Basement outer waterproof structure
By using a recycled soil layer and sloping design made from construction waste around the basement exterior walls, combined with a flexible waterproof layer and blind drain system, the problem of single and environmentally unfriendly waterproofing measures for basement exterior walls is solved. This achieves a comprehensive effect of efficient waterproofing, water insulation, and water drainage, improving waterproofing reliability and environmental benefits.
Patent Information
- Application Number
- CN202522814258.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-30
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-30
AI Technical Summary
Existing waterproofing measures for basement exterior walls are simplistic, easily affected by backfill quality, and structural deformation can lead to waterproofing failure. Furthermore, they are not environmentally friendly.
It adopts a layered filling of recycled soil from construction waste, combined with slope design, flexible waterproof layer and blind ditch drainage system, integrating the functions of prevention, isolation and drainage, and actively reducing soil water pressure.
It significantly improves waterproofing reliability, extends the life of the waterproofing layer, reduces the risk of wall deformation and leakage, achieves resource recycling, and conforms to the green and low-carbon concept.
Smart Images

Figure CN225014364U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building waterproofing engineering technology, and in particular to an external waterproofing structure for basements. Background Technology
[0002] Waterproofing of underground engineering projects is crucial to ensuring the durability, safety, and functionality of buildings. Currently, basement exterior wall waterproofing mainly relies on applying single barrier materials such as waterproof membranes or coatings to the exterior of the wall structure, with design selection based on relevant national standards. However, existing technologies have the following significant drawbacks in practice:
[0003] 1. Waterproofing measures are simplistic and passive: Traditional methods only focus on setting up a "waterproof" layer on the structure itself, without systematically considering the "isolation" and "drainage" of surrounding environmental water (surface water and groundwater). Once the main waterproof layer is damaged due to construction defects, material aging, or structural deformation, leakage is very likely to occur.
[0004] 2. Uncontrolled Backfill Quality Creates Water Collection Channels: Although regulations require backfill to be compacted in layers, in actual projects, inadequate supervision often leads to the use of substandard soil or construction waste for disorderly backfilling, resulting in insufficient compaction. This causes the "deep trench" area between the basement and the foundation pit sidewall to become a loose water collection channel, where surface water and groundwater accumulate, creating long-term hydrostatic pressure on the basement exterior walls, far exceeding design conditions, and subsequently inducing wall cracking and waterproofing layer failure.
[0005] 3. Structural deformation leading to waterproofing failure: Current waterproofing designs are mostly based on the assumption of rigid walls. In reality, basement exterior walls will deform under the soil-water pressure generated by the surrounding soil (especially saturated soil). This deformation may not only cause cracks in the concrete walls, but also cause the flexible waterproofing materials such as membranes and coatings attached to them to break or detach due to excessive stretching, leading to the overall failure of the waterproofing system.
[0006] 4. Resource waste and environmental issues: Traditional backfilling often uses purchased raw soil, which does not make full use of the large amount of construction waste (such as waste concrete and bricks) generated by the project itself or the city, and does not conform to the concept of green and low-carbon building development.
[0007] Therefore, there is an urgent need for a basement exterior waterproofing structure that can combine "prevention, isolation, and drainage," actively reduce water pressure around the wall, improve system reliability, and also have environmental benefits. Utility Model Content
[0008] In view of this, the purpose of this utility model is to provide an external waterproof structure for basements, which overcomes the shortcomings of existing basement waterproofing technologies, such as single measures, susceptibility to backfill quality, passive waterproofing failure, and lack of environmental friendliness. It provides a green and environmentally friendly basement waterproof structure that integrates waterproofing, water-proofing, and water-draining functions and utilizes building waste.
[0009] The basement external waterproofing structure of this utility model includes:
[0010] The basement exterior walls are lined with a waterproof material layer on the outside.
[0011] The backfill area, located between the basement exterior wall and the foundation pit sidewall, is filled with a layer of recycled construction waste soil, which is vertically divided into multiple backfill layers; the upper surface of each backfill layer is constructed as a slope.
