An underwater concrete precast pile sinking device
By installing mud scraping and brushing components on the marker poles and a ring-shaped flushing device inside the installation pipe, the problem of the marker pole markings being obscured by mud film was solved, ensuring the accuracy and reliability of the pile driving operation.
Patent Information
- Application Number
- CN202522762277.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-26
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-26
AI Technical Summary
During underwater precast concrete pile driving operations, the mud on the surface of the marker solidifies to form an opaque mud film, affecting the visibility of the scale and leading to a decrease in the accuracy and reliability of the pile driving operation.
A mud scraper and a brush assembly are installed on the marker, and a ring-shaped flushing device is installed inside the installation pipe to ensure the visibility of the scale by continuously cleaning the surface of the marker.
It effectively maintains the visibility of the benchmark scale, improves the accuracy and reliability of pile driving operations, and enhances project quality.
Smart Images

Figure CN225014145U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of concrete construction, and in particular to an underwater precast concrete pile driving device. Background Technology
[0002] Most underwater precast concrete piles are hollow piles. The driving device for these piles consists of a water injection pipe, a drainage pipe, a sliding rod, and a marker inside the pile. During pile driving, the water injection pipe, drainage pipe, sliding rod, and marker can be simultaneously raised and lowered relative to the pile's axial direction. During driving, water is sprayed through the raised and lowered water injection pipe to loosen and liquefy the soil near the pile bottom, reducing the frontal pressure at the pile bottom and promoting the pile's sinking. The sliding rod guides the pile's driving position. Simultaneously, the drainage pipe pumps out the mud formed after the water injection, assisting in pile driving. The marker's scale indicates the extension position of the water injection and drainage pipes relative to the pile, controlling the driving depth.
[0003] This type of pile driving operation generates mud underwater when loosening liquefied soil, resulting in a high turbidity environment. The mud in the water adheres to the surfaces of the water injection pipes, drainage pipes, sliding rods, and markers as they are raised and lowered. As the pile driving depth increases and the underwater temperature decreases, the mud adhering to these pipe surfaces solidifies, forming an opaque mud film. Since pile driving relies on the marker markings to determine the working depth, this mud film on the markers affects the visibility of the markings. When the markers are raised and lowered, the obscured markings prevent on-site personnel from accurately judging the working depth.
[0004] Regarding the issue of adhering mud, patent publication number CN215290114U discloses a flushing device for driving precast reinforced concrete piles, which involves installing a set of annular spray frames inside a connecting pipe to flush the marker pole by spraying water. However, this flushing structure cannot remove the solidified mud film on the surface of the marker pole, and it cannot guarantee the visibility of the marker pole's scale during pile driving operations, thus affecting the accuracy and reliability of the operation. Utility Model Content
[0005] To address the aforementioned issues, this invention provides an underwater precast concrete pile driving device that continuously cleans the marker during operation, ensuring the visibility of the marker's surface markings throughout the entire pile driving process and improving operational efficiency.
[0006] The technical solution of this utility model is: An underwater precast concrete pile driving device includes a precast pile body, an installation pipe, and an installation frame. The installation pipe is coaxially arranged on the upper part of the precast pile body, and the installation frame is coaxially arranged inside the installation pipe. A sliding rod, a water injection steel pipe, a drainage steel pipe, and a marker rod are installed through the installation frame inside the installation pipe and can be synchronously raised and lowered relative to the axial direction of the precast pile body. Annular flushing devices are coaxially arranged at both ends of the installation pipe along its axial direction, and the installation frame is located between the two annular flushing devices. A marker rod depth cleaning component is sleeved on the marker rod and is fixedly connected to the installation frame.
[0007] In a further technical solution, the benchmark deep cleaning component includes a scraping component and a brush component; The sludge scraping assembly includes a first sleeve and a scraper. The first sleeve is coaxially sleeved on the marker, and the scraper is annularly arranged on the inner wall of the first sleeve and close to the marker. The outer wall of the first sleeve is fixedly connected to the mounting bracket. The brush assembly includes a second sleeve and cleaning bristles. The second sleeve is coaxially fitted onto the marker, and the cleaning bristles are arranged in a ring on the inner wall of the second sleeve and close to the marker. The outer wall of the second sleeve is fixedly connected to the mounting bracket.
