High-precision collaborative construction structure of fabricated prefabricated shear wall and aluminum mold system
By using pre-embedded connectors and BIM technology, the high-precision collaborative installation of precast shear walls and aluminum formwork is achieved, solving the problems of poor precision and low efficiency in high-rise building construction, improving construction quality and efficiency, and reducing costs.
Patent Information
- Application Number
- CN202522743610.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-25
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-25
AI Technical Summary
In the prefabricated construction of high-rise buildings, there are problems such as large errors in the coordination of installation accuracy between precast shear walls and aluminum alloy formwork systems, low construction efficiency, and high costs.
Precast shear walls and aluminum formwork are connected by high-strength bolts using pre-embedded connectors. BIM technology is used for integrated design and factory pre-embedding to ensure the precise positioning of the connectors and achieve high-precision collaborative installation of the precast shear walls and aluminum formwork system.
It achieves millimeter-level coordinated control of precast shear walls and aluminum formwork, eliminates independent errors, shortens the construction cycle, improves the quality of concrete pouring, and reduces the cost of measures.
Smart Images

Figure CN225014394U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of building construction technology, and specifically relates to the construction of precast shear walls and aluminum alloy formwork systems. Specifically, it is a high-precision collaborative construction structure of prefabricated shear walls and aluminum formwork systems. Background Technology
[0002] In prefabricated construction of high-rise buildings, achieving precise coordination between the installation of precast shear walls and aluminum alloy formwork systems has always been a challenge. The current mainstream construction method involves sequential operations: first, the precast shear walls are hoisted, independently adjusted and fixed using temporary support systems such as diagonal braces, and only after their position is completely stable are the external aluminum alloy formwork erected and positioned. This "wall first, formwork later" sequential process has several drawbacks, including: 1) Poor coordination accuracy: The positioning accuracy of the wall (guaranteed by temporary support) and the positioning accuracy of the aluminum formwork (guaranteed by its own support system) are two independent control systems. The cumulative error is large, which makes it easy for common quality problems such as misalignment of more than 5mm, grout leakage and honeycomb surface to appear at the splicing of the wall and the formwork.
[0003] 2) Low construction efficiency: The independent adjustment and temporary support consolidation of the wall takes a long time. The aluminum formwork team must wait for the wall working surface to be completely released before they can enter the site. The process is not tightly connected, which prolongs the construction cycle of a single layer.
[0004] 3) High cost of measures: The large number of temporary support rods and their embedded parts increases the material and labor costs of the measures. Summary of the Invention
[0005] The purpose of this invention is to solve the problems of poor coordination accuracy and loose process connection caused by the separate construction of wall formwork in the prior art, and to provide a high-precision coordinated construction structure for prefabricated shear walls and aluminum formwork systems. This node structure enables rapid and high-precision integrated installation of prefabricated shear walls and aluminum formwork systems.
[0006] This utility model is achieved through the following technical solution: A high-precision collaborative construction structure for prefabricated shear walls and aluminum formwork systems, comprising prefabricated shear walls and aluminum formwork.
[0007] Multiple sets of pre-embedded connectors are pre-embedded on the left and right sides of the precast shear wall, arranged evenly from top to bottom.
[0008] The aluminum formwork is installed at the front and rear positions on the left and right sides of the precast shear wall. The two sets of aluminum formwork on the left side are connected to the precast shear wall through multiple sets of pre-embedded connectors on the left side of the precast shear wall, and the two sets of aluminum formwork on the right side are connected to the precast shear wall through multiple sets of pre-embedded connectors on the right side of the precast shear wall.
[0009] As a preferred technical solution of this utility model, the pre-embedded connector includes two pre-embedded steel plates, which are symmetrically pre-embedded in the front and rear wall surfaces of the precast shear wall; a high-strength screw rod extending outward is fixedly connected to the pre-embedded steel plate, and two locking nuts are threadedly connected to the high-strength screw rod and two locking steel plates are slidably fitted on it, with the two locking steel plates located between the two locking nuts.
[0010] As a preferred technical solution of this utility model, the two embedded steel plates in the embedded connector are connected and fixed by a connecting beam, which is embedded in the precast shear wall.
[0011] As a preferred technical solution of this utility model, multiple sets of back ribs are installed on the aluminum template, which are evenly distributed from top to bottom. The back ribs are sandwiched between two locking steel plates and locked and fixed by two locking nuts.
