Telescopic access frame gallery and telescopic gallery for installation of elevators in old buildings

The design of the telescopic corridor frame solves the problems of low efficiency and safety hazards caused by measurement errors in the length of the corridor when adding elevators to old buildings, and realizes efficient and safe elevator corridor installation.

CN225014734UActive Publication Date: 2026-11-24卢东兴
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202620162227.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2026-02-04
Publication Date
2026-11-24
Estimated Expiration
2036-02-04

AI Technical Summary

Technical Problem

When installing elevators in old buildings, it is impossible to accurately measure the length of the connecting corridor, which makes the installation process cumbersome, labor-intensive, and inefficient. In addition, the elevator connecting corridor structure exerts a pulling force on the old building structure, posing a safety hazard.

Method used

The corridor adopts a telescopic frame structure, which forms a variable-length corridor side by embedding telescopic tubes inside the main square tube. The corridor length is precisely adjusted by using reverse stretching of the main square tube, and it is fixed by an anti-settlement connection device, which reduces manual adjustment and improves production efficiency and safety.

Benefits of technology

This technology enables the efficient installation of elevator corridors without the need for precise distance measurements, reducing labor costs, improving installation efficiency, ensuring the structural stability and safety of old buildings, and minimizing safety hazards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN225014734U_ABST
    Figure CN225014734U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of elevator technology, and discloses a telescopic passage frame corridor and a telescopic corridor for adding elevators to old buildings. The telescopic passage frame corridor includes: a corridor support device (1), a main square tube (2), a telescopic tube (3), a connecting plate (6), bolts (7), and an anti-settlement connection device (4); the telescopic tube (3) is embedded in the main square tube (2) to form a telescopic corridor side, and the four telescopic corridor sides form a telescopic passage frame corridor with variable passage length; the first end (31) of the telescopic tube (3) is connected to the anti-settlement connection device (4); the main square tube (2) in each telescopic corridor side is connected to the corridor support device (1) by extending in the opposite direction, and each telescopic corridor side is fixed by the connecting plate (6) and bolts (7). The telescopic passage frame corridor has variable length to compensate for measurement errors, does not require secondary manual processing of the corridor, reduces labor costs, and improves the efficiency of elevator installation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of elevator technology, and in particular to a telescopic passage frame corridor and telescopic corridor for adding elevators to old buildings. Background Technology

[0002] In existing technologies, when adding elevators to old buildings, the inability to accurately measure the actual distance between the building structure and the connecting corridor support device or the elevator shaft leads to the actual length of the manufactured connecting corridor being either larger or smaller than the actual distance. Consequently, on-site elevator installation often requires welding to lengthen the connecting corridor or cutting to shorten it, resulting in a cumbersome installation process, high labor costs, and low efficiency. Furthermore, existing elevator connecting corridor structures require customization for different measured distances, making modular production impossible and further reducing production efficiency.

[0003] In addition, elevator shafts are prone to settlement, and the settlement of elevator shafts will exert a tensile force on the elevator corridor structure. Therefore, the elevator corridor structure will also exert a tensile force on the old building structure, which can easily cause cracks in the old building structure and even cause greater damage to the old building structure, posing a significant safety hazard. Summary of the Invention

[0004] The purpose of this utility model is to provide at least one retractable passage frame corridor and retractable corridor for adding elevators to old buildings, which can at least solve the technical problems of low efficiency in elevator installation, high labor costs and low efficiency in production corridors, and can at least improve the efficiency of elevator installation, reduce labor costs and improve the efficiency of production corridors.

