An underground engineering deformation joint waterstop material filling structure
By using the chamfered transition design and interface treatment of the modified polymer sealing material, the problems of stress concentration and sealing material peeling in the T-shaped waterstop structure were solved, achieving a long-term waterproof effect for the deformation joints of underground engineering.
Patent Information
- Application Number
- CN202522702132.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-19
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-19
AI Technical Summary
In existing T-shaped waterproofing filling structures, the right-angle transition design at the junction of the outer extension end and the concrete base causes local stress concentration, micro-crack expansion, and edge peeling of the sealing material, affecting the reliability of waterproofing.
A three-component modified polymer sealing material is used, with a continuous and smooth chamfered transition structure and physical isolation gaps. Combined with interface roughening treatment and interpenetrating network interface layer, a contact interface without sharp edges and geometric abrupt changes is formed, ensuring uniform stress distribution and the stability of the sealing material.
It effectively eliminates the initiation and propagation of microcracks, improves interfacial bonding strength, ensures the long-term reliability and anti-peeling performance of the water-stopping system, and extends its service life.
Smart Images

Figure CN225014227U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of waterproof structures in civil engineering, specifically a filling structure for waterproofing materials in expansion joints of underground engineering. Background Technology
[0002] In underground engineering waterproofing systems, expansion joints, as key components adapting to structural deformation, are crucial for reliable waterproofing. Existing technologies often employ T-shaped sealing structures, typically composed of three components of polymer sealant: an internal filling section embedded within the expansion joint and an extension section extending to the concrete substrate on both sides. While this structure achieves basic sealing, in practical engineering applications, the junction between the extension section and the concrete substrate often uses a 90° right-angle transition design. This leads to localized stress concentration in this area under structural settlement, temperature changes, or seismic forces. When the expansion joint experiences significant tensile displacement (e.g., exceeding 30 mm), the abrupt geometric change at the right-angle junction makes it difficult to effectively disperse stress, easily inducing microcracks that gradually propagate and eventually cause the sealant to peel off at the edges. Furthermore, the right-angle interface weakens the molecular-level penetration and bonding effect between the sealant and the concrete substrate, reducing interfacial bond strength. Although attempts have been made to improve durability by increasing the width of the extension section or enhancing the material's bulk bonding properties, these measures fail to eliminate stress concentration sources at the structural level, thus remaining limited in reliability when dealing with repeated deformation conditions. Utility Model Content
[0003] This invention provides a filling structure for waterproofing materials in expansion joints of underground engineering, aiming to solve the technical problems caused by the right-angle transition design at the junction of the outer extension end and the concrete substrate in existing T-shaped waterproofing filling structures, such as local stress concentration, micro-crack propagation, and edge peeling of the sealing material. By reconstructing the geometry of the outer extension end of the sealing material, a continuous and smooth transition interface is formed, effectively dispersing the stress generated during structural deformation and improving the long-term reliability and anti-peeling performance of the waterproofing system.
[0004] To achieve the above objectives, this utility model provides the following technical solution: Design a filling structure for waterproofing materials in expansion joints of underground engineering, comprising a concrete base, a three-component modified polymer sealant, and a backing foam board, wherein: The three-component modified polymer sealing material is formed by chemically reacting and curing polyether polyol, isocyanate and additives to form an integral elastomer. Its cross-section has a T-shaped structure, including an infill section that is vertically embedded in the deformation joint, an extension section that extends horizontally to both sides to cover the concrete base surface, and a chamfered transition structure located at the junction of the extension section and the concrete base surface. The filling section inside the joint is set along the depth direction of the expansion joint, with its bottom end face remaining in a non-contact state with the bottom surface of the expansion joint and its top end face being flush with the concrete base surface. The outer extension extends horizontally from both sides of the inner filling section of the joint, and its bottom surface is closely attached to the concrete base surface to form a continuous bonding interface. The chamfered transition structure is the geometric reconstruction part of the three-component modified polymer sealing material body in the end region. Its outline is a 30-degree inclined arc surface with a radius of curvature between five and eight millimeters, so that the end of the extension section forms a continuous and smooth contact interface with no sharp corners and no geometric abrupt changes between it and the concrete base surface. The backing foam board is placed at the bottom of the expansion joint, and a physical isolation gap is reserved between its upper surface and the lower surface of the filling section inside the joint. The width of the gap is 0.5 mm to 1 mm, which ensures that the filling section inside the joint has free displacement space when it is deformed under force.
