A structural layering corbelled sleeve node

By combining clamps and corbel connectors, rapid connection of precast beams and columns is achieved, solving the problems of complex and time-consuming joints in existing steel structures, improving connection reliability and seismic performance, and making it suitable for various joint types, meeting the requirements of green building.

CN225014322UActive Publication Date: 2026-11-24CHINA RAILWAY 21ST BUREAU GRP SECOND ENG CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202522796984.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-30
Publication Date
2026-11-24
Estimated Expiration
2035-12-30

AI Technical Summary

Technical Problem

Existing prefabricated building steel structure node connections are complex, have poor corrosion and fire resistance, consume time and affect construction efficiency, and traditional beam-column connections require on-site construction operations such as formwork erection and rebar tying.

Method used

The precast concrete beams and H-shaped steel column beams are connected by a clamp and corbel connection structure using corbel connectors, C-type connectors and high-strength bolt groups, avoiding on-site formwork and rebar binding, and using tie bolts to achieve rapid connection.

Benefits of technology

It simplifies the construction process, improves connection reliability and seismic performance, reduces material costs, reduces construction difficulty and time, is applicable to various node types, and meets green building requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014322U_ABST
    Figure CN225014322U_ABST
Patent Text Reader

Abstract

This utility model discloses a corbel-type sleeve joint for structural addition, relating to the field of building steel structure engineering technology. It includes: a precast concrete column, an H-shaped steel column beam, a sleeve, and a connecting mechanism. The outer wall of the precast concrete column is fitted with a sleeve, and H-shaped steel column beams are distributed circumferentially on the outer side of the sleeve. The H-shaped steel column beams are fixedly connected to the precast concrete column through the connecting mechanism. This utility model eliminates the need for formwork erection and rebar tying in the beam-column connection joint area, thus solving the defects of traditional beam-column connection joints that require on-site formwork erection and rebar tying, which are time-consuming and affect construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of building steel structure engineering technology, specifically to a bracket-type hoop joint for structural addition. Background Technology

[0002] Currently, most prefabricated buildings are constructed using concrete, steel, or wood structures. Compared to concrete structures, prefabricated steel structures are generally more complex and have poor corrosion and fire resistance, resulting in lower economic efficiency. For example, Chinese patent document CN214402141U discloses a prefabricated steel beam-column connection node. This node includes multiple end plates with bolt holes, stiffening ribs, H-shaped steel beams, and H-shaped steel columns connected by bolts. However, the node structure is complex, uses a large amount of steel, and is susceptible to external corrosion if left unprotected for extended periods. Existing prefabricated concrete structure connections are mostly welded or bolted. Welding requires calculation and analysis of strength, fatigue, and weld requirements before on-site welding, leading to problems such as complex stress at the weld, increased stress, and impaired fatigue characteristics. Existing column-beam joints typically use cast-in-place methods, requiring on-site formwork erection and rebar tying in the joint area. After the concrete poured into the joint area reaches the required strength, the formwork and supports must be removed, which is time-consuming and impacts construction efficiency. Therefore, a method for using corbel-type sleeve joints in structural additions is needed to solve the above-mentioned technical problems. Utility Model Content

[0003] In view of this, this utility model provides a corbel-type clamp joint for structural additions. The clamps connect and fix precast columns and beams, eliminating the need for formwork erection and rebar tying at the beam-column connection area. This solves the problem of traditional beam-column connection joints requiring on-site formwork erection and rebar tying, which is time-consuming and affects construction timeliness. The precast concrete beams and connectors are prefabricated in the factory; on-site assembly only requires connecting the components with tie bolts, minimizing on-site wet work, saving manpower and resources, increasing production speed, and meeting the requirements of green building. The tie bolt connection not only simplifies construction and allows for easy replacement, but also ensures the quality of the connection, withstands dynamic loads, and improves the overall structural integrity.

[0004] To achieve the above objectives, the present invention adopts the following technical solution: A bracket-type ferrule joint for structural addition includes: a precast concrete column, an H-shaped steel column beam, a ferrule, and a connecting mechanism. The outer wall of the precast concrete column is fitted with a ferrule, and H-shaped steel column beams are distributed circumferentially on the outer side of the ferrule. The H-shaped steel column beams are fixedly connected to the precast concrete column through the connecting mechanism.

[0005] Furthermore, the connecting mechanism includes a bracket connector, a C-type connector, a high-strength bolt group, a common bolt group, and tie bolts. The bracket connector is located at the lower end of the H-shaped steel column beam, and the C-type connector is located in the grooves on both sides of the H-shaped steel column beam. Both the bracket connector and the C-type connector are bolted to the H-shaped steel column beam via the high-strength bolt group. The tie bolts pass through the sleeve and the H-shaped steel column beam in sequence and are bolted to the C-type connector. The C-type connector is also bolted to the bracket connector via the common bolt group.

[0006] Furthermore, the upper plate, side plate, and lower plate of the C-type connector are all provided with bolt holes. The upper plate of the C-type connector is bolted to the bracket connector by a group of ordinary bolts. The side plate of the C-type connector is bolted to the H-shaped steel column beam by tie bolts. The lower plate of the C-type connector is bolted to the bracket connector by a group of high-strength bolts.

