A reinforcement system for a kitchen flue joint

By designing leak-proof connectors and adhesive storage cavities, the sealant is fully filled and mechanically supported, solving the problems of poor sealing and structural stability at the joints of the kitchen flue, and achieving efficient sealing protection and structural reinforcement.

CN225014729UActive Publication Date: 2026-11-24四川省建筑机械化工程有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522798751.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-30
Publication Date
2026-11-24
Estimated Expiration
2035-12-30

AI Technical Summary

Technical Problem

The existing kitchen exhaust duct joints are not properly sealed and lack structural stability, resulting in smoke leakage, odor backflow, and joint cracking, which fails to meet the requirements of a high-quality housing experience.

Method used

The support frame with leak-proof connectors and the sealant storage cavity design allow for all-around filling of the sealant through the connection between the installation groove and the sealant storage cavity. Combined with the fixing ribs and support columns, a mechanical support system is formed to enhance structural stability and sealing effect.

Benefits of technology

Completely blocks the channels for smoke and odor backflow, enhances the structural stability and sealing reliability of the joints, prevents cracking, and improves the overall load-bearing capacity and deformation resistance of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014729U_ABST
    Figure CN225014729U_ABST
Patent Text Reader

Abstract

The utility model relates to flue construction technology field discloses a kind of reinforcing system for kitchen flue joint, including leakage prevention connecting piece, it includes support frame body, the upper and lower ends of support frame body are respectively provided with the first installation slot and the second installation slot of matching first flue and second flue;Wherein, the outside of first installation slot and second installation slot is provided with glue storage cavity, and glue storage cavity is communicated with first installation slot and second installation slot;The utility model realizes the butt joint and positioning of upper and lower flue by installation slot, and glue storage cavity can be filled with sealant to the fitting gap of installation slot and flue, and sealant is evenly covered joint area and peripheral fitting surface under the guidance of communication structure, form omnibearing dead corner sealing structure, both block the channel of smoke return taste from root, and enhance the structural integrity of joint, reduce the cracking risk caused by self weight and use vibration of flue, significantly improve the sealing reliability and structural stability of kitchen flue joint.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of flue construction technology, specifically to a reinforcement system for kitchen flue joints. Background Technology

[0002] With a significant shift in the supply and demand relationship in my country's real estate market, the construction industry has gradually moved from primarily addressing the basic need for housing to focusing on the upgraded demands of housing functionality and quality of life. The concept of "good housing" has become a core guiding principle in the construction market, and consumers are placing higher demands on the user experience and quality stability of various functional areas of housing. As one of the core functional spaces in a home, the comfort of the kitchen directly impacts the overall quality of living, and the construction quality of the flue system is a crucial factor in ensuring a good kitchen experience. Currently, the joint treatment in kitchen flue construction generally suffers from technical shortcomings. Due to the lack of targeted reinforcement and sealing systems, problems such as inadequate sealing and insufficient structural stability easily occur at flue joints, leading to frequent smoke and odor backflow during daily use. This not only seriously affects residents' living environment and comfort but also generates numerous user complaints, becoming a prominent quality pain point hindering the achievement of the "good housing" construction goal. Existing technologies for treating flue joints mostly involve simple splicing or single sealing treatment, which fail to take into account sealing effect, structural load distribution, and installation precision control. They cannot fundamentally solve core problems such as smoke backflow and joint cracking, and are therefore unable to meet the high-quality requirements of the current construction market for housing. Summary of the Invention

[0003] The purpose of this utility model is to provide a reinforcement system for kitchen flue joints, which includes a first mounting groove and a second mounting groove that connect a first flue and a second flue respectively. Each mounting groove is connected to a sealant storage cavity. The sealant in the sealant storage cavity fills both sides of the first flue and the second flue, thereby forming a sealed structure as a whole, fundamentally solving problems such as smoke and odor backflow and joint cracking at flue joints.

[0004] This utility model is achieved through the following technical solution: A reinforcement system for kitchen flue joints, comprising: A leak-proof connector includes a support frame, wherein the upper and lower ends of the support frame are respectively provided with a first mounting groove and a second mounting groove that match the first flue and the second flue. The first mounting groove and the second mounting groove are both provided with glue storage cavities on their outer sides, and the glue storage cavities are connected to the first mounting groove and the second mounting groove.

