Foundation pit supporting device combined with gravity retaining wall and cast-in-place retaining pile

The foundation pit support device, which combines gravity retaining walls with cast-in-place piles, solves the problem of the cumbersome process of pouring concrete for the support device in the existing technology. It improves the stability and structural strength of the foundation pit support, and the support rods can be disassembled and recycled.

CN225014167UActive Publication Date: 2026-11-24CHINA METALLURGICAL SOUTH CHINA CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522697934.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-19
Publication Date
2026-11-24
Estimated Expiration
2035-12-19

AI Technical Summary

Technical Problem

Existing foundation pit support devices require pouring concrete and waiting for it to solidify when the piles are exposed during excavation. This process is cumbersome, and the support effect is prone to structural instability due to tilting.

Method used

The foundation pit support device combines gravity retaining walls and cast-in-place piles. The retaining wall and pile bodies are embedded together to form an anti-lateral displacement defense line. The support rods and screws drive the card seat to fit tightly against the side wall of the piles, enhancing the connection tightness. The tilt of the support rods is judged by magnetic blocks and pull ropes to improve the installation accuracy. Combined with the fixed rods and protrusion reinforcement structure, the overall stability is enhanced.

Benefits of technology

It reduces the subsequent concrete pouring steps in the pile section, improves the stability and installation accuracy of the foundation pit support structure, enhances the overall strength and erosion resistance of the structure, and the support rods are recyclable.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014167U_ABST
    Figure CN225014167U_ABST
Patent Text Reader

Abstract

This utility model belongs to the field of foundation pit support technology, specifically a foundation pit support device for gravity retaining walls combined with cast-in-place pile retaining walls, including a retaining wall body; multiple sets of pile bodies are fixedly connected to the bottom end of the retaining wall body; the pile bodies are arranged in an array at the bottom end of the retaining wall body; support rods are provided on the side walls of the pile bodies; the support rods are arranged between the multiple sets of pile bodies; a pair of screws are threaded to the side walls of the support rods; a fixed seat is rotatably connected to the top of the screw; a retaining seat is fixedly connected to the side wall of the fixed seat; by the transverse support rods driving the screws to tightly adhere to the side walls of the pile bodies, the connection between the pile bodies is made tighter, which can further improve the overall structural stability of the retaining wall body, further reduce the need to tie steel bars and pour concrete between the pile bodies again after excavation and wait for solidification, and the support rods can also be removed after the foundation pit is backfilled, increasing subsequent recycling.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of foundation pit support technology, specifically a foundation pit support device that combines gravity retaining wall with cast-in-place pile retaining. Background Technology

[0002] A foundation pit is a temporary trench excavated for the construction of the foundation or underground structure of a building or structure in underground engineering construction. It is usually located below the ground surface and needs to be excavated to form a space of a certain depth and range according to the design dimensions. During the excavation process, support devices are required to resist the lateral pressure of the soil, prevent collapse and groundwater seepage. It is a core temporary structure to ensure the smooth construction of underground engineering and is widely used in housing construction, municipal engineering, transportation and other construction projects.

[0003] During the construction of the foundation pit support, the site is first leveled, surveyed and laid out, and geological surveys are carried out. Then, the retaining wall trench is excavated around the perimeter of the foundation pit, and a gravity retaining wall is poured. Simultaneously, holes are drilled at preset intervals below or inside the retaining wall, steel cages are lowered, and concrete is poured to form cast-in-place piles. After the concrete strength of the retaining wall and piles reaches the standard, the soil inside the foundation pit is excavated in layers and sections. During the excavation process, the loose soil at the bottom of the pit is cleared, the base is leveled, and supporting facilities such as blind drains behind the wall, anti-seepage layers between piles, and drainage systems around the foundation pit are constructed to ensure the stability of the foundation pit.

