Steel structure footbridge and single-pile single-column structure thereof
By directly connecting steel pipe piles to steel structure piers, and utilizing shear studs, blocks, slabs, and concrete pouring, the problem of cumbersome construction of single-pile and single-column foundations is solved, achieving a fast, low-cost, and high-precision connection effect.
Patent Information
- Application Number
- CN202620009435.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2026-01-06
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2036-01-06
AI Technical Summary
The existing single-pile and single-column steel structure foundation is cumbersome to construct, has a long construction period, high cost, and is difficult to control in terms of precision, especially in the complex connection structure of landscape pedestrian elevated walkway bridges.
The steel pipe piles are directly connected to the steel structure piers. The connection is made by pouring concrete using components such as shear studs, shear blocks, stiffening plates and bearing plates, which simplifies the construction process and improves the accuracy and connection strength.
It achieves a single-pile, single-column structure that is quick to construct, low in cost, and easy to control in precision, improving construction efficiency and connection reliability, and simplifying the construction process.
Smart Images

Figure CN225014204U_ABST
Abstract
Description
Technical Field
[0001] This utility model generally relates to the field of bridge construction technology, and specifically to a steel structure pedestrian bridge and its single-pile, single-column structure. Background Technology
[0002] In the construction of pedestrian bridges, simple structure, beautiful appearance, and convenient construction are often the focus and highlights of bridge design, especially for scenic elevated pedestrian walkways, which mostly adopt simple, beautiful, and lightweight single-pile, single-column foundations. However, conventional single-pile, single-column steel structure foundations are connected in the middle by a large concrete abutment, which requires complex connection structures such as high-strength anchor bolts, bearing plates, anchoring pads, welded anchoring bars, and steel mesh. This not only makes construction cumbersome and time-consuming, but also involves a large workload, high cost, and makes it difficult to control construction accuracy. Utility Model Content
[0003] In view of the above-mentioned defects or deficiencies in the existing technology, it is desirable to provide a steel structure pedestrian bridge and its single-pile single-column structure, which can not only ensure the safety of the connection between the steel pipe pile and the steel structure pier, but also has a simple structure, easy precision control, and convenient and reliable construction.
[0004] In a first aspect, this application provides a single-pile, single-column structure for a steel pedestrian bridge, comprising: a pipe pile and a pier column fitted inside the pipe pile; The pier column has multiple shear studs arranged on its outer wall near the pipe pile, and the pipe pile has multiple shear blocks arranged on its inner wall near the pier column. The pier extends beyond the upper end of the pipe pile. A stiffening plate is provided between the pier and the pipe pile near the upper end of the pipe pile. One end of the stiffening plate extends into the interior of the pipe pile and the other end extends into the exterior of the pipe pile along the height direction. The pipe piles, the piers, the shear studs, the shear blocks, and the stiffening plates are fixedly connected by concrete pouring sections.
[0005] Optionally, the pier includes a first end and a second end disposed along the height direction, the first end extending out of the pipe pile, and the second end disposed inside the pipe pile; The pier has a pressure plate at the bottom of the second end, and the outer diameter of the pressure plate is larger than the outer diameter of the pier.
[0006] Optionally, the pipe pile has a concrete core, one end of which is flush with the second end of the pier column, and the bearing plate is pressed into the concrete core.
[0007] Optionally, the pier column is provided with a concrete pier section inside, which fills upward from the second end of the pier column and does not extend to the first end; The concrete pouring section is located between the pipe pile and the pier, and the concrete pouring section is connected to the concrete pier and extends to the upper end of the pipe pile.
[0008] Optionally, one side of the stiffening plate is welded and fixed to the outer wall of the pier column, and the other side is fixed to the inner wall of the pipe pile through the concrete pouring part; The stiffening plates are multiple and are evenly distributed along the circumference of the outer wall of the pier.
[0009] Optionally, the upper end of the pipe pile is provided with a top reinforcing ring, which is welded and fixed to the outer wall of the pipe pile; and / or, the lower end of the pipe pile is provided with a bottom reinforcing ring, which is welded and fixed to the outer wall of the pipe pile.
[0010] Optionally, the shear studs are welded inside the steel pipe pile, and the shear studs include multiple groups distributed along the direction of the pier column, with multiple shear studs in each group and evenly distributed along the circumference of the outer wall of the pier column.
[0011] Optionally, the shear blocks are welded inside the steel pipe pile, and the shear blocks include multiple groups distributed along the direction of the pipe pile, with multiple shear blocks in each group and evenly distributed along the inner wall of the pipe pile.