[0005] In this solution, the support frame of the leak-proof connector and the dedicated installation grooves at the upper and lower ends that adapt to the first and second flues achieve the docking and positioning of the upper and lower flues, effectively ensuring installation accuracy and reducing sealing risks caused by docking deviations. At the same time, with the help of the glue storage cavity connected to the outside of the installation groove, the gap between the installation groove and the flue can be fully filled with sealant, so that the sealant can be evenly covered in the joint area and surrounding mating surface under the guidance of the connecting structure, forming a comprehensive and dead-angle-free sealing structure. This not only blocks the channels for smoke and odor backflow from the root, but also enhances the structural integrity of the joint through the synergistic effect of the glue storage cavity and the installation groove, reducing the risk of joint cracking caused by the weight of the flue and vibration during use, and significantly improving the sealing reliability and structural stability of the kitchen flue joint.

[0006] As a further solution to the reinforcement system, the bottom of the first mounting groove and the second mounting groove are provided with raised strips at equal intervals to create a flow gap between the flue and the mounting groove. This allows the sealant in the storage cavity to permeate evenly to all parts of the mating surface between the flue and the mounting groove through the gap, avoiding the formation of local sealing dead corners due to the sealant not being able to fill properly because of excessive tightness.

[0007] As a further reinforcement system, a first gap cavity and a second gap cavity are formed between the two sides of the first flue and the first mounting groove, respectively. Similarly, independent first gap cavities and second gap cavities are also formed between the two sides of the second flue and the second mounting groove. The first gap cavity and the second gap cavity allow the sealant flowing in from the sealant storage cavity to fully fill the gaps on both sides of the flue, avoiding insufficient sealing on one side or uneven distribution of the sealant. This ensures that a complete and dense sealing layer can be formed on both sides of the flue, further enhancing the sealing effect at the joint and doubly blocking the path of smoke and odor from both sides. Furthermore, the curing effect of the sealant in the gap cavity enhances the bonding strength between the flue and the mounting groove.

[0008] As a further solution to the reinforcement system, the first mounting groove is connected to the adhesive storage cavity through multiple first through holes, and the second mounting groove is connected to the adhesive storage cavity through multiple second through holes. The distribution design of the multiple through holes can ensure that the amount of sealant filling at different positions is balanced, preventing local insufficient filling or accumulation and waste.

[0009] As a further solution to the reinforcement system, the outer side of the adhesive storage cavity is also uniformly connected with first support columns. The structural characteristics of the support columns can provide additional mechanical support for the entire reinforcement system, effectively dispersing the self-weight of the flue and the load generated during use. Furthermore, the connection between the support columns and the adhesive storage cavity allows the sealant to be filled into the support columns simultaneously. This enables the support columns to not only provide support but also to form a stronger bond between the cured sealant and the surrounding mortar, further enhancing the installation stability of the reinforcement system.

[0010] As a further solution to the reinforcement system, the first support column is hollow inside and communicates with the glue storage cavity. The outer wall of the first support column is also evenly distributed with a plurality of first glue leakage holes that communicate with the hollow interior. The glue overflows evenly into the contact gap between the support column and the surrounding building structure through the evenly distributed glue leakage holes, forming multi-point bonding and improving the connection firmness between the support column and the surrounding structure.

[0011] As a further solution to the reinforcement system, the two sides of the support frame are respectively connected with fixing bars. Through the reliable connection between the fixing bars and the main building structure, a stable installation anchor point is provided for the reinforcement system, which effectively transfers the weight of the flue and the vibration load during use to the main building structure, avoiding the load concentration at the flue joint, which would cause excessive stress and cracking.

[0012] As a further aspect of the reinforcement system, the outer side of the adhesive storage cavity is also uniformly connected to first support columns, which are located above the fixing ribs. The first support columns are hollow and connected to the adhesive storage cavity, and their outer walls are also uniformly distributed with multiple first adhesive leakage holes communicating with the hollow interior. This arrangement of support columns above the fixing ribs forms a coordinated mechanical support system, dispersing the self-weight and vibration load transmitted from the upper part of the flue, preventing stress overload and cracking at the joints due to concentrated loads, and significantly improving the structural stability and load-bearing balance of the reinforcement system. Furthermore, it allows the sealant in the adhesive storage cavity to flow smoothly into the hollow support columns, enhancing the structural rigidity of the support columns themselves. The evenly distributed leakage holes allow the sealant to overflow evenly to the contact points between the support columns and the surrounding building structure, forming multi-point, all-around bonding and fixing, greatly improving the connection strength between the reinforcement system and the main building structure.