[0012] Furthermore, the slope of the ramp is not less than 1‰, and the ramp gradually decreases from the side closest to the basement exterior wall to the side away from the basement exterior wall, and a waterproof layer is laid on the upper surface of each ramp.
[0013] Furthermore, the recycled construction waste mixed soil layer is composed of crushed waste construction aggregate and plain soil in a volume ratio of 2:8 to 4:6. The waste construction aggregate includes at least one of waste concrete, waste bricks and stones and waste bricks and tiles, and the maximum particle size of the aggregate in the recycled construction waste mixed soil does not exceed 100mm, and its gradation coefficient satisfies Cu≥5 and 1≤Cc≤3.
[0014] Furthermore, the vertical spacing between two adjacent backfill layers is 1.5m to 6.0m.
[0015] Furthermore, the waterproof layer is a flexible waterproof material or a clay layer. When the waterproof layer is a clay layer, its thickness is not less than 200 mm and its permeability coefficient is less than 10-7 cm / s.
[0016] Furthermore, it also includes a drainage system comprising blind drains and drainage pipes. The blind drains are laid at the top of each slope and above the waterproof layer, and the drainage pipes are connected to the blind drains for draining water from the blind drains.
[0017] Furthermore, the permeability coefficient of the blind drain is not lower than that of the graded sand and gravel.
[0018] Furthermore, the horizontal distance between the centerline of the blind drain and the outer surface of the basement exterior wall is no more than 300mm.
[0019] Furthermore, the interior of the blind drain is filled with graded crushed stone and / or graded sand and gravel, and / or the exterior of the blind drain is wrapped with geotextile.
[0020] Furthermore, the drainage pipe is connected to at least one of the following: an indoor drainage ditch located inside the building, an outdoor drainage ditch located outside the building, or a municipal drainage network.
[0021] The beneficial effects of this utility model are as follows: The basement exterior waterproofing structure of this utility model significantly improves waterproofing reliability through a systematic design that integrates "prevention, isolation, and drainage." It uses recycled soil from construction waste as backfill material, combined with layered slopes, waterproof layers, and blind drains, which actively guide and drain groundwater, effectively reducing the soil moisture content and hydrostatic pressure around the basement exterior walls. This reduces the risk of wall deformation and cracking, protecting the main structure. It not only fundamentally improves backfill quality and eliminates water collection channels in the trench, but also provides a more favorable working environment for the exterior waterproofing layer, extending its service life. Furthermore, this application utilizes a large amount of construction waste, conforming to the green and low-carbon concept. It is convenient to construct and has significant economic benefits throughout its entire life cycle, achieving an organic unity of technical reliability, environmental benefits, and economic benefits. Attached Figure Description
[0022] The present invention will be further described below with reference to the accompanying drawings and embodiments:
[0023] Figure 1 This is a cross-sectional schematic diagram of the present invention;
[0024] Figure 2 This is a schematic diagram of the drainage structure of this utility model.
[0025] Explanation of reference numerals in the attached drawings: 1. Basement exterior wall; 2. Waterproof material layer; 3. Excavation pit sidewall; 4. Recycled soil layer from construction waste; 5. Slope; 6. Blind drain; 7. Drainage pipe; 8. Drainage ditch. Detailed Implementation
[0026] It should be noted that in the description of this specification, the terms "upper", "lower", "top", "bottom", "inner", "outer", "axial", "radial", "circumferential", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model.
[0027] Figure 1 This is a cross-sectional schematic diagram of the present invention. Figure 2 This is a schematic diagram of the drainage structure of this utility model, as shown in the figure: The basement external waterproofing structure of this embodiment includes:
[0028] The basement exterior wall 1 is pre-installed with a continuous and complete waterproof material layer 2 on its outer side during construction. This layer serves as the first barrier to effectively prevent groundwater infiltration.