[0005] To solve the above-mentioned technical problems, at least one embodiment of this application provides a telescopic passage frame corridor for adding elevators to old buildings, including: a corridor support device (1), four main square tubes (2), four telescopic tubes (3), at least four connecting plates (6), at least four bolts (7), and four anti-settlement connection devices (4); the main square tubes (2) are embedded with the telescopic tubes (3) to form a telescopic corridor side, and the telescopic passage frame corridor with variable passage length is formed by the four telescopic corridor sides, wherein the internal gap between the main square tubes (2) and the embedded telescopic tubes (3) is a preset value; the first end (31) of the telescopic tube (3) in each telescopic corridor side is connected to each of the anti-settlement connection devices (4). The first end (31) of the telescopic tube (3) is the end of the telescopic tube (3) away from the main square tube (2) embedded therein, and the anti-settlement connection device (4) is a device fixed to the old building body (5); the main square tube (2) in each telescopic corridor side is simultaneously connected to the corridor support device (1) by extending in the opposite direction, and when the connection position of each main square tube (2) and the corridor support device (1) is determined, the telescopic passage frame corridor is fixedly welded by at least four connection plates (6) and at least four bolts (7) to fix the connection position, forming a telescopic passage frame corridor with a fixed length that can support and connect the corridor support device (1) and the old building body (5).

[0006] This application utilizes telescopic tubes embedded within main square tubes to form telescopic corridor edges, and four telescopic corridor edges to create a telescopic passageway frame corridor of variable length. By reverse-stretching each main square tube, the length of the telescopic passageway frame corridor is increased. This allows for precise stretching of the telescopic passageway frame corridor to the actual distance between the old building structure and the corridor support device or elevator shaft, without requiring precise measurements. This eliminates the need for manual lengthening or cutting of the corridor, reducing labor costs and improving the efficiency of elevator installation. Furthermore, because the telescopic passageway frame corridor has a variable length, it eliminates the need for custom-made corridors for different measured distances. The modular production of telescopic passageway frame corridors using the same production standards can meet the needs of connecting corridor support devices and old buildings with varying actual distances, significantly improving the production efficiency of telescopic corridors.

[0007] In some examples, each of the main square tubes (2) has a long strip hole (201) of a preset length on both sides, and each of the telescopic tubes (3) has a first fixed hole (301) of a first preset number on both sides. The method of fixing and welding the telescopic passage frame corridor by at least four connecting plates (6) and at least four bolts (7) includes: for each telescopic corridor side in the telescopic passage frame corridor, using at least one bolt (7) to pass through the long strip hole (201) of the main square tube (2) and the first fixed hole (301) of the telescopic tube (3) in the telescopic corridor side, and using the connecting plate (6) to sleeve and weld to the non-bolt head end of the bolt (7) to achieve complete fixation of the telescopic passage frame corridor.

[0008] In some examples, the telescopic pipe (3) has a predetermined number of second fixing holes (302) on both sides near its first end (31), and the anti-settlement connecting device (4) has the predetermined number of settlement holes (401) on both sides, wherein the settlement holes (401) are matched one by one with the second fixing holes (302). The step of connecting the first end (31) of the telescopic pipe (3) in each telescopic corridor side to each anti-settlement connecting device (4) includes: for each telescopic corridor side, using a predetermined number of bolts to pass through the settlement holes (401) and the second fixing holes (302) of the anti-settlement connecting device (4) corresponding to the telescopic corridor side, so that the first end (31) of the telescopic pipe (3) in the telescopic corridor side is connected to the anti-settlement connecting device (4).

[0009] In some examples, the connecting corridor support device (1) is a connecting corridor column or an elevator shaft. When the connecting corridor support device is a connecting corridor column, the telescopic passage frame connecting corridor for adding elevators to old buildings includes at least two telescopic passage frame connecting corridors. A telescopic passage frame connecting corridor is erected between the connecting corridor column and the elevator shaft, and a telescopic passage frame connecting corridor is erected between the connecting corridor column and the old building. If there are multiple connecting corridor columns, a telescopic passage frame connecting corridor is also erected between adjacent connecting corridor columns.

[0010] In some examples, the telescopic corridor frame corridor, which is composed of four telescopic corridor sides with variable corridor length, includes: connecting two telescopic corridor sides on the same vertical plane using vertical connecting rods; connecting the sides of two vertices of the two vertical connecting rods on the same horizontal plane using horizontal connecting rods, and connecting the sides of two bottom points of the two vertical connecting rods on the same horizontal plane; wherein the vertex refers to the end point of the vertical connecting rod away from the ground, and the bottom point refers to the end point of the vertical connecting rod close to the ground.

