A prefabricated brick mold tie structure
By setting anchor bodies and tie rods between the precast brick formwork and the excavation surface of the foundation pit, the stability problem of backfilling soil in the precast brick formwork in the stepped foundation pit was solved, realizing continuous construction and improved safety.
Patent Information
- Application Number
- CN202522789118.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-29
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-29
AI Technical Summary
When existing precast brick formwork is used for backfilling in stepped foundation pits, no effective reinforcement measures are taken, which leads to displacement, deformation or overturning, affecting construction safety and efficiency.
A precast brick formwork tie structure is adopted, which connects the precast brick formwork to the excavation surface of the foundation pit through anchor bodies and tie members to form a horizontal tension, ensuring that the tie members can be quickly installed after each section is backfilled, thus achieving continuous construction.
It improves construction efficiency, enhances the stability and integrity of precast brick molds, prevents displacement, and improves construction safety and speed.
Smart Images

Figure CN225014170U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to a precast brick formwork tie structure, belonging to the field of foundation pit brick formwork construction technology. Background Technology
[0002] In the field of construction engineering, stepped foundation pits are widely used for foundation pit support operations in special locations such as the exterior walls of staggered basements because they can adapt to construction scenarios with large differences in foundation elevation. When such foundation pits do not employ sloping excavation techniques, the exterior walls of the basement at the lower level usually require the use of brick formwork as a forming and support structure. Traditional brick formwork uses clay bricks or sand-lime bricks as the main building materials, requiring layer-by-layer laying and grouting according to masonry construction specifications. The construction process is cumbersome and requires a high level of manual skill. In actual construction, brick formwork is not only slow to build, making it difficult to match the fast pace of modern construction projects, but it also consumes a lot of labor costs. Therefore, the industry is gradually shifting to the use of precast brick formwork, especially glass fiber reinforced cement (GRC) brick formwork.
[0003] Precast brick formwork, with its advantages of being lightweight, high-strength, highly precise in forming, and highly prefabricated, is gradually becoming the preferred technology for industry transformation and upgrading. Compared with traditional brick formwork, precast brick formwork can be constructed through factory prefabrication and on-site assembly, significantly reducing on-site masonry procedures, effectively shortening the construction cycle, and reducing labor input.
[0004] However, in the application of existing precast brick formwork in stepped foundation pits, if only the inner side of the precast brick formwork is supported and then backfilling is carried out directly on the outer side without effective reinforcement measures, the lateral pressure of the backfill soil can easily cause the precast brick formwork to shift, deform, or even overturn after the support is removed, failing to guarantee construction safety and project quality. Therefore, current requirements for precast brick formwork construction include backfilling the outer side to the height of the first slab, pouring a layer of concrete to stabilize the soil layer and the precast brick formwork, and then proceeding with backfilling the next section. However, waiting until the precast brick formwork is completely fixed before backfilling will cause inconsistencies in the process flow, violating the core advantage of efficient construction using precast brick formwork.
[0005] Therefore, a precast brick formwork tie structure was designed, which enables the stable installation of the precast brick formwork in the stepped foundation pit and the continuous construction of the backfill soil on the outside. Summary of the Invention
[0006] The technical problem to be solved by this utility model is to provide a precast brick formwork tie structure, which further improves the construction efficiency of continuous backfilling on the outside of the precast brick formwork.
[0007] The technical problem to be solved by this utility model is achieved by the following technical solution:
[0008] A precast brick formwork tie structure includes:
[0009] A precast brick formwork is vertically installed in the foundation pit by a support structure, and a backfill space is formed between the outer side of the precast brick formwork and the excavation surface of the foundation pit.
[0010] Anchor body, anchored to the excavation surface of the foundation pit;
[0011] The tie member includes a base plate that is tightly attached to the inner side of the joint of the precast brick formwork, a connecting plate that is connected to the base plate and passes through the joint, and an anchor bar that connects the connecting plate to the anchor body. Grout is poured at the joint of the precast brick formwork.