[0012] Optionally, the pipe pile, the pier column, the shear stud, the shear block, and the stiffening plate are all steel structures.
[0013] Secondly, this application provides a steel structure pedestrian bridge, including a bridge and a plurality of steel structure pedestrian bridge single-pile single-column structures as described above, disposed under the bridge; the bridge includes a plurality of box girders, and the steel structure pedestrian bridge single-pile single-column structures are fixed under the box girders.
[0014] The technical solutions provided by the embodiments of this utility model may include the following beneficial effects: The steel structure pedestrian bridge and its single-pile, single-column structure provided in this embodiment of the utility model are directly connected to the steel structure piers via steel pipe piles. Compared with the traditional pile foundation that uses a large concrete platform for intermediate connection, this method is more convenient and faster to construct on-site, with less workload, lower cost, and shorter construction period. The shear blocks, stiffening plates, cylindrical shear studs, and bearing plates between the steel pipe piles and the steel structure piers effectively ensure the effectiveness of the connection and the construction accuracy requirements, making construction quality easier to control. The single-pile, single-column structure is simple, reliable, and highly convenient to use, which helps to improve construction efficiency. Attached Figure Description
[0015] Other features, objects, and advantages of this invention will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings: Figure 1 A schematic diagram of a single-pile, single-column steel structure pedestrian bridge provided for an embodiment of this utility model; Figure 2 for Figure 1 Schematic diagram of the cross section at point AA; Figure 3 for Figure 1 Schematic diagram of the cross section at point BB; Figure 4 A structural schematic diagram of a steel pedestrian bridge provided for an embodiment of this utility model; Figure 5 An assembly diagram of a pier column provided for an embodiment of this utility model; Figure 6 This is a schematic diagram of the assembly of a pipe pile provided for an embodiment of the present utility model.
[0016] In the diagram: 1. Pipe pile; 2. Pier column; 3. Shear stud; 4. Shear block; 5. Stiffening plate; 6. Concrete pouring section; 7. Concrete core filling section; 8. Concrete pier; 9. Bearing plate; 10. Top reinforcing ring; 11. Bottom reinforcing ring; 12. Box girder. Detailed Implementation
[0017] The present invention will now be described in further detail with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and not intended to limit it. Furthermore, it should be noted that, for ease of description, only the parts relevant to the invention are shown in the accompanying drawings.
[0018] It should be noted that, where there is no conflict, the embodiments and features in the embodiments of this utility model can be combined with each other. The present utility model will now be described in detail with reference to the accompanying drawings and embodiments.
[0019] Please see details. Figure 1-3 This application provides a single-pile, single-column steel structure pedestrian bridge, comprising: a pipe pile 1 and a pier 2 sleeved inside the pipe pile 1; the steel structure pier 2 is coaxially arranged with the steel pipe pile 1 to ensure the uniformity of load transfer.
[0020] The pier 2 has multiple shear nails 3 arranged on the outer wall near the pipe pile 1, and the pipe pile 1 has multiple shear blocks 4 arranged on the inner wall near the pier 2.
[0021] The shear studs 3 are welded inside the steel pipe pile 1. The shear studs 3 include multiple groups distributed along the direction of the pier column 2, with multiple shear studs 3 in each group and evenly distributed along the circumference of the outer wall of the pier column 2. The shear blocks 4 are welded inside the steel pipe pile 1. The shear blocks 4 include multiple groups distributed along the direction of the pipe pile 1, with multiple shear blocks 4 in each group and evenly distributed along the circumference of the inner wall of the pipe pile 1.
[0022] In this embodiment, the shear stud 3 can be a cylindrical head shear stud. During welding, ensure that the shear stud 3 is perpendicular to the outer wall of the pier column 2. Through the interlocking action with the concrete, it effectively transmits shear force and prevents relative slippage between the steel structure pier column 2 and the concrete. The shear block 4 is adapted to the shape of the pipe pile 1 and can be an arc-shaped block. The shear block 4 is made of 16mm thick steel plate, with 4 blocks in each group, evenly distributed on the inner wall of the steel pipe pile 1. During welding, ensure that the shear block 4 is tightly fitted to the inner wall of the steel pipe pile 1 and the weld is full. The steel pipe pile 1 and the shear block 4 are firmly connected through the concrete, realizing the effective transfer of load from the concrete to the steel pipe pile 1. The cylindrical head shear stud 3 and the shear block 4 serve as the force transmission medium between the steel structure pier column 2, the steel pipe pile 1 and the concrete, respectively, effectively improving the shear resistance of the connection surface and ensuring the continuity and stability of load transmission.
