Post-cast site formwork device for PEC beam
By using a formwork support device with steel clamps and fixing plates, combined with a quick-locking structure of tie rods and wing nuts, the problems of large construction space occupation, poor sealing, and insufficient versatility of PEC beam formwork support devices are solved, achieving efficient and low-cost construction results.
Patent Information
- Application Number
- CN202522767821.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-26
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2035-12-26
AI Technical Summary
Existing PEC beam formwork devices suffer from problems such as large construction space occupation, poor sealing, and insufficient versatility, which affect construction efficiency and quality.
The formwork support device, which uses steel clamps and fixing plates, combined with a quick-locking structure of tie rods and wing nuts, and a modular design of plug-in plates and plug-in slots, can adapt to PEC beams of different sizes, ensuring sealing and stability.
It significantly improves construction efficiency, reduces the difficulty of manual operation and material costs, and ensures the flatness and density of the concrete surface, which is in line with the concept of green construction.
Smart Images

Figure CN225014624U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building construction technology, and in particular to a formwork support device for the post-cast part of a PEC beam. Background Technology
[0002] PEC beams (partially encased composite beams) are a unique steel-concrete composite structure. By partially encasing the web of the steel beam with concrete on both sides, this type of beam not only significantly improves its load-bearing capacity but also effectively enhances its fire resistance.
[0003] A search revealed Chinese patent CN217353542U, which discloses a formwork system for the post-cast section of a beam-column joint in a PEC structure. For the PEC column joint, a first formwork structure is provided, comprising a precast frame mold with transversely arranged square steel bars on both sides, connected by a first tie rod. A first pouring hole is pre-reserved in the upper section of the precast frame mold. For the PEC beam joint, a second formwork structure is provided, comprising an I-beam and side molds disposed on the sides of the I-beam, connected by a second tie rod. A second pouring hole is pre-reserved between the upper flange of the I-beam and the side molds. This patent, employing the above formwork structure, enables rapid formwork completion with minimal space requirements, thereby ensuring the smooth progress of formwork, concrete pouring, and vibration for the post-cast section of the beam-column joint in the PEC structure.
[0004] Based on the above search and existing technology, the findings were as follows:
[0005] The existing patented square steel is arranged laterally on both sides of the mold, which occupies the construction space and affects the parallel construction of other processes; the side mold is rigidly attached to the I-beam without a sealing design, which is prone to gaps due to vibration and causes grout leakage; the precast frame mold is customized as needed, has poor versatility, and cannot be quickly adapted to variable cross-section conditions, so it has certain limitations. Utility Model Content
[0006] To address the aforementioned technical problems, this utility model proposes a formwork support device for the post-cast section of PEC beams, which reduces the formwork installation process on the construction site, thereby achieving rapid construction and saving construction costs.
[0007] The technical solution to achieve the purpose of this utility model is: a formwork support device for the post-cast section of a PEC beam, comprising a steel beam, a formwork support device, and a fixing plate.
[0008] The formwork support device includes steel clamps set on both sides of the steel beam, and each steel clamp is provided with multiple reserved installation holes;
[0009] The fixing plate is fixedly installed on the inner side of the steel clamp and is snapped onto the top of the steel beam.
[0010] Preferably, a tie rod is threadedly installed between the steel clamps through pre-reserved mounting holes, and a wing nut is threaded onto one end of each tie rod, with a feeding port opened on one side of the steel clamp.
[0011] Preferably, a pair of plug-in plates are fixedly installed on one side of each steel clamp, and a pair of plug-in slots are opened on the other side of each steel clamp, with adjacent plug-in plates inserted into the plug-in slots.
[0012] Compared with existing technologies, the significant advantages of this invention are:
[0013] Firstly, this utility model uses prefabricated steel clamps and quick-locking tie rods, which greatly reduces the on-site formwork time and significantly improves construction efficiency compared to traditional wooden formwork; the fixing plate temporarily clips onto the top of the steel beam, simplifying the positioning process and reducing the difficulty of manual operation; the steel clamps achieve modular assembly through pre-reserved installation holes and plug-in structures, adapting to PEC beams of different sizes; the steel components can be cleaned and reused after dismantling, with strong turnover and reduced material costs.
[0014] Secondly, this utility model uses steel formwork to replace wooden formwork, avoiding the problems of easy deformation and grout leakage of wooden formwork, and ensuring the flatness and density of the concrete surface; the triangular feeding port design facilitates concrete pouring and vibration, reducing air bubbles and voids; the double-threaded tie rod with wing nuts applies uniform pressure to prevent the steel clamps from shifting or bulging; the interlocking design of the interlocking plate and the interlocking groove enhances the overall rigidity and resists the lateral pressure of the concrete; it reduces wood consumption and conforms to the concept of green construction; and the long-term use cost is lower than that of traditional wooden formwork.
[0015] This invention solves the problems of existing patents where square steel is arranged laterally on both sides of the mold, which encroaches on construction space and affects the parallel construction of other processes; the side mold is rigidly attached to the I-beam without a sealing design, which is prone to gaps due to vibration and causes grout leakage; and the prefabricated frame mold is customized as needed, has poor versatility, and cannot be quickly adapted to variable cross-section conditions. Attached Figure Description
[0016] The present invention will be further explained below with reference to the accompanying drawings and embodiments:
[0017] Figure 1 This is a schematic diagram of the front structure after use provided in one embodiment of the present invention;
[0018] Figure 2 This is a top view of the structure after use provided in one embodiment of the present invention;
[0019] Figure 3 This is a side view of the installation structure provided in two embodiments of the present invention;
[0020] Figure 4This is a schematic diagram of the steel clamp structure provided in two embodiments of this utility model.
