Parabolic slope scaffold auxiliary stabilizing device

By using a parabolic inclined scaffolding auxiliary stabilization device, and by adapting the lifting control rod and adjustable rod to the angle of the flow channel inclined plane, the problem of instability at the bottom of the scaffolding in the hump structure was solved, thereby improving stability and structural durability.

CN225014571UActive Publication Date: 2026-11-24POWERCHINA MUNICIPAL CONSTR GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522742748.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-24
Publication Date
2026-11-24
Estimated Expiration
2035-12-24

AI Technical Summary

Technical Problem

In the water outlet channel of the hump structure, it is difficult for the bottom of the scaffold to remain stable on the slope, and the existing technology relies on a large number of pre-reserved steel bars, which leads to steel bar waste and concrete corrosion problems.

Method used

A parabolic inclined scaffolding auxiliary stabilization device is adopted, including an erection base and an inclined adjustment unit. Through lifting control rods, horizontal connecting rods and adjustable inclined adjustment rods, the device adapts to the angle of the flow channel inclined plane. The device uses a detachable connection structure and U-bolts to connect the pre-embedded reinforcing bars in the concrete to form a stable scaffolding erection base.

Benefits of technology

This technology enables scaffolding to remain stable without requiring a large amount of pre-reinforced steel bars, reducing steel waste and concrete corrosion, and improving construction efficiency and structural durability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014571U_ABST
    Figure CN225014571U_ABST
Patent Text Reader

Abstract

This utility model provides an auxiliary stabilization device for parabolic inclined scaffolding, relating to the field of scaffolding construction technology. This application first connects the horizontally positioned erection base to the pre-embedded concrete reinforcing bars in the base plate. Then, the base surface is leveled using an inclined adjustment unit. The lifting control rod is arranged vertically, with one end connected to a horizontal connecting rod, and the other end connected to the erection base. Simultaneously, an adjustable inclined adjustment rod is used, with its two ends connected to the bottom of the lifting control rod and the erection base respectively, to adjust the length of the inclined adjustment rod so that the erection base adapts to the inclined angle of the flow channel, ultimately forming a stable scaffolding erection base. The limiting component allows for the insertion and installation of scaffolding steel pipes. It eliminates the need for a large amount of pre-reserved reinforcing steel to maintain stability, and the adjustable structure adapts to different inclined angles, ensuring the stability of the scaffolding erection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of scaffolding construction technology, and in particular relates to an auxiliary stabilization device for parabolic inclined plane scaffolding. Background Technology

[0002] The Yangwan Pumping Station, part of the main project of the Huayang River Flood Detention Area Construction Project, consists of intake structures, intake culverts, pump houses, outlet channels, and outlet structures. The pumping station is classified as Class II, with a designed drainage flow rate of 55 m³ / s. This project employs a siphon-type hump outlet channel, composed of three parts: an ascending section, a hump section, and a descending section. A vacuum breaker valve is installed in the hump section. When the pump stops, a vacuum is created in the hump section, allowing air to flow in through the vacuum breaker valve, separating the ascending and descending sections and achieving a natural flow interruption. When the pump starts, the water level in the ascending section rises continuously until it reaches the highest point of the hump. As the water pumped by the pump accumulates in the outlet channel, the air in the channel is continuously compressed. When the pressure sensor of the vacuum breaker valve reaches a certain limit, the vacuum breaker valve is opened by the pressure inside the air passage, expelling the air. The water flowing above the highest point of the hump falls smoothly to the surface of the descending section until the air is expelled and the channel is filled with water, thus completing a full siphon process.

[0003] When erecting full-span scaffolding for the three-hole walls and top slab of the water outlet channel after the base slab was completed, the entire channel had a hump structure. The scaffolding inside the holes was spaced 60cm apart, and there was no flat foundation surface at the bottom. The entire base of the scaffolding rested on the sloping surface of the hump, making it difficult to maintain stability. Furthermore, during construction, a portion of the reinforcing steel was typically pre-installed when pouring the base slab concrete. During erection, steel pipes were inserted into the reinforcing steel to maintain stability on the slope. However, in the past, excessive rebar ends were left on the concrete surface, requiring the use of a cutting machine for removal. This was not only time-consuming and labor-intensive, but also allowed water to seep into the concrete structure over time, leading to concrete corrosion and rebar rust. Utility Model Content

[0004] In view of this, the present invention aims to provide an auxiliary stabilization device for parabolic inclined plane scaffolding to solve the above-mentioned technical problems.