[0005] Optionally, the contact boundary line between the arc-shaped surface of the chamfered transition structure and the concrete substrate is an S-shaped spatial curve. This S-shaped curve is distributed along the extension direction of the outer section, and its radius of curvature gradually changes from five millimeters near the filling section to eight millimeters away from the filling section, so as to achieve gradient dispersion of stress along the interface.
[0006] Optionally, the embedding depth of the filling section in the slit is equal to the horizontal extension width of the single-sided extension section, and the two form a proportional T-shaped section with a depth-to-width ratio of 1:1. This proportional configuration ensures that the stress distribution on both sides of the extension section is symmetrical when the structure is subjected to bidirectional tensile or compressive deformation, thus avoiding single-sided section failure caused by uneven stress.
[0007] Optionally, the left and right side walls of the backing foam board are respectively provided with positioning protrusions, which extend continuously along the height direction of the foam board and have a rectangular or trapezoidal cross-section; the concrete base surface has a groove at the corresponding position on the side wall of the expansion joint, the inner contour dimension of the groove is slightly smaller than the outer contour dimension of the positioning protrusion, and the two are fitted together to form an interference connection, with the interference amount controlled within the range of 0.2 mm to 0.3 mm, so as to limit the axial displacement of the backing foam board during construction and grouting and ensure its precise positioning in the expansion joint.
[0008] Optionally, the concrete substrate may be pre-treated with interface roughening in the area in contact with the extension segment. The treatment method may include sandblasting, roughening, or coating with an interface reinforcing agent to form a micro-anchoring structure, thereby enhancing the physical interlocking force and chemical bond strength between the three-component modified polymer sealant and the concrete substrate.
[0009] Optionally, during the curing process, the bottom surface of the three-component modified polymer sealant undergoes a polymer chain penetration reaction in the contact area between its outer end and the concrete substrate, forming an interpenetrating network interface layer with a depth of not less than 0.3 mm. This interface layer penetrates the chamfered transition structure area, ensuring that the chamfered transition structure and the concrete substrate have integrated bonding performance.
[0010] Optionally, the 30-degree inclined arc surface of the chamfered transition structure extends continuously along the length of the deformation joint in three-dimensional space, and its surface smoothness is controlled to Ra value not greater than 3.2 micrometers to avoid introducing additional stress disturbance due to surface roughness differences.
[0011] Optionally, the backing foam board is made of closed-cell polyethylene with a density of 25 to 35 kilograms per cubic meter and a compressive strength of not less than 50 kPa, ensuring that no plastic deformation occurs under the injection pressure of the sealing material, while having good resilience to adapt to subsequent structural deformation.
[0012] This utility model provides a filling structure for waterproofing materials in expansion joints of underground engineering, which has the following beneficial effects: This structure completely eliminates geometric abrupt changes by reconstructing the traditional right-angle intersection into a chamfered transition structure with a 30-degree inclined arc surface, effectively suppressing the initiation and propagation of microcracks. The S-shaped contact boundary line design further guides stress to be evenly distributed along the interface, preventing local peak stress from exceeding the material strength limit. The proportional T-shaped cross-section ensures balanced stress on both sides of the extended section during deformation, improving the overall structural deformation coordination. The physical isolation gap between the backing foam board and the filling section provides the necessary deformation freedom for the sealing material, preventing internal cracking caused by excessive bottom constraint. The interference fit between the positioning protrusion and the groove ensures the stability of the backing foam board during construction, ensuring uniform thickness of the filling section and maintaining consistent water-stopping performance. The interface roughening treatment and the interpenetrating network interface layer formed by polymer chain penetration jointly enhance the bonding reliability, allowing the chamfered transition structure to maintain a complete seal during long-term service. The synergistic effect of these technical features fundamentally solves the problem of edge cracking and peeling caused by structural defects in existing technologies, significantly extending the service life of the water-stopping system. Attached Figure Description
[0013] Figure 1 This is a schematic diagram of the three-dimensional installation structure between the present invention and the concrete substrate.
[0014] Figure 2 This is a schematic diagram of the three-dimensional structure of the concrete base surface of this utility model.
[0015] Figure 3 This is a utility model Figure 1 A partial structural diagram.
[0016] Figure 4 This is a utility model Figure 3 A magnified view of part A.
[0017] Figure 5 This is a practical book Figure 3 A magnified view of section B.
[0018] Figure 6 This is a schematic diagram of the three-dimensional structure of the filling section inside the seam in this practical application.
[0019] Figure 7 This is a three-dimensional structural diagram of the practical backing foam board.
[0020] Figure 8 This is a bottom view of the three-dimensional structure of the extension section of this practical application.
