Novel flower basket pull rod type cantilever scaffold

The innovative structural design of the basket-style cantilever scaffolding solves the problems of insufficient stability and inconvenient construction of cantilever scaffolding, achieving efficient and safe construction and adapting to the needs of complex building facades.

CN225014575UActive Publication Date: 2026-11-245TH ENGINEERING LTD OF THE FIRST HIGHWAY ENGINEERING BUREAU CCCC +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522837290.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-31
Publication Date
2026-11-24
Estimated Expiration
2035-12-31

AI Technical Summary

Technical Problem

Existing cantilever scaffolding lacks stability, has limited connection strength, poses safety hazards, and is inconvenient to construct, making it difficult to adapt to complex building facades.

Method used

It adopts a basket-style tie rod structure, which is connected to the horizontal bar by double-sided fillet welds through double hanging lugs. Combined with the double limiting design of pins and pin anti-disengagement, a stable triangular force system is formed. The combination design of short steel pipes, swivel fasteners and type 3 clips and nuts enables detachable connection and adapts to different building facade sizes.

Benefits of technology

It significantly improves the wind load and lateral displacement resistance of cantilever scaffolding, simplifies the construction process, reduces construction costs, enhances structural stability and ease of assembly and disassembly, and adapts to complex building structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014575U_ABST
    Figure CN225014575U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of scaffolding technology and provides a novel basket-type cantilever scaffolding, including a wall. In this utility model, the stabilizing component is connected to the horizontal horizontal bar by double-sided fillet welds using double-ear plates, combined with a double-limiting design of pins and anti-disengagement pins, which significantly improves the connection strength between the lower pull rod and the horizontal horizontal bar. At the same time, the tension of the pull rod can be flexibly adjusted by the middle basket, so that the stabilizing component, the wall, and the scaffolding form a triangular stable force system, effectively dispersing the construction load and avoiding structural deformation caused by local stress concentration. Compared with the traditional pull rod structure, the wind load resistance and lateral displacement resistance are greatly enhanced. The installation component uses a combination design of short steel pipes, swivel couplers, and type 3 clips and nuts, so that the scaffolding can be disassembled and assembled without damaging the main building structure, greatly shortening the construction cycle and improving the turnover efficiency. It solves the drawbacks of traditional cantilever scaffolding, such as cumbersome pre-embedding and the need for structural repair after dismantling.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of scaffolding technology, and in particular to a novel flower basket tie rod type cantilever scaffolding. Background Technology

[0002] In the field of modern construction engineering, the number of high-rise buildings, large-span structures, and complex-shaped buildings is increasing. As an indispensable temporary working platform in the construction process, the safety, economy, and ease of construction of external scaffolding directly affect the project quality, construction progress, and cost control. Cantilevered scaffolding, because it does not need to be erected from the ground to the roof, can effectively solve problems such as limited space at the bottom of high-rise buildings and avoid interference from basement structures, and has become the mainstream support form for the construction of high-rise building facades.

[0003] Traditional cantilever scaffolding has significant structural design flaws, leading to inadequate stability. Existing scaffolding often uses single welds or ordinary bolts to connect tie rods and horizontal bars, resulting in limited connection strength and a lack of effective anti-detachment and restraint structures. Under complex conditions such as high-altitude wind loads and fluctuating construction loads, these connections are prone to loosening and detachment, potentially causing lateral displacement, deformation, or even collapse of the scaffolding. Furthermore, traditional structures lack a complete triangular load-bearing system, resulting in an unreasonable load transfer path, widespread localized stress concentration, and weak resistance to wind loads and lateral displacement, seriously threatening the lives of workers at height. Utility Model Content

[0004] The purpose of this invention is to solve the problems of insufficient stability and high safety risks in the existing technology.

[0005] To achieve the above objectives, this utility model adopts the following technical solution: A novel flower basket-style tie-rod type cantilever scaffold: including a wall, the novel flower basket-style tie-rod type cantilever scaffold further includes: Several inner uprights are set on one side of the wall. The several inner uprights are distributed at equal intervals, and the joints of the several inner uprights are surrounded by fillet welds. Several outer uprights are set on one side of several inner uprights, the several outer uprights are equidistantly distributed, and the joints of the several outer uprights are surrounded by fillet welds. Several longitudinal horizontal bars are respectively arranged between two adjacent inner uprights and two adjacent outer uprights; Several horizontal bars are installed on top of the corresponding longitudinal horizontal bars, and the longitudinal and horizontal bars together form a rectangular distribution structure. Among them, several longitudinal horizontal bars and several transverse horizontal bars are connected by multiple cross couplers; Several stabilizing components are respectively installed between the top of several horizontal bars and the wall; Several installation components are respectively disposed between several of the inner uprights and the wall.