[0005] To achieve the above objectives, the technical solution of this utility model is implemented as follows: This utility model provides an auxiliary stabilization device for parabolic inclined scaffolding, including an erection base and an inclined adjustment unit. The erection base is horizontally arranged and connected to pre-embedded reinforcing bars in concrete. Multiple vertically arranged limiting members are provided on the erection base, spaced apart along its length. The inclined adjustment unit includes a lifting control rod, a horizontal connecting rod, and an inclined adjustment rod. The lifting control rod is vertically arranged, with its body connected to one end of the horizontal connecting rod, and the other end connected to the erection base. The inclined adjustment rod is an adjustable rod-shaped object along its length, with one end rotatably connected to the bottom of the lifting control rod and the other end rotatably connected to the erection base.

[0006] In one embodiment, the lifting control rod is connected to one end of the transverse connecting rod via a detachable connection structure.

[0007] In one embodiment, the detachable connection structure is a snap-fit ​​connection structure, a pin connection structure, or a bolt connection structure.

[0008] In one embodiment, the detachable connection structure includes a chuck and a locking member. The chuck has a sliding hole and is slidably fitted onto the outer periphery of the lifting control rod. The chuck also has an insertion hole. The transverse connecting rod is connected to the chuck. The locking member is inserted into the insertion hole and is used to lock the relative position of the chuck and the lifting control rod.

[0009] In one embodiment, the lifting control rod is provided with multiple sets of anti-slip blocks on its body, and the multiple sets of anti-slip blocks are spaced apart along the length direction of the lifting control rod.

[0010] In one embodiment, a connecting assembly is provided between the erection base and the pre-embedded concrete reinforcing bar, the connecting assembly comprising: The U-shaped bolt has a U-shaped body that spans and fits the outer circumference of the pre-embedded concrete reinforcing bar. The two parallel threads of the U-shaped bolt are located on both sides of the pre-embedded concrete reinforcing bar. The two parallel threads pass through two corresponding through holes pre-set in the foundation. A matching nut is provided for threaded connection with the screw.

[0011] In one embodiment, the locking element is a wedge-shaped block.

[0012] In one embodiment, the erection base is a T-shaped component, the web of the T-shaped component is provided with multiple sets of through holes, the through holes are used to pass through the screw; the upper plane of the wing plate of the T-shaped component is the erection reference plane.

[0013] In one embodiment, the limiting member is a cylinder.

[0014] Beneficial effects: This utility model provides a parabolic inclined plane scaffolding auxiliary stabilization device. First, a horizontally positioned erection base is connected to pre-embedded concrete reinforcing bars in the base plate. Then, an inclined plane adjustment unit is used to level the base surface. The lifting control rod is vertically positioned, with one end connected to a horizontal connecting rod, and the other end connected to the erection base. Simultaneously, an adjustable inclined adjustment rod is used. By rotating its two ends to the bottom of the lifting control rod and the erection base respectively, the length of the inclined adjustment rod is adjusted to adapt the erection base to the inclined plane angle, ultimately forming a stable scaffolding erection base. A limiting component allows for the insertion and installation of scaffolding steel pipes. This eliminates the need for a large amount of pre-reserved reinforcing steel for stability, and the adjustable structure adapts to different inclined plane angles, ensuring the stability of the scaffolding erection. Attached Figure Description

[0015] The accompanying drawings, which form part of this utility model, are used to provide a further understanding of the utility model. The illustrative embodiments of the utility model and their descriptions are used to explain the utility model and do not constitute an undue limitation of the utility model. In the drawings: Figure 1 This is a three-dimensional structural diagram of the parabolic inclined plane scaffolding auxiliary stabilization device described in an embodiment of the present invention; Figure 2 This is a schematic diagram of the viewing structure of the parabolic inclined plane scaffolding auxiliary stabilization device described in this embodiment of the utility model; Figure 3 This is a schematic diagram of the structure of the base erection according to an embodiment of the present utility model; Figure 4 This is a schematic diagram of the chuck structure according to an embodiment of the present utility model; Figure 5 This is a schematic diagram of the structure of the U-bolt and nut described in the embodiment of this utility model.

