A pre-stressed anti-floating anchor rod structure for a pipe jacking shaft

By integrating the drilling and grouting process of screw piles, the problem of hole collapse during the construction of anchor bolts in pipe jacking working wells has been solved, improving the anti-buoyancy capacity and construction efficiency, and reducing costs and pollution.

CN225014143UActive Publication Date: 2026-11-24ZHEJIANG COMM CONSTR GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522786461.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-29
Publication Date
2026-11-24
Estimated Expiration
2035-12-29

AI Technical Summary

Technical Problem

In the construction of pipe jacking working shafts in water-rich areas, the existing technology has a high risk of hole collapse in soft strata after the anchor bolts are drilled, which affects the grouting quality and the pull-out strength of the anchor bolts. In addition, the construction process is complicated and inefficient.

Method used

The process of drilling and grouting of screw piles is integrated to form threaded pile segments in hard rock layers. Prestressed threaded steel bars are inserted into the uncured grout and equipped with a grout recovery device to ensure the quality of anchor installation and material utilization.

Benefits of technology

It improves the pull-out bearing capacity of anchor bolts, avoids the risk of hole collapse, simplifies construction procedures, reduces costs and environmental pollution, and improves construction efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014143U_ABST
    Figure CN225014143U_ABST
Patent Text Reader

Abstract

This utility model provides a prestressed anti-buoyancy anchor structure for a pipe jacking well. The structure includes an anchor hole, prestressed threaded steel bars, and a positioning frame. The lower part of the anchor hole is a threaded pile segment formed in hard rock, and the upper part is a cylindrical pile segment formed in soft soil. Grout is injected into the anchor hole. The prestressed threaded steel bars are suitable for insertion into the unsolidified grout. The prestressed threaded steel bars include a threaded section and a straight section. The threaded section is anchored to the threaded pile segment of the anchor hole, and the straight section is located within the cylindrical pile segment. The positioning frame is supported between the prestressed threaded steel bars and the hole wall of the anchor hole. A grout recovery device is installed at the opening of the anchor hole to collect grout overflowing during the insertion of the prestressed threaded steel bars.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of underground engineering construction and relates to the anti-buoyancy structure of pipe jacking working shaft in water-rich areas. Specifically, it relates to a prestressed anti-buoyancy anchor structure for anti-buoyancy of pipe jacking working shaft. Background Technology

[0002] The working shaft is a crucial structure in pipe jacking engineering. When the working shaft is located in a water-rich area with a high groundwater level, its resistance to buoyancy and tilting under adverse conditions such as the flood season are critical issues that must be addressed during design and construction. In engineering practice, anti-buoyancy measures for the shaft mainly include increasing the structural self-weight, adding capping beams, anti-uplift piles, anchor bolts, dewatering, and water interception for anti-buoyancy.

[0003] Due to their strong adaptability to site soil layers, low cost, and convenient construction, anti-buoyancy anchors have been widely promoted and applied in the anti-buoyancy design of underground structures such as pipe jacking shafts.

[0004] Anti-buoyancy anchors can be divided into non-prestressed and prestressed types. Their conventional construction process mainly involves drilling with an anchor drilling machine, fabricating and installing the anchor rod (with grouting pipe), and grouting inside the hole. Using existing processes, the risk of hole collapse is relatively high in soft strata sections after drilling and before grouting, thus affecting grouting quality and anchor pull-out strength. Therefore, there is an urgent need for a new type of anti-buoyancy anchor structure and construction method that can effectively avoid hole collapse and ensure construction quality. Utility Model Content

[0005] This utility model aims to overcome the shortcomings of the existing technology and provide a prestressed anti-buoyancy anchor structure for jacking wells that integrates drilling and grouting, has high pull-out resistance, and reliable construction quality.

[0006] To achieve the above objectives, the present invention adopts the following technical solution:

[0007] A prestressed anti-buoyancy anchor structure for a pipe jacking shaft, the structure comprising:

[0008] An anchor bolt hole, the lower part of which is a threaded pile segment formed in hard rock layer, and the upper part of which is a cylindrical pile segment formed in soft soil layer; grout, which is poured into the anchor bolt hole; prestressed threaded steel bars, which are inserted into the unsolidified grout by a post-installation method; the prestressed threaded steel bars include threaded sections and straight sections, the threaded sections are anchored to the threaded pile segment of the anchor bolt hole, and the straight sections are located in the cylindrical pile segment; at least one positioning frame, which is supported between the prestressed threaded steel bars and the hole wall of the anchor bolt hole; a grout recovery device, which is installed at the opening of the anchor bolt hole, is used to collect the grout overflowing during the insertion of the prestressed threaded steel bars.