[0012] As a preferred example, the joint of the precast brick mold is provided with a concave surface, and the bottom plate is embedded in the concave surface.
[0013] As a preferred example, the anchor body is one or more of structural piles, anchor blocks, and anchor piles.
[0014] As a preferred example, the backfill space is filled with backfill soil.
[0015] As a preferred embodiment, the base plate is fixed perpendicularly to the connecting plate, and the anchor bar is perpendicular to the base plate.
[0016] As a preferred example, the joint of the precast brick mold is provided with tenons and mortises that fit together vertically, and the tenons are provided with notches that allow the connecting plate to pass through.
[0017] As a preferred example, the anchor bar is a prefabricated steel bar with an outer rust-proof isolation layer.
[0018] As a preferred example, the reinforcing steel of the outer anti-rust isolation layer is a prefabricated steel bar wrapped in a cement mortar layer containing a rust inhibitor, and the connection between the steel bar and the connecting plate and the anchor body is covered by the mortar.
[0019] As a preferred example, a ground bedding layer is laid on the top of the precast brick formwork, the top of the backfill soil, and the top of the foundation pit.
[0020] As a preferred example, both the bottom bedding layer and the ground bedding layer are made of concrete.
[0021] The beneficial effects of this utility model are:
[0022] 1. By setting tie members at the joints between the upper and lower sections of the precast brick formwork and connecting them tightly with the anchor body on the excavation face, it is not necessary to pour a layer of concrete and wait for it to cure during the backfilling process section by section. After the outer side of each precast brick formwork is backfilled, the tie members can be quickly installed, enabling continuous backfilling construction and improving construction efficiency.
[0023] 2. The horizontal tensile force is transmitted through the base plate, connecting plate, anchor bars and anchor body. The stress-bearing structure is perpendicular to the joint between the precast brick molds. The forces on the inner and outer sides of the precast brick molds are balanced, and the structure is stable.
[0024] 3. By pouring grout at the joints of the precast brick formwork, it is beneficial to fix the tie members, enhance the overall integrity of each precast brick formwork after assembly, and improve the joint waterproofing performance. Attached Figure Description
[0025] Figure 1 It is a precast brick formwork tie structure;
[0026] Figure 2 This is a three-dimensional structural diagram of the tie rod;
[0027] Figure 3 This is a schematic diagram of the side structure of the tie rod;
[0028] Figure 4 A schematic diagram of the structure for installing tie members in the joints of precast brick molds;
[0029] Figure 5 This is a schematic diagram of the construction structure of an existing precast brick formwork.
[0030] In the picture:
[0031] 1. Precast brick mold; 101. Joint; 102. Concave surface; 103. Tenon; 104. Mortise and tenon;
[0032] 2. Excavation pit; 201. Excavation face; 202. Backfill space; 203. Backfill soil;
[0033] 3. Anchor body;
[0034] 4. Tie-in components; 401. Base plate; 402. Connecting plate; 403. Anchor bars;
[0035] 5. Concrete layer;
[0036] 6. Support structure; 601. Horizontal support; 602. Vertical support; 603. Diagonal support;
[0037] 7. Bottom padding layer;
[0038] 8. Slurry;
[0039] 9. Ground subbase. Detailed Implementation
[0040] In order to make the technical means, creative features, objectives and effects of this utility model easier to understand, the following description, in conjunction with specific illustrations, further elaborates on this utility model.
[0041] like Figure 1As shown, the precast brick formwork 1 tie structure includes multiple precast brick formwork 1 sections assembled together, an anchor body 3 fixed to the excavation face 201 of the foundation pit 2, and tie members 4 installed in the joint 101 between adjacent precast brick formwork 1 sections. The tie members 4 are connected to the anchor body 3, providing horizontal tension to the precast brick formwork 1. This structure is particularly suitable for construction scenarios where the backfill soil 203 behind the wall has good quality, the backfill height does not exceed 3m, the soil pressure is small, and the construction period is short. In this case, adding tie members 4 appropriately to the precast brick formwork 1 can ensure the stability of the precast brick formwork 1 and the backfill soil system behind the wall, without the need to pour concrete layers 5 multiple times to achieve a stable structure.