[0021] Explanation of reference numerals in the attached drawings: 1. Concrete substrate; 2. Three-component modified polymer sealant; 3. Backing foam board; 4. In-joint filling section; 5. Outer extension section; 6. Chamfered transition structure; 7. Expansion joint; 8. Physical isolation gap; 9. Positioning protrusion; 10. Groove; 11. Interface roughening area; 12. Interpenetrating network interface layer; 13. Thirty-degree inclined arc surface; 14. S-shaped contact boundary line; 15. Top end face of the in-joint filling section; 16. Bottom end face of the in-joint filling section; 17. Bottom surface of the outer extension section; 18. End of the outer extension section; 19. Intersection with the concrete substrate; 21. Upper surface of the backing foam board; 22. Lower surface of the backing foam board; 23. Left side wall of the backing foam board; 24. Right side wall of the backing foam board; 30. Surface of the chamfered transition structure. Detailed Implementation
[0022] The following is in conjunction with the appendix Figures 1 to 8 This application will be described in further detail.
[0023] This invention provides a waterproofing material filling structure for expansion joints in underground engineering. This structure is applied to expansion joints (7 areas) in underground engineering concrete structures where relative displacement occurs due to temperature changes, settlement differences, or seismic forces, to achieve a long-term, reliable waterproof sealing function. The structure includes a concrete base surface (1), a three-component modified polymer sealant (2), and a backing foam board (3).
[0024] The concrete base surface 1 forms the main structure on both sides of the expansion joint 7, and its surface has an interface roughening area 11 in the contact area with the three-component modified polymer sealant 2; the three-component modified polymer sealant 2 has a T-shaped cross-section structure and is embedded in the expansion joint 7 and the top opening; the backing foam board 3 is placed at the bottom of the expansion joint 7, below the three-component modified polymer sealant 2, and a physical isolation gap 8 is reserved between it and its bottom end face.
[0025] The three-component modified polymer sealant 2 is made by mixing polyether polyol, isocyanate, and additives on-site and then injecting them into the expansion joint 7, where they are cured through a chemical reaction to form an integral elastomer. The material's cross-section includes an infill section 4, an extension section 5, and a chamfered transition structure 6. The infill section 4 is positioned along the depth of the expansion joint 7, with its top end face 15 flush with the concrete base surface 1, and its bottom end face 16 maintaining a non-contact state with the upper surface 21 of the backing foam board. The distance between these two surfaces forms a physical isolation gap 8, with a width of 0.5 mm to 1 mm. The extension section 5 extends horizontally from both sides of the infill section 4, with its bottom surface 17 tightly adhering to the concrete base surface 1, forming a continuous bonding interface. The chamfered transition structure 6 is located between the end 18 of the extension section and the junction 19 of the concrete base surface, and is the geometric reconstruction portion of the three-component modified polymer sealant 2 body in the end region.
[0026] The chamfered transition structure 6 has a contour of a 30-degree inclined arc surface 13, which extends continuously along the length of the expansion joint 7 in three-dimensional space, and its surface smoothness is controlled to have an Ra value of no more than 3.2 micrometers. The radius of curvature of the 30-degree inclined arc surface 13 is between 5 mm and 8 mm, and the center of curvature is located on one side inside the concrete base surface 1.
[0027] The contact boundary line between the chamfered transition structure 6 and the concrete base surface 1 is an S-shaped contact boundary line 14. The S-shaped contact boundary line 14 is distributed along the extension direction of the outer extension section 5, and its radius of curvature gradually changes from five millimeters on the side close to the filling section 4 to eight millimeters on the side away from the filling section 4.
[0028] The embedment depth of the filling section within the slit is equal to the horizontal extension width of the single-sided extension section, forming a proportional T-section that is symmetrical about the centerline of the proportional T-section. This proportional configuration ensures that the stress distribution on both sides of the extension section 5 is symmetrical when the structure is subjected to biaxial tensile or compressive deformation.
[0029] The backing foam board 3 is made of closed-cell polyethylene with a density of 25 to 35 kg per cubic meter and a compressive strength of not less than 50 kPa. Positioning protrusions 9 are provided on the left side wall 23 and right side wall 24 of the backing foam board 3, respectively. These protrusions 9 extend continuously along the height of the foam board 3, and their cross-sections are rectangular or trapezoidal. The outer contour dimensions are slightly larger than the inner contour dimensions of the groove 10 opened at the corresponding position on the side wall of the expansion joint 7 on the concrete base surface 1. The two fit together to form an interference fit, with the interference amount controlled within the range of 0.2 mm to 0.3 mm. The lower surface 22 of the backing foam board 3 contacts the bottom surface of the expansion joint 7, and a physical isolation gap 8 is formed between the upper surface 21 of the backing foam board 3 and the bottom end face 16 of the filling section within the joint.