[0004] When the support device exposes the piles during excavation, concrete needs to be poured between the piles and allowed to solidify, which is quite cumbersome. Utility Model Content

[0005] The technical solution adopted by this utility model to solve its technical problem is as follows: The foundation pit support device of gravity retaining wall combined with cast-in-place pile retaining of this utility model includes a retaining wall body; multiple sets of pile bodies are fixedly connected to the bottom end of the retaining wall body; the pile bodies are arranged in an array at the bottom end of the retaining wall body; support rods are provided on the side walls of the pile bodies; the support rods are arranged between the multiple sets of pile bodies; a pair of screws are threadedly connected to the side walls of the support rods; a fixed seat is rotatably connected to the top of the screws; a retaining seat is fixedly connected to the side wall of the fixed seat; the retaining wall body utilizes its own weight... The force and the embedment of the bottom pile body form an anti-lateral displacement defense line, preventing the collapse of the soil on the side wall of the foundation pit. The arrangement of multiple sets of pile bodies in an array can enhance the fixation effect on the deep soil. The lateral support rods are driven by screws to tightly adhere to the side wall of the pile body, realizing the tight connection between the pile bodies. This can further improve the overall stability of the retaining wall structure and further reduce the need to tie steel bars and pour concrete between the pile bodies again after excavation and wait for solidification. The support rods can also be removed after the foundation pit is backfilled, increasing the subsequent recycling.

[0006] Preferably, a support base is fixedly connected to the side wall of the support rod; a magnetic block is magnetically connected to the bottom end of the support base; a pull rope is fixedly connected to the bottom end of the magnetic block; a gravity block is fixedly connected to the bottom end of the pull rope; the magnetic block can be detachably attached to the bottom of the support base of multiple support rods, and the pull rope can be observed to intuitively determine whether the support rod is tilted, which can further increase the overall accuracy of the support rod during installation and reduce the weakening of the support effect caused by the tilt of the support rod after installation.

[0007] Preferably, a fixing rod is fixedly connected to the side wall of the main body of the pile; the fixing rod is L-shaped; the fixing rod is located at the connection between the main body of the retaining wall and the main body of the pile; a pair of bolts are fixedly connected to the side wall of the fixing rod; by fitting the fixing rod to the connection between the main body of the retaining wall and the main body of the pile, the connection between the main body of the retaining wall and the main body of the pile can be further strengthened on the basis of supporting multiple sets of pile bodies, thereby further increasing the overall structural strength of the main body of the retaining wall.

[0008] Preferably, the side wall of the card holder is fixed with multiple sets of protrusions; the protrusions are evenly distributed on the side wall of the card holder; the multiple sets of protrusions on the side wall of the card holder can form multiple points of contact with the concave and convex surfaces formed after the main body of the pile is poured, so that the protrusions are embedded in the side wall of the main body of the pile, which can reduce the problem of some parts of the card holder being suspended when it contacts the side wall of the main body of the pile due to unevenness, and increase the tight fit between the card holder and the side wall of the main body of the pile.

[0009] Preferably, multiple sets of rotating rods are fixedly connected to the side wall of the screw; the rotating rods are arranged in an array on the side wall of the screw; a flexible layer is fixedly connected to the top of the rotating rod; the flexible layer wraps around the rotating rod; the multiple sets of rotating rods arranged in an array on the side wall of the screw increase the force points of the screw when rotating, improve the smoothness of the screw when rotating, and, in conjunction with the flexible layer, can further increase the friction when gripping.

[0010] Preferably, a waterproof blanket is fixed to the side wall of the retaining wall body; a geotextile is fixed to the side wall of the waterproof blanket; by the waterproof blanket being tightly attached to the side wall of the retaining wall body, rainwater in the soil can be effectively prevented from seeping into the interior of the retaining wall body. In conjunction with the geotextile, it can prevent sharp stones in the soil from contacting the waterproof blanket, which can further increase the overall erosion resistance of the retaining wall body and ensure the stability of the retaining wall body when used in the foundation pit.

[0011] The advantages of this utility model are:

[0012] 1. By utilizing its own weight and the embedment effect of the bottom pile body, the retaining wall forms an anti-lateral displacement defense line, preventing the collapse of the soil on the side wall of the foundation pit. The arrangement of multiple sets of pile bodies in an array can enhance the fixation effect on the deep soil. The lateral support rods are driven by screws to tightly adhere to the side wall of the pile body, achieving tight connection between the pile bodies. This can further improve the overall stability of the retaining wall structure and further reduce the need to tie steel bars and pour concrete between the pile bodies again after excavation, and wait for it to solidify. The support rods can also be removed after the foundation pit is backfilled, increasing the subsequent recycling capacity.

