A tower crane attached construction operation platform under a sliding mode construction process
By designing a connection structure between the slipform lifting platform and the hanging basket operating platform in the slipform construction process, the problems of high safety and cost in tower crane attachment construction are solved, realizing a safe and convenient tower crane attachment connection and reducing construction costs.
Patent Information
- Application Number
- CN202522560604.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-02
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-02
AI Technical Summary
Under the slipform construction process, independent installation of tower cranes cannot meet safety requirements, traditional truck crane operating platforms have poor safety and high costs, and the slipform lifting platform with its own bracket cannot meet the needs of tower crane attachment operation platform, resulting in insufficient construction safety and convenience.
Design a tower crane attachment construction operation platform for slipform construction technology, including a slipform lifting platform, a first hanging basket operation platform, a first hanging rope, a second hanging basket operation platform and a second hanging rope. The hanging rope is ≥5m long and is used to connect the slipform lifting platform and the hanging basket operation platform, providing a safe connection point between the tower crane attachment rod and the main structure of the building.
It improves construction safety and ease of operation, reduces construction costs, has a simple structure, and is suitable for large-scale promotion and application.
Smart Images

Figure CN225014590U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building construction technology, and particularly to the field of slipform construction technology, specifically referring to a tower crane attachment construction operation platform under slipform construction technology. Background Technology
[0002] Building construction refers to the production activities during the implementation phase of an engineering project. It is the process of building various types of structures, or the process of turning the lines on design drawings into a physical object at a designated location. It includes foundation construction, main structure construction, roofing construction, and decoration construction.
[0003] During the construction of high-rise buildings, the buildings are tall, and independent installation of tower cranes cannot meet safety requirements. It is necessary to attach and connect the tower crane to the main structure of the building. This requires connecting the attachment rod of the tower crane to the main structure of the building. The connection work mainly involves connecting the attachment rod to the embedded parts in the main structure of the building through ear plates. Specifically, the ear plates and the embedded parts are welded together, and the attachment rod is connected to the ear plates through pins. This requires a tower crane attachment construction operation platform.
[0004] In traditional methods, a mobile crane's front-end basket is used as a platform for carrying personnel and attaching to the tower crane. However, mobile crane work platforms have poor safety, high costs, and increase the occupation of construction sites, leading to restrictions on their use in many areas.
[0005] Under the slipform construction process, the vertical lifting speed of the slipform lifting platform (i.e., the lifting part in the slipform, mainly including jacks, lifting frames, inner trusses, outer trusses, inner formwork, outer formwork, inner operating platform, outer operating platform, inner hanging frame, and outer hanging frame, etc., the jacks are connected to the inner and outer trusses respectively through the lifting frames, the inner and outer formwork are located between the inner and outer trusses and are connected to the inner and outer trusses respectively, the inner and outer operating platforms are set on the inner and outer trusses respectively, the inner hanging frame and outer hanging frame are hung under the inner and outer trusses respectively, and the slipform lifting platform is lifted along the support rod by the jacks) is about 300mm / 2h, and the daily lifting height is about 3.6m. The construction speed is fast. However, when the slipform lifting platform is lifted and the embedded parts in the main structure of the building are exposed, the concrete strength in the embedded part area does not meet the tower crane attachment requirements. When the concrete strength in the area of the embedded parts meets the requirements, the slipform lifting platform has been lifted about 5m. The slipform lifting platform's own brackets (i.e., the inner brackets and the outer brackets, usually 2m high) cannot meet the needs of the tower crane's attachment operation platform.
[0006] Therefore, it is desirable to provide a tower crane attachment operation platform for slipform construction, which can perform the connection operation of the tower crane attachment rod to the main structure of the building, improve construction safety and operation convenience, and effectively reduce construction costs. Utility Model Content
[0007] In order to overcome the shortcomings of the prior art, one objective of this utility model is to provide a tower crane attachment construction operation platform under the slipform construction process, which can perform the connection operation of the tower crane attachment rod to the main structure of the building, improve construction safety and operation convenience, effectively reduce construction costs, and is suitable for large-scale promotion and application.
[0008] Another objective of this utility model is to provide a tower crane attachment construction operation platform for slipform construction, which is ingeniously designed, simple in structure, easy to manufacture, and low in manufacturing cost, making it suitable for large-scale promotion and application.