[0030] The concrete substrate 1 undergoes pre-treatment of the interface roughening process in the area contacting the extension segment 5. This treatment includes sandblasting, roughening, or coating with an interface reinforcing agent to form an interface roughened area 11, the surface of which has a microscopic anchoring structure. During the curing process, the bottom surface 17 of the three-component modified polymer sealant 2 undergoes a polymer chain penetration reaction in the contact area with the concrete substrate 1, forming an interpenetrating network interface layer 12. This interface layer 12 has a depth of not less than 0.3 mm and penetrates the chamfered transition structure 6 area, enabling the chamfered transition structure 6 and the concrete substrate 1 to have integrated bonding performance.
[0031] During construction, the concrete base surface 1 is first roughened at the predetermined bonding area on both sides of the expansion joint 7, forming roughened area 11. Then, the backing foam board 3 is placed at the bottom of the expansion joint 7, and axial positioning is achieved through the interference fit between the positioning protrusion 9 and the groove 10, ensuring that the backing foam board 3 does not shift during subsequent grouting. Next, the three-component modified polymer sealant 2, mixed in proportion, is injected into the expansion joint 7. The material naturally flows and covers the concrete base surface 1 under gravity, while simultaneously, in the area at the end 18 of the outer extension section... Surface tension and mold constraint form a 30-degree inclined arc surface 13; during the material curing process, polymer chains penetrate into the concrete base surface 1, forming an interpenetrating network interface layer 12 in the roughened interface area 11; in the final structure, a physical isolation gap 8 is maintained between the filler section 4 and the backing foam board 3, and the bottom surface 17 of the extension section 5 is firmly bonded to the concrete base surface 1 through the interpenetrating network interface layer 12. The chamfered transition structure 6 connects the end of the extension section 18 and the junction 19 of the concrete base surface in a way that is without sharp edges and geometric abrupt changes.
[0032] During the service life of the structure, when the underground works undergo relative displacement due to external loads or environmental factors, the width of the expansion joint 7 changes, and the filling section 4 inside the joint undergoes lateral tensile or compressive deformation accordingly. Due to the presence of the physical isolation gap 8, the bottom end face 16 of the filling section inside the joint is not constrained by the backing foam board 3 and can deform freely. The extension section 5 deforms synchronously with the filling section 4 inside the joint, and the bonding interface between its bottom surface 17 and the concrete base surface 1 bears shear stress. The 30-degree inclined arc surface 13 of the chamfered transition structure 6 eliminates the geometric abrupt change in the traditional right-angle structure, so that the stress is evenly distributed along the S-shaped contact boundary line 14, avoiding local stress concentration. The interpenetrating network interface layer 12 and the interface roughening area 11 together provide sufficient bonding strength to prevent the extension section 5 from peeling off from the concrete base surface 1. The proportional T-section structure ensures that the deformation of the extension sections 5 on both sides is coordinated, avoiding unilateral failure. The backing foam board 3 maintains shape stability under the injection pressure of the sealing material and provides rebound support in subsequent deformation, maintaining the effectiveness of the physical isolation gap 8.
[0033] In the formulation of the three-component modified polymer sealing material 2, polyether polyol serves as the main chain to provide flexibility, isocyanate acts as a crosslinking agent to form a network structure, and additives include catalysts, fillers, and coupling agents. The coupling agent promotes the chemical bonding between the polymer chains and the concrete substrate 1, enhancing the formation effect of the interpenetrating network interface layer 12. The closed-cell structure of the backing foam board 3 prevents moisture penetration, and its low density and high resilience meet the requirements of long-term repeated deformation. The slot 10 is pre-embedded during the concrete pouring stage or processed by grooving in the later stage, with its positional accuracy controlled within ±1 mm to ensure that the positioning protrusion 9 is smoothly embedded and forms an effective interference fit.
[0034] The 30-degree inclined arc-shaped surface 13 of the chamfered transition structure 6 can be shaped by a special scraper before the material initially sets, or directly shaped during pouring using a pre-set mold; the spatial shape of the S-shaped contact boundary line 14 is achieved by controlling the scraper trajectory or the mold edge contour; the surface smoothness is controlled by the scraper surface finish and operating technique to ensure that the Ra value is not greater than 3.2 micrometers. The width of the physical isolation gap 8 is controlled by the height tolerance of the backing foam board 3 and the pouring volume of the filling section 4 in the gap. During construction acceptance, a feeler gauge is used to check whether the gap size is within the range of 0.5 mm to 1 mm.