[0013] 2. The magnetic blocks can be detachably attached to the bottom of the support base of multiple support rods. By observing the pull rope, it is easy to see whether the support rod is tilted. This can further increase the overall accuracy of the support rod during installation and reduce the weakening of the support effect caused by tilting after installation. Attached Figure Description

[0014] Figure 1 This is a schematic diagram of the main body of this utility model;

[0015] Figure 2 This is a schematic diagram of the structure of the fixing rod in this utility model;

[0016] Figure 3 This is a schematic diagram of the support rod in this utility model;

[0017] Figure 4 This is a schematic diagram of the protrusion structure in this utility model;

[0018] Figure 5 This is a schematic diagram of the geotextile structure in this utility model.

[0019] In the diagram: 1. Main body of retaining wall; 11. Main body of pile; 12. Support rod; 13. Screw rod; 14. Fixing seat; 15. Card seat; 2. Supporting seat; 21. Magnetic block; 22. Pull rope; 23. Gravity block; 3. Fixing rod; 31. Bolt; 4. Protrusion; 5. Rotating rod; 51. Flexible layer; 6. Waterproof blanket; 61. Geotextile. Detailed Implementation

[0020] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the scope of protection of the present utility model.

[0021] like Figures 1 to 5As shown in the embodiment of this utility model, the foundation pit support device for gravity retaining wall combined with cast-in-place pile retaining includes a retaining wall body 1; multiple sets of pile bodies 11 are fixedly connected to the bottom end of the retaining wall body 1; the pile bodies 11 are arranged in an array at the bottom end of the retaining wall body 1; support rods 12 are provided on the side walls of the pile bodies 11; the support rods 12 are arranged between the multiple sets of pile bodies 11; a pair of screws 13 are threadedly connected to the side walls of the support rods 12; a fixed seat 14 is rotatably connected to the top end of the screws 13; the fixed seat 14... The side wall is fixed with a mounting bracket 15; during operation, the retaining wall body 1 and multiple sets of pile bodies 11 are first poured. After the retaining wall body 1 and pile bodies 11 have solidified, construction can be carried out around the retaining wall body 1. The retaining wall body 1 can continuously block the soil on the side of the foundation pit. When the ground around the retaining wall body 1 is excavated to the pile bodies 11, the soil between the pile bodies 11 can be removed. Then, multiple sets of support rods 12 are placed between the multiple sets of pile bodies 11, and a rotational force is applied to a pair of screws 13 on both sides of the support rods 12. The mounting bracket 15 is moved closer to the side wall of the pile body 11, and then the mounting bracket 15 is engaged with the side wall of the pile body 11. A rotational force is continued to be applied to the screw rod 13, which is rotatably connected to the fixing seat 14. This ensures that the mounting bracket 15 remains tightly against the side wall of the pile body 11 as the screw rod 13 rotates, thus horizontally fixing the support rod 12 between multiple sets of pile bodies 11 and providing support for them. Through the retaining wall body 1 utilizing its own weight and the embedding effect with the bottom pile body 11, an anti-lateral displacement defense line is formed, blocking the soil from the side wall of the foundation pit. The collapse of the main body, along with the array arrangement of multiple sets of pile bodies 11, can enhance the fixation effect on the deep soil. The transverse support rod 12 drives the card seat 15 to be tightly attached to the side wall of the pile body 11 through the screw rod 13, realizing the tight connection between the pile bodies 11. This can further improve the overall stability of the retaining wall body 1 and further reduce the need to tie steel bars and pour concrete between the pile bodies 11 again after excavation and wait for solidification. The support rod 12 can also be removed after the foundation pit is backfilled, increasing the subsequent recycling.

[0022] like Figure 3As shown, a support base 2 is fixedly connected to the side wall of the support rod 12; a magnetic block 21 is magnetically connected to the bottom end of the support base 2; a pull rope 22 is fixedly connected to the bottom end of the magnetic block 21; and a gravity block 23 is fixedly connected to the bottom end of the pull rope 22. During operation, when the support rod 12 is connected as a whole between the pile body 11, the magnetic block 21 can be connected to the support base 2, and the magnetic block 21 can be attracted to the bottom of the support base 2. Subsequently, the gravity block 23 continuously applies a pulling force to the pull rope 22 due to gravity. The position of the support rod 12 installed between the pile body 11 can be observed through the pull rope 22 to see if it is tilted. Since the magnetic block 21 can be detachably attracted to the bottom of the support base 2 of multiple sets of support rods 12, the tilt of the support rod 12 can be directly judged by observing the pull rope 22. This can further increase the accuracy of the support rod 12 during installation and reduce the weakening of the support effect caused by the tilt of the support rod 12 after installation.