[0011] In some examples, the anti-settlement connection device (4) includes: a base plate (41), a first vertical plate (42), and a second vertical plate (43), wherein the first vertical plate (42) and the second vertical plate (43) are the same size; the second end (411) of the base plate (41) is connected to the old building body (5); the first vertical plate (42) and the second vertical plate (43) are vertically parallel, and the third end (421) of the first vertical plate (42) is connected to the fourth end (412) of the base plate (41). Then, the fifth end (431) of the second upright plate (43) is connected to the fourth end (412) of the bottom plate (41); the first upright plate (42) has a second preset number of first vertical elongated holes (4001) in the vertical direction at a preset position, and the second upright plate (43) has a second preset number of second vertical elongated holes (4002) in the vertical direction at the preset position, and the first vertical elongated holes (4001) and the second vertical elongated holes (4002) are matched one by one.

[0012] In some examples, the first vertical elongated hole (4001) and the second vertical elongated hole (4002) are vertical elongated holes with length markings.

[0013] In some examples, the anti-settlement connection device (4) further includes two triangular reinforcing plates (44), one right-angled side of which is connected to the side of the second upright plate (43), and the other right-angled side of which is connected to the fourth end (412) of the base plate (41); the other right-angled side of which is connected to the side of the first upright plate (42), and the other right-angled side of which is connected to the fourth end (412) of the base plate (41).

[0014] Another embodiment of this application provides a retractable corridor for adding elevators to an old building, including: a retractable passage frame corridor for adding elevators to an old building, and at least one set of four-sided load-bearing panels; the four load-bearing panels are respectively fixed to the four sides of the retractable passage frame corridor to form a retractable corridor, so as to connect the corridor support device and the old building based on the retractable corridor. Attached Figure Description

[0015] One or more embodiments are illustrated by way of example with reference to the accompanying drawings, and these illustrative descriptions do not constitute a limitation on the embodiments.

[0016] Figure 1 This is a structural diagram of a retractable passageway frame corridor for adding elevators to an old building, provided in one embodiment of this application; Figure 2 This is a side view of a telescopic passageway frame corridor provided in one embodiment of this application; Figure 3 This is a schematic diagram of a connecting telescopic pipe and an anti-settlement connection device provided in another embodiment of this application; Figure 4 This is a schematic diagram of the structure of the anti-settlement connection device and the old building body provided in one embodiment of this application; Figure 5 This is a schematic diagram of the anti-settlement connection device provided in one embodiment of this application. Detailed Implementation

[0017] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the various embodiments of this application will be described in detail below with reference to the accompanying drawings. However, those skilled in the art will understand that many technical details have been provided in the various embodiments of this application to help readers better understand this application. However, the technical solutions claimed in this application can be implemented even without these technical details and various changes and modifications based on the following embodiments. The division of the various embodiments below is for the convenience of description and should not constitute any limitation on the specific implementation of this application. The various embodiments can be combined with and referenced by each other without contradiction.

[0018] To address the aforementioned technical problems of high labor costs, low installation efficiency, and low efficiency in creating connecting corridors for elevator installation in old buildings, this utility model proposes a retractable passage frame connecting corridor for elevator installation in old buildings. The implementation details of this embodiment are described below. The following content is only for ease of understanding and is not necessary for implementing this solution. Example

[0019] This solution provides a retractable passageway frame corridor for adding elevators to old buildings, such as... Figure 1 As shown, it includes: The corridor support device (1), four main square tubes (2), four telescopic tubes (3), at least four connecting plates (6), at least four bolts (7), and four anti-settlement connecting devices (4); the main square tubes (2) are embedded with the telescopic tubes (3) to form a telescopic corridor side, and the four telescopic corridor sides form a telescopic corridor frame corridor with variable corridor length, wherein the internal gap between the main square tubes (2) and the embedded telescopic tubes (3) is a preset value; the first end (31) of the telescopic tube (3) in each telescopic corridor side is connected to each of the anti-settlement connecting devices (4), wherein the first end (31) of the telescopic tube (3) is the... The telescopic tube (3) is located away from the end of the main square tube (2) embedded therein. The anti-settlement connection device (4) is a device fixed to the old building body (5). The main square tube (2) in each telescopic corridor side is simultaneously connected to the corridor support device (1) by extending in the opposite direction. When the connection position of each main square tube (2) and the corridor support device (1) is determined, the telescopic passage frame corridor is fixedly welded by at least four connecting plates (6) and at least four bolts (7) to fix the connection position and form a telescopic passage frame corridor with a fixed length that can support and connect the corridor support device (1) and the old building body (5).