[0013] As a further solution to the reinforcement system, in order to further improve the connection between the reinforcement system and the main building, a second support column is evenly distributed and connected to the outside of the glue storage cavity, and the second support column is located below the fixing bar; The second support column is hollow inside and communicates with the glue storage cavity, and the outer wall of the second support column is also evenly distributed with a plurality of second glue leakage holes that communicate with the hollow interior.

[0014] As a further solution to the reinforcement system, the upper end face of the support frame is connected to an adhesive column, which is connected to the adhesive storage cavity. The top of the adhesive column is also threaded with a nut, which can quickly seal the adhesive column after the adhesive is injected, preventing the uncured sealant from being lost or contaminated by external impurities, and ensuring that the sealant is uniformly cured and formed in the sealed space.

[0015] Compared with the prior art, this utility model has the following advantages and beneficial effects: 1. This utility model, through the interconnection design of the glue storage cavity and the installation groove, enables the sealant to fill the joints of the flue and the contact parts with the surrounding structure in all directions, forming multiple sealing protections and completely blocking the channels for smoke and odor backflow. 2. This utility model forms a force-bearing system by fixing the ribs on both sides and evenly distributed support columns, which effectively disperses the self-weight of the flue and the load caused by vibration during use, avoiding joint cracking caused by load concentration. At the same time, the combination of support columns and sealant enhances the bonding strength with the main building structure, improving the overall load-bearing capacity and deformation resistance of the structure. Attached Figure Description

[0016] The accompanying drawings, which are included to provide a further understanding of the embodiments of the present invention and form part of this application, do not constitute a limitation thereof. In the drawings: Figure 1 This is a schematic diagram of the overall structure of an embodiment of the present utility model; Figure 2 This is an exploded view of the overall structure of an embodiment of the present utility model; Figure 3 This is a cross-sectional structural diagram of an embodiment of the present utility model; Figure 4 This is a schematic diagram of the leak-proof connector structure according to an embodiment of the present utility model; Figure 5 A cross-sectional structural diagram of the connector to prevent leakage.

[0017] The attached diagram shows the markings and corresponding component names: First flue; Second flue; 3- Leak-proof connector, 300- Support frame, 301- First support column, 302- First glue leakage hole, 303- Fixing rib, 304- Glue storage cavity, 305- First through hole, 306- First gap cavity, 307- Second gap cavity, 308- Protruding strip, 309- Second through hole, 310- Second support column, 311- Second glue leakage hole, 312- Glue filling column, 313- Nut, 314- First mounting groove, 315- Second mounting groove. Detailed Implementation

[0018] To make the objectives, technical solutions, and advantages of this utility model clearer, the present utility model will be further described in detail below with reference to the embodiments and accompanying drawings. The illustrative embodiments and descriptions of this utility model are only used to explain this utility model and are not intended to limit this utility model. Example 1

[0019] This embodiment 1 provides a reinforcement system for kitchen flue joints, such as... Figures 1-2As shown, it includes a leak-proof connector 3, which is a core reinforcing and sealing component used to achieve the connection, sealing protection and structural reinforcement of the first flue 1 and the second flue 2.

[0020] Specifically, such as Figures 3-5 As shown, the leak-proof connector 3 includes an integrated support frame 300, the overall size of which is adapted to the cross-sectional specifications of common kitchen flues (adjustable according to the actual flue size) to ensure a good fit with the flue. The upper and lower ends of the support frame 300 are respectively integrally formed with a first mounting groove 314 and a second mounting groove 315. The groove opening size of the first mounting groove 314 matches the lower cross-sectional size of the first flue 1, and the groove opening size of the second mounting groove 315 matches the upper cross-sectional size of the second flue 2. The depth of the mounting groove is set to 20-30mm to ensure the connection stability after the flue is inserted.

[0021] At the same time, such as Figure 3 and Figure 5 As shown, an annular sealant storage cavity 304 is provided around the support frame 300 on the outside of the first mounting groove 314 and the second mounting groove 315. The cross-section of the sealant storage cavity 304 is rectangular, which can store a sufficient amount of sealant to meet the needs of all-round filling. The sealant storage cavity 304 is connected to the first mounting groove 314 and the second mounting groove 315, providing a channel for the flow and filling of sealant.