[0016] Explanation of reference numerals in the attached figures: 1-Erecting base; 11-Web plate; 12-Wing plate; 2-Chuck; 21-Sliding hole; 22-Insertion hole; 23-Locking component; 3-Transverse connecting rod; 4-Angled adjusting rod; 5-Lifting control rod; 6-Anti-slip block; 7-Rotating shaft; 8-Limiting component; 9-Concrete embedded reinforcing bar; 10-Demountable connection structure; 101-U-bolt; 102-Nut. Detailed Implementation

[0017] It should be noted that, unless otherwise specified, the embodiments and features described in these embodiments can be combined with each other.

[0018] In the description of this utility model, it should be understood that the terms "center," "longitudinal," "lateral," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicating orientation or positional relationships based on the orientation or positional relationships shown in the accompanying drawings, are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model. Furthermore, the terms "first," "second," etc., are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Thus, features defined with "first," "second," etc., may explicitly or implicitly include one or more of that feature. In the description of this utility model, unless otherwise stated, "a plurality of" means two or more.

[0019] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0020] The following will refer to the appendix. Figure 1-5 The present invention will be described in detail with reference to the embodiments.

[0021] This utility model provides an auxiliary stabilization device for parabolic inclined plane scaffolding, as shown in the attached figure. Figure 1-2 As shown, a parabolic inclined scaffolding auxiliary stabilization device includes an erection base 1 and an inclined adjustment unit. The erection base 1 is horizontally set and connected to pre-embedded concrete reinforcing bars 9. Multiple vertically set limiting members 8 are provided on the erection base 1, and the limiting members 8 are spaced apart along the length of the erection base 1. The inclined adjustment unit includes a lifting control rod 5, a transverse connecting rod 3, and an inclined adjustment rod 4. The lifting control rod 5 is vertically set, and its body is connected to one end of the transverse connecting rod 3. The other end of the transverse connecting rod 3 is connected to the erection base 1. The inclined adjustment rod 4 is an adjustable rod-shaped object along its length, with one end rotatably connected to the bottom of the lifting control rod 5 and the other end rotatably connected to the erection base 1.

[0022] In this embodiment, the horizontally positioned scaffolding base 1 is first connected to the pre-embedded concrete reinforcing bars 9 in the base plate. Then, the base surface is leveled using an inclined adjustment unit. The lifting control rod 5 is vertically positioned, with one end connected to a horizontal connecting rod 3, and the other end connected to the scaffolding base 1. Simultaneously, an adjustable inclined adjustment rod 4 is used. By rotating its two ends to the bottom of the lifting control rod 5 and the scaffolding base 1 respectively, the length of the inclined adjustment rod 4 is adjusted to adapt the scaffolding base 1 to the inclined angle of the flow channel, ultimately forming a stable scaffolding erection base. The limiting member 8 allows for the insertion and installation of scaffolding steel pipes. This not only solves the core problem of instability when the scaffolding base is situated on a hump-shaped inclined surface, eliminating the need for extensive pre-reserved reinforcing bars to maintain stability, but also ensures the stability of the scaffolding erection by adapting to different inclined angles through an adjustable structure. Furthermore, it lays the foundation for reducing subsequent steel bar waste and structural damage.

[0023] Specifically, in combination Figure 2 Both ends of the inclined adjustment rod 4 are rotatably connected to the bottom of the lifting control rod 5 and the erection base 1 respectively through the rotating shaft 7.

[0024] Based on the above embodiments, the lifting control rod 5 is connected to one end of the transverse connecting rod 3 by a detachable connection structure 10.

[0025] The lifting control rod 5 and the horizontal connecting rod 3 are connected by a detachable connection structure 10. The two are quickly assembled during device installation. When it is necessary to adjust the device angle, perform maintenance, or disassemble and recycle, the connection between the two can be easily disconnected. The position of each component can be flexibly adjusted or disassembled for storage, which improves the flexibility of disassembly and assembly between device components. It is convenient for fine-tuning of angles and maintenance and replacement of components during construction. At the same time, it provides convenience for the recycling of the device and avoids damage to components caused by fixed connections. It further adapts to the complex construction requirements of the inclined surface of the flow channel.

[0026] Specifically, the detachable connection structure 10 can be a snap-fit ​​connection, a pin connection, or a bolt connection. Depending on the stress requirements of the flow channel construction and the on-site operating conditions, any one of these structures can be selected to connect the lifting control rod 5 and the transverse connecting rod 3. If a snap-fit ​​connection is used, quick docking and fixing are achieved by opening and closing the snap-fit. If a pin connection is used, positioning is achieved by inserting a pin into the corresponding pin hole. If a bolt connection is used, the bolt passes through both and is tightened with the nut 102 for fixation. Multiple detachable connection methods are available to adapt to different construction scenarios, allowing for flexible selection based on construction strength and ease of operation requirements. This ensures the reliability of the connection structure while also considering assembly and disassembly efficiency, avoiding the limitations of a single connection method on different construction scenarios and improving the versatility of the device.