[0042] The precast brick formwork 1, preferably a glass fiber reinforced cement brick formwork (GRC brick formwork), is the preferred solution for precast assembled foundation pit 2 formwork. Compared with traditional brick masonry and cast-in-place concrete formwork, it has core advantages such as lightweight, high strength, efficient construction, and good durability. The side of the precast brick formwork 1 closest to the excavation face 201 is the outer side, and the side furthest from the excavation face 201 is the inner side. It is vertically installed on the bottom cushion layer 7 of the foundation pit 2 by a support body 6, which is a temporary support. The support body 6 includes a horizontal support 601 placed adjacent to the bottom of the precast brick formwork 1 and on the bottom cushion layer 7, and a vertical support 602 attached to the inner side of the precast brick formwork 1. Multiple diagonal supports 603 are set between the horizontal support 601 and the vertical support 602, forming a stable support body 6 structure. The bottom of the lowest section of the precast brick formwork 1 is fixed to the bottom cushion layer 7 by grouting. A backfill space 202 is formed between the outer side of the precast brick formwork 1 and the excavation surface 201 of the foundation pit 2. The backfill space 202 is filled with good quality backfill soil 203.
[0043] Anchor body 3 is one or more of the structural piles, anchor blocks, and anchor piles commonly used in this field. Anchor body 3 is required to be stably anchored to the excavation face 201 of the foundation pit 2.
[0044] like Figure 2 , Figure 3 As shown, the tie member 4 includes a base plate 401, a connecting plate 402 connected to the base plate 401, and an anchor bar 403 connected to the connecting plate 402. The base plate 401 is vertically fixed to the connecting plate 402, and the anchor bar 403 is perpendicular to the base plate 401. The base plate 401, connecting plate 402, and anchor bar 403 are all made of steel. The contact joints of the base plate 401 and connecting plate 402 are fixed on both sides by welding, and the contact joints of the anchor bar 403 and connecting plate 402 are also fixed on both sides by welding. The surface of the tie member 4 is treated with rust prevention, for example, by using a rust-proof coating or rust-proof paint.
[0045] like Figure 1 , Figure 4As shown, the base plate 401 of the tie member 4 is tightly attached to the inner side of the joint 101 of the precast brick formwork 1. The connecting plate 402 horizontally passes through the joint 101 of the precast brick formwork 1 and connects to the base plate 401. The anchor bar 403 connects the connecting plate 402 to the anchor body 3, providing horizontal tension for the precast brick formwork 1. Grout 8 is poured at the joint 101 of the precast brick formwork 1. The grout 8 is preferably M5 strength cement mortar, which has good workability and water retention, and can achieve basic sealing and bonding at the joint, ensuring the initial fixation between GRC panels. After the support body 6 inside the precast brick formwork 1 is removed (during the construction stage of the underground structure base plate 401 and stepped wall), the tie member 4 works together with the backfill soil 203 of the wall to achieve the effect of system stability. The tie member 4 improves the construction speed of the stepped foundation pit 2 brick formwork (eliminating the time for pouring concrete for each section and waiting for it to dry), while enhancing the system's safety, effectively preventing soil slippage behind the wall, and improving work efficiency and on-site operational safety. The base plate 401 holds the edges of the upper and lower precast brick formwork 1, and its thickness should be able to withstand the pressure of the backfill soil 203 behind the plate. By adjusting the length of the anchor bars 403, the tie member 4 is fixed to the precast anchor blocks, structural piles, or other fixed piles. If the anchor bars 403 are too long, they can be cut and reconnected; if the anchor bars 403 are too short, they can be lengthened by welding, enabling the connection between the precast brick formwork 1 and the original foundation structure components such as engineering piles, making the brick formwork system more reliable.