[0009] In some embodiments, the anchor structure further includes a tensioning end assembly, which includes a pad and a tensioning end anchor.

[0010] In some embodiments, the bottom end of the prestressed threaded steel bar is fitted with a tapered guide cap.

[0011] In some embodiments, the positioning frame is a conical positioning device.

[0012] In some embodiments, the slurry recovery device includes an annular container body composed of an inner wall and an outer wall. The bottom of the inner wall has an opening for receiving anchor bolt holes, and at least one slurry collection port is provided on its side wall. The bottom of the outer wall is connected to a slurry discharge pipe with a slurry outlet.

[0013] In some embodiments, two handles are symmetrically arranged on the outer wall along its top edge.

[0014] In some embodiments, the top of the prestressed threaded steel bar passes through the base plate and the pad plate in sequence and is anchored by the tensioning end anchor.

[0015] In some embodiments, a waterproof rubber sleeve is fitted at the position where the prestressed threaded steel bar passes through the base plate, and a tensioning end spiral bar is provided between the pad and the base plate.

[0016] In some embodiments, the ratio S / D of the threaded pile pitch S to the anchor hole diameter D is 1.0.

[0017] In some embodiments, the anchor holes are formed using a bolt pile process.

[0018] Compared with the prior art, the prestressed anti-buoyancy anchor structure provided by this utility model has the following significant advantages:

[0019] 1. This utility model forms a threaded pile segment in the hard rock layer at the bottom of the anchor bolt hole. By utilizing the huge mechanical interlocking force and end bearing force generated by its spiral disc surface and the surrounding rock and soil, the anchoring efficiency of the anchor bolt is greatly enhanced. This provides the jacking working well with a pull-out bearing capacity far exceeding that of traditional straight hole anchor bolts, effectively resisting the buoyancy of groundwater and preventing the working well from floating or tilting.

[0020] 2. An integrated construction process for bolt pile drilling and grouting is adopted. High-pressure grouting is performed simultaneously during the drill rod lifting process, ensuring the grout consistently fills the gap between the borehole wall and the drill rod, providing continuous support to the borehole wall. This fundamentally eliminates the risk of borehole collapse in weak soil layers and ensures the quality of both the drilling and the grouting. Simultaneous completion of drilling and grouting simplifies the previously separate "drilling-anchoring-grouting" processes, shortens the construction cycle, and improves overall efficiency.

[0021] 3. To address the issue of grout overflowing from the borehole during the post-installation of anchor bolts, a grout recovery device was specifically designed. This device effectively collects the overflowing fresh grout and recycles it through pipelines to a grout storage tank for reuse, avoiding material waste and environmental pollution, and reducing construction costs.

[0022] 4. The conical guide cap at the bottom of the prestressed steel bar and the conical locator installed on the rod greatly reduce the sinking resistance when inserting the anchor rod into the uncured grout, ensuring that the anchor rod can be smoothly installed to the designed depth. At the same time, the locator ensures that the anchor rod is precisely aligned in the grout, forming a uniform protective layer thickness, which is beneficial to ensuring long-term durability.

[0023] In addition, pads, spiral reinforcements, and waterproof rubber sleeves are installed at the tensioning end to ensure that the tension stress is effectively transferred to the bottom plate of the well body, and to enhance the crack resistance and waterproof sealing of the joint area, thus ensuring the long-term safety of the pipe jacking working well structure. Attached Figure Description

[0024] Figure 1 A schematic diagram of the prestressed anti-buoyancy anchor structure for the jacking shaft provided by this utility model; Figure 2 This is a schematic diagram of the slurry recovery device in this utility model;

[0025] Figure 3 for Figure 1 A partial schematic diagram;

[0026] in,

[0027] 1-Prestressed threaded steel bar, 2-Anchor hole, 3-Threaded rod section, 4-Straight rod section, 5-Anchor, 6-Metal bearing body, 7-Conical guide cap, 8-Sleeve, 9-Positioning frame, 10-Borehole wall, 11-Groove, 12-Groove recovery device, 13-Groove discharge port, 14-Inner wall, 15-Outer wall, 16-Groove collection port, 17-Groove outlet, 18-Groove discharge hose, 19-Lifting lug, 20-Well bottom plate, 21-Waterproof rubber collar, 22-Tension end spiral reinforcement, 23-Pad plate, 24-Tension end anchor. Detailed Implementation

[0028] The prestressed anti-buoyancy anchor structure for the jacking well provided by this utility model will be described in detail below with reference to the accompanying drawings, so that those skilled in the art can better understand the technical solution of this utility model.