[0012] As a preferred technical solution of this utility model, the back rib includes two parallel square tubes arranged at the top and bottom. The two square tubes are connected and fixed by multiple connecting ribs. The two square tubes are placed at the top and bottom of the high-strength screw, and the two square tubes are sandwiched between two locking steel plates and locked and fixed by two locking nuts.
[0013] The core of this invention is the introduction of a standardized connection node pre-embedded within the precast shear wall. This node serves as the installation benchmark and fixing point for the aluminum formwork system during the wall panel hoisting stage, thereby integrating two independent systems into a unified whole. Based on BIM technology, this invention integrates the coordinates of all pre-embedded connectors with the layout of the aluminum formwork system, the position of the back ribs, and the bolt hole positions during the design phase, ensuring that all connection points are "aligned and have consistent elevations."
[0014] This utility model is scientifically designed, structurally sound, simple to manufacture, and easy to operate. Compared with the prior art, it has the following advantages: 1) Precision Coordination: Through rigid high-strength screw connection, the position of the wall and the position of the aluminum formwork are strongly correlated, eliminating independent errors between the two systems and realizing millimeter-level (≤2mm) coordinated control, effectively preventing misalignment and grout leakage.
[0015] 2) Process optimization: Some of the positioning functions that were traditionally undertaken by temporary supports were transferred to the aluminum formwork as a permanent system, which enabled parallel and overlapping processes, shortened the critical construction period, and significantly shortened the construction cycle of a single layer.
[0016] 3) Quality improvement: The connection has good rigidity and high overall stability, resulting in a significant improvement in the quality of concrete pouring and forming.
[0017] 4) Cost savings: The number of temporary supports used and the adjustment time were reduced, thus lowering the cost of the measures. Attached Figure Description
[0018] To more clearly illustrate the technical solutions of the specific embodiments of this utility model, the accompanying drawings used in the specific embodiments will be briefly introduced below. In the drawings, the components or parts are not necessarily drawn to actual scale.
[0019] Figure 1 This is the front view of the structure of this utility model.
[0020] Figure 2 This is a top view of the structure of this utility model.
[0021] Figure 3 This is a schematic diagram of the connection of the pre-embedded connector in this utility model.
[0022] In the diagram: 1-Precast shear wall; 2-Aluminum formwork; 3-Embedded connector; 4-Embedded steel plate; 5-Connecting beam; 6-High-strength bolt; 7-Locking nut; 8-Locking steel plate; 9-Back rib; 10-Square tube; 11-Connecting bar. Detailed Implementation
[0023] The embodiments of the present utility model will now be described in detail with reference to the accompanying drawings. These embodiments are merely illustrative of the present utility model and are not intended to limit its scope of protection. It should be noted that, unless otherwise stated, the technical or scientific terms used in this application should have the ordinary meaning understood by those skilled in the art to which this utility model pertains.
[0024] like Figures 1 to 3 As shown, this embodiment provides a high-precision collaborative construction structure for prefabricated shear wall 1 and aluminum formwork system, including prefabricated shear wall 1 and aluminum formwork 2.
[0025] Multiple sets of pre-embedded connectors 3 are pre-embedded on the precast shear wall 1 near its left and right sides, arranged in a top-to-bottom order.
[0026] The embedded connector 3 includes two embedded steel plates 4, which are symmetrically embedded in the front and rear walls of the precast shear wall 1. The two embedded steel plates 4 are connected and fixed by a connecting beam 5, which is embedded in the precast shear wall 1. A high-strength screw 6 extending outward is fixedly connected to the embedded steel plate 4. Two locking nuts 7 are threadedly connected to the high-strength screw 6, and two locking steel plates 8 are slidably fitted on the high-strength screw 6. The two locking steel plates 8 are located between the two locking nuts 7.
[0027] Aluminum formwork 2 is installed at the front and rear positions on the left and right sides of the precast shear wall 1. The two sets of aluminum formwork 2 on the left side are connected to the precast shear wall 1 through multiple sets of pre-embedded connectors 3 on the left side of the precast shear wall 1. The two sets of aluminum formwork 2 on the right side are connected to the precast shear wall 1 through multiple sets of pre-embedded connectors 3 on the right side of the precast shear wall 1. The aluminum formwork 2 and the precast shear wall 1 are connected and fitted together at the connection point.
[0028] Multiple sets of back ribs 9 are installed on the aluminum template 2, arranged evenly from top to bottom. The back ribs 9 are sandwiched between two locking steel plates 8 and locked and fixed by two locking nuts 7.
