Compensated compartmented joint structure for basement floor
By introducing a concrete layer, a corundum wear-resistant layer, an interface agent layer, and an induced joint into the floor compartment joint structure, combined with intelligent sensors and a sprinkler system, the stress control and intelligent monitoring problems of the floor structure are solved, achieving high impermeability, high crack resistance, and high durability, thus improving the overall performance of the floor system.
Patent Information
- Application Number
- CN202522789300.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-29
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-29
AI Technical Summary
The existing floor slab compartment joint structure lacks an active stress guidance mechanism, which cannot effectively control shrinkage and temperature stress, resulting in a high risk of disordered cracks. Furthermore, it lacks an integrated intelligent monitoring and maintenance system, resulting in insufficient impermeability and durability, and making it prone to hollowing and delamination.
The system combines a concrete layer, a corundum wear-resistant layer, an interface agent layer, induced joints, and expansion joints. It also incorporates environmental sensors, stress sensors, and spray nozzles for intelligent monitoring. A nano-composite silicate curing agent is used to form a silica gel network, which enhances interlayer adhesion and impermeability.
It achieves active stress guidance, intelligent monitoring, and high impermeability, crack resistance, and durability of the flooring system, effectively avoiding disordered cracks, preventing hollowing and delamination, and improving overall performance.
Smart Images

Figure CN225014539U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of building engineering technology, specifically relating to a basement floor compensation compartment joint structure. Background Technology
[0002] Construction engineering refers to the process of constructing various buildings, roads, bridges, tunnels, and other engineering entities according to design requirements through a series of technical and management activities such as surveying, design, construction, and supervision. It includes not only the preliminary planning and design, but more importantly, the on-site construction, involving the collaborative work of multiple disciplines such as earthwork, foundation, structure, decoration, and equipment installation. Its ultimate goal is to form fixed assets that meet the predetermined functional requirements and safety standards, providing material space carriers for human production and life, and serving as the foundation for urban and rural construction and socio-economic development.
[0003] A review of announcement number CN207079865U reveals a floor slab compartment joint structure. This technology discloses "two floor slab bodies with a compartment joint between them. A corner protection device for the floor slab compartment joint is installed at the joint opening. This corner protection device includes two strip-shaped back plates located within the compartment joint. The upper ends of the strip-shaped back plates are bent towards their adjacent floor slab bodies to form horizontally positioned protective plates. The upper surfaces of the protective plates are flush with the upper surfaces of the floor slab bodies." On the same horizontal plane, the lower end of the strip backing plate is bent to form a fixing plate, which is inserted into the floor body. Below the two strip backing plates, a foam board extending horizontally is vertically arranged, with its upper end abutting the lower end of the two strip backing plates and its lower end flush with the lower surface of the floor body. This utility model has a simple structure, which not only ensures the free shrinkage of the floor but also protects the corners of the floor compartment joints, improving its resistance to rolling and making it less prone to damage.
[0004] While the design allows for the free shrinkage of the floor and provides protection for the corners of the floor compartment joints, improving its resistance to rolling and making it less prone to damage, the structure lacks an active stress guiding mechanism and cannot effectively control shrinkage and temperature stress, resulting in a higher risk of disordered cracks. Secondly, the structure does not integrate an intelligent monitoring and maintenance system, and the maintenance process relies on manual labor, which cannot accurately suppress early cracking. In addition, it does not involve surface curing treatment, resulting in insufficient impermeability and durability. Finally, it does not use micro-expansion agents and interface agents to enhance interlayer adhesion, making it prone to problems such as delamination and peeling.
[0005] To address the aforementioned issues, this application proposes a basement floor compensation compartment joint structure. Utility Model Content
[0006] To address the problems mentioned in the background section, this invention provides a compensating compartmentalized joint structure for basement flooring. By incorporating a concrete layer, a corundum wear-resistant layer, and an interface agent layer, interlayer adhesion is enhanced, preventing hollow areas and delamination. Induction joints and expansion joints actively guide and release stress, effectively avoiding disordered cracking. Intelligent monitoring and maintenance are achieved through environmental sensors, stress sensors, a data management terminal, and sprinkler heads, dynamically controlling maintenance conditions and suppressing early plastic cracking. Finally, a deep-penetrating curing agent layer forms a silica gel network, permanently sealing capillaries and achieving high impermeability, high crack resistance, and high durability. The overall structure is proactive, intelligent, and efficient, improving the comprehensive performance of the flooring system.