[0029] like Figure 1-3 As shown, the prestressed anti-buoyancy anchor structure of this utility model mainly includes, from bottom to top, anchor holes and grout, prestressed threaded steel bars, tensioning end components and grout recovery device;

[0030] The anchor hole 2 is a cavity formed in the soil layer using a screw pile process. Its lower part penetrates into the hard rock layer, forming a threaded pile segment. Through the squeezing action of the screw blades, this segment forms continuous spiral ridges on the hole wall, increasing the surface area and mechanical interlocking force, thereby significantly improving the pull-out bearing capacity of the anchor. The upper part of the anchor hole 2 penetrates through the soft soil layer, forming a cylindrical pile segment. The entire anchor hole is filled with cement-based grout, forming a consolidated pile body.

[0031] The prestressed threaded steel bar 1 is inserted into the uncured grout 11 using a post-installation method. A conical guide cap 7 is fitted to its bottom end; this design effectively reduces resistance during insertion into the grout, ensuring smooth installation of the anchor rod. The prestressed threaded steel bar includes a threaded section 3 and a straight section 4. The threaded section 3 is anchored to the threaded pile section of the anchor bolt hole 2, and the straight section 4 is located within the cylindrical pile section.

[0032] Multiple positioning frames 9 are provided on the rod body. The positioning frame 9 is preferably a conical positioning device, and its outer edge is supported on the hole wall 10. The positioning frame 9 can ensure that the prestressed threaded steel bar 1 is centered in the hole, so that a uniform grout protective layer is formed around it, ensuring uniform stress and long-term durability.

[0033] The top of the prestressed threaded steel bar 1 passes through the bottom plate 20 of the jacking shaft. A waterproof rubber sleeve 21 is fitted at the point where the bar passes through, playing a crucial role in sealing and waterproofing, preventing groundwater from seeping into the shaft along the steel bar. A pad 23 and a tensioning end anchor 24 are sequentially installed above the bottom plate 20 for tensioning and locking the prestress. A tensioning end spiral reinforcement 22 is also installed below the pad 23 to locally reinforce the bottom plate concrete, effectively dispersing the tension stress and preventing the concrete from splitting at the anchoring point.

[0034] like Figure 2 As shown, the grout recovery device 12 is installed at the opening of the anchor bolt hole 2. Its main body consists of an inner wall 14 and an outer wall 15. A grout collection port 16 is opened on the side wall of the inner wall 14, and a grout discharge hose 18 with a grout outlet 17 is connected to the bottom of the outer wall 15. This device allows for the effective collection of fresh grout overflowing during the post-installation of reinforcing bars, which is then recycled to a grout storage tank via the hose 18 for reuse. This not only saves materials and reduces costs but also avoids grout pollution of the construction site, meeting the requirements of green construction. The symmetrically arranged lugs 19 on the outer wall 15 facilitate handling and installation.

[0035] This invention aims to construct anti-buoyancy anchor bolts for jacking shafts by forming threaded piles at the lower end of anchor bolts using a screw pile drilling process, followed by simultaneous grouting and lifting within the drill rod, subsequent insertion of prestressed anchor bolts, installation of water-stopping devices, tensioning, and sealing. This integrated screw pile drilling and grouting construction not only effectively improves the strength of the anti-buoyancy anchor bolts but also simplifies the construction process and accelerates progress. Furthermore, it effectively avoids the drawbacks of conventional construction methods, such as end sedimentation and hole collapse, which occur when anchor bolts are inserted first and then grouted.