[0022] In this embodiment, weather-resistant structural adhesive is injected into the adhesive storage cavity 304. Under pressure, the sealant flows into the gap cavities of the first mounting groove 314 and the second mounting groove 315. After the sealant is fully filled, it is left to stand until the sealant is completely cured, thus completing the assembly of the entire reinforcement system. Example 2

[0023] To enhance the connection strength between the reinforcement system and the building structure, this embodiment 2 further provides a reinforcement system for kitchen flue joints based on embodiment 1, such as... Figures 1-5 As shown, both the first mounting groove 314 and the second mounting groove 315 have raised strips 308 evenly spaced along their length at the bottom. The raised strips 308 are integrally formed with the support frame 300, and their cross-section is semi-circular with a height of 3-5mm. When the first flue 1 is inserted into the first mounting groove 314 and the second flue 2 is inserted into the second mounting groove 315, the raised strips 308 can support the outer wall of the flue, forming a uniform flow gap between the flue and the bottom of the mounting groove, providing space for the flow and distribution of sealant.

[0024] Meanwhile, independent first gap cavities 306 and second gap cavities 307 are formed between the outer walls of the first flue 1 and the groove walls of the first mounting groove 314, respectively. Similarly, independent first gap cavities 306 and second gap cavities 307 are also formed between the outer walls of the second flue 2 and the groove walls of the second mounting groove 315. The width of each gap cavity is 5-8mm, which can accommodate sealant and form a side sealing layer.

[0025] To facilitate the flow of sealant between the sealant storage cavity 304 and the mounting groove and gap cavity, multiple first through holes 305 are evenly distributed on both sides of the first mounting groove 314, and multiple second through holes 309 are evenly distributed on both sides of the second mounting groove 315. The inner end of the first through hole 305 is connected to the sealant storage cavity 304, and the outer end is connected to the first gap cavity 306 and the second gap cavity 307 respectively. The inner end of the second through hole 309 is connected to the sealant storage cavity 304, and the outer end is connected to the first gap cavity 306 and the second gap cavity 307 corresponding to the second flue 2, forming a multi-channel sealant flow network.

[0026] On the outside of the glue storage cavity 304, multiple first support columns 301 are evenly distributed and connected along the circumference. The first support columns 301 are made of hollow steel pipes, and their internal hollow structure is connected to the glue storage cavity 304. Multiple first glue leakage holes 302 are evenly distributed on the outer wall. The sealant overflows evenly through the evenly distributed first glue leakage holes 302 into the contact gap between the support column and the surrounding building structure, forming multi-point bonding and improving the connection firmness between the support column and the surrounding structure. Example 3

[0027] To further enhance the connection strength between the reinforcement system and the building structure, this embodiment 3, based on embodiment 1 or embodiment 2, further provides a reinforcement system for kitchen flue joints, such as... Figures 1-5 As shown, fixing ribs 303 are welded on the left and right sides of the support frame 300. The fixing ribs 303 are made of threaded steel and their outer ends can be bent with hooks to facilitate binding and fixing with the pre-embedded structure of the building floor or wall, so as to achieve reliable anchoring between the reinforcement system and the main body of the building.

[0028] like Figure 5As shown, on the outer side of the adhesive storage cavity 304, multiple first support columns 301 and multiple second support columns 310 are evenly distributed and connected along the circumference. The first support columns 301 are located above the fixing ribs 303, and the second support columns 310 are located below the fixing ribs 303. The first support columns 301 and the second support columns 310 are staggered to ensure uniform transmission of support force. Both the first support columns 301 and the second support columns 310 are made of hollow steel pipes. Their internal hollow structures are connected to the adhesive storage cavity 304, and multiple first adhesive leakage holes 302 (corresponding to the first support column 301) and second adhesive leakage holes 311 (corresponding to the second support column 310) are evenly distributed on their outer walls. The sealant overflows evenly through the evenly distributed adhesive leakage holes into the contact gap between the support column and the surrounding building structure, forming multi-point bonding and improving the connection firmness between the support column and the surrounding structure.

[0029] In this embodiment, an adhesive column 312 is integrally formed at the center of the upper end face of the support frame 300. The adhesive column 312 is a cylindrical hollow structure. Its lower end is connected to the adhesive storage cavity 304. The upper end is provided with external threads and is connected to a nut 313. The nut 313 can achieve rapid sealing after adhesive injection.