[0020] For a concise and clear understanding of the retractable walkway frame connecting corridor in this plan, please refer to [reference needed]. Figure 2 , Figure 2 Side view of a retractable walkway frame connecting corridor for adding elevators to an old building.

[0021] The telescopic passageway frame corridor is of variable length and serves as the framework for the telescopic corridor. A telescopic corridor connects the existing building structure with its supporting structure for pedestrian access. "Reverse" refers to the horizontal direction of the main square tube near the corridor's supporting structure. "Internal gap" refers to the shortest distance between the inner wall of the main square tube and the outer wall of the embedded telescopic tube. Preset values ​​can be set according to actual needs, such as 2mm, 3mm, 4mm, or other values.

[0022] Specifically, the internal gaps between the telescopic tube (3) and each of the four sides of the main square tube (2) are all preset values.

[0023] In some examples, the length of the main square tube (2) can be set according to actual needs. For example, the length of the main square tube (2) can be set to 1m, 1.5m, 2m or other values. The length of the telescopic tube (3) can also be set according to actual needs. For example, the length of the telescopic tube (3) can be set to 1.4m, 1.9m, 2.0m or other values. The telescopic range of the telescopic corridor can be set according to actual needs. For example, the telescopic range can be greater than or equal to 0mm and less than or equal to 800mm or other ranges.

[0024] In some examples, the connecting corridor support device (1) is a connecting corridor column or an elevator shaft. When the connecting corridor support device is a connecting corridor column, the telescopic passage frame connecting corridor for adding elevators to old buildings includes at least two telescopic passage frame connecting corridors. A telescopic passage frame connecting corridor is erected between the connecting corridor column and the elevator shaft, and a telescopic passage frame connecting corridor is erected between the connecting corridor column and the old building. If there are multiple connecting corridor columns, a telescopic passage frame connecting corridor is also erected between adjacent connecting corridor columns. Among them, the elevator shaft refers to the dedicated vertical passage for elevator operation. Specifically, for safety reasons, when the distance between the old building and the elevator shaft is greater than a preset distance, the connecting corridor support device is a connecting corridor column, and one or more connecting corridor columns are set between the elevator shaft and the old building to ensure that the distance between the connecting corridor support devices and between the connecting corridor support device and the old building is a safe distance; when the distance between the old building and the elevator shaft is less than a preset distance, the connecting corridor support device is an elevator shaft. The preset distance can be set according to actual needs; this solution recommends setting the preset distance to 6m.

[0025] Therefore, when the distance between the old building and the elevator shaft is greater than the preset distance, the stability and safety of the overall structure of the elevator installation are ensured by adding connecting corridor columns.

[0026] In some examples, each of the main square tubes (2) has a long strip hole (201) of a preset length on both sides, and each of the telescopic tubes (3) has a first fixed hole (301) of a first preset number on both sides. The method of fixing and welding the telescopic passage frame corridor by at least four connecting plates (6) and at least four bolts (7) includes: for each telescopic corridor side in the telescopic passage frame corridor, using at least one bolt (7) to pass through the long strip hole (201) of the main square tube (2) and the first fixed hole (301) of the telescopic tube (3) in the telescopic corridor side, and using the connecting plate (6) to sleeve and weld to the non-bolt head end of the bolt (7) to achieve complete fixation of the telescopic passage frame corridor.