[0036] By way of example, the present invention provides a construction step for the aforementioned structure:

[0037] 1. Integrated Construction of Anchor Bolt and Screw Pile Drilling and Grouting: Anchor bolt holes are drilled using a small screw-type drilling machine. A cylindrical pile is formed in the upper soft soil, while a spiral pile with high pull-out bearing capacity is formed in the lower hard rock layer. Specifically: A small-diameter screw-type grouting machine is matched to the designed hole size of the anti-buoyancy anchor pile, where the ratio of the screw pitch S to the anchor hole diameter D should be 1.0. During drilling, the forward rotation is used to compact the soil before drilling. Drilling stops when the drill bit reaches the designed depth. Then, the drill bit is rotated upwards using a reverse synchronous technique while simultaneously injecting high-pressure grout into the pipe. At the straight section, a forward asynchronous technique is used for rotation and high-pressure grouting. The materials used for the grout, such as cement grade, sand particle parameters (maximum particle size, mud content, organic matter content, etc.), and mix proportions, should meet the design requirements.

[0038] 2. Fabrication and Installation of Prestressed Anchor Bolts: The anchorage, metal bearing, conical guide cap, sleeve, and external anti-corrosion coating of the prestressed anchor bolt anchoring end are fabricated according to conventional processes. Since this invention uses a post-installation method (grouting before anchor bolt installation), a conical locator is used for the anchor bolt positioning frame to reduce the resistance during anchor bolt lowering. The spacing of the locators meets design requirements and does not exceed 2m. Simultaneously, a grout recovery device is designed at the borehole opening to promptly collect and reuse the grout overflowing during anchor bolt installation. The recovery device is a circular container made of 6mm thick steel plate. The inner ring diameter is the anchor bolt hole diameter + 2cm, the inner wall height is 20cm, and four 5cm wide U-shaped grout collection ports are opened at the cross intersection of the anchor bolt holes, approximately 5cm from the bottom of the inner wall. The outer ring diameter of the container is the anchor bolt hole diameter + 15cm, and the outer wall height is 35cm. A grout outlet with a steel nozzle, 8cm in diameter, is opened along the bottom of the outer wall. Through an external flexible hose, all overflowing grout during anchor bolt hoisting can be collected and reused at a designated location. Two lifting lugs are installed on the outer ring wall of the container, 10cm from the top, along the diameter, to facilitate container handling and positioning.

[0039] After the anchor bolts are installed in place, the installation of the water-stopping device, tensioning, and anchor sealing are carried out using conventional processes.

Claims

1. A prestressed anti-buoyancy anchor structure for a pipe jacking shaft, characterized in that, The structure includes: Anchor bolt holes, the lower part of which is a threaded pile segment formed in hard rock layer, and the upper part is a cylindrical pile segment formed in soft soil layer; grout is injected into the anchor bolt holes; Prestressed threaded steel bars, suitable for insertion into the uncured grout, the prestressed threaded steel bars comprising threaded sections and straight sections, the threaded sections being anchored to the threaded pile sections of the anchor holes, and the straight sections being located within the cylindrical pile sections; At least one positioning frame is supported between the prestressed threaded steel bar and the wall of the anchor bolt hole; A grout recovery device is installed at the opening of the anchor bolt hole to collect the grout that overflows during the insertion of prestressed threaded steel bars.

2. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 1, characterized in that, The anchor structure also includes a tensioning end assembly, which includes a pad and a tensioning end anchor.

3. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 1, characterized in that, The prestressed threaded steel bar is fitted with a tapered guide cap at its bottom end.

4. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 1, characterized in that, The positioning frame is a conical positioning device.

5. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 1, characterized in that, The slurry recovery device includes an annular container body, which is composed of an inner wall and an outer wall. The bottom of the inner wall has an opening for accommodating anchor bolt holes, and at least one slurry collection port is provided on its side wall. The bottom of the outer wall is connected to a slurry discharge pipe with a slurry outlet.

6. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 5, characterized in that, Two handles are symmetrically arranged along the top edge of the outer wall.

7. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 2, characterized in that, The top of the prestressed threaded steel bar passes through the bottom plate and the pad plate in sequence, and is anchored by the tensioning end anchor.

8. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 7, characterized in that, A waterproof rubber sleeve is fitted at the position where the prestressed threaded steel bar passes through the base plate, and a tensioning end spiral bar is provided between the pad and the base plate.

9. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 1, characterized in that, The ratio of the thread pitch S to the anchor hole diameter D of the threaded pile segment, S / D, is 1.

0.

10. The prestressed anti-buoyancy anchor structure for pipe jacking shafts according to claim 1, characterized in that, The anchor holes are formed using the bolt pile process.