[0006] In a preferred embodiment, the stabilizing component includes: A double-ear plate is installed on the top of the transverse horizontal bar, and a double-sided fillet weld is used between the double-ear plate and the transverse horizontal bar; The pull rod is located inside the double lifting lug plate; The middle flower basket is installed at the top of the pull-down rod; The upper pull rod is installed on top of the lower pull rod; A connector is installed at the top of the upper pull rod; A through-wall bolt is installed at one end of the connector, and the through-wall bolt is fixed by a pre-reserved through-wall sleeve and a high-strength bolt.

[0007] The technical effects of adopting the above-mentioned further solutions are as follows: the double-sided fillet weld connection between the double-hung lug plate and the horizontal bar enhances the fixing strength; the tension of the tie rod can be flexibly adjusted by the middle basket; and the through-wall bolt is anchored to the wall through the reserved sleeve and high-strength bolt, thus constructing a stable force link, effectively transmitting and distributing the load, and improving the frame's resistance to lateral displacement.

[0008] In a preferred embodiment, the stabilizing component further includes: A pin is installed at the top of the double lifting lug plate, and the pin passes through the bottom end of the pull rod; A pin anti-disengagement buckle is provided on one side of the double lifting lug plate, and the pin anti-disengagement buckle passes through one side of the pin for limiting.

[0009] The technical effect of adopting the above-mentioned further solution is that the pin passes through the pull rod and the double lifting lugs, and together with the pin anti-disengagement buckle, a double limit is formed to prevent the pull rod from loosening and falling off, further strengthening the reliability of the component connection and reducing the safety hazards of high-altitude operations.

[0010] In a preferred embodiment, the mounting component includes: Two short steel pipes are installed at the bottom of the horizontal bar, and the two short steel pipes are fixed by pre-reserved through-wall sleeves and tie rods; Two swivel couplers are installed on one side of the horizontal bar, and two short steel pipes pass through the bottom of the two swivel couplers; Two type 3 clips and nuts are installed at one end of the two short steel pipes.

[0011] The technical effect of adopting the above-mentioned further solution is that the short steel pipe is fixed with the tie rod through the reserved sleeve, and the connection is reinforced with swivel fasteners, type 3 clips and nuts. Multiple fixation improves the stability of the connection between the frame and the wall and prevents the installation part from loosening and shifting.

[0012] As a preferred embodiment, the novel basket-style cantilever scaffold also includes: Several slots are respectively provided on one side of the inner upright, the outer upright and the longitudinal horizontal bar, several adjacent slots are arranged opposite each other, and several slots are fixed by bolts.

[0013] The technical effect of adopting the above-mentioned further solution is that the strip hole and bolt connection can flexibly adjust the connection length between the upright and the longitudinal horizontal bar, adapt to different frame layout requirements, and enhance the structural versatility and installation flexibility.

[0014] As a preferred embodiment, the novel basket-style cantilever scaffold also includes: Several connecting rods are respectively arranged between several adjacent horizontal bars, and the several connecting rods are arranged diagonally.

[0015] The technical effect of adopting the above-mentioned further solution is that the diagonally arranged connecting rods form oblique support, fill the stress gap between the horizontal bars of the frame, improve the overall rigidity and torsional resistance of the frame, and reduce the risk of deformation.

[0016] As a preferred embodiment, the novel basket-style cantilever scaffold also includes: Several detachable pre-embedded high-strength bolts are used to pre-embed several inner and outer uprights through iron sleeves.

[0017] The technical advantages of adopting the above-mentioned further solution are: the detachable pre-embedded high-strength bolts combined with the iron sleeve pre-embedded poles not only ensure the stability of the pole base installation, but also facilitate disassembly and relocation, avoid damage to the building structure, and reduce construction and maintenance costs.

[0018] As a preferred embodiment, the novel basket-style cantilever scaffold also includes: Several bolts at the lifting lugs are used to cooperate with pins to achieve a detachable connection between the pull rod and the longitudinal horizontal bar.