[0007] To achieve the above objectives, this utility model provides the following technical solution: a basement floor compensation type compartment joint structure, including a base layer and a concrete layer disposed on the base layer. The surface of the concrete layer is provided with a corundum wear-resistant layer. A curing agent layer is disposed on the surface of the concrete layer and the corundum wear-resistant layer. An interface agent layer is disposed between the concrete layer and the corundum wear-resistant layer. A stress sensor is disposed between the base layer and the concrete layer. A data management terminal is also disposed on the outside of the stress sensor.
[0008] As a preferred embodiment of the basement floor compensation compartment joint structure of this utility model, the surface of the concrete layer is provided with induced joints and expansion joints. The cutting depth of the induced joint is one-third to one-quarter of the thickness of the concrete layer, and the expansion joint runs through the entire concrete layer. The induced joint and the expansion joint are equidistantly opened on the surface of the concrete layer.
[0009] As a preferred embodiment of the basement floor compensation compartment joint structure of this utility model, the curing agent layer is a nano-composite silicate curing agent, the curing agent layer has a penetration depth of more than 3mm, and forms a silica gel network structure in the capillary pores of the concrete layer and the diamond abrasion wear-resistant layer.
[0010] As a preferred embodiment of the basement floor compensation type compartment joint structure of this utility model, the interface agent layer is a special material coated on the surface of the concrete layer, and the diamond abrasion wear-resistant layer is uniformly mixed with a micro-expansion agent.
[0011] As a preferred embodiment of the basement floor compensation compartment joint structure of this utility model, the signal of the stress sensor is connected to the data management terminal, and the data management terminal is also externally connected to an environmental sensor and a sprinkler head.
[0012] As a preferred embodiment of the basement floor compensation compartment joint structure of this utility model, the data management terminal is connected to the sprinkler head via a signal and dynamically controls the start and stop of the sprinkler head based on the data from the environmental sensor and the stress sensor.
[0013] Compared with existing technologies, the beneficial effects of this utility model are as follows: by setting a concrete layer and a corundum wear-resistant layer combined with an interface agent layer, the interlayer adhesion is enhanced, preventing hollowing and delamination; by setting induced joints and expansion joints, stress is actively guided and released, effectively avoiding disordered cracks; intelligent monitoring and maintenance are achieved through environmental sensors, stress sensors, data management terminals, and spray heads, dynamically controlling maintenance conditions and inhibiting early plastic cracking; finally, the deep penetration of the curing agent layer forms a silica gel network, permanently sealing capillaries, achieving high impermeability, high crack resistance, and high durability. The overall structure is proactive, intelligent, and efficient, improving the comprehensive performance of the flooring system. Attached Figure Description
[0014] The accompanying drawings are provided to further illustrate the present invention and form part of the specification. They are used together with the embodiments of the present invention to explain the present invention, but do not constitute a limitation thereof. In the drawings:
[0015] Figure 1 This is a schematic diagram of the overall structure of this utility model;
[0016] Figure 2 This is a schematic diagram of the environmental sensor and spray head structure in this utility model;
[0017] Figure 3 This is a schematic diagram of the concrete layer and stress sensor structure in this utility model;
[0018] Figure 4 This is a cross-sectional structural diagram of the present invention;
[0019] In the picture:
[0020] 1. Subbase; 2. Concrete layer; 3. Abrasive wear-resistant layer; 4. Curing agent layer; 5. Interface agent layer; 6. Induction joint; 7. Expansion joint; 8. Environmental sensor; 9. Stress sensor; 10. Data management terminal; 11. Sprinkler head. Detailed Implementation
[0021] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0022] Example 1
[0023] like Figure 1 As shown:
[0024] A basement floor compensation type compartment joint structure includes a base layer 1.