[0009] To achieve the above objectives, this utility model provides a tower crane attachment construction operation platform under slipform construction technology, including a slipform lifting platform. The platform is characterized in that it further includes a first hanging basket operation platform, a first hanging rope, a second hanging basket operation platform, and a second hanging rope, wherein: Both the first and second hanging basket operating platforms are located below the slipform lifting platform and below the outer side of the outer template of the slipform lifting platform, and are horizontally spaced apart from each other in a direction parallel to the circumference of the outer template. Both the first and second hanging ropes are vertically arranged. The first hanging rope is located between the slipform lifting platform and the first hanging basket operating platform and connects the slipform lifting platform and the first hanging basket operating platform respectively. The second hanging rope is located between the slipform lifting platform and the second hanging basket operating platform and connects the slipform lifting platform and the second hanging basket operating platform respectively. The lengths of the first and second hanging ropes are the same and both are ≥5m.
[0010] Preferably, the length of both the first hanging rope and the second hanging rope is 6m.
[0011] Preferably, both the first and second hanging ropes are connected to the outer truss of the slipform lifting platform.
[0012] Preferably, both the first and second hanging ropes are steel wire ropes.
[0013] Preferably, there are multiple first hanging ropes, and these multiple first hanging ropes are arranged horizontally at intervals from each other in a direction parallel to the circumference of the outer template.
[0014] More preferably, the number of the first hanging ropes is 2.
[0015] Preferably, there are multiple second hanging ropes, and these multiple second hanging ropes are arranged horizontally at intervals from each other in a direction parallel to the circumference of the outer template.
[0016] More preferably, the number of the second hanging ropes is 2.
[0017] Preferably, the outer template is a circular template.
[0018] More preferably, the central angle between the first hanging basket operating platform and the second hanging basket operating platform is 60°.
[0019] The main beneficial effects of this utility model are as follows: 1. The tower crane attachment operation platform under the slipform construction process of this utility model includes a slipform lifting platform, a first hanging basket operation platform, a first hanging rope, a second hanging basket operation platform, and a second hanging rope. The first and second hanging basket operation platforms are both located below the slipform lifting platform and below the outer side of the outer template of the slipform lifting platform, and are horizontally spaced apart from each other in a direction parallel to the circumference of the outer template. The first and second hanging ropes are both vertically arranged. The first hanging rope is located between the slipform lifting platform and the first hanging basket operation platform and connects the slipform lifting platform and the first hanging basket operation platform respectively. The length of the first hanging rope and the second hanging basket operation platform are the same and both are ≥5m. Therefore, it is possible to connect the tower crane attachment rod to the main structure of the building, improve construction safety and operation convenience, effectively reduce construction costs, and is suitable for large-scale promotion and application.
[0020] 2. The tower crane attachment operation platform under the slipform construction process of this utility model includes a slipform lifting platform, a first hanging basket operation platform, a first hanging rope, a second hanging basket operation platform, and a second hanging rope. The first and second hanging basket operation platforms are both located below the slipform lifting platform and below the outer side of the outer template of the slipform lifting platform, and are horizontally spaced apart from each other in a direction parallel to the circumference of the outer template. The first and second hanging ropes are both vertically arranged. The first hanging rope is located between the slipform lifting platform and the first hanging basket operation platform and connects the slipform lifting platform and the first hanging basket operation platform respectively. The length of the first hanging rope and the second hanging basket operation platform are the same and both are ≥5m. Therefore, its design is ingenious, its structure is simple, its manufacturing is convenient, its manufacturing cost is low, and it is suitable for large-scale promotion and application.
[0021] These and other objects, features and advantages of this utility model will be fully apparent from the following detailed description and drawings, and can be achieved by the means, devices and combinations thereof specifically pointed out in the description of the utility model. Attached Figure Description
[0022] Figure 1 This is a partial front sectional view of a specific embodiment of the tower crane attachment construction operation platform under the slipform construction process of this utility model.
[0023] Figure 2 yes Figure 1 A partially enlarged schematic diagram of the structure shown.
[0024] Figure 3 yes Figure 1 The diagram shown is a partial top-view perspective illustration of the specific embodiment in use.
[0025] Figure 4 yes Figure 3 A partially enlarged schematic diagram of the structure shown.