[0019] The technical advantages of adopting the above-mentioned further solution are: the bolts and pins at the lifting lugs cooperate to achieve a detachable connection, simplifying the disassembly and assembly process of the pull rod and the longitudinal horizontal bar, improving the assembly efficiency of the frame, and facilitating the later maintenance and replacement of components.

[0020] Compared with the prior art, the advantages and positive effects of this utility model are as follows: 1. This utility model solves the problems of insufficient stability and poor ease of assembly and disassembly of existing cantilever scaffolding by optimizing the overall structural layout and component connection method. On the one hand, the stabilizing component adopts a double-sided fillet weld connection between the double-hanging lug plate and the horizontal bar, combined with the double limiting design of the pin and the pin anti-disengagement buckle, which significantly improves the connection strength between the pull rod and the horizontal bar. At the same time, the tension of the pull rod can be flexibly adjusted by the middle basket, so that the stabilizing component, the wall and the scaffolding form a triangular stable force system, effectively dispersing the construction load and avoiding structural deformation caused by local stress concentration. Compared with the traditional tie rod structure, the wind load resistance and lateral displacement resistance are greatly enhanced. On the other hand, the installation component adopts a combination design of short steel pipe, swivel coupler and type 3 clip and nut, so that the disassembly and assembly of the scaffolding does not need to damage the main structure of the building, which greatly shortens the construction cycle and improves the turnover efficiency, solving the drawbacks of the traditional cantilever scaffolding of complicated pre-embedding and the need to repair the structure after dismantling.

[0021] 2. This utility model utilizes an inner upright, an outer upright, and longitudinal and transverse horizontal bars that are detachably fastened together via slotted holes and bolts. This allows for flexible adjustment of the scaffold spacing according to different building facade dimensions. Combined with diagonally positioned connecting rods, it enhances the overall rigidity of the scaffold and adapts to complex building structures such as external and internal corners, offering a wider range of applications compared to traditional fixed-spacing scaffolding. Furthermore, it incorporates a multi-layered safety protection system: anti-loosening pins prevent the risk of loosening and falling off; pre-installed through-wall sleeves and high-strength bolts, along with tie rods, provide dual fixing, improving the reliability of the connection between components and the wall; and standardized fasteners are used for all component connections, ensuring easy control over installation accuracy and reducing safety hazards caused by human error. Attached Figure Description

[0022] Figure 1 This is a perspective view of an embodiment of this application; Figure 2 This is a top view of an embodiment of this application; Figure 3 This is a perspective view of the upper and lower pull rods according to an embodiment of this application; Figure 4 This is a partial enlarged view of the installation components in an embodiment of this application; Figure 5 This is a front view of the pre-embedded high-strength bolts and the bolts at the lifting lugs in the embodiments of this application.

[0023] Legend: 1. Wall; 2. Inner upright; 3. Outer upright; 4. Longitudinal horizontal bar; 5. Transverse horizontal bar; 6. Connecting rod; 7. Cross coupler; 8. Intermediate basket; 9. Pull-down rod; 10. Pin; 11. Pin anti-disengagement buckle; 12. Double lifting lug plate; 13. Connector; 14. Through-wall bolt; 15. Swivel coupler; 16. Short steel pipe; 17. Tie rod; 18. Type 3 clip and nut; 19. Slot hole; 20. Upper pull rod; 21. Detachable pre-embedded high-strength bolt; 22. Bolt at lifting lug. Detailed Implementation

[0024] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0025] Example 1: Please see Figures 1-5 This embodiment provides a novel flower basket-style tie rod type cantilever scaffold, the specific concept of which is as follows: A novel basket-style cantilever scaffolding includes a wall 1. The novel basket-style cantilever scaffolding also includes: inner uprights 2 arranged at uniform intervals along one side of the wall 1, and the joints of adjacent inner uprights 2 are connected by fillet welds to achieve a stable connection.

[0026] Among them, the outer uprights 3 are arranged in parallel on the side of the inner uprights 2 away from the wall 1, and are also distributed in an equidistant manner. The connection between adjacent uprights is also reinforced by fillet welds to ensure the integrity of the upright structure.

[0027] It should be noted that the longitudinal and transverse ground-level bracing used to reinforce the main body of the frame is arranged horizontally on the inner side and below the bottom of the inner upright 2 and the outer upright 3. One end of the wall tie is connected to the inner upright 2 or the horizontal bar, and the other end is fixed to the building structure. The scissor bracing arranged diagonally along the outer facade of the frame spans multiple uprights and is connected to the extended ends of the uprights and the transverse horizontal bars 5. The three together strengthen the stability of the bottom of the frame, prevent the frame from shifting, and improve the overall resistance to lateral displacement.