[0007] Furthermore, the top of the bracket connector is provided with a reserved hole, which corresponds to the bolt hole on the lower plate of the C-shaped connector.

[0008] Furthermore, the sleeve has insertion holes distributed around its perimeter, and these insertion holes correspond to the bolt holes on the side plate of the C-type connector.

[0009] The beneficial effects of this utility model are as follows: 1. The corbel structure provides better bending and shear resistance, improves the reliability of the connection between the concrete column and the steel beam, eliminates the need for a large number of bolts and tie rods, reduces the construction difficulty of large cantilever steel beams, and can be used for the construction of cantilever steel beams with a cantilever length of 4m and above. 2. The bracket connector can be prefabricated, which reduces the difficulty of on-site process control and facilitates improved construction quality; it avoids quality defects caused by improper pre-embedded parts and the need for rework such as rebar reinforcement later. 3. Materials are readily available, avoiding the use of complex and expensive special building materials, thus achieving material conservation and reducing the adverse effects of production, transportation and construction, which is conducive to the manufacture of environmentally friendly green buildings.

[0010] 4. The hoop structure can effectively reduce costs and increase efficiency, as well as achieve rapid and effective connection. It can also effectively reduce on-site wet work, so that the load-bearing column has the characteristics of low cost of concrete components and superior seismic performance and convenient node connection of steel components.

[0011] 5. This node avoids a large number of destructive operations such as rebar installation and hole drilling, and mainly relies on friction to transmit force, making it safe and reliable.

[0012] 6. Widely applicable to various types of node configurations. Through the coordinated work of the clamp-bracket connector-C-type connector, the force transmission path is clear, and the node stiffness and strength are high. Attached Figure Description

[0013] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on the provided drawings without creative effort.

[0014] Figure 1 This is a schematic diagram of the overall structure of this utility model; Figure 2 This is the front view of the present invention; Figure 3 This is a top view of the present invention; Figure 4 This is an exploded view of the overall structure of this utility model; Figure 5 A schematic diagram of the overall structure of the bracket connector; In the figure: 1-H-shaped steel column beam; 2-Precast concrete column; 3-Corner connector; 4-High-strength bolt group; 5-Bolt hole; 6-C-type connector; 7-Ordinary bolt group; 8-Cuff; 9-Tie bolt. Detailed Implementation

[0015] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0016] Please see the appendix Figure 1-5 This utility model provides a corbel-type sleeve joint for structural addition, including: a precast concrete column 2, an H-shaped steel column beam 1, a sleeve 8, and a connecting mechanism. The outer wall of the precast concrete column 2 is fitted with a sleeve 8, and H-shaped steel column beams 1 are distributed circumferentially on the outer side of the sleeve 8. The H-shaped steel column beams 1 are fixedly connected to the precast concrete column 2 through the connecting mechanism.

[0017] Preferably, the connecting mechanism includes a bracket connector 3, a C-type connector 6, a high-strength bolt group 4, a common bolt group 7, and a tie bolt 9. The bracket connector 3 is located at the lower end of the H-shaped steel column beam 1, and the C-type connector 6 is located in the grooves on both sides of the H-shaped steel column beam 1. Both the bracket connector 3 and the C-type connector 6 are bolted to the H-shaped steel column beam 1 by the high-strength bolt group 4. The tie bolt 9 passes through the sleeve 8 and the H-shaped steel column beam 1 in sequence and is bolted to the C-type connector 6. The C-type connector 6 is also bolted to the bracket connector 3 by the common bolt group 7.

[0018] Preferably, the upper plate, side plate and lower plate of the C-type connector 6 are all provided with bolt holes 5. The upper plate of the C-type connector 6 is bolted to the bracket connector 3 by ordinary bolt group 7. The side plate of the C-type connector 6 is bolted to the H-shaped steel column beam 1 by tie bolts 9. The lower plate of the C-type connector 6 is bolted to the bracket connector 3 by high-strength bolt group 4.

[0019] There is no need to erect formwork (erecting formwork requires supporting columns to support the formwork) or tie reinforcing bars in the beam-column connection area, thus solving the problem of time-consuming and time-consuming construction that traditional beam-column connection nodes require on-site erection of formwork and tying of reinforcing bars.

[0020] Preferably, the top end of the bracket connector 3 is provided with a reserved hole, which corresponds to the bolt hole 5 on the lower plate of the C-type connector 6.

[0021] Preferably, the sleeve 8 has insertion holes distributed around its four sides, and the insertion holes correspond to the bolt holes 5 on the side plate of the C-type connector 6.

[0022] When the H-shaped steel column beam 1 is placed on the precast concrete column 2 through the corbel connector 3, and the H-shaped steel column beam 1 is locked to the corbel connector 3 through the sleeve 8, C-type connector 6, and C-type connector 6, the connection between the beam and the column can be completed before the concrete hardens to the required level. This greatly improves the connection performance between the corbel connector 3 and the precast concrete column 2, thereby improving the seismic performance of the beam and column.