[0023] like Figure 2 As shown, a fixing rod 3 is fixedly connected to the side wall of the pile body 11; the fixing rod 3 is L-shaped; the fixing rod 3 is located at the connection between the retaining wall body 1 and the pile body 11; a pair of bolts 31 are fixedly connected to the side wall of the fixing rod 3; during operation, the fixing rod 3 can be placed at the connection between the retaining wall body 1 and the pile body 11, and then the bolts 31 are installed on the side wall of the fixing rod 3. The bolts 31 can be connected to the side walls of the retaining wall body 1 and the pile body 11 to fix the fixing rod 3; by fitting the fixing rod 3 against the connection between the retaining wall body 1 and the pile body 11, the connection between the retaining wall body 1 and the pile body 11 can be further strengthened on the basis of supporting multiple sets of pile bodies 11, thereby further increasing the overall structural strength of the retaining wall body 1.

[0024] like Figure 4 As shown, the side wall of the card holder 15 is fixed with multiple sets of protrusions 4; the protrusions 4 are evenly arranged on the side wall of the card holder 15; during operation, the side wall of the pile body 11 will have uneven surfaces due to casting. When the card holder 15 is close to the side wall of the pile body 11, the protrusions 4 can contact the side wall of the pile body 11; through the multiple sets of protrusions 4 on the side wall of the card holder 15, multiple points of contact can be formed with the uneven surfaces formed after the pile body 11 is cast, so that the protrusions 4 are embedded in the side wall of the pile body 11. This can reduce the occurrence of some positions being suspended when the card holder 15 contacts the side wall of the pile body 11 due to unevenness of the side wall of the pile body 11, and increase the tight fit between the card holder 15 and the side wall of the pile body 11.

[0025] like Figure 4As shown, multiple sets of rotating rods 5 are fixed to the side wall of the screw 13; the rotating rods 5 are arranged in an array on the side wall of the screw 13; a flexible layer 51 is fixed to the top of the rotating rod 5; the flexible layer 51 wraps around the rotating rod 5; during operation, when the screw 13 at both ends of the support rod 12 is subjected to a rotational force, a rotational force can be applied to the rotating rod 5, causing the screw 13 to rotate; the flexible layer 51 on the side wall of the rotating rod 5 can form a flexible wrap; the multiple sets of rotating rods 5 arranged in an array on the side wall of the screw 13 increase the force points of the screw 13 during rotation, improve the smoothness of the screw 13 during rotation, and, in conjunction with the flexible layer 51, can further increase the friction when gripping.

[0026] like Figure 5 As shown, a waterproof blanket 6 is fixedly attached to the side wall of the retaining wall body 1; a geotextile 61 is fixedly attached to the side wall of the waterproof blanket 6; during operation, the waterproof blanket 6 on the side wall of the retaining wall body 1 can prevent moisture inside the soil from contacting the retaining wall body 1, and the geotextile 61 can further protect the waterproof blanket 6 from being punctured by sharp stones in the soil layer; by the waterproof blanket 6 being tightly attached to the side wall of the retaining wall body 1, rainwater in the soil can be effectively prevented from seeping into the interior of the retaining wall body 1, and in conjunction with the geotextile 61, sharp stones in the soil can be prevented from contacting the waterproof blanket 6, which can further increase the overall anti-erosion effect of the retaining wall body 1 and ensure the stability of the retaining wall body 1 when used in the foundation pit.