[0026] (Explanation of reference numerals in the attached image) 1. Slipform lifting platform; 11. Jacks; 12. Lifting frame; 13. Inner truss; 14. Outer truss; 15. Inner formwork; 16. Outer formwork; 17. Inner operating platform; 18. Outer operating platform; 19. Inner hanging frame; 20. Outer hanging frame; 2. Support rod; 3. First hanging basket operating platform; 4. First hanging rope; 5. Second hanging basket operating platform; 6 tower cranes; 61 attached booms; 7. Main structure; 8. Embedded parts; 81. Embedded plates; 82. Embedded rods; 9. Earplates. Detailed Implementation
[0027] In order to better understand the technical content of this utility model, the following embodiments are provided for detailed description.
[0028] In the description of this utility model, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model.
[0029] Please see Figures 1-4 As shown, in a specific embodiment of this utility model, the tower crane attachment construction operation platform under the slipform construction process of this utility model includes a slipform lifting platform 1, a first hanging basket operation platform 3, a first hanging rope 4, a second hanging basket operation platform 5, and a second hanging rope (not shown in the figure), wherein: The first hanging basket operating platform 3 and the second hanging basket operating platform 5 are both located below the sliding formwork lifting platform 1 and below the outer side of the outer template 16 of the sliding formwork lifting platform 1, and are horizontally spaced apart from each other in a direction parallel to the circumference of the outer template 16. The first hanging rope 4 and the second hanging rope are both vertically arranged. The first hanging rope 4 is located between the sliding formwork lifting platform 1 and the first hanging basket operating platform 3 and connects the sliding formwork lifting platform 1 and the first hanging basket operating platform 3 respectively. The second hanging rope is located between the sliding formwork lifting platform 1 and the second hanging basket operating platform 5 and connects the sliding formwork lifting platform 1 and the second hanging basket operating platform 5 respectively. The length of the first hanging rope 4 and the length of the second hanging rope are the same and both are ≥5m.
[0030] The lengths of the first hanging rope 4 and the second hanging rope can be determined as needed. In a specific embodiment of this utility model, the lengths of both the first hanging rope 4 and the second hanging rope are 6m.
[0031] Both the first hanging rope 4 and the second hanging rope are connected to the slipform lifting platform 1, and can be connected to any suitable component of the slipform lifting platform 1. Please refer to [link to relevant documentation]. Figure 2 As shown, in a specific embodiment of this utility model, both the first hanging rope 4 and the second hanging rope are connected to the outer truss 14 of the sliding formwork platform 1.
[0032] The first hanging rope 4 and the second hanging rope can be ropes of any suitable material. In a specific embodiment of this utility model, the first hanging rope 4 and the second hanging rope are both steel wire ropes.
[0033] The number of the first hanging ropes 4 can be determined as needed. Preferably, there are multiple first hanging ropes 4, which are horizontally spaced apart from each other in a direction parallel to the circumference of the outer template 16. The term "multiple" refers to two or more ropes. In a specific embodiment of this utility model, there are two first hanging ropes 4.
[0034] The number of the second hanging ropes can be determined as needed. Preferably, there are multiple second hanging ropes, which are horizontally spaced apart from each other in a direction parallel to the circumference of the outer template 16. In a specific embodiment of this utility model, there are two second hanging ropes.
[0035] The outer template 16 can have any suitable shape. In a specific embodiment of this utility model, the outer template 16 is a circular template.
[0036] The central angle between the first hanging basket operating platform 3 and the second hanging basket operating platform 5 can be determined as needed. In a specific embodiment of this utility model, the central angle between the first hanging basket operating platform 3 and the second hanging basket operating platform 5 is 60°. That is, the angle formed by the line connecting the center of the first hanging basket operating platform 3 and the center of the annular template and the line connecting the center of the second hanging basket operating platform 5 and the center of the annular template is 60°.
[0037] In manufacturing this utility model, the distance between the first hanging basket operating platform 3 and the second hanging basket operating platform 5 is set according to the distance between the two embedded parts 8 that need to be pre-embedded in the main structure 7 of the building. During use, in the slipform construction process, two embedded parts 8 are pre-embedded in the main structure 7 of the building. When the slipform lifting platform 1 is raised to the positions of the two embedded parts 8 on the first hanging basket operating platform 3 and the second hanging basket operating platform 5 respectively, the construction personnel perform the connection operation between the tower crane 6's attachment rod 61 and the main structure 7 of the building on the first hanging basket operating platform 3 and the second hanging basket operating platform 5. This mainly includes welding the ear plate 9 to the embedded parts 8. The embedded part 8 typically includes an embedded plate 81 and multiple, for example, three embedded rods 82. The embedded plate 81 is embedded in the outer side of the main structure 7 of the building, and the embedded rods 82 are embedded in the main structure 7 of the building and are connected to the embedded plate 81 at one end and have a hook at the other end. In this case, the ear plate 9 is welded to the embedded plate 81 of the embedded part 8, and then the end of the attached hanging rod 61 is connected to the ear plate 9 by a pin. Specifically, in the first hanging basket operating platform 3, the ends of two attached hanging rods 61 are connected to one ear plate 9 by a pin, and in the second hanging basket operating platform 5, the end of the remaining attached hanging rod 61 is connected to the other ear plate 9 by a pin.