[0029] The backfill area is located between the basement exterior wall 1 and the excavated foundation pit sidewall 3. The backfill area is filled with a mixed soil layer 4 made from recycled construction waste, which not only realizes the recycling of resources but also improves the engineering performance of the backfill. At the same time, the mixed soil layer is planned to be divided into multiple backfill layers with controllable thickness in the vertical direction to optimize the compaction and seepage prevention effect. The upper surface of each backfill layer is constructed as a slope 5 with a certain angle, that is, the slope gradually slopes upward from the foundation pit sidewall 3 away from the basement exterior wall 1 towards the basement exterior wall 1. The slope 5 helps to guide the water flow that may seep down laterally away from the wall. To ensure the drainage effect, the slope 5 has a clear lower limit, and its slope rate is not less than 1‰.
[0030] In addition, a continuous waterproof layer is laid on the surface of each backfilled and layered slope 5, thus forming multiple stepped waterproof defense lines in the vertical direction.
[0031] Furthermore, the recycled construction waste mixed soil layer 4 is composed of crushed waste construction aggregate and plain soil in a volume ratio of 2:8 to 4:6. The waste construction aggregate has a wide range of sources and may include one or more combinations of waste concrete blocks, waste bricks and stones, and waste bricks and tiles, realizing the reuse of construction waste. The maximum particle size of the aggregate shall not exceed 100mm to avoid excessively large particles causing insufficient compaction or puncturing the waterproof layer. At the same time, its particle size distribution must meet the conditions of non-uniformity coefficient Cu≥5 and curvature coefficient 1≤Cc≤3. Such gradation characteristics help to form a dense structure and reduce seepage channels.
[0032] In this embodiment, the thickness of the backfill layer (i.e., the vertical distance between two adjacent backfill layers) is controlled between 1.5 meters and 6.0 meters to ensure the reliability of the layered waterproofing effect and the overall construction efficiency.
[0033] In this embodiment, the waterproof layer is a flexible waterproof material or a clay layer. When a flexible waterproof material is selected, polymer waterproof membranes, composite geomembranes, waterproof coatings, etc. can be used. These materials have advantages such as good flexibility, strong crack resistance, and convenient construction. They can adapt to slight deformation of backfill soil and avoid cracking of the waterproof layer due to soil settlement. They are suitable for projects with complex terrain and certain deformation risks in the backfill area. When the waterproof layer is a clay layer, it is a natural waterproof material that is easy to obtain and has a low cost. It is suitable for areas with abundant clay resources. Its thickness is not less than 200mm. At the same time, the permeability coefficient of the clay layer is less than 10-7cm / s, which can effectively prevent groundwater from seeping into the basement exterior wall 1 through the clay layer.
[0034] In this embodiment, a drainage system is also included, comprising blind drains 6 and drainage pipes 7. The blind drains 6 are laid at the top of each slope 5 (i.e., the higher side near the basement exterior wall 1) and are located above the waterproof layer of that layer, for collecting water that permeates through the upper soil or flows down along the interface of the waterproof layer. The drainage pipes 7 are connected to the blind drains 6 of each layer, forming an effective water collection network, responsible for timely draining the water collected in the blind drains 6 to prevent water accumulation.
[0035] In this embodiment, to ensure that the drainage efficiency of blind ditch 6 is higher than that of the surrounding backfill soil, the permeability coefficient of blind ditch 6 itself (including its filler) shall not be lower than that of the graded sand and gravel of the recycled construction waste mixed soil layer 4, so as to ensure that water can flow into blind ditch 6 quickly instead of lingering around it.
[0036] In this embodiment, the horizontal distance between the centerline of the blind drain 6 and the outer surface of the basement exterior wall 1 is limited to no more than 300 mm. This close proximity is designed to intercept groundwater that may seep down the wall or flow laterally within the shortest path, thus maximizing the protection of the wall.
[0037] In this embodiment, the interior of the blind drain 6 is filled with graded crushed stone and / or graded sand and gravel to form a stable and unobstructed drainage channel; at the same time, in order to prevent the surrounding fine soil from intruding into the blind drain 6 and causing siltation, a permeable geotextile can also be wrapped around the outside of the blind drain 6 as a filter layer.