[0027] Working principle: First, the retaining wall body 1 and multiple sets of pile bodies 11 are poured. After the retaining wall body 1 and pile bodies 11 have solidified, construction can be carried out around the retaining wall body 1. The retaining wall body 1 can continuously block the soil on the side of the foundation pit. When the ground around the retaining wall body 1 is excavated to the pile bodies 11, the soil between the pile bodies 11 can be removed. Then, multiple sets of support rods 12 are placed between the multiple sets of pile bodies 11, and rotational force is applied to a pair of screws 13 on both sides of the support rods 12. This allows the card holder 15 to move closer to the side wall of the pile body 11, and then the card holder 15 to engage with the side wall of the pile body 11. Continued rotational force is applied to the screw 13, which is rotatably connected to the fixed seat 14. This ensures that the card holder 15 remains tightly against the side wall of the pile body 11 as the screw 13 rotates, thus horizontally fixing the support rod 12 between multiple pile bodies 11 and providing support. When the support rod 12 is connected between the pile bodies 11, the magnetic block 21 can be attached to the support rod 12. The support base 2 is connected, and the magnetic block 21 can be attracted to the bottom of the support base 2. Then, the gravity block 23 continuously applies a pulling force to the pull rope 22 due to gravity. The position of the support rod 12 installed between the pile body 11 can be observed through the pull rope 22 to see if it is tilted. The fixing rod 3 can be placed at the connection between the retaining wall body 1 and the pile body 11. Then, the bolt 31 is installed on the side wall of the fixing rod 3. The bolt 31 can be connected to the side wall of the retaining wall body 1 and the pile body 11 to fix the fixing rod 3. The side wall of the pile body 11 is due to gravity. The pouring process will create uneven surfaces. When the card seat 15 is close to the side wall of the pile body 11, the protrusion 4 can contact the side wall of the pile body 11. When the screws 13 at both ends of the support rod 12 are subjected to rotational force, they can apply rotational force to the rotating rod 5, causing the screws 13 to rotate. The flexible layer 51 is set on the side wall of the rotating rod 5 to form a flexible wrap. The waterproof blanket 6 on the side wall of the retaining wall body 1 can prevent the water inside the soil from contacting the retaining wall body 1. The geotextile 61 can further protect the waterproof blanket 6 from being punctured by sharp stones in the soil.

Claims

1. A foundation pit support device combining gravity retaining wall and cast-in-place pile retaining, characterized in that: The structure includes a retaining wall body (1); multiple sets of pile bodies (11) are fixedly connected to the bottom end of the retaining wall body (1); the pile bodies (11) are arranged in an array at the bottom end of the retaining wall body (1); a support rod (12) is provided on the side wall of the pile body (11); the support rod (12) is arranged between the multiple sets of pile bodies (11); a pair of screws (13) are threadedly connected to the side wall of the support rod (12); a fixed seat (14) is rotatably connected to the top of the screw (13); a card seat (15) is fixedly connected to the side wall of the fixed seat (14).

2. The foundation pit support device for gravity retaining wall combined with cast-in-place pile retaining as described in claim 1, characterized in that: The support rod (12) is fixed to a support base (2) on its side wall; the support base (2) is magnetically connected to a magnetic block (21) at its bottom end; a pull rope (22) is fixed to the bottom end of the magnetic block (21); and a gravity block (23) is fixed to the bottom end of the pull rope (22).

3. The foundation pit support device for gravity retaining wall combined with cast-in-place pile retaining as described in claim 1, characterized in that: The side wall of the pile body (11) is fixed with a fixing rod (3); the fixing rod (3) is L-shaped; the fixing rod (3) is located at the connection between the retaining wall body (1) and the pile body (11); a pair of bolts (31) are fixed to the side wall of the fixing rod (3).

4. The foundation pit support device for gravity retaining wall combined with cast-in-place pile retaining as described in claim 1, characterized in that: The card holder (15) has multiple sets of protrusions (4) fixed to its side wall; the protrusions (4) are evenly distributed on the side wall of the card holder (15).

5. The foundation pit support device for gravity retaining wall combined with cast-in-place pile retaining as described in any one of claims 1 to 4, characterized in that: Multiple sets of rotating rods (5) are fixed to the side wall of the screw (13); the rotating rods (5) are arranged in an array on the side wall of the screw (13); a flexible layer (51) is fixed to the top of the rotating rod (5); the flexible layer (51) wraps around the rotating rod (5).

6. The foundation pit support device for gravity retaining wall combined with cast-in-place pile retaining as described in claim 5, characterized in that: The retaining wall body (1) is fixedly connected to a waterproof blanket (6) on its side wall; the waterproof blanket (6) is fixedly connected to a geotextile (61) on its side wall.