[0025] In this implementation plan: The existing announcement number CN207079865U discloses a floor compartment joint structure. The technical means of this will not be described in detail here. For details on the improvement of this prior art, please refer to the following disclosure. In order to solve the technical problems existing in this prior art, such as the above background disclosure, "the structure lacks an active stress guiding mechanism, cannot effectively control shrinkage and temperature stress, resulting in a high risk of disordered cracks. Secondly, the structure does not integrate an intelligent monitoring and maintenance system, and the maintenance process relies on manual labor, which cannot accurately suppress early cracking. In addition, it does not involve surface curing treatment, resulting in insufficient impermeability and durability. Finally, it does not use micro-expansion agents and interface agents to enhance interlayer bonding, which easily leads to hollow and delamination problems." In combination, this problem is obviously a real and difficult problem to solve. In view of this, in order to solve the above problems, a diamond abrasion wear-resistant layer 3 and a curing agent layer 4 are added on the basis.
[0026] Furthermore:
[0027] like Figure 1 - Figure 4 As shown:
[0028] In conjunction with the above, it also includes a concrete layer 2 set on the base layer 1, a corundum wear-resistant layer 3 on the surface of the concrete layer 2, a curing agent layer 4 on the surface of the concrete layer 2 and the corundum wear-resistant layer 3, an interface agent layer 5 between the concrete layer 2 and the corundum wear-resistant layer 3, a stress sensor 9 between the base layer 1 and the concrete layer 2, and a data management terminal 10 on the outside of the stress sensor 9.
[0029] In this implementation plan: a concrete layer 2 and a diamond abrasion wear-resistant layer 3 are set to form the main load-bearing and wear-resistant layers, an interface agent layer 5 enhances the interlayer bonding, a curing agent layer 4 provides surface curing, and a stress sensor 9 and a data management terminal 10 realize intelligent monitoring, which together improve the overall performance of the floor.
[0030] Furthermore:
[0031] In an optional embodiment, the surface of the concrete layer 2 is provided with an induction joint 6 and an expansion joint 7. The cutting depth of the induction joint 6 is one-third to one-quarter of the thickness of the concrete layer 2, and the expansion joint 7 runs through the entire concrete layer 2. The induction joint 6 and the expansion joint 7 are equidistantly provided on the surface of the concrete layer 2.
[0032] In this embodiment, by setting induced joints 6 and expansion joints 7 to actively guide and release shrinkage and temperature stress, the generation of disordered cracks is effectively avoided, and the crack resistance of the floor is improved.
[0033] Furthermore:
[0034] In an optional embodiment, the curing agent layer 4 is a nano-composite silicate curing agent, the curing agent layer 4 penetrates to a depth greater than 3 mm, and forms a silica gel network structure in the capillaries of the concrete layer 2 and the diamond abrasion wear-resistant layer 3.
[0035] In this embodiment: the curing agent layer 4 deeply penetrates to form a dense silicone gel network, permanently sealing the capillary channels and significantly improving the impermeability and durability of the floor.
[0036] Furthermore:
[0037] In an optional embodiment, the interface agent layer 5 is a special material coated on the surface of the concrete layer 2, and the diamond abrasion wear-resistant layer 3 is uniformly mixed with a micro-expansion agent.
[0038] In this embodiment: the interface agent layer 5 enhances the adhesion between the concrete layer 2 and the diamond abrasion wear-resistant layer 3, preventing hollowing and delamination, and the micro-expansion agent compensates for shrinkage, further reducing the risk of cracking.
[0039] Furthermore:
[0040] In an optional embodiment, the stress sensor 9 is connected to a signal and data management terminal 10, which is externally connected to an environmental sensor 8 and a sprinkler head 11.
[0041] In this embodiment, an intelligent monitoring system is constructed by environmental sensor 8, stress sensor 9, data management terminal 10, and spray head 11 to monitor environmental data and stress changes in real time, providing data support for precise maintenance.
[0042] Furthermore:
[0043] In an optional embodiment, the data management terminal 10 is connected to the sprinkler head 11 via a signal and dynamically controls the start and stop of the sprinkler head 11 based on data from the environmental sensor 8 and the stress sensor 9.