[0028] In addition, the longitudinal horizontal bar 4 extends laterally between adjacent inner uprights 2 and adjacent outer uprights 3, forming longitudinal support for the frame.

[0029] In addition, the transverse horizontal bars 5 are erected on the top of the corresponding longitudinal horizontal bars 4, and intersect each other perpendicularly with the longitudinal horizontal bars 4 to form a regular rectangular distribution structure, providing a stable basic frame for construction operations. Several longitudinal horizontal bars 4 and several transverse horizontal bars 5 are connected by multiple cross fasteners 7.

[0030] It should be noted that among the cantilevered main beam components that bear the frame and construction load, the cantilevered main beam that can be horizontally cantilevered to the outside of the building structure provides top support for the inner upright 2 and the outer upright 3. The spreader beam that intersects the cantilevered main beam perpendicularly is fixed by U-bolts. The positioning piles that are vertically welded to the cantilevered main beam realize the positioning and fixing of the uprights, so that the uprights and the cantilevered main beam form vertical support, while enhancing the stability of the frame.

[0031] Among them, the stabilizing component, as the core load-bearing support component of the frame, is connected between the top of the horizontal bar 5 and the wall 1 to realize the transfer of the frame load to the main body of the building.

[0032] As some examples, in this embodiment, the stabilizing component includes: a double lug plate 12 welded to the top of the transverse horizontal bar 5 by double-sided fillet welds, the plate structure forming an accommodating space, and a pull-down rod 9 embedded in the accommodating space.

[0033] The top of the double lug plate 12 is equipped with a pin 10, which passes through the bottom end of the pull rod 9 from top to bottom. At the same time, the pin anti-disengagement buckle 11 set on one side of the double lug plate 12 passes through the end of the pin 10 laterally, forming a double limiting fixation to prevent the pull rod 9 from detaching from the double lug plate 12.

[0034] In addition, the top of the pull rod 9 is equipped with a middle flower basket 8 and an upper pull rod 20. The end of the upper pull rod 20 away from the pull rod 9 is equipped with a connector 13. The end of the connector 13 away from the upper pull rod 20 is fixedly connected to the through-wall screw 14. The through-wall screw 14 is firmly anchored to the wall 1 through a preset through-wall sleeve and a high-strength bolt, so that the stabilizing component forms a stable force link between the horizontal bar 5, the pull rod and the wall 1.

[0035] It should be noted that the connecting gaskets used to strengthen the connection are welded to the ends of the upper pull rod 20 and the lower pull rod 9 in the stabilizing assembly, which can improve the fit between the pull rod and the connection structure and the reliability of the connection.

[0036] Example 2: Please see Figures 1-5 Based on Example 1, this example provides a novel basket-style tie-rod cantilever scaffold, the specific concept of which is as follows: The new type of flower basket tie rod cantilever scaffold also includes: the inner upright 2, the outer upright 3 and the longitudinal horizontal bar 4 are all provided with slot holes 19 on the side. After the slot holes 19 of adjacent components are aligned, they are fastened by bolts. The connection length of the components can be flexibly adjusted to adapt to different scaffold layout requirements.

[0037] Among them, several connecting rods 6 are diagonally connected between adjacent horizontal bars 5 to form diagonal support, thereby improving the overall anti-lateral displacement capability of the frame.

[0038] In addition, the bottoms of the inner upright 2 and the outer upright 3 are pre-embedded and fixed to the ground with pre-embedded iron sleeves and detachable pre-embedded high-strength bolts 21 to ensure the installation stability of the bottom of the uprights.

[0039] It should be noted that among the embedded parts used to provide the pre-embedded fixed foundation, the pre-embedded sleeve is embedded in the concrete structure of the building wall 1 or beam, and the through-wall high-strength bolt is inserted therein and distributed adjacent to the inner upright 2, the outer upright 3 and the wall 1. This can avoid displacement during concrete pouring and ensure the accuracy of subsequent installation.

[0040] Among them, the bolt 22 at the lifting lug is used in conjunction with the pin 10 to realize the detachable connection between the pull rod 9 and the longitudinal horizontal bar 4, which facilitates the disassembly, assembly and turnover of the frame.

