300 is placed inside the steel casing 400, and the mixed filler 301 from the mixer 403 is filled into the steel casing 400. The hammer 300 is used to traction the filler 301 to impact below the pile bottom, forming a bearing body 100 below the pile end, consisting of a compacted filler reinforcement zone 101, a bearing layer compaction zone 102, and a bearing layer densification zone 103. Finally, concrete is poured into the steel casing 400, and the steel casing 400 is then vibrated out of the borehole. Figure 6 As shown, 500 concrete piles are formed.

[0072] Example 3: Construction of Compaction-Reinforced Cast-in-Place Piles Based on Spiral Pipes (I) Cast-in-place pile structure The structure of the cast-in-place pile is consistent with the previous two embodiments. The compaction reinforcement includes a compaction filler reinforcement zone 101, a bearing layer compaction zone 102, and a bearing layer compaction zone 103. The compaction filler reinforcement zone 101 uses graded crushed stone as filler 301 with a particle size of 45mm.

[0073] (ii) Construction equipment Hollow channel components: Spiral tube 604 is selected. Spiral tube 604 is a segmented steel pipe with spiral protrusions on the pipe wall and an open bottom structure. The spiral tube 604 is driven into the pile hole in segments until it reaches the bearing layer at the bottom of the pile. The spiral protrusions can increase the friction between the pipe wall and the soil, thereby improving the stability of the spiral tube 604.

[0074] Plunger Assembly: The plunger 300 is vertically mounted within the helical tube 604, and the diameter of the hammer assembly is adapted to the inner diameter of the helical tube 604. The plunger 300 has an impact boss at its bottom, the diameter of which is larger than the diameter of the middle part of the hammer body, and the bottom end has a frustum-shaped impact surface. The plunger assembly also includes a traction steel cable for controlling the lifting and lowering of the plunger 300.

[0075] The filler material delivery assembly consists of a mixer 403 and a feeding pipe. After the mixer 403 mixes the graded crushed stone evenly, the filler material 301 is transported to the top inlet of the spiral pipe 604 through the feeding pipe. The filler material enters the pipe and slides down to the bottom of the pile.

[0076] (III) Construction Process Driving the spiral pipe: Drill a pile hole at a predetermined location using drilling equipment, and drive the spiral pipe 604 into the pile hole in sections until it reaches the bearing layer at the bottom of the pile.

[0077] Adding filler: Start the mixer 403 and add graded crushed stone filler 301 into the spiral tube 604 through the filler feeding component.

[0078] Compacting the fill material: Raise the column hammer 300 to a certain height, and then let it fall freely to compact the fill material 301 at the bottom of the pile, forming a compacted fill material reinforcement zone 101.

[0079] Compacting the bearing layer: Continue to raise and lower the column hammer 300 to compact the bearing layer, forming the bearing layer compaction zone 102 and the bearing layer squeezing zone 103.

[0080] Concrete pouring: After the compaction operation is completed, the spiral pipe 604 is pulled out and concrete is poured into the pile hole to form a concrete pile body.

[0081] Specifically, such as Figure 2 , Figure 8 As shown, a reverse circulation drilling tool is used to form a hole. The hole wall 600 is drilled from the bottom of the hole 603 by the wall protection mud 602; then the spiral pipe 604 is inserted into the bottom of the hole 603.

[0082] like Figure 9 As shown, the plunger 300 is sunk into the spiral tube 604, and concrete is poured from the spiral tube 604 into the hole to displace the mud inside the hole.

[0083] A protective pipe 700 is inserted into the concrete, and the filler 301 is impacted below the bottom of the pile by a traction hammer 300, forming a structure below the pile end. Figure 6 The reinforced support body 100 is composed of the compacted filler reinforcement zone 101, the bearing layer compaction zone 102, and the bearing layer extrusion zone 103 shown.

[0084] As a further optimization design, the hollow channel component can also be designed as a steel protective pipe inserted into the center of the uncured concrete pile in a reverse circulation drilling or rotary drilling rig bored pile.

[0085] The above description is only a preferred embodiment of this application and is not intended to limit the present utility model. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present utility model should be included within the protection scope of the present utility model.

[0086] Furthermore, the technical solutions of the various embodiments can be combined with each other, but only if they are feasible for those skilled in the art. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such combination of technical solutions does not exist and is not within the scope of protection claimed by this utility model.

Claims

1. A type of enlarged-base cast-in-place pile formed by compacting and reinforcing pile tip sediment and bearing layer, comprising a concrete pile body, characterized in that: The bottom of the concrete pile is connected to a compaction reinforcement body, the compaction degree of which is controlled by the penetration depth of the compaction hammer; the compaction reinforcement body comprises a three-layer composite structure from top to bottom: The compacted filler reinforcement zone (101) embedded in the bearing layer is composed of compacted filler (301); The bearing layer compaction zone (102) located below the filler (301) zone is a reinforced layer formed by compaction of the original bearing layer; The bearing layer compaction zone (103) that encloses the bearing layer compaction zone (102) is a transitional compaction zone formed by the compression of the bearing layer.

2. The enlarged-base cast-in-place pile formed by compacting and reinforcing the pile tip sediment and bearing layer according to claim 1, characterized in that: The filler (301) in the compaction filler reinforcement zone (101) is dry powdered cement sand or dry crushed stone concrete aggregate with a particle size not greater than 5 mm.

3. A construction device for enlarged-base cast-in-place piles that compacts and reinforces the pile tip sediment and bearing layer, applied to the enlarged-base cast-in-place piles described in claim 1 or 2, characterized in that... include: Hollow channel components, column hammer assembly, and filler dispensing assembly; The hollow channel component runs through the pile body, and its bottom end extends to the bearing layer at the bottom of the pile. The hammer assembly is vertically and vertically mounted inside the hollow channel component, and the diameter of the hammer assembly is adapted to the inner diameter of the hollow channel component. The packing dispensing assembly is used to dispense packing material (301) into the hollow channel component.

4. The apparatus according to claim 3, characterized in that: The hollow channel component is a hollow drill rod (201) of a long spiral drill bit, with an openable and closable gate at its bottom end.

5. The apparatus according to claim 3, characterized in that: The hollow channel component is a steel casing (400) for the driven pipe pile.

6. The apparatus according to claim 3, characterized in that: The hollow channel component is a steel protective pipe inserted into the center of the uncured concrete pile in a reverse circulation drilling or rotary drilling bored pile.

7. The apparatus according to claim 5, characterized in that: The bottom end of the steel casing (400) is connected to a separable pile tip (402) or end plate. The pile tip (402) and the steel casing (400) are detachably connected by a snap-fit. The pile tip can be separated from the casing by impacting the pile with a hammer.

8. The apparatus according to claim 3, characterized in that: The hollow channel component is a spiral tube (604) or a rear-inserted protective tube (700). The spiral tube (604) is a segmented steel pipe with spiral threads on the pipe wall for easy insertion or extraction. The bottom of the pipe is an open structure that connects to the pile tip or end plate.

9. The apparatus according to claim 3, characterized in that: The filler dispensing assembly includes a mixer (403) and a feeding pipe, with the outlet of the feeding pipe aligned with the top inlet of the hollow channel component.

10. The apparatus according to claim 3, characterized in that: The hammer assembly includes a hammer (300) and a traction cable, and the bottom end of the hammer (300) has a frustum-shaped impact surface.