[0044] In this embodiment: based on the data from the environmental sensor 8 and the stress sensor 9, the data management terminal 10 dynamically controls the start and stop of the spray head 11 to achieve automated atomized curing and effectively suppress early plastic cracking.
[0045] The working principle and usage process of this utility model are as follows: First, the workers can clean, wet, and level the base layer 1 to ensure that it is solid and flat as the foundation of the entire flooring system. Then, the concrete layer 2 is poured, and the diamond abrasion wear-resistant layer 3 with built-in micro-expansion agent is constructed simultaneously. Before the initial setting of the concrete layer 2, a special interface agent is applied to its surface to form an interface agent layer 5, which enhances the adhesion with the diamond abrasion wear-resistant layer 3 and prevents hollowing and delamination. During the critical window period of 6-12 hours after the initial setting of the concrete, independent stress-regulating components are used to cut joints, forming an induction joint 6 and an expansion joint 7. This step actively guides and releases shrinkage. Shrinkage and temperature stress effectively prevent the generation of disordered cracks. During the curing stage, an independent intelligent monitoring system is activated, with environmental sensors 8 and stress sensors 9 continuously monitoring data and transmitting it to the data management terminal 10. The platform dynamically controls the spray head 11 to perform atomized curing based on the data model, inhibiting early plastic cracking. Finally, after the surface layer strength meets the standard, a nano-composite silicate curing agent is sprayed to form a curing agent layer 4. This curing agent deeply penetrates into the concrete layer 2 and the diamond abrasion wear-resistant layer 3, generating a dense silica gel network structure that permanently seals capillary pores, thereby ultimately achieving high impermeability, high crack resistance and high durability of the flooring system.
[0046] Finally, it should be noted that the above are merely preferred embodiments of this utility model and are not intended to limit the utility model. Although the utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the protection scope of this utility model.
Claims
1. A basement floor compensating compartmented joint structure comprising a foundation layer (1), characterized in that: It also includes a concrete layer (2) disposed on the base layer (1), the surface of the concrete layer (2) is provided with a diamond abrasion wear-resistant layer (3), the surfaces of the concrete layer (2) and the diamond abrasion wear-resistant layer (3) are provided with a curing agent layer (4), an interface agent layer (5) is provided between the concrete layer (2) and the diamond abrasion wear-resistant layer (3), a stress sensor (9) is provided between the base layer (1) and the concrete layer (2), and a data management terminal (10) is also provided on the outside of the stress sensor (9).
2. The basement floor compensating pocket joint structure according to claim 1, characterized by: The surface of the concrete layer (2) is provided with an induction joint (6) and an expansion joint (7). The cutting depth of the induction joint (6) is one-third to one-quarter of the thickness of the concrete layer (2). The expansion joint (7) penetrates the entire concrete layer (2). The induction joint (6) and the expansion joint (7) are equidistantly opened on the surface of the concrete layer (2).
3. The basement floor compensating pocket joint structure according to claim 1, characterized in that: The curing agent layer (4) is a nano-composite silicate curing agent. The curing agent layer (4) has a penetration depth of more than 3 mm and forms a silica gel network structure in the capillaries of the concrete layer (2) and the diamond abrasion wear-resistant layer (3).
4. The basement floor compensating pocket joint structure according to claim 1, characterized by: The interface agent layer (5) is a special material coated on the surface of the concrete layer (2), and the diamond abrasion wear-resistant layer (3) is uniformly mixed with a micro-expansion agent.
5. The basement floor compensation compartment joint structure according to claim 1, characterized in that: The stress sensor (9) is connected to the data management terminal (10) via a signal. An environmental sensor (8) and a spray head (11) are also connected to the outside of the data management terminal (10).
6. The basement floor compensation compartment joint structure according to claim 5, characterized in that: The data management terminal (10) is connected to the spray head (11) via a signal and dynamically controls the start and stop of the spray head (11) based on the data from the environmental sensor (8) and the stress sensor (9).
Citation Information
Patent Citations
Terrace divides storehouse seam structure
CN207079865U