[0030] Working principle: First, the bent hook of the fixing bar 303 is tied and fixed to the pre-embedded steel bar in the building floor slab to ensure the support frame 300 Maintaining a vertical position, align the first mounting groove 314 of the leak-proof connector 3 with the upper end of the first flue 1, inserting the lower end of the first flue 1 into the first mounting groove 314. Align the second mounting groove 315 with the upper end of the second flue 2, inserting the upper end of the second flue 2 into the second mounting groove 315, until the outer wall of the flue is in contact with the raised strip 308. Then, fully coat the upper and lower parts of the component with polymer anti-crack mortar. Next, inject weather-resistant structural adhesive into the adhesive storage cavity 304 through the adhesive column 312. Under pressure, the sealant flows into each gap cavity through the first through hole 305 and the second through hole 309, simultaneously filling the hollow interior of the first support column 301 and the second support column 310, and overflowing through the leakage hole into the contact gap between the support column and the surrounding building structure. After the sealant is fully filled, tighten the nut 313 to seal the adhesive column 312. After the sealant has completely cured, apply polymer anti-crack mortar again until it is flush with the nut 313, completing the assembly of the entire reinforcement system.

[0031] In this embodiment, the sealant is cured and formed inside the gap cavity, the sealant storage cavity 304, and the support column to form a 360° sealed structure without dead angles, which can block the passage of smoke and odor. In addition, the fixing rib 303 works together with the first and second support columns to distribute the weight of the flue and the vibration load to the main body of the building, and also avoid stress concentration at the joints. The support column is bonded to the surrounding structure through the sealant leakage hole, which further improves the overall structural stability and achieves the dual functions of sealing protection and structural reinforcement.

[0032] The specific embodiments described above further illustrate the purpose, technical solution, and beneficial effects of this utility model. It should be understood that the above description is only a specific embodiment of this utility model and is not intended to limit the scope of protection of this utility model. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the scope of protection of this utility model.

Claims

1. A reinforcement system for kitchen flue joints, characterized in that, include: Leak-proof connector (3) includes a support frame (300), and the upper and lower ends of the support frame (300) are respectively provided with a first mounting groove (314) and a second mounting groove (315) matching the first flue (1) and the second flue (2). The first mounting groove (314) and the second mounting groove (315) are provided with glue storage cavities (304) on their outer sides, and the glue storage cavities (304) are connected to the first mounting groove (314) and the second mounting groove (315).

2. The reinforcement system for kitchen flue joints according to claim 1, characterized in that, The bottom of the first mounting groove (314) and the second mounting groove (315) are provided with raised strips (308) at equal intervals to form a flow gap between the flue and the mounting groove.

3. The reinforcement system for kitchen flue joints according to claim 2, characterized in that, A first gap cavity (306) and a second gap cavity (307) are formed between the two sides of the first flue (1) and the first mounting groove (314), respectively. A separate first gap cavity (306) and a second gap cavity (307) are also formed between the two sides of the second flue (2) and the second mounting groove (315).

4. The reinforcement system for kitchen flue joints according to claim 3, characterized in that, The first mounting groove (314) is connected to the glue storage cavity (304) through a plurality of first through holes (305), and the second mounting groove (315) is connected to the glue storage cavity (304) through a plurality of second through holes (309).

5. A reinforcement system for kitchen flue joints according to any one of claims 1-4, characterized in that, The outer side of the glue storage cavity (304) is also evenly connected with the first support column (301).

6. A reinforcement system for kitchen flue joints according to claim 5, characterized in that, The first support column (301) is hollow inside and communicates with the glue storage cavity (304), and the outer wall of the first support column (301) is also evenly distributed with a plurality of first glue leakage holes (302) communicating with the hollow interior.

7. A reinforcement system for kitchen flue joints according to any one of claims 1-4, characterized in that, The support frame (300) is connected to fixing ribs (303) on both sides.

8. A reinforcement system for kitchen flue joints according to claim 7, characterized in that, The outer side of the glue storage cavity (304) is also evenly connected with a first support column (301), which is located above the fixing rib (303). The first support column (301) is hollow inside and communicates with the glue storage cavity (304), and the outer side wall of the first support column (301) is also evenly distributed with a plurality of first glue leakage holes (302) communicating with the hollow interior.

9. A reinforcement system for kitchen flue joints according to claim 8, characterized in that, The outer side of the glue storage cavity (304) is also evenly connected with a second support column (310), which is located below the fixing rib (303); The second support column (310) is hollow inside and communicates with the glue storage cavity (304), and the outer wall of the second support column (310) is also evenly distributed with a plurality of second glue leakage holes (311) that communicate with the hollow interior.

10. A reinforcement system for kitchen flue joints according to claim 1, characterized in that, The upper end face of the support frame (300) is connected to a glue-adding column (312), the glue-adding column (312) is connected to the glue storage cavity (304), and the top end of the glue-adding column (312) is also threaded with a nut (313).