Submarine trenching apparatus
By designing a high-strength alloy steel support frame and a wear-resistant cast iron slurry pump for the submarine pipeline sludge removal equipment, the problem of low sludge cleaning efficiency has been solved, achieving stable and efficient sludge discharge and ensuring the safety and efficiency of pipeline laying.
Patent Information
- Application Number
- CN202522506099.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-26
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-11-26
AI Technical Summary
In existing submarine pipeline laying projects, the efficiency of cleaning silt inside the trench is low and the equipment stability is poor, which affects the service life and safety of the pipeline and may even lead to laying failure, increasing project costs and construction difficulty.
Design a sludge removal device for subsea pipeline trenches, which adopts a V-shaped support frame made of high-strength alloy steel and a wear-resistant and corrosion-resistant cast iron slurry pump. The device uses multiple pipes to pump and transport sludge, ensuring the stability of the equipment in the pipeline trench and the smooth discharge of sludge.
It improves sludge removal efficiency, ensures the stability of equipment in complex seabed environments and smooth sludge transport, reduces equipment adjustment time, lowers maintenance costs, and enhances the safety and efficiency of pipeline laying.
Smart Images

Figure CN225014255U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of submarine pipeline laying technology, specifically a submarine trench sludge removal device. Background Technology
[0002] In submarine pipeline laying projects, to ensure the stability and safety of the pipeline, A-type support structures are usually pre-installed under the mud surface to form a trench and protect the pipeline. However, after the A-type support has been under the mud surface for a period of time, a certain amount of silt often accumulates in the trench inside. If this silt is not removed in time, it will damage the pipeline during the laying process, affecting the service life and safety of the pipeline, and may even lead to pipeline laying failure, increasing project costs and construction difficulty. Therefore, before laying submarine pipelines, the silt inside the trench must be effectively cleaned. Existing silt removal equipment often suffers from low silt removal efficiency, poor equipment stability, and complex operation when cleaning silt inside the trench, making it difficult to meet the high requirements for trench cleaning in submarine pipeline laying projects. Utility Model Content
[0003] To overcome the above-mentioned defects, this utility model provides a sludge removal device for submarine pipeline trenches, which solves the problem that after the support is under the mud surface for a period of time, a certain amount of sludge often accumulates in the internal trench. If this sludge is not removed in time, it will damage the pipeline during the pipeline laying process, affect the service life and safety of the pipeline, and may even lead to pipeline laying failure, increasing project costs and construction difficulty.
[0004] To achieve the above objectives, this utility model provides the following technical solution: a submarine trench sludge removal device, comprising a base plate, two support frames arranged in a V-shape on the top of the base plate, the openings of the two support frames facing each other, the two support frames being distributed on both sides of the base plate, the bottom ends of the support frames being fixedly connected to the base plate, a connecting pipe being provided above the base plate, a sludge removal pipe being fixedly connected to the top end of the connecting pipe, the sludge removal pipe and the connecting pipe being T-shaped, the top ends of the support frames being connected to the sludge removal pipe, a reinforcing rib being fixedly connected to the middle of the support frame, the reinforcing rib being inclined and its other end being connected to the sludge removal pipe, and two sludge removal ports being opened at both ends of the sludge removal pipe.
[0005] As a further embodiment of this utility model: a support base is fixedly connected above the base plate, and the number of the support bases is three, which are respectively distributed at the three equal division points of the base plate.
[0006] As a further embodiment of this utility model: a slurry pump is fixedly connected above the support base, and three conveying pipes are fixedly connected evenly and at equal intervals on the outer wall of the connecting pipe.
[0007] As a further embodiment of this utility model: two suction pipes are symmetrically fixedly connected to the outer wall of the conveying pipe, and a connecting flange is fixedly connected to the bottom end of the conveying pipe.
[0008] As a further embodiment of this utility model: the conveying end of the slurry pump is connected to the conveying pipe through a connecting flange, and two lifting lugs are symmetrically fixedly connected above the sludge discharge pipe.
[0009] As a further embodiment of this utility model: the support frame is made of high-strength alloy steel, and the outer shell of the slurry pump is made of wear-resistant and corrosion-resistant cast iron.