[0008] In a further technical solution, each of the annular flushing devices includes a connecting pipe annularly disposed on the inner wall of the mounting pipe and nozzles evenly distributed along the connecting pipe.
[0009] In a further technical solution, the nozzle's water outlet direction faces the center of the mounting frame.
[0010] In a further technical solution, a limiting protrusion is provided on one side of the marker axis, and the surface of the limiting protrusion is marked with scale along the marker axis.
[0011] In a further technical solution, the installation pipe is plugged into the precast pile body.
[0012] In a further technical solution, the installation pipe is provided with an insert block at the connection between the installation pipe and the precast pile body, and the precast pile body is provided with a slot corresponding to the insert block at the connection between the precast pile body and the installation pipe.
[0013] The beneficial effects of this utility model are: By installing two sets of annular flushing devices at the top and bottom of the mounting frame, in conjunction with a deep cleaning component fitted onto the marker pole, the marker pole is cleaned by the lower annular flushing device and the marker pole deep cleaning component when lowering the sliding rod, water injection steel pipe, drainage steel pipe, and marker pole during pile driving operations; and the marker pole is deeply cleaned by the upper annular flushing device and the marker pole deep cleaning component when pulling out the sliding rod, water injection steel pipe, drainage steel pipe, and marker pole. This ensures that the marker pole scale remains visible throughout the operation, effectively improving the reliability of pile driving operations and guaranteeing project quality. Attached Figure Description
[0014] Figure 1 This is a schematic diagram of the overall structure of an underwater precast concrete pile driving device according to an embodiment of the present invention; Figure 2 This is a cross-sectional view of an underwater precast concrete pile driving device according to an embodiment of this utility model; Figure 3 This is a schematic diagram of the installation frame of an underwater precast concrete pile driving device according to an embodiment of the present invention; Figure 4 This is a bottom view of the installation pipe of an underwater precast concrete pile driving device according to an embodiment of this utility model; Figure 5 This is a schematic diagram of the structure of the benchmark depth cleaning component of an underwater precast concrete pile driving device according to an embodiment of this utility model.
[0015] Explanation of reference numerals in the attached figures: 1 is the precast pile body, 2 is the installation pipe, 3 is the installation frame, 4 is the marker deep cleaning component, 5 is the fixing frame, 6 is the lower pressure head, 7 is the connecting ring, 11 is the slot, 21 is the annular flushing device, 22 is the insert block, 31 is the sliding rod, 32 is the water injection steel pipe, 33 is the drainage steel pipe, 34 is the marker, 211 is the connecting pipe, 212 is the nozzle, 41 is the mud scraping component, 42 is the brush component, 411 is the first sleeve, 412 is the scraper, 421 is the second sleeve, 422 is the cleaning brush, and 341 is the limiting protrusion. Detailed Implementation
[0016] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present utility model, so as to provide a better understanding of the concept of the present utility model, the technical problem solved, the technical features constituting the technical solution and the technical effects brought about.
[0017] like Figure 1 - Figure 4 As shown, an underwater precast concrete pile driving device includes a precast pile body 1, an installation pipe 2, and an installation frame 3. The installation pipe 2 is coaxially arranged on the upper part of the precast pile body 1, and the installation frame 3 is coaxially arranged inside the installation pipe 2. A sliding rod 31, a water injection steel pipe 32, a drainage steel pipe 33, and a marker 34 are installed through the installation frame 3 inside the installation pipe 2, which can be synchronously raised and lowered relative to the axial direction of the precast pile body 1. Annular flushing devices 21 are coaxially arranged at both ends of the installation pipe 2 along its axial direction, and the installation frame 3 is located between the two annular flushing devices 21. A marker depth cleaning component 4 is sleeved on the marker 34, and the marker depth cleaning component 4 is fixedly connected to the installation frame 3.
[0018] The working principle of the above technical solution is as follows: During the underwater precast concrete pile driving operation, the sliding rod 31, water injection steel pipe 32, drainage steel pipe 33, and marker 34 are connected to the installation pipe 2 via the installation frame 3 and sink together with the precast pile body 1. The sliding rod 31 is used to guide the precast pile body 1 to the working position. After reaching the working position, the sliding rod 31, water injection steel pipe 32, drainage steel pipe 33, and marker 34 are raised and lowered. The working depth is determined according to the scale of the marker 34, and then guidance adjustment, water spraying, and pumping operations are carried out to implement the pile driving operation.