[0038] Therefore, this utility model adds two hanging basket operating platforms below the slipform lifting platform and on the outer side of the outer formwork, at a distance of more than 5m from the slipform lifting platform. These platforms are hung on the slipform lifting platform by ropes. When the slipform lifting platform is raised to the position of the pre-embedded parts on the hanging basket operating platform, the construction personnel can perform the attachment and connection work between the hanging rods and the main structure on the hanging basket operating platform. This greatly improves construction safety and operation convenience, and effectively reduces the cost of use.
[0039] This invention can be made using common materials found on building construction sites, allowing for on-site material sourcing, and is safe and reliable, providing a new solution for setting up a tower crane attachment construction operation platform under slipform construction technology.
[0040] In summary, the tower crane attachment construction operation platform of this utility model under the slipform construction process can perform the connection operation of the tower crane attachment rod with the main structure of the building, improve construction safety and operation convenience, effectively reduce construction costs, and is ingeniously designed, simple in structure, easy to manufacture, and low in manufacturing cost, making it suitable for large-scale promotion and application.
[0041] Therefore, it is evident that the objective of this utility model has been fully and effectively achieved. The function and structural principles of this utility model have been demonstrated and explained in the embodiments. Without departing from the stated principles, any modifications can be made to the implementation methods. Therefore, this utility model includes all modified embodiments based on the spirit and scope of the claims.
Claims
1. A tower crane attachment construction operation platform for slipform construction, comprising a slipform lifting platform, characterized in that, The tower crane attachment operation platform under the slipform construction process also includes a first hanging basket operation platform, a first hanging rope, a second hanging basket operation platform, and a second hanging rope, wherein: Both the first and second hanging basket operating platforms are located below the slipform lifting platform and below the outer side of the outer template of the slipform lifting platform, and are horizontally spaced apart from each other in a direction parallel to the circumference of the outer template. Both the first and second hanging ropes are vertically arranged. The first hanging rope is located between the slipform lifting platform and the first hanging basket operating platform and connects the slipform lifting platform and the first hanging basket operating platform respectively. The second hanging rope is located between the slipform lifting platform and the second hanging basket operating platform and connects the slipform lifting platform and the second hanging basket operating platform respectively. The lengths of the first and second hanging ropes are the same and both are ≥5m.
2. The tower crane attachment construction operation platform under the slipform construction process as described in claim 1, characterized in that, The length of both the first and second hanging ropes is 6m.
3. The tower crane attachment construction operation platform under the slipform construction process as described in claim 1, characterized in that, Both the first and second hanging ropes are connected to the outer truss of the slipform lifting platform.
4. The tower crane attachment construction operation platform under the slipform construction process as described in claim 1, characterized in that, Both the first and second hanging ropes are steel wire ropes.
5. The tower crane attachment construction operation platform under the slipform construction process as described in claim 1, characterized in that, The number of the first hanging ropes is multiple, and the multiple first hanging ropes are arranged horizontally at intervals from each other in a direction parallel to the circumference of the outer template.
6. The tower crane attachment construction operation platform under the slipform construction process as described in claim 5, characterized in that, The number of the first hanging ropes is 2.
7. The tower crane attachment construction operation platform under the slipform construction process as described in claim 1, characterized in that, The number of second hanging ropes is multiple, and the multiple second hanging ropes are arranged horizontally at intervals with each other in a direction parallel to the circumference of the outer template.
8. The tower crane attachment construction operation platform under the slipform construction process as described in claim 7, characterized in that, The second hanging rope has two strands.
9. The tower crane attachment construction operation platform under the slipform construction process as described in claim 1, characterized in that, The outer template is a circular template.
10. The tower crane attachment construction operation platform under the slipform construction process as described in claim 9, characterized in that, The central angle between the first hanging basket operating platform and the second hanging basket operating platform is 60°.