[0010] Compared with the prior art, the beneficial effects of this utility model are as follows: 1. This subsea trench sludge removal equipment, through the installation of a base plate and a support frame, utilizes a floating crane connected to the lifting lugs above the sludge removal pipe to hoist and lower the entire sludge removal equipment to the trench support position. Because the support frame is V-shaped with opposing openings, its overall shape matches the shape of the trench, enabling rapid sludge suction and removal operations along the mudguards inside the support. This design makes the equipment more stable and efficient during hoisting and sludge removal, effectively improving sludge removal efficiency, reducing equipment adjustment and positioning time, and accelerating the overall progress of trench sludge removal.
[0011] 2. This subsea trench sludge removal equipment, by setting up slurry pumps and sludge removal pipes, allows three slurry pumps at the bottom to work simultaneously during operation. The sludge is drawn out from inside the trench through the suction pipe and then converged into the sludge removal pipe through the conveying pipe and connecting pipe. Finally, the sludge is discharged from the trench from the sludge removal ports at both ends of the sludge removal pipe. This multi-pipe sludge removal method not only improves the efficiency of sludge transportation but also ensures the smoothness of sludge transportation and avoids sludge blockage, thereby ensuring the reliability of the entire sludge removal equipment. Attached Figure Description
[0012] Figure 1 This is a three-dimensional structural diagram of the present invention.
[0013] Figure 2 This is a front view of the structure of this utility model.
[0014] Figure 3 This is a side view of the structure of this utility model.
[0015] Figure 4 This is a top view of the structure of this utility model.
[0016] Figure 5 This utility model Figure 1 Enlarged structural diagram at point A in the middle.
[0017] In the diagram: 1. Base plate; 2. Support frame; 3. Connecting pipe; 4. Sludge discharge pipe; 5. Reinforcing rib; 6. Sludge discharge port; 7. Support base; 8. Slurry pump; 9. Conveying pipe; 10. Suction pipe; 11. Connecting flange; 12. Lifting lug. Detailed Implementation
[0018] The technical solution of this patent will be further described in detail below with reference to specific embodiments.
[0019] like Figure 1-5 As shown, this utility model provides a technical solution: a subsea trench sludge removal device, including a base plate 1, with two support frames 2 above the base plate 1. The two support frames 2 are V-shaped. Because the support frames 2 are V-shaped and their openings face each other, their structure itself has a certain stability. High-strength alloy steel is used, which enables the support frames 2 to maintain stable support when subjected to large pressure and complex seabed environments, ensuring the stable placement of the entire device inside the trench support and providing a solid foundation for sludge removal operations. The openings of the two support frames 2 face each other, and the two support frames 2 are respectively distributed on both sides of the base plate 1. The bottom end of the support frame 2 is fixedly connected to the base plate 1. A connecting pipe 3 is provided above the base plate 1, and a sludge removal pipe 4 is fixedly connected to the top end of the connecting pipe 3. The sludge removal pipe 4 and the connecting pipe 3 are T-shaped, and the top end of the support frame 2 is connected to the sludge removal pipe 4.
[0020] A reinforcing rib 5 is fixedly connected to the middle of the support frame 2. The reinforcing rib 5 is inclined and its other end is connected to the sludge discharge pipe 4. Two sludge discharge ports 6 are opened at both ends of the sludge discharge pipe 4. The sludge pumped out by the slurry pump 8 is evenly transported to the conveying pipe 9 through the suction pipe 10, and then converged into the connecting pipe 3 through the conveying pipe 9, and finally enters the sludge discharge pipe 4 to be discharged from the trench. This multi-pipe coordination method not only improves the sludge conveying efficiency, but also ensures the smoothness of the sludge during the conveying process and avoids sludge blockage.
[0021] Three support bases 7 are fixedly connected to the top of the base plate 1. The three support bases 7 are distributed at three equal division points of the base plate 1. A slurry pump 8 is fixedly connected to the top of the support bases 7. Three conveying pipes 9 are fixedly connected evenly and at equal intervals to the outer wall of the connecting pipe 3. Two suction pipes 10 are symmetrically fixedly connected to the outer wall of the conveying pipes 9. A connecting flange 11 is fixedly connected to the bottom end of the conveying pipes 9. The conveying end of the slurry pump 8 is connected to the conveying pipes 9 through the connecting flange 11. Two lifting lugs 12 are symmetrically fixedly connected to the top of the sludge discharge pipe 4. The sludge discharge equipment can be easily hoisted and lowered to the trench support position through the lifting lugs 12. The operation is simple and quick, which improves the installation efficiency of the equipment. At the same time, the setting of the lifting lugs 12 also facilitates the adjustment and movement of the equipment during the sludge discharge process, increasing the flexibility and operability of the equipment.