[0029] The back rib 9 includes two parallel square tubes 10, which are connected and fixed by multiple connecting ribs 11. The two square tubes 10 are placed above and below the high-strength screw 6, and are sandwiched between two locking steel plates 8 and locked and fixed by two locking nuts 7.
[0030] The high-precision collaborative construction structure of the prefabricated shear wall and aluminum formwork system described in this embodiment uses the pre-embedded connector 3 embedded in the prefabricated shear wall 1 as a reference point. After the prefabricated shear wall 1 is initially hoisted into place, the aluminum formwork system and the prefabricated shear wall 1 are immediately rigidly connected at multiple points by high-strength screws 6 and nuts, so that the two are mutually constrained and precisely positioned in three-dimensional space.
[0031] The high-precision collaborative construction structure of the prefabricated shear wall and aluminum formwork system described in this embodiment includes the following steps in its construction process: 1) Integrated design stage: Using BIM, based on the aluminum formwork system assembly scheme, accurately locate the position of the embedded connector 3 in the detailed drawing of the precast shear wall 1 (three-dimensional coordinate error ≤ 2mm), and design the corresponding connection hole or installation seam on the back rib 9 of the aluminum formwork 2. In this embodiment, the back rib 9 is composed of two square tubes 10, and the gap between them is the installation seam connected to the embedded connector 3.
[0032] 2) Factory pre-embedded stage: During the production of precast shear wall 1, the pre-embedded connector 3 is strictly fixed in the mold according to the BIM coordinates to ensure accurate positioning after pouring.
[0033] 3) On-site collaborative installation phase: a. Hoisting and initially positioning the precast shear wall 1.
[0034] b. The installer then operates by attaching the aluminum formwork 2 to the wall surface of the precast shear wall 1 at the corresponding position, and inserting the installation seam on the back rib 9 of the aluminum formwork 2 into the fastening screw of the pre-embedded connector 3, with two locking steel plates 8 sandwiched on both sides of the back rib 9.
[0035] c. Use a torque wrench to tighten the locking nut 7 to the specified torque (e.g., 400-500 N·m), thereby locking the two locking steel plates 8 and the back rib 9; at this time, the precast shear wall 1 and the aluminum formwork system have formed a whole.
[0036] d. Based on the first batch of collaborative nodes, quickly improve the aluminum formwork system on both sides of the wall panel, and simultaneously install the necessary traditional diagonal bracing to increase safety redundancy.
[0037] e. Subsequent work, such as concrete pouring, will proceed according to the normal procedures.
[0038] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this utility model, and not to limit it; although the utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features; and these modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of this utility model, and they should all be covered within the scope of the claims and specification of this utility model.
Claims
1. A high-precision collaborative construction structure for prefabricated shear walls and aluminum formwork systems, comprising prefabricated shear walls and aluminum formwork, characterized in that: Multiple sets of pre-embedded connectors are pre-embedded near the left and right sides of the precast shear wall, arranged evenly from top to bottom. The embedded connector includes two embedded steel plates, which are symmetrically embedded in the front and rear walls of the precast shear wall. High-strength screw rods extending outward are fixedly connected to the embedded steel plates. Two locking nuts are threaded onto the high-strength screw rods, and two locking steel plates are slidably fitted onto them. The two locking steel plates are located between the two locking nuts. The two embedded steel plates in the embedded connector are connected and fixed by a connecting beam, which is embedded in the precast shear wall. The aluminum formwork is installed at the front and rear positions on the left and right sides of the precast shear wall. The two sets of aluminum formwork on the left side are connected to the precast shear wall through multiple sets of pre-embedded connectors on the left side of the precast shear wall, and the two sets of aluminum formwork on the right side are connected to the precast shear wall through multiple sets of pre-embedded connectors on the right side of the precast shear wall.
2. The high-precision collaborative construction structure of the prefabricated shear wall and aluminum formwork system according to claim 1, characterized in that: Multiple sets of back ribs are installed on the aluminum formwork, arranged evenly from top to bottom. The back ribs are sandwiched between two locking steel plates and locked in place by two locking nuts.
3. The high-precision collaborative construction structure of the prefabricated shear wall and aluminum formwork system according to claim 2, characterized in that: The back rib consists of two parallel square tubes, which are connected and fixed by multiple connecting ribs. The two square tubes are placed above and below the high-strength screw, and are sandwiched between two locking steel plates and locked and fixed by two locking nuts.