[0027] The preset length can be set according to actual needs, and can be 300mm, 600mm, 800mm or other values. The first preset quantity can be set according to actual needs, for example, it can be 3, 4, 5, 6, 7 or other quantities. The diameter of the hole (301) can be set according to actual needs, and can be 30mm, 32mm, 40mm or other values. The two sides of the telescopic tube (3) are either perpendicular to the horizontal plane or parallel to the horizontal plane, and the two sides of the main square tube (2) are either perpendicular to the horizontal plane or parallel to the horizontal plane, such as Figure 2 As shown, this scheme is illustrated using the example of both sides of the main square tube and both sides of the telescopic tube being perpendicular to the horizontal plane.

[0028] It can be seen that by welding and fixing the main square tube (2) with the telescopic tube (3) through bolts and connecting plates, the safety and stability of the telescopic corridor composed of the telescopic passage frame corridor are ensured.

[0029] In some examples, such as Figure 3 As shown, the telescopic pipe (3) has a preset number of second fixing holes (302) on both sides near its first end (31), and the anti-settlement connecting device (4) has the preset number of settlement holes (401) on both sides. The settlement holes (401) are matched one by one with the second fixing holes (302). The step of connecting the first end (31) of the telescopic pipe (3) in each telescopic corridor side to each anti-settlement connecting device (4) includes: for each telescopic corridor side, using a preset number of bolts to pass through the settlement holes (401) and the second fixing holes (302) of the anti-settlement connecting device (4) corresponding to the telescopic corridor side, so that the first end (31) of the telescopic pipe (3) in the telescopic corridor side is connected to the anti-settlement connecting device (4).

[0030] The preset number can be set according to actual needs, and can be 2, 4 or other values. The diameter of the second fixing hole (302) can be set according to actual needs, and can be 30mm, 32mm, 40mm or other values. The two sides of the anti-settlement connection device (4) are either perpendicular to the horizontal plane or parallel to the horizontal plane, such as... Figure 2 , Figure 3 As shown in the figure, this scheme is illustrated by taking the two sides of the anti-settlement connection device that are perpendicular to the horizontal plane as an example.

[0031] It should be noted that in this solution, for the same component (the component can be a telescopic pipe, a main square pipe, or an anti-settlement connection device), when the two sides of each component overlap, that is, when viewed from a certain side of the component, the holes on the two sides also overlap.

[0032] In some examples, such as Figure 1As shown, the telescopic corridor frame corridor with variable corridor length composed of four telescopic corridor sides includes: connecting two telescopic corridor sides on the same vertical plane using vertical connecting rods (100); connecting the sides of two vertices of the two vertical connecting rods (100) on the same horizontal plane using horizontal connecting rods (200), and connecting the sides of two bottom points of the two vertical connecting rods (100) on the same horizontal plane; wherein, the vertex refers to the end point of the vertical connecting rod away from the ground, and the bottom point refers to the end point of the vertical connecting rod close to the ground.

[0033] Thus, the four connecting rods enable the telescopic corridor to form a structurally stable telescopic passage frame corridor, ensuring the safety and stability of the telescopic corridor based on the telescopic passage frame corridor.

[0034] In some examples, such as Figure 4 As shown, the anti-settlement connection device (4) includes: a base plate (41), a first vertical plate (42), and a second vertical plate (43). The first vertical plate (42) and the second vertical plate (43) are the same size. The second end (411) of the base plate (41) is connected to the old building body (5). The first vertical plate (42) and the second vertical plate (43) are vertically parallel, and the third end (421) of the first vertical plate (42) is connected to the fourth end (412) of the base plate (41). The fifth end (431) of the second upright plate (43) is connected to the fourth end (412) of the bottom plate (41); the first upright plate (42) has a second preset number of first vertical elongated holes (4001) in the vertical direction at a preset position, and the second upright plate (43) has a second preset number of second vertical elongated holes (4002) in the vertical direction at the preset position, and the first vertical elongated holes (4001) and the second vertical elongated holes (4002) are matched one by one.

[0035] Therefore, when the settlement displacement of the connecting corridor support device does not exceed the length of the vertical elongated hole, the anti-settlement connection device will not cause any damage to the old building structure, greatly reducing safety hazards.

[0036] In some examples, such as Figure 5 As shown, the base plate (1) includes four holes (4100), which are located at the four corners of the base plate (1). Chemical anchors are used to pass through each hole (4100) in the base plate (1) so that the base plate (1) is fixed to the old building and connected to the old building.