[0019] When the sliding rod 31, water injection steel pipe 32, drainage steel pipe 33, and marker 34 are lowered, the annular flushing device 21 installed at the lower part of the installation pipe 2 flushes the sliding rod 31, water injection steel pipe 32, drainage steel pipe 33, and marker 34. At the same time, the marker deep cleaning component 4 sleeved on the marker 34 performs deep cleaning of the marker 34. When the sliding rod 31, water injection steel pipe 32, drainage steel pipe 33, and marker 34 are pulled up, the annular flushing device 21 set at the upper part of the installation pipe 2 flushes the above components, and the marker deep cleaning component 4 also performs deep cleaning of the marker 34 simultaneously. This measure can prevent the mud from solidifying rapidly in the low-temperature underwater environment, ensuring the visibility of the marker surface scale throughout the pile driving operation, thereby effectively improving the operation accuracy and efficiency.
[0020] In another embodiment, such as Figure 5 As shown, the deep cleaning component 4 for the benchmark includes a scraper component 41 and a brush component 42. The scraper component 41 includes a first sleeve 411 and a scraper 412. The first sleeve 411 is coaxially sleeved on the benchmark 34. The scraper 412 is arranged in a ring on the inner wall of the first sleeve 411 and is close to the benchmark 34. The outer wall of the first sleeve 411 is fixedly connected to the mounting bracket 3. The bristle assembly 42 includes a second sleeve 421 and cleaning bristles 422. The second sleeve 421 is coaxially sleeved on the marker 34. The cleaning bristles 422 are arranged in a ring on the inner wall of the second sleeve 421 and close to the marker 34. The outer wall of the second sleeve 421 is fixedly connected to the mounting bracket 3. The mud scraping assembly 41 and the bristle assembly 42 are provided on the marker 34.
[0021] In this embodiment, the mud scraping assembly 41 is disposed at the lower part of the mounting frame 3, and the bristle assembly 42 is disposed at the upper part of the mounting frame 3. The outer wall of the first sleeve 411 of the mud scraping assembly 41 is rigidly connected to the lower surface of the mounting frame 3, and the outer wall of the second sleeve 421 of the bristle assembly 42 is rigidly connected to the upper surface of the mounting frame 3 through a connecting rod. When the marker 34 is pulled up and lowered, mud scraping and brushing operations can be performed on the marker 34. The mud and mud film on the surface of the marker are scraped off by the scraper 412, and the impurities on the surface of the marker are brushed off by the cleaning bristles 422, thus forming a dual cleaning effect of "scraping + brushing".
[0022] In another embodiment, such as Figure 2 , Figure 4 As shown, each annular flushing device 21 includes a connecting pipe 211 annularly arranged on the inner wall of the installation pipe 2 and nozzles 212 evenly distributed along the connecting pipe 211. The water outlet direction of the nozzles 212 faces the center of the installation frame 3. The nozzles 212 are inclined to ensure that the marker is continuously flushed during the pipe sinking operation, further reducing mud adhesion, ensuring project quality, and improving operational reliability.
[0023] In another embodiment, such as Figure 4 As shown, a limiting protrusion 341 is provided on one side of the marker 34 along the axial direction. The surface of the limiting protrusion 341 is set with scale along the axial direction of the marker 34. The scale can be set on the surface of the limiting protrusion 341 by engraving. By setting the limiting protrusion 341, it can guide the marker 34 on the one hand, and prevent the marker 34 body from being worn and the scale line from being lost, thus affecting the judgment of the working depth. It also makes it convenient for on-site operators to quickly read the marker data.
[0024] In another embodiment, such as Figure 2 , Figure 3 , Figure 4 As shown, the installation pipe 2 and the precast pile body 1 are connected by an insertion. The installation pipe 2 is provided with an insertion block 22 at the connection between the installation pipe 2 and the precast pile body 1. The precast pile body 1 is provided with a slot 11 corresponding to the insertion block 22 at the connection between the precast pile body 1 and the installation pipe 2. The insertion connection can ensure the stability of the connection between the installation pipe 2 and the precast pile body 1, prevent the installation pipe and the precast pile body from shifting during the pile driving operation, and thus prevent the target position from shifting, ensuring the reliability of the operation.