[0023] The pier 2 extends beyond the upper end of the pipe pile 1. A stiffening plate 5 is provided between the pier 2 and the pipe pile 1 at a position close to the upper end of the pipe pile 1. One end of the stiffening plate 5 extends into the interior of the pipe pile 1 and the other end extends into the exterior of the pipe pile 1 along the height direction.
[0024] In this embodiment, one side of the stiffening plate 5 is welded and fixed to the outer wall of the pier column 2, and the other side is fixed to the inner wall of the pipe pile 1 through the concrete pouring part 6; there are multiple stiffening plates 5 and they are evenly distributed along the circumference of the outer wall of the pier column 2.
[0025] It should be noted that the number of stiffening plates 5 is not limited in this embodiment; this embodiment uses eight stiffening plates 5 as an example for illustrative purposes. The stiffening plates 5 serve a dual function of installation positioning and structural reinforcement, ensuring both the verticality accuracy of the steel structure pier 2 during installation and enhancing the collaborative working ability between the pier 2 and the concrete. In this embodiment, the centerline of the stiffening plate 5 is aligned with the upper surface of the pipe pile 1. The stiffening plate 5 is made of 25mm thick steel plate, and its width is adapted to the gap between the steel pipe pile 1 and the steel structure pier 2. A full penetration welding process is used during welding to ensure connection strength. The evenly distributed stiffening plates 5 ensure uniform stress on the concrete around the steel structure pier 2, preventing excessive local deformation and improving the structure's torsional resistance.
[0026] The pipe pile 1, the pier column 2, the shear stud 3, the shear block 4, and the stiffening plate 5 are fixedly connected by a concrete pouring section 6. In this embodiment, the shear block 4, stiffening plate 5, cylindrical shear stud 3, and bearing plate 9 are used to effectively connect the steel structure pier column 2 and the steel pipe pile 1 to form a whole through concrete pouring. The concrete pouring section 6 is formed by pouring C40 self-compacting concrete between the pipe pile 1 and the pier column 2, which can fill and compact without vibration, effectively avoiding quality defects such as pores and cracks caused by insufficient vibration in traditional concrete pouring, and ensuring the integrity and load-bearing performance of the connection structure.
[0027] The pier 2 described in this application includes a first end and a second end arranged along the height direction, the first end extending out of the pipe pile 1, and the second end disposed inside the pipe pile 1.
[0028] The first end of the steel pier 2 is welded to the single-box, single-cell thin-walled steel box girder 12 of the bridge superstructure to form a pier-beam connection, and the second end extends into the steel pipe pile 1 to achieve a reliable connection with the pile foundation. The steel pier 2 has a diameter of 800mm and a thickness of 20mm, and its length is determined according to the bridge design elevation and foundation bearing capacity requirements to ensure that the load transfer requirements of the superstructure are met.
[0029] The pipe pile 1 has a concrete core 7 inside, one end of which is flush with the second end of the pier 2. The steel pipe pile 1 is made of steel pipe with a diameter of 1200mm and a thickness of 18mm. The bottom of the pile is first filled with sand to the bottom elevation of the core to form a stable support base. Then, C40 self-compacting concrete is poured to the top elevation of the core to form the concrete core 7. The concrete core 7 is tightly attached to the bearing plate 9 to jointly bear and transmit the vertical load.
[0030] The pier 2 has a concrete pier 8 inside, which fills upward from the second end of the pier 2 and does not extend to the first end; the concrete pouring part 6 is located between the pipe pile 1 and the pier 2, and the concrete pouring part 6 is connected to the concrete pier 8 and extends to the upper end of the pipe pile 1.
[0031] The concrete pier 8 is connected to the external C40 self-compacting concrete pouring section 6, forming a synergistic concrete load-bearing system that further enhances the shear and compressive strength of the steel structure pier 2 and improves the overall structural stiffness.
[0032] The pier 2 has a bearing plate 9 at the bottom of the second end, and the outer diameter of the bearing plate 9 is larger than the outer diameter of the pier 2. The bearing plate 9 is pressed into the concrete core 7.
[0033] The bearing plate 9 is made of 30mm thick steel plate to form a ring, which is welded to the steel structure pier 2. Its outer diameter is larger than that of the pier 2. At the same time, it is adapted to the internal space of the steel pipe pile 1, which can evenly distribute the vertical load transmitted by the steel structure pier 2 to the concrete core 7 below, avoiding local stress concentration.