[0037] Specifically, the thickness, length, and width of the base plate can all be set according to actual needs. For example, the thickness of the base plate can be 24mm, 30mm, or other values. The length of the base plate can be 400mm, 500mm, or other values, and the width of the base plate can be 400mm, 500mm, or other values. The length and width can be equal. The base plate material can be Q235B.

[0038] Specifically, the preset position can be the middle position of the upright plate to ensure balanced force distribution and allow it to withstand greater loads. The thickness, length, and width of the upright plate can be set according to actual needs; for example, the thickness can be 24mm, 30mm, or other values. The length and width of the upright plate can be 300mm, 372mm, 400mm, 500mm, or other values. The length and width can be equal. The upright plate material can be Q235 stainless steel.

[0039] Specifically, the second preset quantity can be set according to actual needs, and can be 2, 3, 4 or other values. The length of the vertical elongated hole can also be set according to actual needs, for example, the length of the vertical elongated hole can be 100mm, 110mm, 120mm or other values.

[0040] In some examples, such as Figure 5 As shown, the first vertical elongated hole (4001) and the second vertical elongated hole (4002) are vertical elongated holes with length markings. It can be seen that the displacement of the telescopic passage frame corridor settlement can be directly observed through the length markings of the vertical elongated holes, so as to monitor the settlement displacement and take corresponding protective measures when the settlement displacement reaches a certain level.

[0041] In some examples, such as Figure 5 As shown, the anti-settlement connection device (4) also includes two triangular reinforcing plates (44). One right-angled side of the triangular reinforcing plate (44) is connected to the side of the second upright plate (43), and the other right-angled side of the triangular reinforcing plate (44) is connected to the fourth end (412) of the base plate (41). The other right-angled side of the triangular reinforcing plate (44) is connected to the side of the first upright plate (42), and the other right-angled side of the triangular reinforcing plate (44) is connected to the fourth end (412) of the base plate (41). Thus, the connection between the upright plate and the base plate is made more stable by the triangular reinforcing plates, thereby making the anti-settlement connection device more robust.

[0042] In summary, this application provides a retractable passage frame corridor for adding elevators to old buildings, comprising: a corridor support device (1), four main square tubes (2), four telescopic tubes (3), at least four connecting plates (6), at least four bolts (7), and four anti-settlement connecting devices (4); the main square tubes (2) are embedded with the telescopic tubes (3) to form a retractable corridor side, and the four retractable corridor sides form a retractable passage frame corridor with variable passage length, wherein the internal gap between the main square tubes (2) and the embedded telescopic tubes (3) is a preset value; the first end (31) of the telescopic tube (3) in each of the retractable corridor sides is connected to each of the anti-settlement connecting devices (4), wherein the telescopic tubes (3) The first end (31) is the end of the telescopic tube (3) away from the main square tube (2) embedded therein, and the anti-settlement connection device (4) is a device fixed to the old building body (5); the main square tube (2) in each telescopic corridor side is simultaneously connected to the corridor support device (1) by extending in the opposite direction, and when the connection position of each main square tube (2) and the corridor support device (1) is determined, the telescopic passage frame corridor is fixedly welded by at least four connecting plates (6) and at least four bolts (7) to fix the connection position and form a telescopic passage frame corridor with a fixed length that can support and connect the corridor support device (1) and the old building body (5).

[0043] Telescopic corridors are formed by embedding telescopic tubes within main square tubes. These four telescopic corridors together create a variable-length telescopic passageway frame corridor. By reverse-stretching the main square tubes, the length of the telescopic passageway frame corridor is increased. This allows for precise stretching of the telescopic passageway frame corridor to the actual distance between the old building structure and the corridor support device or elevator shaft, without requiring accurate measurements. The telescopic corridor can be constructed based on this frame, eliminating the need for manual lengthening or cutting of the corridor, thus reducing labor costs and improving the efficiency of elevator installation. Specifically, when there is an error in the measured distance between the corridor support device and the old building structure—for example, when the measured distance is less than the actual distance—the telescopic passageway frame corridor can be lengthened to the actual distance by reverse-stretching the main square tubes, compensating for the measurement error. This eliminates the need for manual lengthening or cutting of the corridor, reducing on-site work and time, improving elevator installation efficiency, and reducing labor costs. Furthermore, because the length of the retractable walkway frame corridor is variable, it is not necessary to customize corridors for different measured distances. Retractable walkway frame corridors, produced modularly using the same production standards, can meet the needs of connecting corridor support devices and old buildings with varying actual distances, greatly improving the production efficiency of retractable walkways.