[0022] The support frame 2 is made of high-strength alloy steel, and the outer shell of the slurry pump 8 is made of wear-resistant and corrosion-resistant cast iron. The three slurry pumps 8 are distributed at three equal points on the bottom plate 1, which can uniformly suck up the sludge inside the trench, improve the sludge discharge efficiency, and the wear-resistant and corrosion-resistant cast iron outer shell can effectively protect the slurry pump 8 to work normally in the harsh seabed environment, ensure its service life, and reduce the maintenance cost of the equipment.
[0023] The working principle of this utility model is as follows: When using the equipment, the floating crane is connected to the lifting lug 12, and the sludge removal equipment is hoisted and lowered to the trench support position by the floating crane. Since the inclination angle of the support frame 2 matches the mud baffle of the inclined surface of the support, the entire equipment can be stably placed inside the support. At this time, the three slurry pumps 8 at the bottom start to work, and the sludge inside the support is extracted through the suction pipe 10 and transported to the conveying pipe 9 by the suction pipe 10, and then transported to the connecting pipe 3 through the conveying pipe 9. The sludge is collected in the sludge discharge pipe 4 through the connecting pipe 3, and finally discharged from the trench through the sludge discharge port 6 at both ends of the sludge discharge pipe 4. As the sludge is continuously discharged, the equipment will gradually sink until the two ends of the sludge discharge pipe 4 are placed above the top cross brace of the support. At this time, the floating crane drags the sludge removal equipment to continue to discharge the sludge inside the support trench along the route until the trench meets the laying conditions.
[0024] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.
[0025] The preferred embodiments of this patent have been described in detail above. However, this patent is not limited to the above embodiments. Within the scope of knowledge possessed by those skilled in the art, various changes can be made without departing from the spirit of this patent.
Claims
1. A subsea trench sludge removal device, comprising a base plate (1), characterized in that: Two support frames (2) are provided above the base plate (1). The two support frames (2) are V-shaped and their openings face each other. The two support frames (2) are distributed on both sides of the base plate (1). The bottom end of the support frame (2) is fixedly connected to the base plate (1). A connecting pipe (3) is provided above the base plate (1). A mud discharge pipe (4) is fixedly connected to the top end of the connecting pipe (3). The mud discharge pipe (4) and the connecting pipe (3) are T-shaped. The top end of the support frame (2) is connected to the mud discharge pipe (4). A reinforcing rib (5) is fixedly connected to the middle of the support frame (2). The reinforcing rib (5) is designed with an inclination and its other end is connected to the mud discharge pipe (4). Two mud discharge ports (6) are opened at both ends of the mud discharge pipe (4).
2. The subsea trench sludge removal equipment according to claim 1, characterized in that: A support base (7) is fixedly connected above the base plate (1). There are three support bases (7), which are distributed at the three equal division points of the base plate (1).
3. The subsea trench sludge removal equipment according to claim 2, characterized in that: A slurry pump (8) is fixedly connected above the support base (7), and three conveying pipes (9) are fixedly connected evenly and at equal intervals on the outer wall of the connecting pipe (3).
4. The subsea trench sludge removal device according to claim 3, characterized in that: Two suction pipes (10) are symmetrically fixedly connected to the outer wall of the conveying pipe (9), and a connecting flange (11) is fixedly connected to the bottom end of the conveying pipe (9).
5. The subsea trench sludge removal device according to claim 4, characterized in that: The conveying end of the slurry pump (8) is connected to the conveying pipe (9) through the connecting flange (11), and two lifting lugs (12) are symmetrically fixedly connected above the sludge discharge pipe (4).
6. The subsea trench sludge removal device according to claim 3, characterized in that: The support frame (2) is made of high-strength alloy steel, and the outer shell of the slurry pump (8) is made of wear-resistant and corrosion-resistant cast iron.