[0034] Optionally, a top reinforcing ring 10 is provided at the upper end of the pipe pile 1, and the top reinforcing ring 10 is welded and fixed to the outer wall of the pipe pile 1; and / or, a bottom reinforcing ring 11 is provided at the lower end of the pipe pile 1, and the top reinforcing ring 10 is welded and fixed to the outer wall of the pipe pile 1. Both the pile top reinforcing ring and the column bottom reinforcing ring are made of 16mm thick steel plate, respectively providing local reinforcement to the top of the steel pipe pile 1 and the bottom of the steel structure pier 2, preventing local structural yielding due to stress concentration and extending service life.
[0035] Optionally, the pipe pile 1, the pier column 2, the shear stud 3, the shear block 4, and the stiffening plate 5 are all steel structures. All steel structural components are prefabricated in a factory, with strict control over dimensional accuracy and welding quality during production. The components are made of high-strength steel that meets the requirements of bridge engineering, ensuring the structure's load-bearing capacity and durability.
[0036] In this embodiment, the steel pier 2 bears the superstructure load of the bridge, which is transferred to the concrete through the cylindrical shear studs 3 and bearing plates 9 on the pier body. The concrete then transfers the load of the pier 2 to the steel pipe pile 1 through the shear blocks 4 welded inside the steel pipe pile 1. The steel pipe pile 1 provides vertical bearing capacity through friction with the soil. The stiffening plates 5 around the pier 2 serve two purposes: firstly, they position the pier 2 during installation; secondly, they provide local reinforcement to the pier 2; and thirdly, their connection with the concrete enhances the vertical bearing capacity of the pier 2.
[0037] like Figure 4 As shown, this application also provides a steel structure pedestrian bridge, including a bridge and a plurality of steel structure pedestrian bridge single-pile single-column structures as described above, disposed under the bridge; the bridge includes a plurality of box girders 12, and the steel structure pedestrian bridge single-pile single-column structures are fixed under the box girders 12.
[0038] The construction of steel pipe pile 1 adopts a high-frequency hydraulic non-resonance construction process. During pile foundation construction, the non-resonance hydraulic vibratory hammer liquefies the soil through high-frequency vibration before pressing the pile into the soil. Because its vibration frequency is higher than the soil's resonant frequency, it does not resonate with the soil, has no soil displacement effect, and does not damage surrounding buildings or existing pile foundations. It also avoids the significant noise and mud pollution generated by traditional pile foundation construction. During specific installation: Factory prefabrication: such as Figure 5As shown, cylindrical shear studs 3 and stiffening plates 5 are welded to the outer wall of the steel structure pier 2 to ensure the verticality of the cylindrical shear studs 3 and the tight fit between the stiffening plates 5 and the outer wall of the pier 2. A bearing plate 9 is welded to the bottom of the second end of the steel structure pier 2, with the center of the bearing plate 9 coinciding with the axis of the pier 2. Figure 6 As shown, shear blocks 4 are welded to the inner wall of steel pipe pile 1. Before welding, shear block 4 positioning lines are marked on the inner wall of steel pipe pile 1 according to the design spacing to ensure that each group of shear blocks 4 is evenly distributed along the circumference and to complete the installation of shear blocks 4. A pile top reinforcing ring is welded to the top of steel pipe pile 1 and a column bottom reinforcing ring is welded to the bottom of steel structure pier 2.
[0039] On-site construction: A crane is used to lift the precast steel pipe pile 1 to the pile location. Sand is then filled into the steel pipe pile 1 to the bottom elevation of the filling core. During the filling process, a layered compaction process is used to ensure the density of the sand cushion layer, providing a stable base for subsequent concrete pouring. A crane is then used to lift the precast steel structure pier 2 above the steel pipe pile 1. The pier 2 is inserted into the steel pipe pile 1. During the insertion process, the stiffening plate 5 is used to initially position the pier by engaging with the inner wall of the steel pipe pile 1.
[0040] Concrete pouring: First, C40 self-compacting concrete is poured into the steel structure pier 2, forming a concrete core 7 on the sand below the steel pipe pile 1; a concrete pier 8 is formed inside the steel structure pier 2, with the pouring height from the second end of the pier 2 upwards to the design elevation; before the concrete inside the steel structure pier 2 initially sets, C40 self-compacting concrete is poured into the gap between the steel pipe pile 1 and the steel structure pier 2, forming a concrete pouring section 6. The construction of the single-pile, single-column structure is completed.