[0025] In another embodiment, the device also includes a fixing frame 5. The bottoms of the sliding rod 31, the water injection steel pipe 32, the drainage steel pipe 33 and the marker 34 are connected by the fixing frame 5, which can ensure that the sliding rod 31, the water injection steel pipe 32, the drainage steel pipe 33 and the marker 34 sink and are retrieved synchronously, and can ensure the controllability and safety of the operation process.
[0026] In another embodiment, such as Figure 1 , Figure 2 As shown, a pressure head 6 is coaxially arranged at the bottom of the precast pile body 1. The pressure head 6 is connected to the precast pile body 1 through a connecting ring 7. The pressure head 6 is a counterweight block, which can increase the weight at the bottom of the precast pile body 1. During the pile driving operation, the pressure head 6 can further reduce the pressure at the bottom of the precast pile body 1, prompting the pile body to sink into the soil quickly, which can reduce the difficulty of the operation.
[0027] When the pile driving operation is completed and the sliding rod 31, water injection steel pipe 32, drainage steel pipe 33 and marker 34 are retrieved, the device can also use the marker deep cleaning component 4 in conjunction with the upper annular flushing device 21 to perform deep cleaning on the marker 34, reducing the difficulty of manual cleaning after retrieval and allowing the next round of pile driving operation to proceed quickly, effectively improving work efficiency.
[0028] The embodiments described above merely illustrate specific implementations of this utility model, and while the descriptions are detailed, they should not be construed as limiting the scope of this utility model patent. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this utility model, and these modifications and improvements all fall within the protection scope of this utility model.
Claims
1. An underwater concrete precast pile sinking device, comprising a precast pile body (1), a mounting pipe (2), and a mounting frame (3); the mounting pipe (2) is coaxially arranged on the upper part of the precast pile body (1), the mounting frame (3) is coaxially arranged in the mounting pipe (2), the slide rod (31), the water injection steel pipe (32), the water drainage steel pipe (33), and the marker rod (34) are installed through the mounting frame (3) in the mounting pipe (2) and can be synchronously pulled up and lowered axially relative to the precast pile body (1), characterized in that: The mounting tube (2) is provided with an annular flushing device (21) coaxially at both ends along its axial direction, and the mounting frame (3) is located between the annular flushing devices (21); the marker (34) is fitted with a marker deep cleaning component (4), and the marker deep cleaning component (4) is fixedly connected to the mounting frame (3).
2. The underwater precast concrete pile driving device according to claim 1, characterized in that: The benchmark deep cleaning component (4) includes a scraping component (41) and a brush component (42). The sludge scraping assembly (41) includes a first sleeve (411) and a scraper (412). The first sleeve (411) is coaxially sleeved on the marker (34). The scraper (412) is circumferentially arranged on the inner wall of the first sleeve (411) and close to the marker (34). The outer wall of the first sleeve (411) is fixedly connected to the mounting bracket (3). The brush assembly (42) includes a second sleeve (421) and cleaning bristles (422). The second sleeve (421) is coaxially sleeved on the marker (34). The cleaning bristles (422) are arranged in a ring on the inner wall of the second sleeve (421) and close to the marker (34). The outer wall of the second sleeve (421) is fixedly connected to the mounting bracket (3).
3. The underwater precast concrete pile driving device according to claim 1, characterized in that: Each of the annular flushing devices (21) includes a connecting pipe (211) annularly disposed on the inner wall of the mounting pipe (2) and nozzles (212) evenly distributed along the connecting pipe (211).
4. The underwater precast concrete pile driving device according to claim 3, characterized in that: The nozzle (212) faces the center of the mounting frame (3) in the direction of water discharge.
5. The underwater precast concrete pile driving device according to claim 1, characterized in that: A limiting protrusion (341) is provided on one side of the axial direction of the marker (34), and the surface of the limiting protrusion (341) is marked with scale along the axial direction of the marker (34).
6. The underwater precast concrete pile driving device according to claim 1, characterized in that: The installation pipe (2) is plugged into the precast pile body (1).
7. The underwater precast concrete pile driving device according to claim 6, characterized in that: The installation pipe (2) is provided with a plug (22) at the connection between the installation pipe (2) and the precast pile body (1), and the precast pile body (1) is provided with a slot (11) corresponding to the plug (22) at the connection between the precast pile body (1) and the installation pipe (2).
Citation Information