[0038] In this embodiment, the drainage pipe 7 needs to discharge the collected water, and its outlet end can be connected to various drainage facilities. The specific selection can be determined according to the project conditions: for example, it can be connected to an indoor drainage ditch 8 set inside the building for centralized treatment; or it can be led to an outdoor drainage ditch 8 set outside the building; or it can be directly connected to the municipal drainage network to achieve organized system discharge.
[0039] This application also discloses a construction method for an external waterproofing structure for a basement, including the following steps:
[0040] S1: Complete the main structure construction of the basement exterior wall 1 and lay a waterproof material layer 2 on its outer side;
[0041] S2: Preparation of recycled soil from construction waste;
[0042] S3: Carry out the first layer of backfill construction: Backfill the recycled soil from the construction waste to the first design elevation, compact it to form the first backfill layer, and trim the top surface of the backfill layer into a slope 5 close to the outer wall of the basement.
[0043] S4: Lay a waterproof layer on the entire upper surface of the slope 5;
[0044] S5: Lay a blind ditch 6 at the top of the slope 5 and above the waterproof layer, and connect the blind ditch 6 to the drainage pipe 7;
[0045] S6: Repeat steps S3 to S5, backfilling layer by layer upwards to form a multi-layered slope 5, lay a waterproof layer and 6 blind drain, until backfilling reaches the final design elevation.
[0046] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this utility model and are not intended to limit it. Although this utility model has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of this utility model without departing from the spirit and scope of the technical solutions of this utility model, and all such modifications or substitutions should be covered within the scope of the claims of this utility model.
Claims
1. A waterproof structure for the exterior of a basement, characterized in that, include: The basement exterior walls are lined with a waterproof material layer on the outside. The backfill area, located between the outer wall of the basement and the side wall of the foundation pit, is filled with a layer of recycled construction waste soil, which is vertically divided into multiple backfill layers. The upper surface of each backfill layer is constructed as a slope.
2. The basement external waterproofing structure according to claim 1, characterized in that: The slope of the ramp is not less than 1‰, and the ramp gradually decreases from the side closest to the basement exterior wall to the side away from the basement exterior wall. The upper surface of each ramp is covered with a waterproof layer.
3. The basement external waterproofing structure according to claim 1, characterized in that: The recycled construction waste mixed soil layer is composed of crushed waste construction aggregate and plain soil in a volume ratio of 2:8 to 4:
6. The waste construction aggregate includes at least one of waste concrete, waste bricks and stones and waste bricks and tiles, and the maximum particle size of the aggregate in the recycled construction waste mixed soil does not exceed 100mm, and its gradation coefficient satisfies Cu≥5 and 1≤Cc≤3.
4. The basement external waterproofing structure according to claim 1, characterized in that: The vertical spacing between two adjacent backfill layers is 1.5m to 6.0m.
5. The basement external waterproofing structure according to claim 2, characterized in that: The waterproof layer is a flexible waterproof material or a clay layer. When the waterproof layer is a clay layer, its thickness is not less than 200 mm and its permeability coefficient is less than 10. -7 cm / s.
6. The basement external waterproofing structure according to claim 2, characterized in that: It also includes a drainage system comprising blind drains and drainage pipes. The blind drains are laid at the top of each slope and above the waterproof layer, and the drainage pipes are connected to the blind drains for draining water from the blind drains.
7. The basement external waterproofing structure according to claim 6, characterized in that: The permeability coefficient of the blind drain is not lower than that of the graded sand and gravel.
8. The basement external waterproofing structure according to claim 6, characterized in that: The horizontal distance between the centerline of the blind drain and the outer surface of the basement exterior wall shall not exceed 300mm.
9. The basement external waterproofing structure according to claim 7, characterized in that: The blind drain is filled with graded crushed stone and / or graded sand and gravel, and / or the blind drain is wrapped with geotextile.
10. The basement external waterproofing structure according to claim 6, characterized in that: The drainage pipe is connected to at least one of the following: an indoor drainage ditch located inside the building, an outdoor drainage ditch located outside the building, or a municipal drainage network.