[0044] Example 2: This solution provides a retractable corridor for adding elevators to old buildings, including: The retractable passageway frame corridor for adding elevators to old buildings, and at least one set of four load-bearing panels; the four load-bearing panels are respectively fixed to the four sides of the retractable passageway frame corridor to form a retractable corridor, so as to connect the corridor support device and the old building body based on the retractable corridor.

[0045] Specifically, the number of retractable passageway frame corridors is the same as the number of sets of four-sided load-bearing panels. For example, when there are two retractable passageway frame corridors, there are two sets of four-sided load-bearing panels, and each set of four-sided load-bearing panels is fixed to each retractable passageway frame corridor.

[0046] The material of the load-bearing panels can be set according to actual needs; this solution does not impose specific restrictions. The telescopic passageway frame corridor is proposed in Example 1.

[0047] Therefore, after accurately connecting the corridor support device to the old building with the retractable corridor frame, a retractable corridor is constructed by installing load-bearing panels on all four sides of the retractable corridor frame. This retractable corridor utilizes the variable length of the retractable corridor frame to compensate for measurement errors, eliminating the need for manual lengthening or cutting of the corridor, reducing labor costs, improving the efficiency of elevator installation, shortening the installation period, and increasing installation efficiency, thus achieving cost reduction and efficiency improvement. Furthermore, the anti-settlement connection device ensures that the settlement displacement of the corridor support device does not exceed the length of the vertical elongated hole, preventing any damage to the old building structure and greatly reducing safety hazards.

[0048] Those skilled in the art will understand that the above embodiments are specific embodiments for implementing this application, and in practical applications, various changes can be made to them in form and detail without departing from the spirit and scope of this application.

Claims

1. A telescopic access frame vestibule for elevator installation in an old building, characterized in that, The utility model relates to a kind of corridor support device (1), four main square tubes (2), four telescopic tubes (3), at least four connecting plates (6), at least four bolts (7) and four anti-settling connecting devices (4);The main square tube (2) is embedded in the telescopic tube (3) and constitutes telescopic corridor edge, and the telescopic corridor edge is formed by four telescopic corridor edges, and the telescopic passageway frame corridor with variable length is formed, wherein the internal gap of the main square tube (2) and the embedded telescopic tube (3) is preset value;The first end (31) of the telescopic tube (3) in each telescopic corridor edge is connected with each anti-settling connecting device (4), wherein the first end (31) of the telescopic tube (3) is the end of the telescopic tube (3) away from the main square tube (2) embedded therein, and the anti-settling connecting device (4) is a device fixed to the old building body (5);The main square tube (2) in each telescopic corridor edge is connected with the corridor support device (1) by reverse extension at the same time, and when the connection position of the main square tube (2) and the corridor support device (1) is determined, the telescopic passageway frame corridor is fixedly welded by at least four connecting plates (6) and at least four bolts (7) to fix the connection position, to form the telescopic passageway frame corridor with fixed length that can support the connection between the corridor support device (1) and the old building body (5). Each main square tube (2) has a predetermined length of long hole (201) on both sides, each telescopic tube (3) has a first predetermined number of first fixing holes (301) on both sides, and the telescopic passageway frame corridor is fixedly welded by at least four connecting plates (6) and at least four bolts (7), including: For each telescopic corridor edge in the telescopic passageway frame corridor, at least one bolt (7) is used to pass through the long hole (201) of the main square tube (2) and the first fixing hole (301) of the telescopic tube (3) in the telescopic corridor edge at the same time, and the connecting plate (6) is sleeved and welded at the end of the bolt (7) other than the bolt head, to completely fix the telescopic passageway frame corridor. The telescopic tube (3) has a predetermined number of second fixing holes (302) on both sides near the first end (31), and the anti-settling connecting device (4) has a predetermined number of settling holes (401) on both sides, wherein the settling hole (401) and the second fixing hole (302) are matched one by one, and the first end (31) of the telescopic tube (3) in each telescopic corridor edge is connected with each anti-settling connecting device (4), including: For each telescopic corridor edge, a predetermined number of bolts are used to pass through the settling hole (401) of the anti-settling connecting device (4) corresponding to the telescopic corridor edge and the second fixing hole (302), so that the first end (31) of the telescopic tube (3) in the telescopic corridor edge is connected with the anti-settling connecting device (4).