[0041] In addition, the installation components are symmetrically arranged between the inner uprights 2 and the wall 1 to enhance the reliability of the connection between the frame and the main building.

[0042] As some examples, in this embodiment, the installation components include: two short steel pipes 16 arranged in parallel at the bottom area of ​​the horizontal bar 5, and fixed to the wall 1 by means of a pre-reserved through-wall sleeve and a tie rod 17.

[0043] Two swivel fasteners 15 are installed on one side of the horizontal bar 5. A short steel pipe 16 passes through the bottom through hole of the swivel fastener 15 from top to bottom, so as to achieve a detachable connection with the horizontal bar 5.

[0044] Two type 3 clips and nuts 18 are fitted at the end of the short steel pipe 16 away from the wall 1. Tightening the nuts further strengthens the connection between the short steel pipe 16 and the relevant components.

[0045] It should be noted that among the protective parts used to ensure operational safety, the guardrail is vertically fixed to the inside of the outer upright 3, the toe board is tightly attached to the bottom of the inside of the outer upright 3 and connected to the guardrail, the scaffold boards are fully laid above the longitudinal and transverse horizontal bars 5, the bottom protective layer of the rigid protective layer covers the top of the cantilevered main beam, the inner protective layer is laid between the inside of the frame and the wall 1, and the horizontal fall protection net is stretched laterally at the preset height of the frame to form multiple layers of protection, which can prevent personnel from falling, prevent materials from falling, provide a safe working surface for construction workers and block falling objects from below.

[0046] Working principle: When using it, the pre-embedded connecting sleeves must be laid out first. The position and spacing of the sleeves should be determined according to the construction plan. They should be firmly fixed to the wall 1 or beam reinforcement. During the concrete pouring, a dedicated person should monitor and protect the sleeves to prevent displacement and deformation. After the concrete reaches the specified strength, the cantilever main beam should be installed. First, place the outer end of the steel beam on the horizontal bar 5 of the lower floor frame. Insert high-strength bolts and complete the initial tightening, re-tightening and final tightening in sequence. For special parts such as external corners, additional spreader beams should be added and fixed to the cantilever beams with U-bolts. At internal corners, bay windows and balconies, additional support poles should be added to ensure the stability of the frame.

[0047] After the main beam is installed, steel tie rods are installed simultaneously. Hole pipes are pre-drilled at corresponding locations in the upper structure. Once the concrete reaches its design strength, the diagonal tie rods are connected to the suspension points and turnbuckles. The adjustable turnbuckles are tightened to the specified torque value to ensure effective unloading of the cantilever beam. Subsequently, the scaffolding is erected according to specifications, and the ground bracing, uprights, and longitudinal and transverse horizontal bars 5 are installed sequentially. The extensions of the uprights and longitudinal horizontal bars 4 must meet the staggered arrangement requirements. Wall ties are installed simultaneously during the scaffolding erection process, using rigid connections arranged at specified intervals. Scissor bracing is continuously installed on the outer facade and erected concurrently with the scaffolding.

[0048] The working level must be equipped with railings and toe boards, painted with warning colors, and fully covered with scaffold boards. The inside of the scaffold must be enclosed with rigid protective barriers between it and the building, and the bottom must be protected with rigid plywood. Horizontal safety nets must be installed as required. During the use of the scaffold, construction loads must be strictly controlled, and it is strictly forbidden to arbitrarily remove key components. Regularly check for rust and loosening of components such as turnbuckles.

[0049] During dismantling operations, first clear debris from the scaffolding and demarcate a warning area. Following a top-down, dismantle-first-then-dismantle principle, remove safety nets, scaffold boards, railings, horizontal bars, vertical bars, and wall ties in sequence. Each section of cantilevered steel and tie rods should only be removed after the entire upper scaffolding has been dismantled. Before dismantling cantilevered I-beams, install lifting rings, inspect hoisting machinery and rigging, remove relevant bolts, and then smoothly lift them to the designated location for stacking. During dismantling, ensure safety precautions are in place and avoid operations in inclement weather or at night.

[0050] All standard parts used in this utility model can be purchased from the market, and irregular parts can be customized according to the description and drawings. The specific connection methods of each part adopt conventional methods such as bolts, rivets, and welding that are mature in the prior art. The machinery, parts and equipment adopt conventional models in the prior art. In addition, the circuit connection adopts conventional connection methods in the prior art, which will not be described in detail here. The contents not described in detail in this specification belong to the prior art known to those skilled in the art.