[0023] The specific construction method of this utility model includes the following steps: Step 1: Accurately measure the precast concrete column to determine its actual cross-sectional dimensions, verticality, and concrete strength.

[0024] According to the design drawings, all node components are precision prefabricated in the factory, including clamps 8, bracket connectors 3, C-type connectors 6, and the required high-strength bolt groups 4 and ordinary bolt groups 7. All bolt holes (reserved holes or insertion holes) are formed in one go using a CNC machine tool to ensure hole position accuracy. The surface of the original structural column where the node is to be installed is cleaned, the plaster layer is removed down to the structural base surface, and leveling is performed to ensure full contact between the clamps and the column surface.

[0025] Step 2: Based on the design elevation, accurately lay out the installation position line of the sleeve 8 on the precast concrete column 2. Use temporary support devices (such as jacks and clamps) to initially fix the lower half of the sleeve 8 at the design elevation. Then install the upper half of the sleeve 8, closing the combined sleeve 8 to cover the precast concrete column 2, and insert some temporary bolts to initially correct the node position;

[0026] Step 3: Hoist the bracket connector 3 to the designed elevation position so that it is tightly attached to the corresponding connection surface of the sleeve 8.

[0027] Install the C-type connector 6, welding or bolting one side to the web of the corbel connector 3, and ensuring a tight fit between the other side and the outer surface of the sleeve 8. This step is crucial for ensuring the corbel's load-bearing capacity, guaranteeing that the load is effectively transferred from the corbel to the sleeve through the stiffening ribs.

[0028] Step 4: Insert all the high-strength bolt groups 4 and ordinary bolt groups 7 as specified in the design. Using a dedicated torque wrench or electric wrench, perform initial and final tightening of the high-strength bolt groups 4 and ordinary bolt groups 7 according to the principle of symmetry and sequence, to achieve the preload value required by the design, so that a large frictional force is generated between the sleeve 8 and the precast concrete column 2, forming the core force transmission mechanism. After all bolts are tightened, remove the temporary fixing device.

[0029] Step 5: Hoist the newly added H-shaped steel column beam 1 into place, with its end supported on the corbel connector 3. Reliably connect the H-shaped steel column beam 1 to the corbel connector 3 using welding or bolting to complete the installation of the entire node.

[0030] Step 6: Reapply the anti-corrosion coating to the welds and areas damaged during transportation and installation to ensure the continuity and integrity of the anti-corrosion system. Inspect the bolt torque, weld quality, and final elevation and location of the joints.

[0031] The various embodiments in this specification are described in a progressive manner, with each embodiment focusing on its differences from other embodiments. Similar or identical parts between embodiments can be referred to interchangeably. For the apparatus disclosed in the embodiments, since they correspond to the methods disclosed in the embodiments, the description is relatively simple; relevant parts can be referred to the method section.

[0032] The above description of the disclosed embodiments enables those skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention is not to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A type of corbel-shaped hoop joint for structural layer addition, characterized in that, include: The precast concrete column (2), H-shaped steel column beam (1), sleeve (8) and connecting mechanism are provided. The outer wall of the precast concrete column (2) is fitted with sleeve (8). H-shaped steel column beam (1) is distributed circumferentially on the outer side of the sleeve (8). The H-shaped steel column beam (1) is fixedly connected to the precast concrete column (2) through the connecting mechanism.

2. A bracket-type hoop joint for structural layer addition according to claim 1, characterized in that, The connecting mechanism includes a bracket connector (3), a C-type connector (6), a high-strength bolt group (4), a common bolt group (7), and a tie bolt (9). The bracket connector (3) is located at the lower end of the H-shaped steel column beam (1), and the C-type connector (6) is located in the grooves on both sides of the H-shaped steel column beam (1). Both the bracket connector (3) and the C-type connector (6) are bolted to the H-shaped steel column beam (1) through the high-strength bolt group (4). The tie bolt (9) passes through the sleeve (8) and the H-shaped steel column beam (1) in sequence and is bolted to the C-type connector (6). The C-type connector (6) is also bolted to the bracket connector (3) through the common bolt group (7).

3. A bracket-type hoop joint for structural layering according to claim 2, characterized in that, The upper plate, side plate and lower plate of the C-type connector (6) are all provided with bolt holes (5). The upper plate of the C-type connector (6) is bolted to the bracket connector (3) by ordinary bolt group (7). The side plate of the C-type connector (6) is bolted to the H-shaped steel column beam (1) by tie bolts (9). The lower plate of the C-type connector (6) is bolted to the bracket connector (3) by high-strength bolt group (4).

4. A bracket-type hoop joint for structural layer addition according to claim 3, characterized in that, The top of the bracket connector (3) is provided with a reserved hole, which corresponds to the bolt hole (5) on the lower plate of the C-type connector (6).

5. A bracket-type hoop joint for structural layering according to claim 3, characterized in that, The sleeve (8) has insertion holes distributed around its perimeter, and the insertion holes correspond to the bolt holes (5) on the side plate of the C-type connector (6).

Citation Information

Patent Citations

  • Fabricated steel beam column connecting joint

    CN214402141U