[0035] The roughness parameter of the roughened interface region 11 is controlled between ten micrometers and fifty micrometers Ra to provide sufficient mechanical embedding without damaging the surface structure of the concrete substrate 1; the formation of the interpenetrating network interface layer 12 depends on the chemical reaction between the active groups in the material formulation and the silanol groups in the concrete substrate 1, and the reaction depth is controlled by the material permeability and curing time.
[0036] It will be apparent to those skilled in the art that this invention is not limited to the details of the exemplary embodiments described above, and that it can be implemented in other specific forms without departing from the spirit or essential characteristics of this invention. Therefore, the embodiments should be considered illustrative and non-limiting in all respects, and the scope of this invention is defined by the appended claims rather than the foregoing description. Thus, it is intended that all variations falling within the meaning and scope of equivalents of the claims be included within this invention. No reference numerals in the claims should be construed as limiting the scope of the claims.
[0037] Furthermore, it should be understood that although this specification describes embodiments, not every embodiment contains only one independent technical solution. This narrative style is merely for clarity. Those skilled in the art should consider the specification as a whole, and the technical solutions in each embodiment can also be appropriately combined to form other embodiments that can be understood by those skilled in the art.
Claims
1. An underground work deformation joint waterstop material filling structure characterized by: It includes a concrete base (1), a three-component modified polymer sealant (2), and a backing foam board (3), wherein: The three-component modified polymer sealing material (2) has a T-shaped cross-section, including an inner filling section (4), an outer extension section (5), and a chamfered transition structure (6). The filling section (4) in the joint is set along the depth direction of the deformation joint (7), with its top end face (15) flush with the concrete base surface (1) and a physical isolation gap (8) between its bottom end face (16) and the upper surface (21) of the backing foam board. The outer extension (5) extends horizontally from both sides of the inner filling section (4), and its bottom surface (17) is in close contact with the concrete base surface (1); The chamfered transition structure (6) is located at the junction (19) of the end of the extension section (18) and the concrete base surface. Its outline is a 30-degree inclined arc surface (13) with a radius of curvature of five to eight millimeters. The backing foam board (3) is placed at the bottom of the expansion joint (7), and the width of the physical isolation gap (8) between its upper surface (21) and the bottom end face (16) of the filling section in the joint is 0.5 mm to 1 mm.
2. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 1, characterized in that: The contact boundary line between the chamfered transition structure (6) and the concrete base surface (1) is an S-shaped contact boundary line (14). The S-shaped contact boundary line (14) is distributed along the extension direction of the outer extension section (5), and its radius of curvature gradually changes from five millimeters on the side close to the filling section (4) to eight millimeters on the side far from the filling section (4).
3. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 1, characterized in that: The embedding depth of the filling section within the slit is equal to the horizontal extension width of the single-sided extension section, forming a proportional T-shaped cross-section symmetrical about the centerline of the proportional T-shaped cross-section.
4. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 1, characterized in that: The left side wall (23) and right side wall (24) of the backing foam board (3) are respectively provided with positioning protrusions (9). The positioning protrusions (9) extend continuously along the height direction of the foam board, and their cross-section is rectangular or trapezoidal.
5. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 4, characterized in that: The concrete base surface (1) has a groove (10) at the corresponding position on the side wall of the expansion joint (7). The inner contour dimension of the groove (10) is smaller than the outer contour dimension of the positioning protrusion (9), and the two form an interference connection with an interference of 0.2 mm to 0.3 mm.
6. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 1, characterized in that: The concrete base surface (1) has an interface roughening region (11) in the contact area with the extension section (5), which forms a micro-anchoring structure by sandblasting, roughening or coating with an interface reinforcing agent.
7. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 6, characterized in that: The three-component modified polymer sealing material (2) forms an interpenetrating network interface layer (12) in the contact area between the bottom surface (17) of the extension section and the concrete base surface (1). The interface layer (12) has a depth of not less than 0.3 mm and penetrates the chamfered transition structure (6) area.
8. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 1, characterized in that: The 30-degree inclined arc-shaped surface (13) of the chamfered transition structure (6) extends continuously along the length of the deformation joint (7), and its surface smoothness Ra value is not greater than 3.2 micrometers.
9. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 1, characterized in that: The backing foam board (3) is made of closed-cell polyethylene with a density of 25 to 35 kg per cubic meter and a compressive strength of not less than 50 kPa.
10. The filling structure for waterproofing materials in underground engineering expansion joints according to claim 1, characterized in that: The physical isolation gap (8) provides free displacement space for the filling section (4) in the seam when it is deformed under force, ensuring that the bottom end face (16) of the filling section in the seam remains in a non-contact state with the upper surface (21) of the backing foam board.