[0046] like Figure 5 The diagram shows a construction structure of the existing precast brick formwork 1. Currently, the construction requirements for precast brick formwork 1 are as follows: backfill the outer side with soil up to the height of the first section of precast brick formwork 1, pour a layer of concrete 5 to stabilize the soil layer and the precast brick formwork 1; then proceed with backfilling the next section. However, waiting until the precast brick formwork 1 is completely fixed before backfilling will cause inconsistencies in the process flow, violating the core advantage of efficient construction of precast brick formwork 1.
[0047] When constructing the precast brick formwork 1 tie structure, after the outer support of the precast brick formwork 1 is installed, install the bottom first precast brick formwork 1, backfill soil 203 on the outside of the precast brick formwork 1, compact the backfill to the upper edge of the bottom first precast brick formwork 1, place the tie member 4, and grout at the joint 101 at the upper edge of the precast brick formwork 1 (only a small amount of grout 8 needs to be poured). Then the second section of precast brick formwork 1 can be quickly installed, the anchor bar 403 is tied and tensioned with the anchor body 3, backfill soil 203 on the outside of the second section of precast brick formwork 1, and repeat this process until the design elevation is reached.
[0048] The working principle of the self-supporting (tail rod type) retaining wall is adopted. The construction characteristics of the second stage of the foundation pit require the pouring of the bottom slab 401 as soon as possible after excavation. This scheme uses T-shaped tie members 4 to tie the precast brick formwork 1 to the anchor point, eliminating the on-site process of pouring concrete for the soil behind the wall and realizing continuous backfilling construction.
[0049] By adopting the above technical solution, the precast brick formwork 1 is constrained by tie members 4, which not only does not affect the stability of the brick formwork, but also achieves continuous construction of backfill soil 203, and can better give play to the advantages of the precast brick formwork 1.
[0050] In some embodiments, a concave surface 102 is provided at the joint 101 of the precast brick mold 1, and the base plate 401 is embedded in the concave surface 102. Since the base plate 401 of the tie member 4 is thin, embedding it in the concave surface 102 keeps the surface of the precast brick mold 1 flat, without the need for further smoothing, and does not affect the construction of the waterproof layer.
[0051] In some embodiments, to ensure that the connecting plate 402 of the tie member 4 can pass horizontally through the upper and lower joints 101 of the precast brick mold 1 without interfering with the original upper and lower tenons 103 and mortises 104 of the precast brick mold 1, a notch is provided in the tenon 103 to allow the connecting plate 402 to pass through (the position where the connecting plate 402 passes through the tenon 103 in the figure). This notch and the joint 101 achieve stable connection, seal the joint 101, and provide a certain degree of waterproofing through the pouring of grout 8.
[0052] In some embodiments, to extend the service life of the tie member 4, a rust-proof isolation layer is provided in the middle of the anchor bar 403 that is not submerged in grout 8. The anchor bar 403 is a prefabricated steel bar with an outer rust-proof isolation layer. The steel bar with the outer rust-proof isolation layer is a prefabricated steel bar wrapped in a cement mortar layer containing a rust inhibitor. The connection between the steel bar and the connecting plate 402 and the anchor body 3 is covered with grout 8. In use, if it is too long, the rust-proof isolation layer can be cut off to expose the end of the internal steel bar, which can then be welded and fixed to the connecting plate 402 and the anchor body 3.
[0053] In some embodiments, a ground bedding layer 9 is laid on the top of the precast brick formwork 1, the top of the backfill soil 203, and the top of the foundation pit 2. Both the bottom bedding layer 7 and the ground bedding layer 9 are made of concrete layer 5. The bottom bedding layer 7 and the ground bedding layer 9 are fixed to the uppermost and lowermost precast brick formwork 1 by grout 8, further improving the stability of the precast brick formwork 1.