[0027] In one embodiment, combined with Figure 1 , Figure 2 and Figure 4 The detachable connection structure 10 includes a chuck 2 and a locking element 23. The chuck 2 is provided with a sliding hole 21, and the chuck 2 is slidably sleeved on the outer periphery of the lifting control rod 5. The chuck 2 is also provided with an insertion hole 22. The transverse connecting rod 3 is connected to the chuck 2. The locking element 23 is inserted into the insertion hole 22. The locking element 23 is used to lock the relative position of the chuck 2 and the lifting control rod 5. The chuck 2 with the sliding hole 21 is slidably fitted onto the outer periphery of the lifting control rod 5, while the transverse connecting rod 3 is fixedly connected to the chuck 2. After adjusting the position of the chuck 2 on the lifting control rod 5, the locking piece 23 is inserted into the insertion hole 22 on the chuck 2 to lock and fix the relative position of the chuck 2 and the lifting control rod 5. The sliding chuck 2 enables flexible adjustment of the connection position between the lifting control rod 5 and the transverse connecting rod 3. With the locking effect of the locking piece 23, the stability of the adjusted position is ensured, and the instability of the scaffolding due to displacement of the connection position during construction is avoided. At the same time, the disassembly and assembly are convenient and adaptable to the adjustment needs of different slope angles.

[0028] Furthermore, the lifting control rod 5 is equipped with multiple sets of anti-slip blocks 6, which are spaced apart along the length of the lifting control rod 5. Utilizing these spaced-apart anti-slip blocks 6 along the length of the lifting control rod 5, when the chuck 2 slides to the corresponding position and the locking member 23 is inserted into the socket 22, it can cooperate with the anti-slip blocks 6 to further restrict the sliding of the chuck 2 and improve the locking stability. Through the synergistic effect of the anti-slip blocks 6 and the locking member 23, the anti-slip capability of the connection between the chuck 2 and the lifting control rod 5 is enhanced, preventing the chuck 2 from shifting due to the load after the scaffolding is erected. This further improves the overall stability of the device and reduces the risk of slippage and collapse of the inclined scaffolding.

[0029] Combination Figure 5 Based on the above embodiment, a connecting component is provided between the erection base 1 and the pre-embedded concrete reinforcing bar 9. The connecting component includes a U-bolt 101 and a matching nut 102. The U-shaped body of the U-bolt 101 spans and fits against the outer circumference of the pre-embedded concrete reinforcing bar 9. The two parallel screws of the U-bolt 101 are located on both sides of the pre-embedded concrete reinforcing bar 9, and the two parallel screws pass through two corresponding through holes preset in the erection base 1. The matching nut 102 is threadedly connected to the screw.

[0030] The U-shaped body of the U-bolt 101 is straddled and fitted onto the outer circumference of the pre-embedded reinforcing bar 9 in the concrete, with the two parallel threads of the U-bolt 101 positioned on either side of the pre-embedded reinforcing bar. The two threads are then passed through two corresponding through holes pre-drilled in the erection base 1. Finally, the matching nut 102 is threadedly connected to the threads and tightened, achieving a secure fixation between the erection base 1 and the pre-embedded reinforcing bar. This method not only solves the problems of cumbersome subsequent processing and structural damage caused by excessive pre-embedded reinforcing bars, but also requires only a small number of pre-embedded reinforcing bars for device fixation. The connection is firm and disassembly is convenient, reducing waste of reinforcing bar materials and preventing excessive reinforcing bar ends from corroding and carbonizing the concrete structure, thus improving structural durability.

[0031] Based on the above embodiments, the locking element 23 is a wedge-shaped block. Using a wedge-shaped block as the locking element 23, after adjusting the position of the chuck 2, the wedge-shaped block is inserted into the insertion hole 22 of the chuck 2. By striking the wedge-shaped block with a hammer, the wedge-shaped structure of the block is utilized to ensure a tight fit within the insertion hole 22, achieving reliable locking of the chuck 2 and the lifting control rod 5. The self-locking characteristic of the wedge-shaped block ensures the firmness of the lock. The striking operation is convenient and efficient, adapting to the rapid construction needs of the construction site. Furthermore, the wedge-shaped block has a simple structure, low cost, is not easily damaged, and can be reused repeatedly.