[0021] Explanation of reference numerals in the attached figures:
[0022] 1. Steel beam; 2. Steel clamp; 3. Feed port; 4. Pre-drilled mounting hole; 5. Insertion slot; 6. Insertion plate; 7. Fixing plate; 8. Tie rod; 9. Wing nut. Detailed Implementation
[0023] The present invention will now be described in detail, and the technical solutions in the embodiments of the present invention will be clearly and completely described. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present invention.
[0024] This utility model provides an improved formwork support device for the post-cast section of a PEC beam. The technical solution of this utility model is as follows:
[0025] Example 1
[0026] like Figures 1-2 As shown, a formwork support device for the post-cast section of a PEC beam includes a steel beam 1. The main components are made of galvanized steel plate or aluminum alloy, which combines lightweight and corrosion resistance, extending service life. It also includes a formwork support device and a fixing plate 7.
[0027] The formwork support device includes steel clamps 2 set on both sides of the steel beam 1. Each steel clamp 2 has multiple reserved installation holes 4. The modular design and durable materials support multiple cycles of use, reduce overall costs, and conform to the concept of sustainable development.
[0028] The fixing plate 7 is fixedly installed on the inner side of the steel clamp plate 2. The fixing plate 7 is snapped onto the top of the steel beam 1 to prevent the steel clamp plate 2 from shifting and to maintain the stability of the formwork.
[0029] Example 2:
[0030] Based on the formwork support device for the post-cast section of a PEC beam provided in the first embodiment of this application, the second embodiment of this application proposes another formwork support device for the post-cast section of a PEC beam. The second embodiment is merely a preferred embodiment of the first embodiment, and the implementation of the second embodiment will not affect the separate implementation of the first embodiment.
[0031] The second embodiment of this utility model will be further described below with reference to the accompanying drawings and embodiments.
[0032] like Figures 3-4As shown, a pull rod 8 is threadedly installed between the steel clamps 2 through the reserved installation holes 4. A wing nut 9 is installed at one end of each pull rod 8. A feeding port 3 is opened on one side of the steel clamp 2. The wing nut 9 can be manually tightened and loosened quickly, which greatly shortens the installation time.
[0033] Furthermore, a pair of plug-in plates 6 are fixedly installed on one side of each steel clamp plate 2, and a pair of plug-in slots 5 are opened on the other side of each steel clamp plate 2. Adjacent plug-in plates 6 are inserted into the inside of the plug-in slots 5. The width can be adjusted by sliding grooves and pins to meet the needs of PEC beams of different thicknesses. In addition, elastic sealing strips are added to the edges of the clamp plates to effectively prevent concrete leakage and improve the molding quality.
[0034] Specific working method: Check the installation position and size of steel beam 1, and clean welding residue; prepare components such as steel clamp plate 2, tie rod 8, and wing nut 9, and confirm that the quantity and specifications match; place steel clamp plate 2 on both sides of steel beam 1, and temporarily fix it to the top of steel beam 1 with fixing piece 7; align the plug plate 6 and plug groove 5 of adjacent steel clamp plate 2, and plug them in to form a continuous template surface; pass tie rod 8 through the reserved installation hole 4, weld the end to limit it, and manually tighten the other end with wing nut 9, applying uniform pressure; pour concrete in layers through triangular feeding port 3, and use vibrator to remove air bubbles; after the concrete reaches the strength, loosen wing nut 9, pull out tie rod 8, and remove steel clamp plate 2; clean the residual concrete on the template surface and apply release agent for later use.
[0035] The technical means disclosed in this utility model are not limited to those described above, but also include technical solutions composed of equivalent substitutions of the above technical features. Matters not covered in this utility model are common knowledge to those skilled in the art.
Claims
1. A device for formwork support of PEC beam post-pouring site, comprising a steel beam (1), characterized in that: Also includes: The formwork support device includes steel clamps (2) set on both sides of the steel beam (1), and each steel clamp (2) is provided with multiple reserved installation holes (4). Fixing piece (7), the fixing piece (7) is fixedly installed on the inner side of the steel clamp (2), and the fixing piece (7) is snapped onto the top of the steel beam (1).
2. The formwork support device for the post-cast section of a PEC beam according to claim 1, characterized in that: A pull rod (8) is threaded between the steel clamps (2) through a reserved mounting hole (4). A wing nut (9) is threaded onto one end of each pull rod (8). A feeding port (3) is provided on one side of the steel clamp (2).
3. A formwork support device for the post-cast portion of a PEC beam according to any one of claims 1-2, characterized in that: Each of the steel clamps (2) has a pair of plug-in plates (6) fixedly installed on one side, and each of the steel clamps (2) has a pair of plug-in slots (5) on the other side, with adjacent plug-in plates (6) inserted into the plug-in slots (5).
Citation Information
Patent Citations
Formwork supporting system for post-pouring section of beam-column joint of PEC structure
CN217353542U