[0054] By setting tie members 4 at the joint 101 between the upper and lower sections of the precast brick formwork 1 and connecting and tightening them with the anchor body 3 of the excavation face 201, it is not necessary to pour a layer of concrete and wait for it to cure during the backfilling process section by section. After the outer side of each section of the precast brick formwork 1 is backfilled, the tie members 4 can be quickly installed, enabling continuous backfilling construction and improving construction efficiency.
[0055] The horizontal tensile force is transmitted through the base plate 401, connecting plate 402, anchor bar 403 and anchor body 3. The stress structure is perpendicular to the joint 101 between the precast brick molds 1. The forces on the inner and outer sides of the precast brick molds 1 are balanced, and the structure is stable.
[0056] By pouring grout 8 at the joint 101 of the precast brick formwork 1, it is beneficial to fix the tie member 4, and also enhances the integrity of each section of the precast brick formwork 1 after assembly, thereby improving the seepage prevention performance of the joint 101.
[0057] In summary, this precast brick formwork 1 can be widely used in stepped foundation pits 2. It eliminates the concrete slab strip between the upper and lower sections, increases the backfilling speed, optimizes the backfilling process after the precast brick formwork 1, and improves the construction speed.
[0058] The above description outlines the main technical features, basic principles, and beneficial effects of this invention. The scope of protection claimed by this invention is defined by the appended claims and their equivalents. Those skilled in the art should understand that this invention is not limited to the above embodiments, and various equivalent changes can be made without departing from the spirit and description of this invention; these equivalent changes will also fall within the scope of protection of this invention.
Claims
1. A precast brick formwork tie structure, characterized in that, include: A precast brick mold (1) is vertically installed in the foundation pit (2) by a support (6), and a backfill space (202) is formed between the outer side of the precast brick mold (1) and the excavation surface (201) of the foundation pit (2); Anchor body (3) is anchored on the excavation face (201) of the foundation pit (2); The tie member (4) includes a bottom plate (401) that is tightly attached to the inside of the joint (101) of the precast brick mold (1), a connecting plate (402) that is connected to the bottom plate (401) and passes through the joint (101), and an anchor bar (403) that connects the connecting plate (402) to the anchor body (3). Grout (8) is poured at the joint (101) of the precast brick mold (1).
2. The precast brick formwork tie structure according to claim 1, characterized in that, The precast brick mold (1) has a concave surface (102) at the joint (101), and the base plate (401) is embedded in the concave surface (102).
3. The precast brick formwork tie structure according to claim 1, characterized in that, The anchor body (3) is one or more of the following: structural pile, anchor block, and anchor pile.
4. The precast brick formwork tie structure according to claim 1, characterized in that, The backfill space (202) is filled with backfill soil (203).
5. The precast brick formwork tie structure according to claim 1, characterized in that, The base plate (401) is fixed perpendicularly to the connecting plate (402), and the anchor bar (403) is perpendicular to the base plate (401).
6. The precast brick formwork tie structure according to claim 1, characterized in that, The precast brick mold (1) is provided with a tenon (103) and a mortise (104) for upper and lower splicing at the joint (101). The tenon (103) is provided with a notch that allows the connecting plate (402) to pass through.
7. The precast brick formwork tie structure according to claim 1, characterized in that, The anchor bar (403) is a prefabricated steel bar with an outer anti-rust isolation layer.
8. A precast brick formwork tie structure according to claim 7, characterized in that, The outer anti-rust isolation layer steel bars are prefabricated steel bars wrapped in a cement mortar layer mixed with rust inhibitor. The connection between the steel bars and the connecting plate (402) and the anchor body (3) is covered by the grout (8).
9. A precast brick formwork tie structure according to claim 1, characterized in that, A ground bedding layer (9) is laid on the top of the precast brick mold (1), the top of the backfill soil (203), and the top of the foundation pit (2).
10. A precast brick formwork tie structure according to claim 9, characterized in that, The bottom cushion layer (7) and the ground cushion layer (9) of the foundation pit (2) are both made of concrete (5).