[0041] Bridge deck installation: The single-box single-cell thin-walled steel box girder 12 is hoisted to the first end of the steel structure pier 2, the position and elevation of the steel box girder 12 are adjusted, and the steel box girder 12 is welded and fixed to the steel structure pier 2 to form a steel structure pedestrian bridge.
[0042] It should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", and "outer" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model.
[0043] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this utility model, "a plurality of" means two or more, unless otherwise explicitly specified.
[0044] Unless otherwise defined, the technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art. The terminology used herein is for descriptive purposes only and is not intended to limit the scope of the invention. Terms such as “set” appearing herein can refer to either a component being directly attached to another component or a component being attached to another component via an intermediary. A feature described in one embodiment may be applied, alone or in combination with other features, to another embodiment, unless that feature is not applicable in that other embodiment or is otherwise stated.
[0045] This utility model has been described through the above embodiments. However, it should be understood that the above embodiments are for illustrative purposes only and are not intended to limit this utility model to the described embodiments. Those skilled in the art will understand that many more variations and modifications can be made based on the teachings of this utility model, and all such variations and modifications fall within the scope of protection claimed by this utility model.
Claims
1. A single-pile, single-column structure for a steel pedestrian bridge, characterized in that, include: Pipe piles and piers fitted inside the pipe piles; The pier column has multiple shear studs arranged on its outer wall near the pipe pile, and the pipe pile has multiple shear blocks arranged on its inner wall near the pier column. The pier extends beyond the upper end of the pipe pile. A stiffening plate is provided between the pier and the pipe pile near the upper end of the pipe pile. One end of the stiffening plate extends into the interior of the pipe pile and the other end extends into the exterior of the pipe pile along the height direction. The pipe piles, the piers, the shear studs, the shear blocks, and the stiffening plates are fixedly connected by concrete pouring sections.
2. The single-pile, single-column steel structure pedestrian bridge according to claim 1, characterized in that, The pier includes a first end and a second end arranged along the height direction, the first end extending out of the pipe pile, and the second end disposed inside the pipe pile; The pier has a pressure plate at the bottom of the second end, and the outer diameter of the pressure plate is larger than the outer diameter of the pier.
3. The single-pile, single-column steel structure pedestrian bridge according to claim 2, characterized in that, The pipe pile has a concrete core, one end of which is flush with the second end of the pier column, and the bearing plate is pressed into the concrete core.
4. The single-pile, single-column steel structure pedestrian bridge according to claim 2, characterized in that, The pier has a concrete pier section inside, which fills the second end of the pier upwards and does not extend to the first end. The concrete pouring section is located between the pipe pile and the pier, and the concrete pouring section is connected to the concrete pier and extends to the upper end of the pipe pile.
5. The single-pile, single-column structure of the steel pedestrian bridge according to claim 4, characterized in that, The stiffening plate is welded and fixed to the outer wall of the pier column on one side, and fixed to the inner wall of the pipe pile on the other side through the concrete pouring part. The stiffening plates are multiple and are evenly distributed along the circumference of the outer wall of the pier.
6. The single-pile, single-column structure of the steel pedestrian bridge according to claim 1, characterized in that, The upper end of the pipe pile is provided with a top reinforcing ring, which is welded and fixed to the outer wall of the pipe pile; and / or, the lower end of the pipe pile is provided with a bottom reinforcing ring, which is welded and fixed to the outer wall of the pipe pile.
7. The single-pile, single-column steel structure pedestrian bridge according to claim 1, characterized in that, The shear studs are welded inside the steel pipe pile. The shear studs include multiple groups distributed along the direction of the pier column. Each group contains multiple shear studs that are evenly distributed circumferentially along the outer wall of the pier column.
8. The single-pile, single-column structure of the steel pedestrian bridge according to claim 1, characterized in that, The shear blocks are welded inside the steel pipe pile. The shear blocks include multiple groups distributed along the direction of the pipe pile. Each group contains multiple shear blocks that are evenly distributed circumferentially along the inner wall of the pipe pile.
9. The single-pile, single-column structure of the steel pedestrian bridge according to claim 1, characterized in that, The pipe piles, the piers, the shear studs, the shear blocks, and the stiffening plates are all steel structures.
10. A steel structure pedestrian bridge, characterized in that, The system includes a bridge and multiple steel-structured pedestrian bridge single-pile and single-column structures as described in any one of claims 1-9, disposed beneath the bridge; the bridge includes multiple box girders, and the steel-structured pedestrian bridge single-pile and single-column structures are fixed beneath the box girders.