2. A telescoping access frame vestibule for an elevator addition to an existing building according to claim 1, wherein, ​ ​ 3. The telescoping access frame vestibule of claim 1, wherein, ​ ​ 4. The telescoping access frame vestibule of claim 1, wherein, The connecting corridor support device (1) is a connecting corridor column or an elevator shaft. When the connecting corridor support device is a connecting corridor column, the telescopic passage frame connecting corridor for adding elevators to old buildings includes at least two telescopic passage frame connecting corridors. A telescopic passage frame connecting corridor is erected between the connecting corridor column and the elevator shaft, and a telescopic passage frame connecting corridor is erected between the connecting corridor column and the old building. If there are multiple connecting corridor columns, a telescopic passage frame connecting corridor is also erected between adjacent connecting corridor columns.

5. The telescoping access frame vestibule of claim 1, wherein, The telescopic corridor frame corridor, whose length is variable and is formed by the four telescopic corridor sides, includes: Two retractable corridors on the same vertical plane are connected by vertical connecting rods; Using a horizontal connecting rod, the sides of the two vertices of the two vertical connecting rods that are on the same horizontal plane are connected, and the sides of the two bottom points of the two vertical connecting rods that are on the same horizontal plane are connected. The vertex refers to the end point of the vertical connecting rod that is furthest from the ground, and the bottom point refers to the end point of the vertical connecting rod that is closest to the ground.

6. The telescoping access frame vestibule of claim 1, wherein, The anti-settlement connection device (4) includes: a base plate (41), a first vertical plate (42) and a second vertical plate (43), wherein the first vertical plate (42) and the second vertical plate (43) are the same size; The second end (411) of the base plate (41) is connected to the old building body (5); The first upright plate (42) is vertically parallel to the second upright plate (43), and the third end (421) of the first upright plate (42) is connected to the fourth end (412) of the base plate (41), and the fifth end (431) of the second upright plate (43) is connected to the fourth end (412) of the base plate (41). The first upright plate (42) has a second preset number of first vertical elongated holes (4001) in the vertical direction at a preset position, and the second upright plate (43) has a second preset number of second vertical elongated holes (4002) in the vertical direction at the preset position, with the first vertical elongated holes (4001) and the second vertical elongated holes (4002) matching one by one.

7. A telescoping access frame vestibule for a lift addition to an existing building according to claim 6, wherein, The first vertical elongated hole (4001) and the second vertical elongated hole (4002) are vertical elongated holes with length markings.

8. The telescoping access frame vestibule of claim 6, wherein, The anti-settlement connection device (4) also includes two triangular reinforcing plates (44), one right-angle side of the triangular reinforcing plate (44) is connected to the side of the second upright plate (43), and the other right-angle side of the triangular reinforcing plate (44) is connected to the fourth end (412) of the base plate (41). Another right-angled side of the triangular reinforcing plate (44) is connected to the side of the first upright plate (42), and the other right-angled side of the triangular reinforcing plate (44) is connected to the fourth end (412) of the base plate (41).

9. A telescopic gallery for the installation of an elevator in an existing building, characterized in that, include: The retractable passageway connecting corridor for adding elevators to old buildings, and at least one set of four-sided load-bearing panels; The load-bearing panels on the four sides are respectively fixed to the four sides of the telescopic passage frame corridor to form a telescopic corridor, so as to connect the corridor support device and the old building based on the telescopic corridor.