[0051] The above description is merely a preferred embodiment of the present utility model and is not intended to limit the present utility model in any other way. Any person skilled in the art may make changes or modifications to the above-disclosed technical content to create equivalent embodiments for application in other fields. However, any simple modifications, equivalent changes, and modifications made to the above embodiments based on the technical essence of the present utility model without departing from the technical solution of the present utility model shall still fall within the protection scope of the technical solution of the present utility model.

Claims

1. A novel flower basket-style tie-rod type cantilever scaffold, comprising a wall (1), characterized in that, This new type of basket-style cantilevered scaffolding also includes: Several inner uprights (2) are set on one side of the wall (1), the several inner uprights (2) are evenly distributed, and the connection of the several inner uprights (2) is surrounded by fillet welds; Several outer uprights (3) are set on one side of several inner uprights (2), the several outer uprights (3) are evenly distributed, and the connection of several outer uprights (3) is surrounded by fillet welds; Several longitudinal horizontal bars (4) are respectively set between two adjacent inner uprights (2) and two adjacent outer uprights (3); Several horizontal bars (5) are installed on the top of the oppositely arranged longitudinal horizontal bars (4), and the longitudinal horizontal bars (4) and the horizontal bars (5) together form a rectangular distribution structure; Among them, several longitudinal horizontal bars (4) and several transverse horizontal bars (5) are connected by multiple cross fasteners (7); Several stabilizing components are respectively set between the top of several horizontal bars (5) and the wall (1); Several installation components are respectively disposed between several of the inner uprights (2) and the wall (1).

2. The novel flower basket tie-rod type cantilever scaffolding according to claim 1, characterized in that, The stabilizing component includes: Double lifting lugs (12) are installed on the top of the transverse horizontal bar (5), and a double-sided fillet weld is used between the double lifting lugs (12) and the transverse horizontal bar (5); The pull rod (9) is located inside the double lug plate (12); The middle flower basket (8) is installed on top of the pull rod (9); The upper pull rod (20) is installed on top of the lower pull rod (9); A connector (13) is installed at the top of the upper pull rod (20); A through-wall screw (14) is installed at one end of the connector (13). The through-wall screw (14) is fixed by a pre-reserved through-wall sleeve and a high-strength bolt.

3. The novel flower basket-style tie-rod cantilever scaffolding according to claim 2, characterized in that, The stabilizing component also includes: A pin (10) is installed on the top of the double lug plate (12), and the pin (10) passes through the bottom end of the pull rod (9); A pin anti-disengagement buckle (11) is provided on one side of the double lifting lug plate (12), and the pin anti-disengagement buckle (11) is limited by passing through one side of the pin (10).

4. A novel flower basket-style tie-rod type cantilever scaffold according to claim 1, characterized in that, The installation components include: Two short steel pipes (16) are set at the bottom of the horizontal bar (5), and the two short steel pipes (16) are fixed by pre-reserved through-wall sleeves and tie rods (17); Two swivel fasteners (15) are provided on one side of the horizontal bar (5), and two short steel pipes (16) pass through the bottom of the two swivel fasteners (15); Two type 3 clips and nuts (18) are installed at one end of the two short steel pipes (16).

5. A novel flower basket-style tie-rod type cantilever scaffold according to claim 1, characterized in that, This new type of basket-style cantilevered scaffolding also includes: Several slots (19) are respectively provided on one side of the inner upright (2), the outer upright (3) and the longitudinal horizontal bar (4), several adjacent slots (19) are arranged opposite to each other, and several slots (19) are fixed by bolts.

6. A novel flower basket-style tie-rod type cantilever scaffold according to claim 1, characterized in that, This new type of basket-style cantilevered scaffolding also includes: Several connecting rods (6) are respectively arranged between several adjacent horizontal bars (5), and the several connecting rods (6) are arranged diagonally.

7. A novel flower basket-style tie-rod type cantilever scaffold according to claim 1, characterized in that, This new type of basket-style cantilevered scaffolding also includes: Several detachable pre-embedded high-strength bolts (21) are pre-embedded in several inner uprights (2) and outer uprights (3) through iron sleeves.

8. A novel flower basket-style tie-rod type cantilever scaffold according to claim 2, characterized in that, This new type of basket-style cantilevered scaffolding also includes: Several lug bolts (22) are used to cooperate with pins (10) to achieve a detachable connection between the pull rod (9) and the longitudinal horizontal bar (4).