[0032] Combination Figures 1 to 3 In one embodiment, the erection base 1 is a T-shaped component. The web 11 of the T-shaped component has multiple sets of through holes for threaded rods. The upper surface of the wing plate 12 of the T-shaped component serves as the erection reference surface. Using the T-shaped component as the erection base 1, the U-bolts 101 are passed through the pre-set through holes on the web 11 of the T-shaped component and tightened with nuts 102. Simultaneously, the upper surface of the wing plate 12 of the T-shaped component serves as the reference surface for scaffolding erection, allowing scaffolding steel pipes to be directly inserted into the anti-slip steel rods on this reference surface to complete the erection. The through hole design of the web 11 of the T-shaped component can accommodate the connection requirements of pre-embedded reinforcing bars at different spacings, improving the adaptability of the device. The flat reference surface formed by the wing plate 12 solves the problem that inclined surfaces cannot provide a flat erection base surface, ensuring the standardization and stability of scaffolding erection. At the same time, the T-shaped structure has strong load-bearing capacity, effectively distributing the scaffolding load and improving the overall support reliability. Meanwhile, multiple limiting components 8 are installed on the upper surface of the wing plate 12, and steel pipes are inserted into the limiting components 8, making the installation of the scaffolding more stable.

[0033] Combination Figure 1 Specifically, the limiting member 8 is a cylinder. This allows the scaffolding to be easily inserted into the outside of the limiting member 8, preventing the scaffolding from shifting and improving safety.

[0034] The above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present utility model should be included within the protection scope of the present utility model.

Claims

1. A parabolic inclined plane scaffolding auxiliary stabilization device, characterized in that, include: A base is erected, horizontally positioned, and connected to pre-embedded reinforcing bars in concrete. Multiple vertically positioned limiting members are provided on the base, and the limiting members are spaced apart along the length of the base. The inclined adjustment unit includes a lifting control rod, a horizontal connecting rod, and an inclined adjustment rod. The lifting control rod is vertically arranged along the vertical direction, and its body is connected to one end of the horizontal connecting rod, while the other end of the horizontal connecting rod is connected to the erection base. The inclined adjustment rod is an adjustable rod-shaped object along its length, with one end rotatably connected to the bottom of the lifting control rod and the other end rotatably connected to the erection base.

2. The parabolic inclined plane scaffolding auxiliary stabilization device according to claim 1, characterized in that, The lifting control rod is connected to one end of the transverse connecting rod via a detachable connection structure.

3. The parabolic inclined plane scaffolding auxiliary stabilization device according to claim 2, characterized in that, The detachable connection structure can be a snap-fit ​​connection, a pin connection, or a bolt connection.

4. The parabolic inclined plane scaffolding auxiliary stabilization device according to claim 2, characterized in that, The detachable connection structure includes: The chuck has a sliding hole and is slidably sleeved on the outer periphery of the lifting control rod. The chuck also has an insertion hole. The transverse connecting rod is connected to the chuck. A locking element is inserted into the socket to lock the relative position of the chuck and the lifting control lever.

5. The parabolic inclined plane scaffolding auxiliary stabilization device according to claim 4, characterized in that, The lifting control rod is provided with multiple sets of anti-slip blocks, which are spaced apart along the length of the lifting control rod.

6. The parabolic inclined plane scaffolding auxiliary stabilization device according to claim 5, characterized in that, A connecting assembly is provided between the erected base and the pre-embedded concrete reinforcing bar, the connecting assembly including: The U-shaped bolt has a U-shaped body that spans and fits the outer circumference of the pre-embedded concrete reinforcing bar. The two parallel threads of the U-shaped bolt are located on both sides of the pre-embedded concrete reinforcing bar. The two parallel threads pass through two corresponding through holes pre-set in the foundation. A matching nut is provided for threaded connection with the screw.

7. The parabolic inclined plane scaffolding auxiliary stabilization device according to claim 6, characterized in that, The locking element is a wedge-shaped block.

8. The parabolic inclined plane scaffolding auxiliary stabilization device according to claim 7, characterized in that, The erection base is a T-shaped component, and the web of the T-shaped component is provided with multiple sets of through holes for inserting the screw; the upper plane of the wing plate of the T-shaped component is the erection reference plane.

9. The parabolic inclined plane scaffolding auxiliary stabilization device according to claim 8, characterized in that, The limiting component is a cylinder.